CN1837482A - Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring - Google Patents

Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring Download PDF

Info

Publication number
CN1837482A
CN1837482A CN 200610020687 CN200610020687A CN1837482A CN 1837482 A CN1837482 A CN 1837482A CN 200610020687 CN200610020687 CN 200610020687 CN 200610020687 A CN200610020687 A CN 200610020687A CN 1837482 A CN1837482 A CN 1837482A
Authority
CN
China
Prior art keywords
concrete
steel pipe
pipe
perfusion
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 200610020687
Other languages
Chinese (zh)
Other versions
CN100425785C (en
Inventor
郑远鹄
郑旭峰
牟廷敏
张琪
朱学雷
陈应忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INST OF HIGHWAY SURVEY AND DESIGN SICHUAN COMMUNIATION OFFICE
Original Assignee
INST OF HIGHWAY SURVEY AND DESIGN SICHUAN COMMUNIATION OFFICE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INST OF HIGHWAY SURVEY AND DESIGN SICHUAN COMMUNIATION OFFICE filed Critical INST OF HIGHWAY SURVEY AND DESIGN SICHUAN COMMUNIATION OFFICE
Priority to CNB2006100206870A priority Critical patent/CN100425785C/en
Publication of CN1837482A publication Critical patent/CN1837482A/en
Application granted granted Critical
Publication of CN100425785C publication Critical patent/CN100425785C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a steel tube concrete arc ring steel tube inner concrete filling method and relative filling device, which can meet the demand of continuous operation of big-diameter main string tube, and reducing the construction time. The filling method comprises: a, dividing filling sections that dividing at least two sections with certain height difference at the left and right semi steel tubes of main string tube; b, arranging filling device on the initial points of each filling section; c, filling concrete from the arc foot to the top. With said invention, the filled concrete has better continuous property, high reliability, and better safety and reduced construction period.

Description

Concrete into steel pipe of steel pipe concrete arch ring method for filling and device for casting
Technical field
The present invention relates to a kind of job practices and concrete-spouting plant of concrete-filled steel tubes arch bridge, relate in particular to concrete into steel pipe of steel pipe concrete arch ring method for filling and device for casting.
Background technology
Concrete filled steel tube is the combined material that fill concrete forms in steel pipe.Stability, corrosion stability and durability when steel pipe improves the steel pipe walls pressurized by concrete filled.Concrete then by the cuff effect of steel pipe walls, has improved concrete compressive strength and ductility, and steel and concrete are organically combined; Aspect construction, concrete filled steel tube can utilize hollow steel pipe as stiff skeleton and template, and construction hoisting is in light weight, and progress is fast, and the construction steel using amount is economized.Because the superiority on material and job practices is very rational with this structure applications in the arch bridge based on pressurized.Because concrete filled steel tube has above-mentioned advantage, the concrete-filled steel tubes arch bridge development in recent years is very fast, is widely used in the highway bridge, and present maximum span has reached 492m.
In the construction of concrete-filled steel tubes arch bridge, concrete perfusion in the main chord tube that constitutes steel pipe concrete arch rib, past employing following two kinds of methods are arranged:
One, perfusion in whole storehouse
Less when the main chord tube caliber, when main chord tube pipe inner concrete quantity is little, adopt this method more.This method is at arch springing the grouting mouth to be set, and emits the slurry mouth in the vault setting, finishes the concrete spouting construction of a main chord tube from the arch springing to the vault incessantly.Through the pipe inner concrete good integrity of this method perfusion, construction speed is fast, but the only suitable less occasion of main chord tube caliber of this method, when the main chord tube caliber is big, pipe inner concrete quantity is big, when arch camber is higher, just can't be used.
Two, divide repeatedly perfusion of storehouse
Big or perfusion equipment ability too hour adopts this method perfusion usually when the main chord tube caliber.This method is that main chord tube is separated into some sections (storehouse) with diaphragm, according to loading procedure, by storehouse (not necessarily adjacent storehouse) intrusion pipe inner concrete.This method to have an equipment needed thereby simple and can satisfy the characteristics of various execution conditions needs.But there is following defective shortcoming in this method: after a storehouse inner concrete intensity will arrive 70%, just can carry out next storehouse concrete spouting, can not construct continuously, thereby the construction period be longer; At the diaphragm place, the pipe inner concrete is separated, concrete in addition contraction, and slight gap may appear in the diaphragm both sides.Therefore, adopt pipe inner concrete continuity, the globality of this method perfusion all relatively poor.
Summary of the invention
One of technical problem to be solved by this invention provides a kind of concrete into steel pipe of steel pipe concrete arch ring method for filling, this method for filling can satisfy the requirement of construction continuously of major diameter main chord tube concrete spouting well, and shortens the construction period of concrete filled steel tube arch ring effectively.
For solving this technical problem, the technical solution adopted in the present invention is: concrete into steel pipe of steel pipe concrete arch ring method for filling of the present invention, comprise the steps: that a. divides the perfusion section, partly stride steel pipe on a main chord tube left side that constitutes steel pipe concrete arch rib, right partly striding respectively marks off the perfusion section that two-stage at least has certain height difference each other on the steel pipe; B. lay device for casting, device for casting is set respectively in starting points of pouring into section at different levels; C. concrete perfusion is partly striden steel pipe, the right side by device for casting step by step left from arch springing to the vault at main chord tube two ends and is partly striden continous pouring concrete in the steel pipe.
After taking technique scheme, because the main chord tube classification is regardless of the storehouse, the continous pouring step by step from arch springing to vault, a gas is finished the pipe inner concrete perfusion work of a main chord tube, main chord tube pipe inner concrete continuity, good integrity, thus guarantee the quality of concrete-filled steel tube arch.In addition, owing to adopt classification relay reperfusion mode, the pressure altitude of concrete pumping and difficulty, and overcritical to concrete performance, all the perfusion in existing whole storehouse has significantly and reduces.Therefore, method for filling of the present invention can satisfy the requirement of construction continuously of major diameter main chord tube concrete spouting well, and shortens the construction period of concrete filled steel tube arch ring effectively.
Another technical problem to be solved by this invention provides a kind of device for casting that is applied to above-mentioned concrete into steel pipe of steel pipe concrete arch ring method for filling.
For solving this technical problem, the technical solution adopted in the present invention is: device for casting of the present invention, comprise delivery pump, carrier pipe and intrusion pipe, the port of export of intrusion pipe is connected with main chord tube, it is characterized in that: described intrusion pipe place is provided with the slurry that emits that matches with it and manages, and the control sluice valve system that intrusion pipe is changed between plasma discharge, two kinds of duties of perfusion.It is simple and can satisfy the characteristics of various execution conditions needs that device for casting of the present invention has an equipment needed thereby.
The invention has the beneficial effects as follows, main chord tube pipe inner concrete continuity, good integrity, thereby guarantee the quality of concrete filled steel tube arch ring, pressure altitude, difficulty and making excessive demands have been reduced significantly to concrete performance to concrete pumping, therefore can satisfy the requirement of construction continuously of major diameter main chord tube concrete spouting well, reliability, safety are good, and can shorten the construction period of arch ring effectively.The device for casting equipment needed thereby is simple, and can satisfy the needs of various execution conditions well.
Method for filling of the present invention is equally applicable to the concrete spouting construction of building steel tube concrete column.
Description of drawings
This manual comprises following three width of cloth accompanying drawings:
Fig. 1 is the set-up mode schematic diagram of partly striding device for casting on the steel pipe in the concrete into steel pipe of steel pipe concrete arch ring method for filling of the present invention on a left side;
Fig. 2 is the set-up mode schematic diagram of partly striding device for casting on the steel pipe in the concrete into steel pipe of steel pipe concrete arch ring method for filling of the present invention on the right side;
Fig. 3 is the structural representation of device for casting of the present invention.
Component, position and numbering among the figure: main chord tube 10, a left side stride partly that steel pipe 10a, the right side are partly striden steel pipe 10b, emitted slurry pipe 11, device for casting 20a, device for casting 20b, device for casting 21a, device for casting 21b, device for casting 22a, device for casting 22b, intrusion pipe 201, emit slurry pipe 202, gate valve 203, gate valve 204, flap valve 205.
The specific embodiment
The present invention is further described below in conjunction with drawings and Examples.
See figures.1.and.2, concrete into steel pipe of steel pipe concrete arch ring method for filling of the present invention, comprise the steps: that a. divides the perfusion section, partly stride steel pipe 10a on main chord tube 10 left sides that constitute steel pipe concrete arch rib, right partly striding respectively marks off the perfusion section that two-stage at least has certain height difference each other on the steel pipe 10b; B. lay device for casting, device for casting is set respectively in starting points of pouring into section at different levels; C. concrete perfusion is partly striden steel pipe 10a, the right side by device for casting step by step left from arch springing to the vault at main chord tube 10 two ends and is partly striden continous pouring concrete in the steel pipe 10b.Determining of perfusion section progression is relevant with the transmission and concrete transmission ability of arch rib arrow degree, concrete spouting amount and filling system, and generally speaking, perfusion section progression is divided for 2~5 grades more.Because main chord tube 10 classifications are regardless of the storehouse, the continous pouring step by step from arch springing to vault, a gas is finished the pipe inner concrete perfusion work of a main chord tube 10, concrete continuous, good integrity in main chord tube 10 pipes, thus can guarantee the quality of concrete-filled steel tube arch.In addition, owing to adopt classification relay reperfusion mode, the pressure altitude of concrete pumping and difficulty, and overcritical to concrete performance, all the perfusion in existing whole storehouse reduces significantly.Therefore, can satisfy the requirement of construction continuously of major diameter main chord tube concrete spouting well, and shorten the construction period of concrete filled steel tube arch ring effectively.
For ease of construction and stress balance, as preferred embodiment a kind of, steel pipe 10a is partly striden on a described left side, the right perfusion sections at different levels that mark off respectively on the steel pipe 10b of partly striding are striden vertical center line symmetry directly with respect to main chord tube 10, a left side is partly striden steel pipe 10a, the right side and is partly striden steel pipe 10b symmetry and carry out concrete spouting, and promptly both pipe inner concretes perfusion process is consistent.See figures.1.and.2, for improving and guaranteeing quality of concreting, laitance, old slurry that perfusion sections at different levels are produced in the concrete spouting process are expelled to outside the main chord tube 10 by its tail end.
Device for casting of the present invention comprises delivery pump, carrier pipe and intrusion pipe 201, and the port of export of intrusion pipe 201 is connected with main chord tube 10.With reference to Fig. 3, described intrusion pipe 201 places are provided with the slurry that emits that matches with it and manage 202, and the control sluice valve system that intrusion pipe 201 is changed between plasma discharge, two kinds of duties of perfusion.
Fig. 3 shows a kind of concrete set-up mode of described control sluice valve system.With reference to Fig. 3, described control sluice valve system comprises: a. gate valve 203, and be arranged at and emit on the slurry pipe 202, also can directly be arranged at the tail end place that main chord tube 10 pours into section mutually, be used to control the open and close that emits slurry pipe 202, and match with intrusion pipe 201 duties; B. gate valve 204, are arranged on the intrusion pipe 201, are used to control the switching of intrusion pipe 201; See figures.1.and.2, partly stride steel pipe 10a, the right side on a left side and partly stride on the steel pipe 10b, the laitance that upper level perfusion section is produced in the concrete spouting process, old slurry are discharged by the slurry pipe 202 that emits of back one-level device for casting.Because initial one-level device for casting need not be got rid of laitance, old slurry, therefore be arranged on to save in the main chord tube device for casting at the 10 arch ends and emit slurry pipe 202 and control corresponding gate valve.With reference to Fig. 1, be provided with at the vault of main chord tube 10 and emit slurry pipe 11, a left side partly to stride steel pipe 10a, rightly partly stride laitance, the old slurry that the last section of steel pipe 10b perfusion section produced emit slurry pipe 11 to discharge in the concrete spouting process by this.
With reference to Fig. 2, for preventing in the main chord tube 10 that concrete perfusion falls after rise, and can in time remove, clean intrusion pipe 201 and gate valve 204, guarantee working security, also be provided with flap valve 205 on the described intrusion pipe 201, this flap valve 205 is between intrusion pipe 201 ports of export and gate valve 204.Described flap valve 206 can preferably adopt plate or slotting skewer formula flap valve.
The pouring construction of embodiment----Wushan Yangtze Bridge main arch circle.The Wushan Yangtze Bridge has another name called the Wu Gorge Yangtze Bridge, and road bridge is a steel pipe half-through arch bridge.612.2 meters of bridge total lengths, 19 meters of bridge floor clear span, two-way 4 tracks, 492 meters of main spans occupy bridge the first in the world of the same type.This bridge main arch circle arrow degree is up to 121 meters, the concrete of one root arch rib main chord tube pipe domestic demand perfusion reaches more than 600 cubic metres, traditional concrete spouting method can't satisfy the construction needs of this bridge, and the applicant successfully is applied to concrete into steel pipe of steel pipe concrete arch ring method for filling of the present invention and device for casting in the construction of this bridge.See figures.1.and.2, partly stride steel pipe 10a on a left side that constitutes main chord tube 10, right partly striding respectively marks off three grades of perfusion sections that have certain height difference each other on the steel pipe 10b.With reference to Fig. 1, partly stride on the steel pipe 10a on a left side, lay three grades of device for casting 20a, 21a, 22a successively from the arch end to vault.With reference to Fig. 2, partly stride on the steel pipe 10b on the right side, lay three grades of device for casting 20b, 21b, 22b successively from the arch end to vault.During pouring construction, partly stride steel pipe 10a, the right side by corresponding device for casting step by step left from arch springing to the vault at main chord tube 10 two ends and partly stride continous pouring concrete in the steel pipe 10b, be that a left side is partly striden steel pipe 10a, the right side and partly striden steel pipe 10b and divide three sections relay continous pourings, in 10 hours, can finish the pouring construction of a main chord tube pipe inner concrete, demonstrate short and reliability of construction period, characteristics that safety is good.If adopt the repeatedly perfusion construction of traditional branch storehouse, every pipe need be divided into 5~9 sections, and two semiarch symmetries are poured into, and 3~5 ability to irritate a main chord tube.After each perfusion, all need the maintenance of time a couple of days, wait the pipe inner concrete to reach 70~80% design strengths after, just can carry out perfusion next time.Repeatedly the perfusion construction period will be 3~5 times of method for filling of the present invention in tradition branch storehouse.
It is pointed out that top described principles more of the present invention that just explain through diagrams.Because the those of ordinary skill to constructed field is easy to carry out on this basis some modifications and change, therefore this manual be not be invention to be confined to shown in and in the described concrete structure and the scope of application, so every the corresponding modify and equivalent that might be utilized, the claim that all belongs to the present invention and applied for.

Claims (8)

1, the concrete into steel pipe of steel pipe concrete arch ring method for filling comprises the steps:
A. divide the perfusion section, partly stride steel pipe (10a), the right side on main chord tube (a 10) left side that constitutes steel pipe concrete arch rib and partly stride and respectively mark off the perfusion section that two-stage at least has certain height difference each other on the steel pipe (10b);
B. lay device for casting, device for casting is set respectively in starting points of pouring into section at different levels;
C. concrete perfusion, by device for casting from arch springing to the vault at main chord tube (10) two ends partly stride steel pipe (10a) step by step left, the interior continous pouring concrete of steel pipe (10b) is partly striden on the right side.
2, concrete into steel pipe of steel pipe concrete arch ring method for filling as claimed in claim 1 is characterized in that: steel pipe (10a) is partly striden on a described left side, the perfusion sections at different levels that mark off respectively on the steel pipe (10b) are striden the footpath with respect to main chord tube (10) vertical center line symmetry is partly striden on the right side.
3, concrete into steel pipe of steel pipe concrete arch ring method for filling as claimed in claim 2 is characterized in that: steel pipe (10a) is partly striden on a described left side, the right side is partly striden steel pipe (10b) symmetry and managed the inner concrete perfusion.
4, concrete into steel pipe of steel pipe concrete arch ring method for filling as claimed in claim 1 is characterized in that: laitance, old slurry that described perfusion sections at different levels are produced in the concrete spouting process are expelled to outside the main chord tube (10) by the tail end of its perfusion section.
5, be applied to the device for casting of concrete into steel pipe of steel pipe concrete arch ring method for filling according to claim 1, comprise delivery pump, carrier pipe and intrusion pipe (201), the port of export of intrusion pipe (201) is connected with main chord tube (10), it is characterized in that: described intrusion pipe (201) is located to be provided with the slurry that emits that matches with it and is managed (202), and the control sluice valve system that intrusion pipe (201) is changed between plasma discharge, two kinds of duties of perfusion.
6, device for casting as claimed in claim 5 is characterized in that: described control sluice valve system comprises:
A. gate valve (203) is arranged at and emits slurry pipe (202) to go up or pour into the tail end of section, is used for the open and close that slurry pipe (202) is emitted in control, and matches with intrusion pipe (201) duty;
B. gate valve (204) is arranged on the intrusion pipe (201), is used to control the switching of intrusion pipe (201).
7, device for casting as claimed in claim 6, it is characterized in that: also be provided with the flap valve (205) that is used to prevent in the main chord tube (10) that concrete perfusion falls after rise on the described intrusion pipe (201), this flap valve (205) is positioned between intrusion pipe (201) port of export and the gate valve (204).
8, device for casting as claimed in claim 7 is characterized in that: what described flap valve (206) adopted is plate or slotting skewer formula flap valve.
CNB2006100206870A 2006-04-12 2006-04-12 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring Expired - Fee Related CN100425785C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2006100206870A CN100425785C (en) 2006-04-12 2006-04-12 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2006100206870A CN100425785C (en) 2006-04-12 2006-04-12 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring

Publications (2)

Publication Number Publication Date
CN1837482A true CN1837482A (en) 2006-09-27
CN100425785C CN100425785C (en) 2008-10-15

Family

ID=37014980

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2006100206870A Expired - Fee Related CN100425785C (en) 2006-04-12 2006-04-12 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring

Country Status (1)

Country Link
CN (1) CN100425785C (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758531A (en) * 2012-06-06 2012-10-31 广西壮族自治区公路桥梁工程总公司 In-pipe concrete vacuum auxiliary filling method for large concrete-filled steel tubular structure and filling method
CN104153295A (en) * 2014-07-21 2014-11-19 广东省基础工程公司 Self-compacting concrete jack-up pouring construction method for steel tube arch bridges
CN105424485A (en) * 2015-12-16 2016-03-23 山东科技大学 Concrete filled steel tube arch grouting test system and test method
CN106501496A (en) * 2016-10-28 2017-03-15 重庆交通大学 A kind of visual CFST Arch Bridge pipe inner concrete irrigates assay device
CN106835998A (en) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete
CN108708264A (en) * 2018-05-28 2018-10-26 广西路桥工程集团有限公司 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete
CN109505250A (en) * 2018-12-07 2019-03-22 中铁局集团厦门建设工程有限公司 A kind of filling concrete method of steel tube arch rib
CN109577205A (en) * 2018-11-28 2019-04-05 中铁十四局集团第工程发展有限公司 A kind of 180m long-span Steel Arch casting method
CN113279333A (en) * 2021-05-18 2021-08-20 中电建十一局工程有限公司 Construction method for filling concrete in steel pipe arch bridge
CN113718623A (en) * 2021-08-05 2021-11-30 贵州省公路工程集团有限公司 Hollow steel pipe concrete arch bridge structure

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0825593B2 (en) * 1986-09-30 1996-03-13 三菱重工業株式会社 Liquid filling device
CN87103180A (en) * 1987-05-04 1988-11-23 首都钢铁公司 Job technique of jack inverted perfusion steel pipe concrete
JP2000129783A (en) * 1998-10-21 2000-05-09 Maeda Corp Construction method for steel pipe concrete column
JP2001020523A (en) * 1999-07-07 2001-01-23 Taisei Corp Concrete press-in device and concrete guide device

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758531A (en) * 2012-06-06 2012-10-31 广西壮族自治区公路桥梁工程总公司 In-pipe concrete vacuum auxiliary filling method for large concrete-filled steel tubular structure and filling method
CN102758531B (en) * 2012-06-06 2013-05-15 广西壮族自治区公路桥梁工程总公司 In-pipe concrete vacuum auxiliary filling method for large concrete-filled steel tubular structure and filling system
CN104153295A (en) * 2014-07-21 2014-11-19 广东省基础工程公司 Self-compacting concrete jack-up pouring construction method for steel tube arch bridges
CN105424485A (en) * 2015-12-16 2016-03-23 山东科技大学 Concrete filled steel tube arch grouting test system and test method
CN106501496A (en) * 2016-10-28 2017-03-15 重庆交通大学 A kind of visual CFST Arch Bridge pipe inner concrete irrigates assay device
CN106501496B (en) * 2016-10-28 2019-04-02 重庆交通大学 A kind of visual CFST Arch Bridge pipe inner concrete perfusion experimental rig
CN106835998A (en) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete
CN108708264A (en) * 2018-05-28 2018-10-26 广西路桥工程集团有限公司 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete
CN109577205A (en) * 2018-11-28 2019-04-05 中铁十四局集团第工程发展有限公司 A kind of 180m long-span Steel Arch casting method
CN109505250A (en) * 2018-12-07 2019-03-22 中铁局集团厦门建设工程有限公司 A kind of filling concrete method of steel tube arch rib
CN113279333A (en) * 2021-05-18 2021-08-20 中电建十一局工程有限公司 Construction method for filling concrete in steel pipe arch bridge
CN113718623A (en) * 2021-08-05 2021-11-30 贵州省公路工程集团有限公司 Hollow steel pipe concrete arch bridge structure

Also Published As

Publication number Publication date
CN100425785C (en) 2008-10-15

Similar Documents

Publication Publication Date Title
CN100425785C (en) Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring
CN101260644B (en) Method of manufacture for simply supported girder box
CN107700361B (en) A kind of dumb-bell shape grout sleeve and the method for carrying out assembly construction with the grout sleeve
CN1811070A (en) First-arch-then-beam concrete steel skeleton constructing process for through arch bridge with mooring post of steel pipe concrete
CN1916289A (en) Diamond shaped cradle in truss type
CN101982629A (en) Assembly-type self-compaction steel tube and concrete composite structure
CN101041980A (en) Lightweight plaster wall and integral pouring procedure thereof
CN108103965A (en) It is a kind of to reinforce with prestressing force Bailey beam and its construction method
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN105568868A (en) Suspension pouring construction method for box girder hanging basket
CN208151833U (en) A kind of construction of novel RC-masonry combination arch bridge
CN204311614U (en) The fabricated shear wall of prestressing force splicing
CN108867483A (en) A kind of prefabricated assembled FRP tendons material concrete side crashproof guardrail of half grout sleeve connection
CN201180254Y (en) Simply supported box girder
CN102877415B (en) Ultra-high-difference, ultra-long and ultra-large-tonnage prestress pipeline grouting method and herring-bone pipe bundle
CN204356896U (en) Based on the assembling Framed Structure with Special-Shaped Columns that 3D prints
CN207582275U (en) A kind of PBL puts more energy into type flat steel case concrete plate arch
CN202925459U (en) Fish ridge pipe bundle of super altitude difference, super long length, and super tonnage
CN201554155U (en) Steel pipe concrete column structure
CN108411801A (en) One kind reinforcing the old hollow slab bridge construction of single hole and construction method by real abdomen Bars In Poured Concrete Slab
CN208830150U (en) A kind of half grout sleeve connection prefabricated assembled FRP tendons material concrete center anticollision barrier
CN208830225U (en) A kind of half grout sleeve connection prefabricated assembling type reinforced concrete center anticollision barrier
CN209670223U (en) A kind of truss assembled stair
CN108797343A (en) A kind of half grout sleeve connection prefabricated assembled FRP tendons material concrete center anticollision barrier
CN204626986U (en) The mounting structure of steel pipe concrete pumping, jacking stop valve

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081015