CN108677967A - Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum - Google Patents

Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum Download PDF

Info

Publication number
CN108677967A
CN108677967A CN201810525858.8A CN201810525858A CN108677967A CN 108677967 A CN108677967 A CN 108677967A CN 201810525858 A CN201810525858 A CN 201810525858A CN 108677967 A CN108677967 A CN 108677967A
Authority
CN
China
Prior art keywords
floral tube
earth anchor
steps
fill stratum
steel floral
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810525858.8A
Other languages
Chinese (zh)
Inventor
房连生
戴连双
张洪运
刘跃
郑林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHINA XINXING CONSTRUCTION ENGINEERING Co.,Ltd.
Original Assignee
郑林
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 郑林 filed Critical 郑林
Priority to CN201810525858.8A priority Critical patent/CN108677967A/en
Publication of CN108677967A publication Critical patent/CN108677967A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Abstract

The present invention proposes perforated soil nail combination earth anchor method for protecting support in a kind of fill stratum, includes the following steps:S1, steel floral tube processing form the structure that can easily enter under the action of pneumatic hammer in fill stratum;S2, measurement simultaneously mark steel floral tube to enter the position of fill stratum, and the steel floral tube that S1 steps machine is placed in fill stratum side slope according to the position of label;Slurries are poured into S3, the steel floral tube being placed in fill stratum side slope to S2 steps;S4, progress earth anchor lacing wire are attached with the steel floral tube top machined in S1 steps;S5, the earth anchor being connect with steel floral tube in S4 steps is fixed, and carries out face layer supporting after the completion of fixed;Cost of labor is reduced while the construction period that perforated soil nail combination earth anchor method for protecting support can shorten in fill stratum proposed by the present invention.

Description

Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum
Technical field
The present invention relates to the realm of building construction, perforated soil nail combination earth anchor supporting side in a kind of fill stratum is particularly related to Method.
Background technology
Foundation pit is the heatable adobe sleeping platform excavated by substrate absolute altitude and basic plane size in basic engineering position;As China is built The fast development of industry, the building waste that construction generates are increasing.Urban building waste total amount is 2,100,000,000 to 2,800,000,000 at present Ton, the annual new building waste that generates is more than 300,000,000 tons, has accounted for 1/3 of municipal refuse total amount or more.Most of Solid construction rubbish Simple landfill disposal mode is taken, it is annual thus all to occupy 1.5 hundred million to 200,000,000 square metres of lands used.
In foundation pit construction, finding stratum subsurface slag the thickness of the layer is increasing.With the transition from the old to the new of building, The stabilization of fill stratum side slope also gradually becomes the key points and difficulties of foundation pit support construction.
It is in the prior art to pass to use the supporting of jumbolter pore-forming or pile-anchor retaining to fill stratum slope retaining;However it is such Mode one side operation difficulty is larger, while causing the operation cycle to increase operating cost is increased,
Invention content
Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum of present invention proposition, solves in the prior art right Long construction period and the high problem of construction cost in fill stratum Bracing Process.
The technical proposal of the invention is realized in this way:
Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum, includes the following steps:
S1, steel floral tube processing form the structure that can easily enter under the action of pneumatic hammer in fill stratum;
S2, measurement simultaneously mark steel floral tube to enter the position of fill stratum, and are machined S1 steps according to the position of label Steel floral tube be placed in fill stratum side slope;
Slurries are poured into S3, the steel floral tube being placed in fill stratum side slope to S2 steps;
S4, progress earth anchor lacing wire are attached with the steel floral tube top machined in S1 steps;
S5, the earth anchor being connect with steel floral tube in S4 steps is fixed, and carries out face layer supporting after the completion of fixed.
As further technical solution, further include:S6 steps:The horizontal component of earth anchor lacing wire is poured with ground It builds.
As further technical solution, S1 steps are:
Extravasating hole is bored on spray of molten steel tube wall;And penetrated through with circular hole at the top of floral tube, it is inserted into bar connecting head;And in floral tube bottom Make tapered pipe cap.
As further technical solution, S1 steps are:
It is spaced 300mm on spray of molten steel tube wall and bores extravasating hole;And a diameter of of the two-way firing perforation of cutting torch is used at the top of floral tube 20mm circular holes are inserted into the bar connecting head that a diameter of 16mm and length are 30cm;And make tapered pipe cap in floral tube bottom.
As further technical solution, S2 includes:
S21, the position for needing to be placed in steel floral tube is measured in fill stratum side slope, and above-mentioned position is labeled;
S22, according to the position marked in S21, steel floral tube is placed in by labeling position by pneumatic hammer successively.
As further technical solution, S3 steps are:
Slurries are pressed into steel floral tube by slip casting machine, are poured into fill stratum after so that slurries is passed through steel floral tube, steel floral tube fills It is 0.4~0.5 to starch the ratio of mud in the mud used.
As further technical solution, S3 steps are:
The slurries containing non-irrigated strong agent are pressed into steel floral tube by slip casting machine, fill stratum is poured into after so that slurries is passed through steel floral tube In, the ratio of mud in the mud that steel floral tube grouting uses is 0.4~0.5.
As further technical solution, S4 steps are:It will be welded at the top of earth anchor lacing wire and steel floral tube using electric welding machine.
As further technical solution, S4 steps are:
It will be connect with the reinforcement welding at the top of steel floral tube with the earth anchor lacing wire of a diameter of 16mm using electric welding machine;And it is welding After the completion extending to earth anchor lacing wire distal end, foundation pit 4m suitable for reading is outer to be connect with earth anchor stress point;Earth anchor lacing wire is along ramp portion and face Layer mesh sheet fitting, is bonded more than the earth anchor lacing wire point at the top of side slope with ground.
As further technical solution, S5 steps are:
The vertical pore-forming of earth anchor stress point injects cement mortar after being inserted into reinforcing bar;By at the top of reinforcing bar and ground after cement mortar condensation Anchor lacing wire is welded.
The construction method of technical solution of the present invention is reasonable, can ensure that construction procedure is simple in work progress, and reduces and apply The work period, due to needing manpower intervention in work progress, therefore, because the construction period shortened, and then cost of labor is reduced, with Jumbolter pore-forming supporting in the prior art or pile-anchor retaining method construction compares, the present invention can cost-effective 40% with On.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Obtain other attached drawings according to these attached drawings.
Fig. 1 is the flow chart that perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum of the present invention;
Fig. 2 is the flow that perforated soil nail combines another embodiment of earth anchor method for protecting support in a kind of fill stratum of the present invention Figure.
Fig. 3 combines the support after the completion of the construction of earth anchor method for protecting support for perforated soil nail in a kind of fill stratum through the invention The topology view of mechanism.
In figure:
1, steel floral tube;2, earth anchor reinforcing bar;3, fill stratum side slope.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art are obtained every other without creative efforts Embodiment shall fall within the protection scope of the present invention.
As shown in Figs. 1-3,1 soil nailing of steel floral tube combines earth anchor method for protecting support in a kind of fill stratum proposed by the present invention, including Following steps:
First, it carries out steel floral tube 1 to process, forms the structure that can easily enter under the action of pneumatic hammer in fill stratum;At this In invention, specifically, being to bore extravasating hole on 1 wall of steel floral tube;And penetrated through with circular hole at the top of floral tube, it is inserted into bar connecting head; And make tapered pipe cap in floral tube bottom;And in the present invention, convenient for safety and ensure under intensity and rational cost, preferably , it is spaced 300mm on 1 wall of steel floral tube and bores extravasating hole;And with a diameter of 20mm circles of the two-way firing perforation of cutting torch at the top of floral tube The bar connecting head that a diameter of 16mm and length are 30cm is inserted into hole;And tapered pipe cap is made in floral tube bottom, in this way in air Can be the entering in fill stratum of being more prone to of steel floral tube 1 under the action of hammer;
Secondly, the position for measuring and steel floral tube 1 being marked to enter fill stratum, and the steel that will be machined according to the position of label Floral tube 1 is placed in fill stratum side slope 3;In the present invention, due to needing more people to be carried out at the same time operation, can add in steel floral tube 1 It is measured while work and steel floral tube 1 is marked to enter the position of fill stratum, and the steel floral tube 1 machined is placed in fill stratum side slope In 3;
Specifically, during measuring and mark position, it is divided into the measurement in fill stratum side slope 3 and needs to be placed in steel floral tube 1 position, and above-mentioned position is labeled, certainly when measuring, according to the fill stratum side slope 3 of different gradient, required mark The position of note differs, and specifically determines according to actual conditions, the present invention no longer further limits this;According to the position of mark It sets, steel floral tube 1 is placed in by labeling position by pneumatic hammer successively;It needs to ensure that steel floral tube 1 is set during being placed in steel floral tube 1 The uniformity for entering length ensures whole balance to ensure to carry out subsequent operation.
After steel floral tube 1 is placed in fill stratum side slope 3, slurries are poured into steel floral tube 1;Specifically, will be starched by slip casting machine Hydraulic pressure enters in steel floral tube 1, is poured into fill stratum after so that slurries is passed through steel floral tube 1, and the water that steel floral tube 1 is in the milk in the mud used is grey Than being 0.4~0.5;Since slip casting machine is accompanied by the generation of pressure, can be after slurries rush across steel floral tube 1, preferably into Enter to fill stratum side slope 3, pass into so cementing in the slurries and fill stratum of fill stratum, improves fixed intensity;Certainly, To improve the early strength of floral tube anchoring, in the present invention, it is preferred to the slurries containing non-irrigated strong agent are pressed by steel by slip casting machine It in floral tube 1, is poured into fill stratum after so that slurries is passed through steel floral tube 1, the ratio of mud that steel floral tube 1 is in the milk in the mud used is 0.4 ~0.5.
Earth anchor lacing wire 2 is carried out to be attached with 1 top of steel floral tube machined;Particularly use electric welding machine by earth anchor Lacing wire 2 is welded with 1 top of steel floral tube;It and in the present invention, will be with the earth anchor lacing wire 2 of a diameter of 16mm and the spray of molten steel using electric welding machine The reinforcement welding connection at 1 top of pipe;And welding after the completion of make 2 distal end of earth anchor lacing wire extend to outside foundation pit 4m suitable for reading with earth anchor by Force connects;Earth anchor lacing wire 2 is bonded along ramp portion with face layer mesh sheet, is divided and ground face paste more than the earth anchor lacing wire 2 at the top of side slope It closes;As shown in figure 3, the connection of earth anchor lacing wire 2 is completed to be attached with 1 top of steel floral tube and ground respectively, to ensure earth anchor lacing wire 2 Fixed intensity, and need to ensure there is no barrier in 2 lower part of earth anchor lacing wire after the setup.
After the completion of earth anchor lacing wire 2 and steel floral tube 1 are fixed, need over the ground anchor be fixed, and carried out after the completion of fixed Face layer supporting, specifically, needing, in the vertical pore-forming of earth anchor stress point, to inject cement mortar after being inserted into reinforcing bar;After cement mortar condensation It will be welded with earth anchor lacing wire 2 at the top of reinforcing bar;And in the present invention, the vertical pore-forming of earth anchor stress point, depth of pore forming 1.50m, hole Diameter 150mm, earth anchor horizontal direction spacing is consistent with the horizontal direction spacing of floral tube, is inserted into a diameter of 20mm reinforcing bars and injects cement Slurry;It will be welded with earth anchor lacing wire 2 at the top of reinforcing bar after slurry condensation.
As shown in Fig. 2, preferably to be operated, the intensity after the completion of ensureing, in of the invention, preferably in earth anchor lacing wire After 2 fix, the horizontal component of earth anchor lacing wire 2 is poured with ground;Before pouring, need the slope surface of fill stratum side slope 3 most It is smooth that amount repaiies slope, and surfacing steel bar net is compiled after the completion of the construction of earth anchor lacing wire 2;Netting size, the present invention are adjusted according to fill stratum soil property In, netting size is less than 150mm × 150mm;In fill stratum depth bounds when jet face layer, should control surface thickness is 100mm;That is vertical slope surface injection from bottom to top, a jet thickness is preferably 40mm-70mm, second of gunite concrete thickness The mark position of 100mm.
Technical scheme of the present invention can effectively save cost and time, there is preferable economic benefit.It is better Illustrate, is further illustrated with specific example:
Foundation depth is 13.0m, and 3 layers of underground, 23 layers on the ground, pattern foundation pit supporting structure form uses soil nailed wall retaining structure.The base Zhou Changwei 800m are cheated, live dregs thickness is 2.5~3m after excavation.According to design scheme soil nailing under nature terrace 1.5m, water Flat spacing is 1.5m.Soil-nail parameter is 6m.It is 3200m to need pore-forming soil nailing linear meter(lin.m.) number, according to technical scheme of the present invention and set Pipe jumbolter hole creating technology compares, and technical scheme of the present invention comprehensive unit price is 50 yuan every meter, and casing jumbolter synthesis is single Valence is 90 yuan.152000 yuan of expense can be saved, the duration can be saved 4 days.
The above is merely preferred embodiments of the present invention, be not intended to limit the invention, it is all the present invention spirit and Within principle, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (10)

1. perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum, which is characterized in that include the following steps:
S1, steel floral tube processing form the structure that can easily enter under the action of pneumatic hammer in fill stratum;
S2, measurement simultaneously mark steel floral tube to enter the position of fill stratum, and the steel for machining S1 steps according to the position of label Floral tube is placed in fill stratum side slope;
Slurries are poured into S3, the steel floral tube being placed in fill stratum side slope to S2 steps;
S4, progress earth anchor lacing wire are attached with the steel floral tube top machined in S1 steps;
S5, the earth anchor being connect with steel floral tube in S4 steps is fixed, and carries out face layer supporting after the completion of fixed.
2. method as described in claim 1, which is characterized in that further include:S6 steps:By the horizontal component of earth anchor lacing wire and ground It is poured.
3. method as described in claim 1, which is characterized in that the S1 steps are:
Extravasating hole is bored on spray of molten steel tube wall;And penetrated through with circular hole at the top of floral tube, it is inserted into bar connecting head;And it is made in floral tube bottom Tapered pipe cap.
4. method as claimed in claim 3, which is characterized in that the S1 steps are:
It is spaced 300mm on spray of molten steel tube wall and bores extravasating hole;And with a diameter of 20mm circles of the two-way firing perforation of cutting torch at the top of floral tube The bar connecting head that a diameter of 16mm and length are 30cm is inserted into hole;And make tapered pipe cap in floral tube bottom.
5. method as described in claim 1, which is characterized in that the S2 includes:
S21, the position for needing to be placed in steel floral tube is measured in fill stratum side slope, and above-mentioned position is labeled;
S22, according to the position marked in S21, steel floral tube is placed in by labeling position by pneumatic hammer successively.
6. method as described in claim 1, which is characterized in that the S3 steps are:
Slurries are pressed into steel floral tube by slip casting machine, are poured into fill stratum after so that slurries is passed through steel floral tube, steel floral tube grouting makes The ratio of mud in mud is 0.4~0.5.
7. method as claimed in claim 6, which is characterized in that the S3 steps are:
The slurries containing non-irrigated strong agent are pressed into steel floral tube by slip casting machine, are poured into fill stratum after so that slurries is passed through steel floral tube, The ratio of mud in the mud that steel floral tube grouting uses is 0.4~0.5.
8. method as described in claim 1, which is characterized in that the S4 steps are:Using electric welding machine by earth anchor lacing wire and the spray of molten steel It welds in tube top portion.
9. method as claimed in claim 8, which is characterized in that the S4 steps are:
It will be connect with the reinforcement welding at the top of steel floral tube with the earth anchor lacing wire of a diameter of 16mm using electric welding machine;And it is completed in welding After so that earth anchor lacing wire distal end is extended to foundation pit 4m suitable for reading is outer to be connect with earth anchor stress point;Earth anchor lacing wire is along ramp portion and face layer net Piece is bonded, and is bonded with ground more than the earth anchor lacing wire point at the top of side slope.
10. method as described in claim 1, which is characterized in that the S5 steps are:
The vertical pore-forming of earth anchor stress point injects cement mortar after being inserted into reinforcing bar;It will be drawn with earth anchor at the top of reinforcing bar after cement mortar condensation Muscle welds.
CN201810525858.8A 2018-05-28 2018-05-28 Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum Pending CN108677967A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810525858.8A CN108677967A (en) 2018-05-28 2018-05-28 Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810525858.8A CN108677967A (en) 2018-05-28 2018-05-28 Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum

Publications (1)

Publication Number Publication Date
CN108677967A true CN108677967A (en) 2018-10-19

Family

ID=63808483

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810525858.8A Pending CN108677967A (en) 2018-05-28 2018-05-28 Perforated soil nail combines earth anchor method for protecting support in a kind of fill stratum

Country Status (1)

Country Link
CN (1) CN108677967A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116028A (en) * 2011-01-13 2011-07-06 中建四局第三建筑工程有限公司 Method and structure for excavating soil in core tube region based on raft pile supporting
CN202787275U (en) * 2012-09-19 2013-03-13 浙江通达建设集团有限公司 Tubular soil nailing wall of novel pneumatic impact anchor
KR20130113563A (en) * 2012-04-06 2013-10-16 주식회사 삼우기초기술 Compression and distribution type permanent anchor being able to replace the tension member of the free length range
CN203383217U (en) * 2013-07-19 2014-01-08 北京市勘察设计研究院有限公司 Prestressed ground anchor device for foundation pit supporting
CN103790168A (en) * 2014-01-17 2014-05-14 洛阳广鑫建设集团有限公司 Application method of soil nailing wall in deep foundation pit supporting
CN206408614U (en) * 2017-01-10 2017-08-15 天津市森源建筑有限公司 A kind of floral tube soil nailing

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116028A (en) * 2011-01-13 2011-07-06 中建四局第三建筑工程有限公司 Method and structure for excavating soil in core tube region based on raft pile supporting
KR20130113563A (en) * 2012-04-06 2013-10-16 주식회사 삼우기초기술 Compression and distribution type permanent anchor being able to replace the tension member of the free length range
CN202787275U (en) * 2012-09-19 2013-03-13 浙江通达建设集团有限公司 Tubular soil nailing wall of novel pneumatic impact anchor
CN203383217U (en) * 2013-07-19 2014-01-08 北京市勘察设计研究院有限公司 Prestressed ground anchor device for foundation pit supporting
CN103790168A (en) * 2014-01-17 2014-05-14 洛阳广鑫建设集团有限公司 Application method of soil nailing wall in deep foundation pit supporting
CN206408614U (en) * 2017-01-10 2017-08-15 天津市森源建筑有限公司 A kind of floral tube soil nailing

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨静: "西安浐灞文化中心深基坑土钉墙(花管)支护施工", 《山西建筑》 *
王立祥: "钢花管土钉支护在基坑事故处理中的应用", 《四川建材》 *

Similar Documents

Publication Publication Date Title
CN101644160B (en) High ground stress soft rock stress-relief construction method
CN101736760B (en) Construction method of prestressed anti-floating anchor rod
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN202509532U (en) Multi-rib tension type anti-floating anchor
CN109611102B (en) Construction method for cold excavation underpass overpass
CN100462507C (en) Construction method for pulling-resistant and pressure-resistant slip casting pipe pile
CN103603369B (en) Construction method of anchor pile counterfort retaining wall
CN110821513B (en) Construction method for performing advanced grouting and supporting on tunnel local collapse
CN106498943B (en) Disposable high-pressure rotary-spray type enlarged footing Prestressed Soil anchor pole construction method
CN109610470A (en) A kind of base pit stand construction using three axes agitating pile machine
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN202509533U (en) Single reinforcement pulling force type anti-floating anchor rod
CN107165435B (en) A kind of reinforced construction method having crack interior wall
CN101333815B (en) Concrete anchor rod and its construction method
CN103498425A (en) Full-dismounting combination type multifunctional bracket supporting structure and construction method thereof
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN1067453C (en) Supporting and protecting method for base pit, side slope, flat anchor and spray net
CN105442605A (en) Construction method for drawing out prestress high concrete (PHC) pile and reusing PHC pile for retaining in deep excavation
CN110273441A (en) A kind of old factory building foundation uses the structural strengthening and construction method of newly-increased steel-pipe pile and newly-increased concrete bearing platform
CN109457694A (en) A kind of variable diameters steel reinforcement cage enlarged footing anti-floating or pressure bearing pile and construction in conjunction with mixing pile or rotary churning pile
CN201395794Y (en) Foundation ditch with concealed columns and soil-nailing support
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN101550693B (en) Method for reinforcing base with bored pile in the underground structure of high groundwater level

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20200602

Address after: 100000 Beijing City, Xicheng District Jing Yong 3

Applicant after: CHINA XINXING CONSTRUCTION ENGINEERING Co.,Ltd.

Address before: 100079 Beijing City, Fengtai District, Shun eight No. 9

Applicant before: Zheng Lin

TA01 Transfer of patent application right
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181019

WD01 Invention patent application deemed withdrawn after publication