CN108661063A - A kind of sand foundation base pit dewatering constructing structure and construction method - Google Patents
A kind of sand foundation base pit dewatering constructing structure and construction method Download PDFInfo
- Publication number
- CN108661063A CN108661063A CN201810636362.8A CN201810636362A CN108661063A CN 108661063 A CN108661063 A CN 108661063A CN 201810636362 A CN201810636362 A CN 201810636362A CN 108661063 A CN108661063 A CN 108661063A
- Authority
- CN
- China
- Prior art keywords
- pit
- wall
- dewatering
- locally deep
- strainer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004576 sand Substances 0.000 title claims abstract description 39
- 238000010276 construction Methods 0.000 title claims abstract description 36
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 28
- 238000009412 basement excavation Methods 0.000 claims abstract description 6
- 238000007789 sealing Methods 0.000 claims description 19
- 238000012946 outsourcing Methods 0.000 claims description 6
- 238000009434 installation Methods 0.000 claims description 3
- 238000001556 precipitation Methods 0.000 abstract description 5
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 16
- 230000000694 effects Effects 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 230000013011 mating Effects 0.000 description 5
- 238000000034 method Methods 0.000 description 4
- 102000002322 Egg Proteins Human genes 0.000 description 2
- 108010000912 Egg Proteins Proteins 0.000 description 2
- 230000009977 dual effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000000945 filler Substances 0.000 description 2
- 238000002386 leaching Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 239000000178 monomer Substances 0.000 description 2
- 210000004681 ovum Anatomy 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
- Filtration Of Liquid (AREA)
Abstract
The present invention provides a kind of sand foundation base pit dewatering constructing structures, including:The casing being set in foundation pit locally deep pit is provided with several through-holes on the tube wall of described sleeve pipe;And it is set to the drainage layer between described sleeve pipe outer wall and the locally deep pit inner wall;And it is set to foundation pit locally deep pit bottom, the water pump in described sleeve pipe;And it is set to the filter pipe in described sleeve pipe, described filter pipe one end is connect with the water pump, and the other end stretches out the foundation pit locally deep pit;Additionally provide a kind of construction method carrying out sand foundation dewatering construction using the constructing structure, including excavation of foundation pit, locally deep pit excavates, arrange dewatering construction structure, dewatering operation, well head closure pour bottom plate, and the beneficial effects of the invention are as follows the locally deep pit precipitation for being appropriate for sand foundation, construction efficiency is high, and construction safety is easy.
Description
Technical field
The invention belongs to building engineering fields, construct more particularly, to a kind of deeper region base pit dewatering in sand foundation part
Structure and construction method.
Background technology
The area of building construction underground structure continues to increase, and depth is constantly deepened, and construction and excavation quantities is big.Sand refers to
Soil particle forms the higher soil of sand grains content, often with there is a higher-strength under dead weight, but when carrying out excavation work
When industry, shock loads effect is generated, it is possible to create sand liquefaction largely shakes notch distortion, loses bearing capacity, causes to cave in.
Moreover, because sand quality is loosely, jumbo is difficult to enter, and materials dumping is difficult.
Therefore, it is excavated on sand foundation, has and be easy landslide, the technologies such as materials dumping is difficult, and construction efficiency is low
Difficult point.
In the deeper region in the foundation pits such as elevator and catch pit part than periphery foundation pit depth, so the meeting when excavating locally deep pit
Encounter underground water, need to carry out precipitation processing, and due to the bulk characteristics of sand, be susceptible to when precipitation processing landslide and
Drift sand influences working efficiency.
Invention content
The problem to be solved in the present invention be to provide it is a kind of suitable for sand foundation base pit dewatering construction constructing structure and apply
Work method is especially suitable for carrying out the locally deep pit precipitation of sand foundation, and construction efficiency is high, and construction safety is easy.
In order to solve the above technical problems, the technical solution adopted by the present invention is:One kind being suitable for sand foundation base pit dewatering
The constructing structure of construction, including:
The casing being set in foundation pit locally deep pit is provided with several through-holes on the tube wall of described sleeve pipe;And
The drainage layer being set between described sleeve pipe outer wall and the locally deep pit inner wall;And
It is set to foundation pit locally deep pit bottom, the water pump in described sleeve pipe;And
The filter pipe being set in described sleeve pipe, described filter pipe one end are connect with the water pump, described in other end stretching
Foundation pit locally deep pit.
Preferably, further include ring flange, the ring flange is arranged at the filter pipe and stretches out the foundation pit part
One end of dell.Setting ring flange is to block well head in order to be matched with blind flange after the completion of dewatering construction and use, using flange
Closure shaft collar is simpler, and sealing effect is good, and connection reliability is high.
It is further used as preferably, annular groove is provided on the ring flange, the groove, which is arranged for installation, to be stopped
Water cushion circle.With the above arrangement, sealing washer is arranged in the mating surface of ring flange and blind flange, well head envelope is further increased
The leakproofness of bridging structure.
The purpose that drainage layer is arranged avoids extracting the mud of underground together with underground water out when groundwater abstraction, avoid because
This and may caused by drift sand or the prominent unexpected situation for the influences construction such as gushing.
There are many forms that drainage layer is arranged, depending on the specific situation of construction,
Preferably, to adapt to sand foundation the characteristics of, the drainage layer include be set to described sleeve pipe outer wall outer
Wall strainer, and the cobble drainage layer that is set between described sleeve pipe outer wall and the locally deep pit inner wall.
It is further used as preferably further including the inner wall strainer for being set to described sleeve pipe inner wall;The mesh of the inner wall strainer
Mesh number of the number more than the outer wall strainer.It is arranged by double-layer leaching net, further avoids water pump by sand together with underground water one
It rises and pumps out.
It is further used as preferably, to adapt to the characteristic of sand foundation, the form of strainer uses plain net.Metal can be used
Net or nonmetallic net preferably select type easy to process simple in structure.
The present invention also provides a kind of sand foundation base pit dewatering construction method using the above constructing structure, feature exists
In including the following steps:
S1. use caisson excavation pit to marking depth;Preferably, the caisson used is the combination of multi-layer compact caisson,
Single Large Caisson is replaced using multi-layer compact caisson, the weight of caisson monomer can be reduced, can also reduce its mating fortune
The weight of defeated lifting machine is suitable for sand foundation construction, improves construction efficiency;
S2. locally deep pit is excavated;
S3., the casing of the eyelet of outsourcing strainer is set in locally deep pit, ovum is filled between casing and dell crater wall
Stone;Preferably, the strainer of outsourcing strainer mesh number is more than in inside pipe casing setting mesh number.By the way that dual strainer is arranged, into one
Step avoids water pump and pumps out sand together with underground water.
S4. water pump is set in locally deep pit bottom;
S5., filter pipe is set, and one end of filter pipe is connect with water pump, and the other end stretches out locally deep pit;
S6. dewatering operation is carried out;
S7. water pump is taken out;
S8. base plate of foundation pit, sealing wellhead are poured.
Preferably, filter pipe top mounting flange, in step S8, Slab Waterproof Construction, waterproof is rolled up to ring flange
Bottom, and carry out waterproof reinforced.Before underplate concrete pours, with flange disk cover by wellhead sealing, ring flange and flange disk cover
Between add sealing washer, play sealing effect.Then underplate concrete is poured, the local dewatering of the dells such as elevator foundation pit is completed
Operation.
The invention has the advantages and positive effects that:
1, it can ensure stability of slope, the stake stabilization in foundation pit, prevent drift sand and foundation pit collapse.
2, dewatering effect is good, accelerates construction progress, and ensures construction quality.
Description of the drawings
Fig. 1 be one embodiment of the invention dewatering construction in status diagram
Fig. 2 is the dewatering construction completion status schematic diagram of one embodiment of the invention
Fig. 3 is the strainer partial schematic diagram of one embodiment of the invention
In figure:
1, casing 2, filter pipe 3, ring flange
4, outer wall strainer 5, inner wall strainer 6, water pump
7, cobble drainage layer 8, blind flange 9, sealing washer
10, waterproof layer 11, pour bottom plate
Specific implementation mode
As Fig. 1, one embodiment of the invention dewatering construction in shown in status diagram, one embodiment of the invention includes:
The casing 1 being set in foundation pit locally deep pit is provided with several through-holes on the tube wall of casing 1;And
It is set to foundation pit locally deep pit bottom, the water pump in casing;And
The filter pipe being set in casing, filter pipe one end are connect with water pump, and the other end stretches out foundation pit locally deep pit;And
The cobble drainage layer 7 being set between 1 outer wall of casing and locally deep pit inner wall;According to sand in the present embodiment
The characteristics of base, in other embodiments of the invention, can select other using cobble as drainage layer filler according to actual demand
The drainage layer filler of type.
Preferably, double-layer leaching net is used in the present embodiment, is surrounded by outer wall strainer 4 on 1 outer wall of casing, inner wall is surrounded by
Inner wall strainer 5.The mesh number of inner wall strainer 5 is more than the mesh number of outer wall strainer 4, to achieve the effect that further to filter.
It in other embodiments of the invention, also can be individually only with outer wall strainer 4 or inner wall strainer 5.
In the present embodiment, as shown in figure 3, to adapt to the characteristic of sand foundation, the form of strainer uses plain net.
In the present embodiment, preferably, further include ring flange 3, ring flange is arranged at filter pipe 2 and stretches out foundation pit office
One end of portion's dell.Setting ring flange 3 is to block well head in order to be matched with blind flange 8 after the completion of dewatering construction and use, use
Flange closure shaft collar is simpler, and sealing effect is good, and connection reliability is high.
It is further used as preferably, annular groove is provided on ring flange 3, groove is arranged for installation sealing washer 9.
With the above arrangement, sealing washer 9 can be arranged in the mating surface of ring flange 3 and blind flange 6, well head envelope is further increased
The leakproofness of bridging structure.
Such as Fig. 2, the dewatering construction completion status schematic diagram of one embodiment of the invention, one embodiment of the invention precipitation is completed
Afterwards, well head, which blocks, completes.
Water pump 6 is withdrawn from from well;
Underplate concrete 11 is poured to 3 bottom of ring flange, and pouring has waterproof layer 10 between bottom plate 11 and ring flange 3;
Coordinated using blind flange 7 and ring flange 3, carries out well head closure, set in mating surface of the ring flange 3 with blind flange 6
Set sealing washer 9.
One embodiment of sand foundation base pit dewatering construction method provided by the present invention:
S1. use caisson excavation pit to marking depth;In the present embodiment, preferably, the caisson used is that multilayer is small
The combination of type caisson replaces single Large Caisson using multi-layer compact caisson, can reduce the weight of caisson monomer, can also subtract
The weight of its small mating transporting and hoisting machinery is suitable for sand foundation construction, improves construction efficiency;
S2. locally deep pit is excavated;
S3., the casing of the eyelet of outsourcing strainer is set in locally deep pit, ovum is filled between casing and dell crater wall
Stone;In the present embodiment, preferably, the strainer of outsourcing strainer mesh number is more than in inside pipe casing setting mesh number.Pass through setting
Dual strainer further avoids water pump and pumps out sand together with underground water.In other embodiments of the invention, also may be used
It is arranged using single layer strainer;
S4. water pump is set in locally deep pit bottom;
S5., filter pipe is set, and one end of filter pipe is connect with water pump, and the other end stretches out locally deep pit;
S6. dewatering operation is carried out;
S7. water pump is taken out;
S8. base plate of foundation pit, sealing wellhead are poured.
In the present embodiment, preferably, filter pipe top mounting flange, in step S8, Slab Waterproof Construction
Waterproof is rolled up to flange pan bottom, and carries out waterproof reinforced.Before underplate concrete pours, with flange disk cover by wellhead sealing, method
Sealing washer is added between blue disk and flange disk cover, plays sealing effect.Then underplate concrete is poured, elevator foundation pit etc. is completed
The local dewatering operation of dell.In other embodiments of the invention, other wellhead sealing methods can also be used.
The embodiments of the present invention have been described in detail above, content is only the preferred embodiment of the present invention, no
It can be believed to be used to limit the scope of the invention.Any changes and modifications in accordance with the scope of the present application,
It should still fall within the scope of the patent of the present invention.
Claims (10)
1. a kind of sand foundation base pit dewatering constructing structure, which is characterized in that
Including:
The casing being set in foundation pit locally deep pit is provided with several through-holes on the tube wall of described sleeve pipe;And
The drainage layer being set between described sleeve pipe outer wall and the locally deep pit inner wall;And
It is set to foundation pit locally deep pit bottom, the water pump in described sleeve pipe;And
The filter pipe being set in described sleeve pipe, described filter pipe one end are connect with the water pump, and the other end stretches out the foundation pit
Locally deep pit.
2. a kind of sand foundation base pit dewatering constructing structure according to claim 1, it is characterised in that:
Further include ring flange, the ring flange is arranged at one end that the filter pipe stretches out the foundation pit locally deep pit.
3. a kind of sand foundation base pit dewatering constructing structure according to claim 2, it is characterised in that:
Annular groove is provided on the ring flange, the groove is arranged for installation sealing washer.
4. a kind of sand foundation base pit dewatering constructing structure as claimed in any of claims 1 to 3, feature exist
In:
The drainage layer include be set to the outer wall strainer of described sleeve pipe outer wall, and
The cobble drainage layer being set between described sleeve pipe outer wall and the locally deep pit inner wall.
5. a kind of sand foundation base pit dewatering constructing structure according to claim 4, it is characterised in that:
It further include the inner wall strainer for being set to described sleeve pipe inner wall;
The mesh number of the inner wall strainer is more than the mesh number of the outer wall strainer.
6. a kind of sand foundation base pit dewatering constructing structure according to claims 1 or 2 or 3 or 5, it is characterised in that:
The type of weave of the strainer is plain net.
7. a kind of sand foundation base pit dewatering construction method, which is characterized in that include the following steps:
S1. use caisson excavation pit to marking depth;
S2. locally deep pit is excavated;
S3., the casing of the eyelet of outsourcing strainer is set in locally deep pit, cobble is filled between casing and dell crater wall;
S4. water pump is set in locally deep pit bottom;
S5., filter pipe is set, and one end of filter pipe is connect with water pump, and the other end stretches out locally deep pit;
S6. dewatering operation is carried out;
S7. water pump is taken out;
S8. base plate of foundation pit, sealing wellhead are poured.
8. a kind of sand foundation base pit dewatering construction method according to claim 7, it is characterised in that:Execute step S3
When, it is more than the strainer of outsourcing strainer mesh number in inside pipe casing setting mesh number.
9. a kind of sand foundation base pit dewatering construction method according to claim 7, it is characterised in that:Execute step S1
When, the caisson used is the combination of multi-layer compact caisson.
10. a kind of sand foundation base pit dewatering construction method according to any one of claim 7 to 9, feature exist
In:
When executing step S5, one end mounting flange of locally deep pit is stretched out in filter pipe;
When executing step S8, is coordinated using blind flange and ring flange, sealing washer is added between ring flange and blind flange.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810636362.8A CN108661063A (en) | 2018-06-20 | 2018-06-20 | A kind of sand foundation base pit dewatering constructing structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810636362.8A CN108661063A (en) | 2018-06-20 | 2018-06-20 | A kind of sand foundation base pit dewatering constructing structure and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108661063A true CN108661063A (en) | 2018-10-16 |
Family
ID=63772182
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810636362.8A Pending CN108661063A (en) | 2018-06-20 | 2018-06-20 | A kind of sand foundation base pit dewatering constructing structure and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108661063A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111501767A (en) * | 2020-03-24 | 2020-08-07 | 中铁隧道局集团建设有限公司 | Foundation pit base surface hydration-free construction structure under sandy cobble and mudstone geological conditions |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5813819A (en) * | 1981-07-19 | 1983-01-26 | Kato Seisakusho:Kk | Lowering work for ground water level |
CN103556644A (en) * | 2013-10-23 | 2014-02-05 | 中天建设集团有限公司 | Basement bottom plate dewatering well mouth plugging casing and construction method |
CN104179189A (en) * | 2014-08-29 | 2014-12-03 | 上海建工七建集团有限公司 | Dewatering and drainage structure of foundation pit deep drop area and construction method thereof |
CN208545764U (en) * | 2018-06-20 | 2019-02-26 | 中冶天工集团天津有限公司 | A kind of sand foundation base pit dewatering constructing structure |
-
2018
- 2018-06-20 CN CN201810636362.8A patent/CN108661063A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5813819A (en) * | 1981-07-19 | 1983-01-26 | Kato Seisakusho:Kk | Lowering work for ground water level |
CN103556644A (en) * | 2013-10-23 | 2014-02-05 | 中天建设集团有限公司 | Basement bottom plate dewatering well mouth plugging casing and construction method |
CN104179189A (en) * | 2014-08-29 | 2014-12-03 | 上海建工七建集团有限公司 | Dewatering and drainage structure of foundation pit deep drop area and construction method thereof |
CN208545764U (en) * | 2018-06-20 | 2019-02-26 | 中冶天工集团天津有限公司 | A kind of sand foundation base pit dewatering constructing structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111501767A (en) * | 2020-03-24 | 2020-08-07 | 中铁隧道局集团建设有限公司 | Foundation pit base surface hydration-free construction structure under sandy cobble and mudstone geological conditions |
CN111501767B (en) * | 2020-03-24 | 2021-10-26 | 中铁隧道局集团建设有限公司 | Foundation pit base surface hydration-free construction structure under sandy cobble and mudstone geological conditions |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
CN107447770A (en) | A kind of big open caisson of superelevation and construction method | |
CN103882858A (en) | Construction method of micro-piles with diameter of 300 mm | |
CN110735600B (en) | Mechanical pore-forming pile construction process for karst geology | |
CN106638640A (en) | Modular coffer construction method for concrete without subsealing in the geologic condition of stratum | |
CN103967028A (en) | Immersed tube drainage structure and method for handling suddenly-produced foundation pit water bursting and fountains through immersed tube drainage structure | |
CN107227961A (en) | Heavy caliber dewatering well construction method in metro built by mining method hole | |
CN101024950A (en) | Salinized-soil-strong tamping and water-discharging pile foundation processing method | |
CN104532957A (en) | Inversed construction method for adding basement in existing building | |
CN104818713A (en) | Profile steel cement soil pile construction method adaptive to various stratums | |
CN110080169A (en) | A kind of construction method reclaimed fields from the sea utilized based on basement | |
CN106480891B (en) | A kind of shaft construction method | |
CN208545764U (en) | A kind of sand foundation base pit dewatering constructing structure | |
CN107059904A (en) | A kind of underground pipe gallery ponding well excavation method | |
CN212641468U (en) | Pit-in-pit rapid construction structure | |
CN105386462A (en) | Integral construction type small and medium-sized basement and construction method thereof | |
CN108661063A (en) | A kind of sand foundation base pit dewatering constructing structure and construction method | |
JP4114944B2 (en) | Ground improvement method | |
CN105113492A (en) | Construction method of composite pile applicable to cohesive soil, sandy soil and muddy soil foundations | |
CN111764396A (en) | Construction method for water-rich stratum pit-in-pit | |
CN102677657A (en) | Construction method of row cast thin-walled concrete compound pile wall and special hole forming device thereof | |
CN207004431U (en) | Soft soil foundation exciting drilling device | |
CN108457279A (en) | A kind of foundation pit enclosure structure cast-in-situ bored pile collapse hole in-situ treatment method | |
CN105544551B (en) | A kind of super-long filling pile quickly transfers the construction method of steel reinforcement cage | |
CN107476293A (en) | A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181016 |