CN108643206A - Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method - Google Patents

Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method Download PDF

Info

Publication number
CN108643206A
CN108643206A CN201810594553.2A CN201810594553A CN108643206A CN 108643206 A CN108643206 A CN 108643206A CN 201810594553 A CN201810594553 A CN 201810594553A CN 108643206 A CN108643206 A CN 108643206A
Authority
CN
China
Prior art keywords
steel
plate
lifted trunk
bottom plate
steel lifted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810594553.2A
Other languages
Chinese (zh)
Inventor
张坤球
张勇
何崇雄
陈家海
韦权
李回颜
谢易
韦大川
赵亚飞
陆保佐
覃向来
胡习文
覃悠泰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road Construction Engineering Group Co Ltd
Original Assignee
Guangxi Road Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road Construction Engineering Group Co Ltd filed Critical Guangxi Road Construction Engineering Group Co Ltd
Priority to CN201810594553.2A priority Critical patent/CN108643206A/en
Publication of CN108643206A publication Critical patent/CN108643206A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/02Restraining of open water
    • E02D19/04Restraining of open water by coffer-dams, e.g. made of sheet piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to the technical field of steel lifted trunk, specially one kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Including steel lifted trunk bottom plate, support structure, bush structure and steel lifted trunk cage plate, steel lifted trunk bottom plate is installed at the top of the support structure, the steel lifted trunk bottom plate is connect by steel lifted trunk cage plate with steel pile casting;The support structure lower part is equipped with bush structure, and the bush structure bottom is equipped with sleeve cage plate, and the sleeve cage plate is placed on steel pile casting;The construction method carried out using this device.The present invention exempts the bottom concrete of steel lifted trunk, saves more concrete, realizes considerable economic benefit, greatly shorten the construction period, water-stagnating effect is good, and structure is safe and reliable, while simple in structure, easy construction.

Description

Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method
Technical field
The present invention relates to a kind of technical field of steel lifted trunk, specially one kind exempting from bottom concrete steel lifted trunk bottom plate and steel shield Cylinder attachment device and its construction method.
Background technology
In recent years, flourishing with China's expressway construction, it is super-huge across great river, great river, bay, straits etc. Bridge continues to bring out, and the construction of a large amount of deep-water bridges is necessarily put forward higher requirements to the construction of bridge foundation.Territory the Liao Dynasty of China Wealthy, the hydrology, geology, weather conditions are complicated and changeable, and the method and complexity of foundation construction are had nothing in common with each other on bridge water, base waterborne Plinth is constructed because sightless unknown factor is more, parameter is big, the bridge foundation construction difficulty especially under Complex Hydrogeological Conditions It is larger, have become the most critical technology in large bridge construction.
Steel lifted trunk is suitable for high-rise pile cap construction, and the dry operating environment of bearing platform construction is provided by side plate and bottom plate, is reached This target is mainly by realizing following key technology:(1)The steel lifted trunk bottom plate and side plate knot that design stress is met the requirements Structure;(2)Sealing problem between siding and between siding and bottom plate;(3)The connectivity problem between steel lifted trunk bottom plate and steel pile casting is solved, So that steel lifted trunk bears vertical force(The vertical effect of water buoyancy and cushion cap concrete liquid-plastic state)When it is in a safe condition, and Ne-leakage phenomenon between steel pile casting and steel lifted trunk bottom plate.
For the structure design of first problem, there is very ripe design method and economic design standard;It is right In Second Problem, weld seam full qualification can realize good water-stagnating effect between plate by rubber fastening band;For third Problem is generally realized using the modes such as welding shear connector on bottom concrete and steel pile casting.
It is excessive using general method back cover concrete usage amount for above-mentioned third problem, using exempting from back cover concrete method The construction setting in some steel lifted trunks is influenced again.
Through retrieving the Chinese patent literature in relation to steel lifted trunk, it is as follows now to enumerate some:
1, Chinese patent<Application number>201720746402.5<Utility model title>A kind of steel lifted trunk of integral hoisting<Abstract> The utility model discloses a kind of steel lifted trunks of integral hoisting, belong to beam substructure construction field, including floor structure, wall body Structure, outrigger, lateral stability support and shaped steel sunpender, floor structure and walled structure are assembled into bottom surface and four walls of steel lifted trunk, Several lateral stabilities support between horizontal, vertical bridge is connected to the walled structure of four walls to right-angled intersection, several outriggers edge cross, Vertical bridge is set to steel lifted trunk top surface to right-angled intersection, and outrigger end is welded with walled structure longeron, is equipped with and hangs at outrigger right-angled intersection Ear, lateral stability support construction are located at below outrigger structure, and several shaped steel sunpenders are connected between floor structure and outrigger.This A kind of steel lifted trunk of integral hoisting of utility model reduces difficulty of construction and work consumption, shortens the construction period, while installation accuracy is more It is easy to control.
2, Chinese patent<Application number>201611051443.9<Denomination of invention>A kind of assembling type steel hanging box<Abstract>This hair Bright to be related to a kind of assembling type steel hanging box, including side wall and bottom plate, the side wall and bottom plate are equipped with structural beams and panel;The side wall Including polylith unit side plate, unit side plate that the unit side plate is provided with the structural beams, that panel is rectangle, the unit While equipped with cell board connection, the adjacent unit side plate connects side by the cell board and interconnects assembling the four of side plate At side wall;The periphery of the bottom plate is equipped with bottom plate and connects side, the bottom on cell board the connection side and the bottom plate of the unit side plate Plate connects side connection.
3, Chinese patent<Application number>201420159102.3<Utility model title>A kind of assembling type steel hanging box<Abstract> The utility model large steel suspension box, including bottom plate and side plate, the side plate are divided into inside panel and exterior panel, the inside panel and outer Sub-truss is equipped between siding, the sub-truss includes the identical vertical horse of multiple spacing.By traditional large steel suspension Annular truss inside and outside case between siding is changed to vertical chip truss, can at the scene be assembled with the good vertical horse of pre-production When horse is inserted into one by one between inside and outside siding, then be fixedly connected with one.
4, Chinese patent<Application number>201510085637.X<Denomination of invention>A kind of steel lifted trunk and positioning construction method<It plucks It wants>The present invention relates to technical field of bridge construction more particularly to a kind of steel lifted trunks and positioning construction method.The steel lifted trunk includes hanging Bottom plate, suspension box side sheet, guide pipe and limit bracket;The suspension box side sheet is vertically installed in the edge of hanging box bottom plate, and with hang Bottom plate surrounds the babinet of an open top;There is the mounting hole set for wearing pile foundation steel pile casting on the hanging box bottom plate;It is described Limit bracket is set to the edge of mounting hole;The guide pipe is set on pile foundation steel pile casting and is close to suspension box side sheet, is used for Guide babinet along the axial sinking of pile foundation steel pile casting.
From document disclosed above it is found that being not very convenient, bottom plate and side in the installation of steel lifted trunk overall structure and dismounting Seal shortcoming between plate, be easy to cause leak;The concrete of loss is also more;It, need to be to existing in order to overcome these defects The technology of steel lifted trunk is innovated.
Invention content
The present invention in view of the drawbacks of the prior art, and provides one kind and exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting company Connection device and its construction method greatly reduce steel lifted trunk concrete amount, and not using the steel lifted trunk bottom plate of no bottom concrete The arrangement of cushion cap reinforcing bar is influenced, working procedure is reduced, accelerates construction speed, generate larger economic benefit;And solves it Stress problem and provide construction method.
In order to realize the purpose of aforementioned present invention, adopt the following technical scheme that:
One kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, including steel lifted trunk bottom plate, support structure, sleeve structure Make with steel lifted trunk cage plate, steel lifted trunk bottom plate is installed at the top of the support structure, the steel lifted trunk bottom plate by steel lifted trunk cage plate with Steel pile casting connects;The support structure lower part is equipped with bush structure, and the bush structure bottom is equipped with sleeve cage plate, the set Jacket casing sleeve-board is in steel pile casting, and the steel lifted trunk bottom plate surrounding installs steel lifted trunk side plate.
The bush structure includes sleeve body and set tube end plate, the sleeve body bottom installation sleeve bottom plate, the sleeve Bottom plate is equipped with sleeve cage plate.
The set tube end plate is equipped with sleeve bottom plate reinforcing rib, set tube end plate annular ribbed stiffener and set tube end plate outer ring and adds Strength rib, the sleeve bottom plate reinforcing rib are installed on set tube end plate bottom surface, and both ends correspond to respectively puts more energy into set tube end plate annular Rib is connected with set tube end plate outer ring ribbed stiffener.
The sleeve body takes steel plate to roll.
It is equipped with outer triangle stiffener between the sleeve body bottom outer wall and set tube end plate.
It is equipped with stiffener between the sleeve body top exterior walls and set tube end plate.
Interior triangular stiffener is installed between the sleeve body bottom interior wall and set tube end plate.
The support structure includes circular beam, cant beam, crossbeam and longeron, and the circular beam is equipped with by circumference equal distribution Pipe nipple beam, crossbeam is installed positioned at longitudinal pipe nipple beam, longeron is installed positioned at lateral pipe nipple beam;And the pipe nipple beam two Cant beam is equipped between two;The longeron, crossbeam are mounted on several stiff girders.
Its construction method of above-mentioned apparatus includes the following steps:
(1)Steel pile casting is transferred, carries out pile foundation construction, while steel lifted trunk bottom plate, steel lifted trunk side are carried out according to suspended steel box design drawing The making of plate and support structure;
(2)Added according to construction drawing fabrication and installation sleeve bottom plate reinforcing rib, set tube end plate, sleeve cage plate, set tube end plate annular Strength rib and set tube end plate outer ring ribbed stiffener;
(3)Tube end plate and sleeve body welding will be covered, and the inside and outside triangle between erecting and welding set tube end plate and sleeve body is put more energy into Plate;
(4)Sleeve body and support structure are attached, and the stiffener between installation set cylinder and support structure;
(5)Bracket is welded on the steel pile casting apart from water surface 1.8m or so, builds operating platform, as steel lifted trunk platform for lining, Steel lifted trunk bottom plate is lifted, sleeve backplanes support installs hanging box suspension system on bracket;
(6)Installation steel lifted trunk side plate, transfers guidance system and hangs system inner support, in place by steel lifted trunk decentralization;
(7)Installation sleeve cage plate is simultaneously transferred on set tube end plate, will be covered the gap between tube end plate and steel pile casting and is blocked, and The underwater concrete for pouring 5cm lower than sleeve top after health reaches intensity requirement, realizes the company between steel lifted trunk and steel pile casting It connects;
(8)Anti-floating compression bar is installed, completes to draw water in cofferdam, removes concrete laitance, and screed of mating formation in sleeve so that sand Pulp surface maintains an equal level with steel lifted trunk bottom plate;
(9)Steel lifted trunk cage plate is installed on steel lifted trunk bottom plate, by steel lifted trunk cage plate inner ring side and steel pile casting outer wall full weld, outer annular edge With steel lifted trunk steel plate of baseplate full weld, two curved plate seams carry out full weld connection, complete the installation of all steel lifted trunk cage plates;
(10)Steel lifted trunk suspension system, anti-floating compression bar and interior guidance system are removed, the binding of cushion cap reinforcing bar and concreting are carried out Bearing platform construction is completed in work.
Substantive distinguishing features outstanding and significant progress at least have the following to the present invention compared with prior art:
1. the present invention greatly reduces steel lifted trunk concrete amount, and do not influence to hold using the steel lifted trunk bottom plate of no bottom concrete The arrangement of platform reinforcing bar reduces working procedure, and easy construction is reliable, accelerates construction progress, and generates larger economic benefit.
2. the reserved 5cm mortar leveling layers in sleeve top of the present invention, increase by one of device of later stage sealing.
3. steel lifted trunk cage plate of the present invention performs after the completion of cofferdam is drawn water, and is welded with steel lifted trunk bottom plate and steel pile casting full weld It connects, increase one of antipriming and enhances the connection between steel lifted trunk bottom plate and steel pile casting.
4. the present invention uses tubbiness sleeve, that is, the amount of concrete filled between sleeve and steel pile casting is saved, by radial load Tubbiness siding is preferable structural form selection, sleeve and steel pile casting and concrete fill can ensure the vertical drag of structure therebetween And the water-stagnating effect between steel lifted trunk bottom plate and steel pile casting.
5. the junction steel plate between sleeve body of the present invention and steel lifted trunk bottom plate enhances the connection of the two.
6. the right angled triangle steel plate on present invention set tube end plate, strengthens the connection of set tube end plate and side plate, while Strengthen the connection between sleeve inner concrete filler and sleeve.
7. the present invention greatly reduces steel lifted trunk concrete amount, reduction is applied using the steel lifted trunk bottom plate of no bottom concrete Work process, accelerates construction speed, generates prodigious economic benefit.
Description of the drawings
Fig. 1 is a kind of front view for exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device of the present invention;
Fig. 2 is that one kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device schematic diagram;
Fig. 3 is that one kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device front view;
Fig. 4 is steel lifted trunk cage plate schematic top plan view;
Fig. 5 is sleeve cage plate schematic top plan view;
Serial number and component names in figure are:1- steel pile castings, 2- sleeve bodies, 3- steel lifted trunk bottom plates, 4- stiffeners, 5- Triangle IDs add Strength plate, the outer triangle stiffeners of 6-, 7- cover tube end plate, 8- sleeve bottom plate reinforcing ribs, and 9- covers tube end plate annular ribbed stiffener, 10- sets Tube end plate outer ring ribbed stiffener, 11- circular beams, 12- cant beams, 13- crossbeams, 14- longerons, 15- steel lifted trunk cage plates, 16- cover jacket casing Plate, 17- bush structures, 18- steel lifted trunk side plates, 19- steel lifted trunk inner supports, 20- anti-floating compression bars, 21- stiff girders, 22- pipe nipple beams.
Specific implementation mode
Present invention will be described in further detail below with reference to the accompanying drawings.
Shown in Fig. 1-Fig. 5,
One kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, including steel lifted trunk bottom plate 3, support structure, sleeve Construction and steel lifted trunk cage plate 15, the support structure top installation steel lifted trunk bottom plate 3, the steel lifted trunk bottom plate 3 passes through steel lifted trunk Cage plate 15 is connect with steel pile casting 1;The support structure lower part is equipped with bush structure, and 17 bottom of the bush structure is equipped with sleeve Cage plate 16, the sleeve cage plate 16 is placed on steel pile casting 1, and 3 surrounding of steel lifted trunk bottom plate installs steel lifted trunk side plate 18;To whole Body constitutes complete steel lifted trunk structure;So each steel pile casting 1, which is correspondence, is equipped with above-mentioned device;And steel lifted trunk bottom plate 3 Full weld is taken to weld between steel lifted trunk side plate 18, steel lifted trunk cage plate 15 and steel pile casting 1, steel lifted trunk bottom plate 3 are to take full weld Welding, full weld welding manner can obtain good obturation effect.
The bush structure 17 includes sleeve body 2 and set tube end plate 7,2 bottom installation sleeve bottom plate 7 of the sleeve body, institute It states set tube end plate 7 and is equipped with sleeve cage plate 16, sleeve cage plate 16 is placed on steel pile casting 1;Hole is opened up on set tube end plate 7, in hole Installation sleeve cage plate 7, then it is inserted in steel pile casting 1;Or semicircle orifice is opened up on set tube end plate, by the semicircle orifice of two same sizes Combination is placed on steel pile casting, constitutes complete attachment device.
The set tube end plate 7 is equipped with sleeve bottom plate reinforcing rib 8, set tube end plate annular ribbed stiffener 9 and set tube end plate outer shroud Shape ribbed stiffener 10, the sleeve bottom plate reinforcing rib 8 are installed on 7 bottom surface of set tube end plate, and both ends are corresponding respectively and cover in tube end plate Annular ribbed stiffener 9 and set tube end plate outer ring ribbed stiffener 10 connect;Sleeve bottom plate reinforcing rib 8, set tube end plate annular ribbed stiffener 9 Set tube end plate 7 can not only be reinforced with set tube end plate outer ring ribbed stiffener 10, and 17 can be constructed to integral sleeve and carried out Reinforce, improves whole anti-extrusion ability so that overall structure firm stable.
The sleeve body 2 takes steel plate to roll, and when sleeve body 2 is installed, need to be placed on steel pile casting 1, sleeve body rolls Made of cylinder, diameter is bigger 40-80cm than 1 diameter of steel pile casting.
Outer triangle stiffener 6,2 top of the sleeve body are equipped between 2 bottom outer wall of the sleeve body and set tube end plate 7 It is equipped with stiffener 4 between outer wall and set tube end plate 7, Triangle ID is installed between 2 bottom interior wall of the sleeve body and set tube end plate Shape stiffener 5;Outer triangle stiffener 6, stiffener 4 and interior triangular stiffener 5 further strengthen work to the realization of sleeve body 2 With, ensure that sleeve body 2 will not deform in stress, ensures integrally-built stabilization, so that it is guaranteed that entire work progress Safety.
The support structure includes circular beam 11, cant beam 12, crossbeam 13 and longeron 14, and the circular beam 11 is equipped with by circle The pipe nipple beam 22 of all equal distributions is equipped with crossbeam 13 positioned at longitudinal pipe nipple beam 22, is equipped with positioned at lateral pipe nipple beam 22 Longeron 14;And the pipe nipple beam 22 is equipped with cant beam 12 between any two;The longeron 14, crossbeam 13 are mounted on several stiff girders 21;It is interconnected to constitute intersecting parallels knot between crossbeam 13 and longeron 14, stiff girder 21 and longeron 14, crossbeam 13 and stiff girder 21 etc. Structure can be realized and be supported effect to whole steel lifted trunk structure as assembled operating platform and realization.
Its construction method of above-mentioned apparatus includes the following steps:
(1)Steel pile casting is transferred, carries out pile foundation construction, while steel lifted trunk bottom plate 3, steel lifted trunk side are carried out according to suspended steel box design drawing The making of plate 18 and support structure;
(2)According to construction drawing fabrication and installation sleeve bottom plate reinforcing rib 4, set tube end plate 7, sleeve cage plate 16, set tube end plate inner ring Shape ribbed stiffener 9 and set tube end plate outer ring ribbed stiffener 10;
(3)Set tube end plate 7 and sleeve body 2 are welded, and the interior triangular between erecting and welding set tube end plate 7 and sleeve body 2 adds Strength plate 5, outer triangle stiffener 6;
(4)Sleeve body 2 is attached, and the stiffener 4 between installation set cylinder 2 and support structure with support structure, is put more energy into Plate 4 realizes support structure the ability that stress is resisted in enhancing, and can play the role of improving support structure stability;
(5)Bracket is welded on the steel pile casting 1 apart from water surface 1.8m or so, as steel lifted trunk platform for lining, lifting steel lifted trunk bottom Plate 3, set tube end plate 7 is supported on bracket, and installs hanging box suspension system;
(6)Installation steel lifted trunk side plate 18, transfers guidance system and hangs system steel lifted trunk inner support 19, and steel lifted trunk is transferred to Position;
(7)Installation sleeve cage plate 16 is simultaneously transferred on set tube end plate 7, will be covered the gap between tube end plate 7 and steel pile casting 1 and is sealed It is stifled, and the underwater concrete of 5cm lower than sleeve top is poured, after health reaches intensity requirement, realize between steel lifted trunk and steel pile casting Connection;
(8)Anti-floating compression bar 20 is installed, completes to draw water in cofferdam, removes concrete laitance, and screed of mating formation in bush structure, So that mortar face maintains an equal level with steel lifted trunk bottom plate 3;
(9)Steel lifted trunk cage plate 15 is installed on steel lifted trunk bottom plate 3, by 15 inner ring side of steel lifted trunk cage plate and 1 outer wall full weld of steel pile casting, Outer annular edge and 3 steel plate full weld of steel lifted trunk bottom plate, two curved plate seams carry out full weld connection, complete all steel lifted trunk cage plates 15 Installation;
(10)Steel lifted trunk suspension system, anti-floating compression bar 20 and interior guidance system are removed, the binding of cushion cap reinforcing bar is carried out and concrete pours Work is built, bearing platform construction is completed.
The anti-floating compression bar, compression bar are I-steel, bottom weld horizontal steel plate, and steel lifted trunk is transferred in place, is pacified before drawing water Dress, which is taken, is placed on steel lifted trunk plate upper surface, and anti-floating compression bar top is connected firmly with steel lifted trunk Lift-on/Lift-off System distribution beam.
Implementation of an application example 1:
It is 1x40+ to create certain grand bridge span distribution(92+172+92)M, main bridge overall length 356m, main bridge are 92+172+92 waveforms Steel web prestressed concrete continuous rigid-framed bridge, access bridge are 1-40m pre-stress concrete prefabricated small box girders, the main bridge masters of overall length 404.5m. Beam uses single box single chamber variable cross-section Wavelike steel webplate prestressed concrete continuous box girder, and main pier is using double limb solid piers, transition pier Using twin columns solid pier, infrastructure connects multi-column pier foundation using cushion cap, and 2# piers, 3# piers are respectively positioned in water, using set up trestle and Steel platform mode is constructed pile foundation, and steel platform is recycled to carry out steel suspended box cofferdam construction.The main pier bearing platform of 2#, 3# are monoblock type, are held Platform bottom surface absolute altitude is 149.1m, and cushion cap top surface absolute altitude is 153.6m, and cushion cap thickness is 4.5m, and structure size is 18 × 16 × 4.5m.It is 153.6m that 2#, 3# pier water surface, which survey water level elevation often,.It is constructed to cushion cap using the present invention, avoids back cover coagulation The pouring of soil, the high leveling process of top mark, directly pour cushion cap, reduce 2 weeks bearing platform construction time, save concrete 432m3, construct It is convenient, there is preferable economic benefit.
Obviously, the above embodiments are merely examples for clarifying the description, and does not limit the embodiments.It is right For those of ordinary skill in the art, can also make on the basis of the above description it is other it is various forms of variation or It changes.There is no necessity and possibility to exhaust all the enbodiments.And it is extended from this it is obvious variation or It changes still within the protection scope of the invention.

Claims (9)

1. one kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Including steel lifted trunk bottom plate, branch Steel lifted trunk bottom plate is installed at support construction, bush structure and steel lifted trunk cage plate, the support structure top, and the steel lifted trunk bottom plate passes through Steel lifted trunk cage plate is connect with steel pile casting;The support structure lower part is equipped with bush structure, and the bush structure bottom is equipped with set Jacket casing plate, the sleeve cage plate are placed on steel pile casting.
2. according to claim 1 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It includes sleeve body and set tube end plate to state bush structure, and the sleeve body bottom installation sleeve bottom plate, the set tube end plate, which is equipped with, to be covered Jacket casing plate.
3. according to claim 2 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It states set tube end plate and is equipped with sleeve bottom plate reinforcing rib, set tube end plate annular ribbed stiffener and set tube end plate outer ring ribbed stiffener, it is described Sleeve bottom plate reinforcing rib is installed on set tube end plate bottom surface, and both ends are corresponding respectively and cover tube end plate annular ribbed stiffener and sleeve bottom Plate outer ring ribbed stiffener connects.
4. according to claim 2 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute Stating sleeve body takes steel plate to roll.
5. according to claim 2 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It states and is equipped with outer triangle stiffener between sleeve body bottom outer wall and set tube end plate.
6. according to claim 2 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It states and is equipped with stiffener between sleeve body top exterior walls and set tube end plate.
7. according to claim 2 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It states and interior triangular stiffener is installed between sleeve body bottom interior wall and set tube end plate.
8. according to claim 1 exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, it is characterised in that:Institute It includes circular beam, cant beam, crossbeam and longeron to state support structure, and the circular beam is equipped with the pipe nipple beam by circumference equal distribution, Crossbeam is installed positioned at longitudinal pipe nipple beam, longeron is installed positioned at lateral pipe nipple beam;And the pipe nipple beam is set between any two There is cant beam;The longeron, crossbeam are mounted on several stiff girders.
9. a kind of construction method for exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device, which is characterized in that the side Method includes the following steps:
(1)Steel pile casting is transferred, carries out pile foundation construction, while steel lifted trunk bottom plate, steel lifted trunk side are carried out according to suspended steel box design drawing The making of plate and support structure;
(2)Added according to construction drawing fabrication and installation sleeve bottom plate reinforcing rib, set tube end plate, sleeve cage plate, set tube end plate annular Strength rib and set tube end plate outer ring ribbed stiffener;
(3)Tube end plate and sleeve body welding will be covered, and the inside and outside triangle between erecting and welding set tube end plate and sleeve body is put more energy into Plate;
(4)Sleeve body and support structure are attached, and the stiffener between installation set cylinder and support structure;
(5)Bracket is welded on the steel pile casting apart from water surface 1.8m or so, as steel lifted trunk platform for lining, lifting steel lifted trunk bottom Plate, sleeve backplanes support install hanging box suspension system on bracket;
(6)Installation steel lifted trunk side plate, transfers guidance system and hangs system inner support, in place by steel lifted trunk decentralization;
(7)Installation sleeve cage plate is simultaneously transferred on set tube end plate, will be covered the gap between tube end plate and steel pile casting and is blocked, and The underwater concrete for pouring 5cm lower than sleeve top after health reaches intensity requirement, realizes the company between steel lifted trunk and steel pile casting It connects;
(8)Anti-floating compression bar is installed, completes to draw water in cofferdam, removes concrete laitance, and screed of mating formation in sleeve so that sand Pulp surface maintains an equal level with steel lifted trunk bottom plate;
(9)Steel lifted trunk cage plate is installed on steel lifted trunk bottom plate, by steel lifted trunk cage plate inner ring side and steel pile casting outer wall full weld, outer annular edge With steel lifted trunk steel plate of baseplate full weld, two curved plate seams carry out full weld connection, complete the installation of all steel lifted trunk cage plates;
(10)Steel lifted trunk suspension system, anti-floating compression bar and interior guidance system are removed, the binding of cushion cap reinforcing bar and concreting are carried out Bearing platform construction is completed in work.
CN201810594553.2A 2018-06-11 2018-06-11 Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method Pending CN108643206A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810594553.2A CN108643206A (en) 2018-06-11 2018-06-11 Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810594553.2A CN108643206A (en) 2018-06-11 2018-06-11 Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method

Publications (1)

Publication Number Publication Date
CN108643206A true CN108643206A (en) 2018-10-12

Family

ID=63752242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810594553.2A Pending CN108643206A (en) 2018-06-11 2018-06-11 Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method

Country Status (1)

Country Link
CN (1) CN108643206A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109570429A (en) * 2018-11-26 2019-04-05 首都航天机械有限公司 A kind of super-large diameter cylinder piece housing and cross beam high-accuracy sleeve holding tool
CN109778887A (en) * 2019-01-03 2019-05-21 中交二航局第四工程有限公司 A kind of novel steel lifted trunk structure and its assembly method based on offshore steel taper pile basis
CN112523104A (en) * 2020-12-16 2021-03-19 中铁建大桥工程局集团第一工程有限公司 Quick plugging device of steel hanging box
CN113529763A (en) * 2021-07-01 2021-10-22 中铁十九局集团华东工程有限公司 Method for constructing sea area shoal cushion cap by utilizing reinforced concrete combined steel cofferdam
CN113863341A (en) * 2021-11-02 2021-12-31 同济大学建筑设计研究院(集团)有限公司 Bottom water sealing device for cofferdam construction process

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951856A (en) * 2016-06-20 2016-09-21 中国铁建港航局集团有限公司 Construction method and structure of underwater reinforced concrete combined suspension-box cofferdam free of bottom-sealing concrete
CN206512730U (en) * 2016-12-30 2017-09-22 中交二航局第四工程有限公司 It is a kind of to realize the box that box wall body is used in turn
JP6336157B1 (en) * 2017-02-21 2018-06-06 株式会社京都スペーサー Sleeve tube and method for manufacturing the same, and method for manufacturing through-hole using sleeve tube
CN208309610U (en) * 2018-06-11 2019-01-01 广西路建工程集团有限公司 One kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105951856A (en) * 2016-06-20 2016-09-21 中国铁建港航局集团有限公司 Construction method and structure of underwater reinforced concrete combined suspension-box cofferdam free of bottom-sealing concrete
CN206512730U (en) * 2016-12-30 2017-09-22 中交二航局第四工程有限公司 It is a kind of to realize the box that box wall body is used in turn
JP6336157B1 (en) * 2017-02-21 2018-06-06 株式会社京都スペーサー Sleeve tube and method for manufacturing the same, and method for manufacturing through-hole using sleeve tube
CN208309610U (en) * 2018-06-11 2019-01-01 广西路建工程集团有限公司 One kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨永恒, 《广州建筑》 *
蔡清愉, 《福建交通科技》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109570429A (en) * 2018-11-26 2019-04-05 首都航天机械有限公司 A kind of super-large diameter cylinder piece housing and cross beam high-accuracy sleeve holding tool
CN109778887A (en) * 2019-01-03 2019-05-21 中交二航局第四工程有限公司 A kind of novel steel lifted trunk structure and its assembly method based on offshore steel taper pile basis
CN112523104A (en) * 2020-12-16 2021-03-19 中铁建大桥工程局集团第一工程有限公司 Quick plugging device of steel hanging box
CN113529763A (en) * 2021-07-01 2021-10-22 中铁十九局集团华东工程有限公司 Method for constructing sea area shoal cushion cap by utilizing reinforced concrete combined steel cofferdam
CN113863341A (en) * 2021-11-02 2021-12-31 同济大学建筑设计研究院(集团)有限公司 Bottom water sealing device for cofferdam construction process

Similar Documents

Publication Publication Date Title
CN108643206A (en) Exempt from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device and its construction method
CN103741657B (en) The construction method of large-sized multifunction waterborne traffic accident
CN205348391U (en) Take prefabricated beam column rebar mechanical connection node of lag
CN107246005A (en) Super-large diameter bores and buries steel pipe hollow foundation pile and its construction method
CN106930191B (en) A kind of cast-in-situ box girder hoop bracket system and its construction method
CN103104102B (en) Construction method for underground storey-addition reconstruction
CN108179735A (en) A kind of boulder bed large-sized deep water foundation construction platform and method
CN109440634A (en) The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN110439013A (en) A kind of main pier bearing platform steel suspended box cofferdam construction method
CN103866693A (en) Installing method of reinforced concrete bowstring rod arch bridge arch ribs and hanging auxiliary bridge
CN108643207A (en) Exempt from bottom concrete steel lifted trunk side plate and bottom board connector and its construction method
CN208309610U (en) One kind exempting from bottom concrete steel lifted trunk bottom plate and steel pile casting attachment device
CN106958259B (en) A kind of concrete towers column foundation and its construction method
CN204000905U (en) A kind of Double-Wall Steel Boxed Cofferdam with binder deep water bearing platform construction
CN203654196U (en) Guide apparatus for large and multifunctional over-water construction platform
CN205889488U (en) Steel sleeve box&#39;s precast reinforced concrete back cover template and hoist device thereof
CN210975819U (en) Recyclable steel jacket box hanger
CN207685879U (en) A kind of lift stake reinforcing bearing platform construction platform
CN109930610A (en) Constrained environment foundation pit adds the construction method of steel pipe mixing diagonal brace using concrete
CN106677075B (en) A kind of cofferdam for Bridge Pier Construction hangs stake and method of passing the flood period
CN206467577U (en) Cast-in-place box beam bracket
CN106192767B (en) A kind of device and construction method that can improve bottom concrete bearing capacity
CN209619836U (en) The prefabricated high strength concrete hollow bent cap structure that internal model can be taken off
CN210482021U (en) Prefabricated assembling pier column structure connected through steel bars inserted into corrugated pipe
CN208981372U (en) Automatic hydraulic power balance stability against floating structure during Underground Construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181012

RJ01 Rejection of invention patent application after publication