CN108625477A - A kind of assembled beam-column node and its construction method - Google Patents

A kind of assembled beam-column node and its construction method Download PDF

Info

Publication number
CN108625477A
CN108625477A CN201810242073.XA CN201810242073A CN108625477A CN 108625477 A CN108625477 A CN 108625477A CN 201810242073 A CN201810242073 A CN 201810242073A CN 108625477 A CN108625477 A CN 108625477A
Authority
CN
China
Prior art keywords
column
prefabricated post
buried
prefabricated
precast beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810242073.XA
Other languages
Chinese (zh)
Inventor
黄�俊
鲁志伟
戴绍斌
郑小林
李玉博
刘轩
金鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201810242073.XA priority Critical patent/CN108625477A/en
Publication of CN108625477A publication Critical patent/CN108625477A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B1/4114Elements with sockets
    • E04B1/4142Elements with sockets with transverse hook- or loop-receiving parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • E04B1/4157Longitudinally-externally threaded elements extending from the concrete or masonry, e.g. anchoring bolt with embedded head

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The present invention relates to a kind of assembled beam-column node and its construction methods, make prefabricated post and precast beam or composite beam in advance first, then the two is connected and fixed at the scene by grout sleeve and mortar etc., forms assembled beam-column node reasonable for structure, easy for construction.The invention avoids bind joint core region reinforcing bar and rear pouring concrete at the construction field (site), the construction quality that ensure that assembled beam-column joint cores can conveniently and efficiently get up the vertical muscle of stress in precast beam or composite beam with the bar connecting in prefabricated post after prefabricated beam column in-site installation is in place.

Description

A kind of assembled beam-column node and its construction method
Technical field
The present invention relates to construction engineering technical fields, and in particular to a kind of assembled beam-column node and its construction method
Background technology
Assembled architecture is high with industrialization degree, it is fast etc. excellent to save material, environmental protection, convenient and quick construction and investment repayment Point is one of the structure type given priority in China's Process of Housing Industrialization.Assembled architecture batch production degree is very high, component It is prefabricated in special precast plant, it is assembled, is similar to " playing with building blocks " by being transported to scene after scientific and reasonable maintenance Assembly model.Structural integrity is one of most important measurement index of assembled architecture durability, therefore the key of its technology Point is the connection between each component.
The connection type of assembled beam-column node mainly has at present:Steel plate welding, bolt, prestressing force connection and joint core Pouring concrete behind area, however there are some problem and shortage in these methods.It is poor that the welding of its light plate connect ductility with prestressing force, Brittle break easily occurs;Be bolted to it is relatively flexible and easy-maintaining when dismounting, but since the number of components is relatively more, whole weight Amount and cost also increase therewith, and stress is excessive vulnerable;This connection type of pouring concrete is needed existing behind joint cores Field carries out the construction technologies such as binding node area reinforcing bar, formwork supporting plate, and situ wet operation is more and is not easy to ensure prefabricated bean column node core The construction quality of heart district.
Therefore, it is necessary to research and develop a kind of assembled beam-column node reasonable for structure, easy for construction, if the joint core region It is prefabricated in the factory in advance and can be directly connected to install at the scene, then can effectively shorten the construction period, ensure construction quality.
Invention content
It is an object of the invention to overcome drawbacks described above of the existing technology, a kind of new assembled beam-column node is provided And its construction method.Compared with after-pouring concrete, the avoidable joint cores reinforcing bar of binding at the construction field (site) of the present invention, After pour joint cores concrete, abolished the processes such as field node area formwork supporting plate, reduced cost of labor, effectively raise The quality of connection in node area.To achieve the above object, the technical solution adopted in the present invention is as follows:
A kind of assembled beam-column node, including prefabricated post, connection reinforcing bar, mortar joint or rear pouring concrete, precast beam or Composite beam;
Gap between prefabricated post and precast beam is filled by mortar joint, composite beam top and its seam between prefabricated post Gap passes through after-pouring Concrete Filled;
Prefabricated post and the connection type of precast beam are:Anchor bar in prefabricated post passes through pre-buried II types grout sleeve, company Connect reinforcing bar, pre-buried I types grout sleeve is indulged muscle with the precast beam in precast beam and is connected and fixed;
Prefabricated post and the connection type of composite beam are:The prefabricated post embedded bar of prefabricated post internal upper part is filled by pre-buried II types Slurry sleeve is connected and fixed with the precast beam upper longitudinal bar in composite beam, and the anchor bar of lower part is filled by pre-buried II types in prefabricated post Slurry sleeve, connection reinforcing bar, pre-buried I types grout sleeve in composite beam precast beam lower part indulge muscle be connected and fixed, i.e., prefabricated post and Composite beam is connected and fixed by two ways, the prefabricated post embedded bar-precast beam upper longitudinal bar on top and the anchoring steel of lower part Indulge muscle in muscle-connection reinforcing bar-precast beam lower part;
It is perfused in pre-buried I types grout sleeve and pre-buried II types grout sleeve and forms grouting material.
Preferably, the prefabricated post embedded bar of prefabricated post internal upper part is connected with the precast beam upper longitudinal bar in composite beam by sleeve It connects and is changed to weld, the length of weld seam is equivalent to 10 times of precast beam upper longitudinal bar diameter.
In said program, the length of pre-buried I type grout sleeve be precast beam indulge muscle diameter (including precast beam upper longitudinal bar and Indulge muscle in precast beam lower part) 21 times, the length of pre-buried II type grout sleeve is 14 times that precast beam indulges muscle diameter, connects reinforcing bar Length is 14 times that precast beam indulges muscle diameter.
In said program, the pre-buried I type grout sleeve and pre-buried II type grout sleeve are that full grout sleeve or half are in the milk Sleeve is connected with Grouting Pipe or discharge pipe thereon, and grouting material used is High Performance Cement Without Shrinkage grouting material in sleeve, and intensity is not Less than 80MPa.
In said program, it is additionally provided in the column of stretching composite beam in precast beam or column in prefabricated post, it is pre- in the column Composite beam and prefabricated post are prefabricated integral in beam or column processed, the end of composite beam and precast beam or overlapping in precast beam or column in column Beam forms bean column node according to connection type above-mentioned.
Further, the precast beam or composite beam beam that composite beam extension elongation is 1.5 times in precast beam or column in the column It is high.
A kind of construction method of assembled beam-column node, includes the following steps:
(a) making of prefabricated post
Prefabricated post is indulged into muscle and the binding of prefabricated column tie-bar into formwork supporting plate after steel reinforcement cage, pre-buried II type grout sleeve is fixed on In template, the anchor bar with rubber stopper is inserted into pre-buried II type grout sleeve, after casting concrete reaches prescribed strength Form removal obtains prefabricated post;
Or muscle and the binding of prefabricated column tie-bar are indulged into formwork supporting plate after steel reinforcement cage in prefabricated post lower part, pre-buried II type is in the milk and is covered Cylinder is fixed in template, the anchor bar with rubber stopper is inserted into pre-buried II type grout sleeve, in prefabricated post upper longitudinal bar The prefabricated post embedded bar for being pierced by template is arranged in position, and form removal obtains prefabricated post after casting concrete reaches prescribed strength;
(b) making of precast beam or composite beam
Precast beam with rubber stopper is indulged muscle to be inserted into prefabricated I type grout sleeve, precast beam is indulged into muscle and precast beam hoop Muscle is bound into formwork supporting plate after steel reinforcement cage, pre-buried I type grout sleeve is fixed in template, after casting concrete reaches prescribed strength Form removal obtains precast beam;
Or muscle is indulged into the precast beam lower part with rubber stopper and is inserted into pre-buried I type grout sleeve, then by its with it is prefabricated Beam upper longitudinal bar, the binding of prefabricated beam stirrup are fixed at formwork supporting plate after steel reinforcement cage, then by pre-buried I type grout sleeve in template, are poured It builds concrete and reaches form removal after prescribed strength and obtain composite beam (precast beam upper longitudinal bar is exposed at this time and does not have connector sleeve Cylinder is not poured into inside cement);
(c) site operation
By the upright simultaneously fixation of prefabricated post, position and the distance of prefabricated post and precast beam are adjusted, in the pre- of precast beam It buries in I type grout sleeve and is put into connection reinforcing bar, it is mobile until connection that pre-buried II type grouting set of the reinforcing bar into prefabricated post will be connected Reinforcing bar contacts or spaced apart with anchor bar, blocks embedded sleeve barrel and is simultaneously in the milk, finally fills prefabricated post with mortar joint Gap between precast beam;
Or by the upright simultaneously fixation of prefabricated post, position and the distance of prefabricated post and composite beam are adjusted, in composite beam Pre-buried I type grout sleeve in be put into connection reinforcing bar, pre-buried II types grout sleeve is inserted in the precast beam upper longitudinal bar of composite beam, Pre-buried II type of the reinforcing bar into prefabricated post will be connected and be in the milk set movement until connection reinforcing bar is contacted or is spaced with anchor bar centainly Distance, by the pre-buried II type grout sleeve on composite beam to the movement of prefabricated post embedded bar direction until the reinforcing bar on sleeve both sides (precast beam upper longitudinal bar and prefabricated post embedded bar) is approximately equal in length, and is blocked embedded sleeve barrel and is in the milk, finally pours coagulation Soil.
In said program, the prefabricated post embedded bar in step (c) in prefabricated post and the precast beam top in composite beam are vertical Connection between muscle is changed to weld by pre-buried II type grout sleeve, and subsequent technique is constant, and the length of weld seam is equivalent to 10 times pre- Beam upper longitudinal bar diameter processed.
In said program, it is additionally provided in the column of stretching composite beam in precast beam or column in prefabricated post, it is pre- in the column Composite beam and prefabricated post are prefabricated integral in beam or column processed, and composite beam extension elongation is 1.5 times pre- in precast beam or column in column Beam or composite beam deck-molding processed, the end of composite beam forms bean column node with precast beam or composite beam in precast beam or column in column.
Compared with prior art, the invention has the advantages that:(1) making of prefabricated post and precast beam or composite beam It can fulfil ahead of schedule, avoid binding joint core region reinforcing bar at the construction field (site) and carry out larger rear pouring concrete operation, It can guarantee the construction quality of assembled beam-column joint cores;It (2) can be conveniently and efficiently after prefabricated beam column in-site installation is in place Stress in precast beam or composite beam is indulged muscle with the bar connecting in prefabricated post to get up.
Description of the drawings
Fig. 1-3 be respectively the structural schematic diagram of I type assembled beam-column nodes in the embodiment of the present invention 1, A-A to sectional view, B-B direction sectional view;
Fig. 4-6 be respectively the structural schematic diagram of II type assembled beam-column nodes in the embodiment of the present invention 2, A-A to sectional view, B-B direction sectional view;
Fig. 7-9 is respectively the structural schematic diagram of type III assembled beam-column node in the embodiment of the present invention 3, A-A to section Figure, B-B direction sectional view;
Figure 10-12 is respectively the structural schematic diagram of IV type assembled beam-column nodes in the embodiment of the present invention 4, A-A to section Figure, B-B direction sectional view;
Figure 13-15 is respectively the structural schematic diagram of V-type assembled beam-column node in the embodiment of the present invention 5, A-A to section Figure, B-B direction sectional view;
Figure 16-18 is respectively the structural schematic diagram of VI type assembled beam-column nodes in the embodiment of the present invention 6, A-A to section Figure, B-B direction sectional view.
In figure, I type assembled beam-column nodes of 1-, II type assembled beam-column nodes of 2-, III type assembled beam-column nodes of 3-, 4- IV type assembled beam-column node, V type assembled beam-column nodes of 5-, VI type assembled beam-column nodes of 6-, 7- prefabricated posts, 8- are prefabricated Beam, the pre-buried I type grout sleeves of 9-, 10- connection reinforcing bars, 11- grouting materials, the pre-buried II type grout sleeves of 12-, 13- anchor bars, 14- prefabricated posts indulge muscle, the prefabricated column tie-bars of 15-, and 16- precast beams indulge muscle, the prefabricated beam stirrups of 17-, 18- mortar joints, 19- Grouting Pipes Or discharge pipe, 20- composite beams, pouring concrete after 21-, 22- prefabricated post embedded bars, 23- weld seams.
Specific implementation mode
To make those of ordinary skill in the art fully understand technical scheme of the present invention and advantageous effect, below in conjunction with specific Embodiment and attached drawing are further described.
Pre-buried I type grout sleeve used in the present invention and pre-buried II type grout sleeve are selected from full grout sleeve or half grouting Sleeve is connected with Grouting Pipe or discharge pipe thereon, and grouting material used is High Performance Cement Without Shrinkage grouting material in sleeve, and intensity is not Less than 80MPa.The length of pre-buried I type grout sleeve is 21 times that precast beam indulges muscle diameter, the length of pre-buried II type grout sleeve Indulge muscle diameter for precast beam 14 times, the length for connecting reinforcing bar are 14 times that precast beam indulges muscle diameter.
Embodiment 1
A kind of I types assembled beam-column node as shown in Figs. 1-3, construction method are as follows:
1) making of prefabricated post 7
Prefabricated post is indulged into muscle 14 and the binding of prefabricated column tie-bar 15 into steel reinforcement cage and formwork supporting plate first.It is in the milk and covers in pre-buried II type The anchor bar 13 with rubber stopper is inserted into one end of cylinder 12, and the other end port of sleeve is concordant with the side of prefabricated post 7 and fixed In on prefabricated pillar forms, guarantee sleeve indulges muscle 16 point-blank with the precast beam in precast beam 8, then casting concrete, Can dismantle template after prescribed strength to be achieved.
2) making of precast beam 8
The precast beam with rubber stopper is indulged into muscle 16 first and is inserted into certain length in pre-buried I type grout sleeve 9, then by it With the binding of prefabricated beam stirrup 17 at steel reinforcement cage and formwork supporting plate, then the other end of pre-buried I type grout sleeve 9 is fixed and beam-ends mould On plate, last casting concrete, can dismantle after prescribed strength to be achieved template.
3) site operation
By the upright simultaneously fixation of prefabricated post 7, connection reinforcing bar 10 is put into the pre-buried I type grout sleeve 9 in precast beam 8 And it is secured using scaffold support, so that connection reinforcing bar 10 is moved into pre-buried II type grout sleeve 12 with hand or tool, until Connection reinforcing bar 10 is in contact with anchor bar 13 or at a distance of 10mm, and grout sleeve is blocked with adhesive plaster or rubber stopper.In prefabricated post 7 Mortar joint 18 is inserted in gap between precast beam 8, and grouting material 11 is passed through into Grouting Pipe or plasma discharge using pressure grouting machine Pipe 19 pours into pre-buried I type grout sleeve 9 and pre-buried II type grout sleeve 12.
Embodiment 2
A kind of II types assembled beam-column node as Figure 4-Figure 6, construction method are as follows:
1) making of prefabricated post 7
Prefabricated post is indulged into muscle 14 and the binding of prefabricated column tie-bar 15 into steel reinforcement cage and formwork supporting plate first.It is in the milk and covers in pre-buried II type The anchor bar 13 with rubber stopper is inserted into one end of cylinder 12, and the other end of sleeve is fixed on the prefabricated post mould with precast beam in column On plate (length that precast beam stretches out in column is equivalent to 1.5 times of 8 deck-molding of precast beam), ensure sleeve with it is prefabricated in precast beam 8 Beam indulges muscle 16 point-blank, then casting concrete, and can dismantle template after prescribed strength to be achieved.
2) making of precast beam 8
It is identical as the production method of precast beam 8 in embodiment 1.
3) site operation
It is identical as component on site construction method in embodiment 1.
Only precast beam, principle are identical in the node region of prefabricated post devises column for the present embodiment.
Embodiment 3
A kind of type III assembled beam-column node as Figure 7-9, construction method are as follows:
1) making of prefabricated post 7
Prefabricated post is indulged into muscle 14 and the binding of prefabricated column tie-bar 15 into steel reinforcement cage and formwork supporting plate first.It is in the milk and covers in pre-buried II type The anchor bar 13 with rubber stopper is inserted into one end of cylinder 12, and the other end port of sleeve is concordant with the side of prefabricated post 7 and fixed On prefabricated pillar forms, ensure that sleeve indulges muscle 16 (indulging muscle in lower part) point-blank with the precast beam in composite beam 20.It will be pre- Column embedded bar 22 processed passes through template, it is made to indulge muscle 16 (upper longitudinal bar) point-blank with the precast beam in composite beam 20, Then casting concrete, can dismantle after prescribed strength to be achieved template.
2) making of composite beam 20
The precast beam with rubber stopper is indulged into muscle 16 (indulging muscle in lower part) first and is inserted into a fixed length in pre-buried I type grout sleeve 9 Then degree binds itself and prefabricated beam stirrup 17 at steel reinforcement cage and formwork supporting plate.The other end of pre-buried I type grout sleeve 9 is fixed In beam-ends template, casting concrete, can dismantle after prescribed strength to be achieved template.The precast beam of thus obtained composite beam 20 Vertical muscle 16 (upper longitudinal bar) is exposed outside, convenient for live after-pouring concrete.
3) site operation
By the upright simultaneously fixation of prefabricated post 7.It is put into connection reinforcing bar in pre-buried I type grout sleeve 9 in composite beam 20 10, precast beam in composite beam 20 indulges 16 (upper longitudinal bar) one end of muscle and is inserted in pre-buried II type grout sleeve 12 and with scaffold branch Support is secured.Make to move in pre-buried II type grout sleeve 12 of the connection reinforcing bar 10 into prefabricated post 7 with hand or tool, until connection Reinforcing bar 10 is in contact with anchor bar 13 or at a distance of 10mm, and grout sleeve is blocked with adhesive plaster or rubber stopper.With hand or tool Make precast beam indulge the pre-buried II type grout sleeve 12 being socketed on muscle 16 (upper longitudinal bar) to move to 22 direction of prefabricated post embedded bar, Until reinforcing bar equal length in both sides in sleeve, finally the sleeve both ends are blocked with rubber stopper.Coagulation is poured after being poured on composite beam Grouting material 11 is finally poured into pre-buried I type grout sleeve 9 and pre- by soil 21 using pressure grouting machine by Grouting Pipe or discharge pipe 19 It buries in II type grout sleeve 12.
Precast beam is only changed to composite beam by the present embodiment, and principle is identical.
Embodiment 4
A kind of IV types assembled beam-column node as shown in figs. 10-12, construction method are as follows:
1) making of prefabricated post 7
Prefabricated post is indulged into muscle 14 and the binding of prefabricated column tie-bar 15 into steel reinforcement cage and formwork supporting plate first.It is in the milk and covers in pre-buried II type The anchor bar 13 with rubber stopper is inserted into one end of cylinder 12, the other end port of sleeve be fixed on in column composite beam it is prefabricated On column template (length that composite beam stretches out in column is equivalent to 1.5 times of 20 deck-molding of composite beam), it is ensured that in sleeve and composite beam 20 Precast beam indulge muscle 16 (indulging muscle in lower part) point-blank.Prefabricated post embedded bar 22 is passed through into template, it is ensured that itself and overlapping Precast beam in beam 20 indulges muscle 16 (upper longitudinal bar) point-blank.Last casting concrete, can after prescribed strength to be achieved It dismantles template.
2) making of composite beam 20
It is identical as the preparation method of composite beam 20 in embodiment 3.
3) site operation
It is identical as the component on site construction method in embodiment 3.
The present embodiment only overlaps in the node region of prefabricated post devises column, and principle is identical.
Embodiment 5
A kind of V-type assembled beam-column node as illustrated in figs. 13-15, construction method are as follows:
1) making of prefabricated post 7
It is identical as the preparation method of prefabricated post 7 in embodiment 3.
2) making of composite beam 20
It is identical as the preparation method of composite beam 20 in embodiment 3.
3) site operation
It is essentially identical with the component on site construction method in embodiment 3, the difference is that:Precast beam in composite beam 20 is indulged The connection between prefabricated post embedded bar 22 in muscle 16 and prefabricated post 7 is changed to overlap welding by pre-buried II type grout sleeve 12 It connects, fusion length is equivalent to 10 times of precast beam upper longitudinal bar diameter.
The precast beam in composite beam 20 in embodiment 3 is only indulged muscle for the present embodiment and the prefabricated post in prefabricated post is pre-buried The connection type of reinforcing bar is changed to weld, and principle is identical.
Embodiment 6
A kind of VI types assembled beam-column node as shown in figs. 16-18, construction method are as follows:
1) making of prefabricated post 7
It is identical as the preparation method of prefabricated post 7 in embodiment 4.
2) making of composite beam 20
It is identical as the preparation method of prefabricated post 7 in embodiment 4.
3) site operation
It is essentially identical with the component on site construction method in embodiment 4, the difference is that:Precast beam in composite beam 20 is indulged The connection between prefabricated post embedded bar 22 in muscle 16 and prefabricated post 7 is changed to overlap joint welding by pre-buried II type grout sleeve 12, Fusion length is equivalent to 10 times of precast beam upper longitudinal bar diameter.
The precast beam in composite beam 20 in embodiment 4 is only indulged muscle for the present embodiment and the prefabricated post in prefabricated post is pre-buried The connection type of reinforcing bar is changed to weld, and principle is identical.

Claims (9)

1. a kind of assembled beam-column node, which is characterized in that the assembled beam-column node includes prefabricated post, connection reinforcing bar, connects Seam mortar or rear pouring concrete, precast beam or composite beam, the wherein gap between prefabricated post and precast beam are filled by mortar joint, Gap between composite beam top and composite beam and prefabricated post passes through after-pouring Concrete Filled;
Prefabricated post and the connection type of precast beam are:Anchor bar in prefabricated post passes through pre-buried II types grout sleeve, connection steel Muscle, pre-buried I types grout sleeve are indulged muscle with the precast beam in precast beam and are connected and fixed;
Prefabricated post and the connection type of composite beam are:The prefabricated post embedded bar of prefabricated post internal upper part is in the milk by pre-buried II types to be covered Cylinder is connected and fixed with the precast beam upper longitudinal bar in composite beam, and the anchor bar of lower part is in the milk by pre-buried II types and is covered in prefabricated post Cylinder, connection reinforcing bar, pre-buried I types grout sleeve are indulged muscle with the precast beam lower part in composite beam and are connected and fixed;
It is perfused in pre-buried I types grout sleeve and pre-buried II types grout sleeve and forms grouting material.
2. a kind of assembled beam-column node as described in claim 1, it is characterised in that:The prefabricated post of prefabricated post internal upper part is pre-buried For reinforcing bar with the precast beam upper longitudinal bar in composite beam by being welded and fixed, the precast beam top that the length of weld seam is equivalent to 10 times is vertical Muscle diameter.
3. a kind of assembled beam-column node as described in claim 1, it is characterised in that:The length of pre-buried I type grout sleeve is Precast beam indulges 21 times of muscle diameter, and the length of pre-buried II type grout sleeve is 14 times that precast beam indulges muscle diameter, connects reinforcing bar Length is 14 times that precast beam indulges muscle diameter.
4. a kind of assembled beam-column node as described in claim 1, it is characterised in that:The pre-buried I type grout sleeve and pre- It is full grout sleeve or half grout sleeve to bury II type grout sleeve, is connected with Grouting Pipe or discharge pipe thereon, filling used in sleeve Slurry is High Performance Cement Without Shrinkage grouting material, and intensity is not less than 80MPa.
5. a kind of assembled beam-column node as described in claim 1, it is characterised in that:Stretching is additionally provided in prefabricated post Composite beam in precast beam or column in column, composite beam and prefabricated post are prefabricated integral in precast beam or column in the column, prefabricated in column The end of composite beam forms bean column node with precast beam or composite beam in beam or column.
6. a kind of assembled beam-column node as claimed in claim 5, it is characterised in that:It is overlapped in precast beam or column in the column The precast beam or composite beam deck-molding that beam extension elongation is 1.5 times.
7. the construction method of any one of the claim 1-6 assembled beam-column nodes, which is characterized in that include the following steps:
(a) making of prefabricated post
Prefabricated post is indulged into muscle and the binding of prefabricated column tie-bar into formwork supporting plate after steel reinforcement cage, pre-buried II type grout sleeve is fixed on template On, the anchor bar with rubber stopper is inserted into pre-buried II type grout sleeve, casting concrete is removed after reaching prescribed strength Template obtains prefabricated post;
Or muscle and the binding of prefabricated column tie-bar are indulged into formwork supporting plate after steel reinforcement cage in prefabricated post lower part, pre-buried II type grout sleeve is consolidated It is scheduled in template, the anchor bar with rubber stopper is inserted into pre-buried II type grout sleeve, in prefabricated post upper longitudinal bar position The prefabricated post embedded bar for being pierced by template is set, and form removal obtains prefabricated post after casting concrete reaches prescribed strength;
(b) making of precast beam or composite beam
Precast beam with rubber stopper is indulged muscle to be inserted into prefabricated I type grout sleeve, precast beam is indulged into muscle and is tied up with prefabricated beam stirrup It is bundled into formwork supporting plate after steel reinforcement cage, pre-buried I type grout sleeve is fixed in template, casting concrete is removed after reaching prescribed strength Template obtains precast beam;
Or muscle is indulged into the precast beam lower part with rubber stopper and is inserted into pre-buried I type grout sleeve, then by its on precast beam Portion indulges muscle, the binding of prefabricated beam stirrup is fixed at formwork supporting plate after steel reinforcement cage, then by pre-buried I type grout sleeve in template, pours mixed Form removal obtains composite beam after solidifying soil reaches prescribed strength;
(c) site operation
By the upright simultaneously fixation of prefabricated post, position and the distance of prefabricated post and precast beam are adjusted, in pre-buried I type of precast beam Connection reinforcing bar is put into grout sleeve, will connect pre-buried II type grouting set of the reinforcing bar into prefabricated post it is mobile until connection reinforcing bar with Anchor bar contacts or spaced apart, blocks embedded sleeve barrel and is simultaneously in the milk, finally fills prefabricated post and prefabricated with mortar joint Gap between beam;
Or by the upright simultaneously fixation of prefabricated post, position and the distance of prefabricated post and composite beam are adjusted, in the pre- of composite beam It buries in I type grout sleeve and is put into connection reinforcing bar, pre-buried II types grout sleeve is inserted in the precast beam upper longitudinal bar of composite beam, it will even Connect that pre-buried II type grouting set of the reinforcing bar into prefabricated post is mobile until connection reinforcing bar contacts or spaced apart with anchor bar, By the pre-buried II type grout sleeve on composite beam to the movement of prefabricated post embedded bar direction until the reinforcing bar length on sleeve both sides is close Patibhaga-nimitta etc. blocks embedded sleeve barrel and is in the milk, last casting concrete.
8. a kind of construction method of assembled beam-column node as claimed in claim 7, it is characterised in that:It is prefabricated in step (c) The connection between precast beam upper longitudinal bar in prefabricated post embedded bar in column and composite beam is changed by pre-buried II type grout sleeve For welding, the length of weld seam is equivalent to 10 times of precast beam upper longitudinal bar diameter.
9. a kind of construction method of assembled beam-column node as claimed in claim 7, it is characterised in that:It is also set in prefabricated post It is equipped in the column of stretching composite beam in precast beam or column, composite beam is prefabricated into one with prefabricated post in precast beam or column in the column Body, the precast beam or composite beam deck-molding that composite beam extension elongation is 1.5 times in precast beam or column in column, in column in precast beam or column The end of composite beam forms bean column node with precast beam or composite beam.
CN201810242073.XA 2018-03-22 2018-03-22 A kind of assembled beam-column node and its construction method Pending CN108625477A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810242073.XA CN108625477A (en) 2018-03-22 2018-03-22 A kind of assembled beam-column node and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810242073.XA CN108625477A (en) 2018-03-22 2018-03-22 A kind of assembled beam-column node and its construction method

Publications (1)

Publication Number Publication Date
CN108625477A true CN108625477A (en) 2018-10-09

Family

ID=63696169

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810242073.XA Pending CN108625477A (en) 2018-03-22 2018-03-22 A kind of assembled beam-column node and its construction method

Country Status (1)

Country Link
CN (1) CN108625477A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109267700A (en) * 2018-10-18 2019-01-25 上海宝冶集团有限公司 A kind of assembled beam-column node area reinforcing bar arrangement
CN109322388A (en) * 2018-11-13 2019-02-12 深圳大学 A kind of assembled beam-column node structure positioned at plastic zone energy dissipation
CN111236423A (en) * 2020-01-06 2020-06-05 三箭建设工程集团有限公司 Semi-dry type connecting joint of frame beam and column and construction method thereof
CN113684922A (en) * 2021-09-27 2021-11-23 南通市建设工程质量监督站 Weather-proof structure of assembled component connecting interface and construction method
CN115354759A (en) * 2022-07-26 2022-11-18 中国航空规划设计研究总院有限公司 Connecting joint of prefabricated steel reinforced concrete column and prefabricated reinforced concrete beam and construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205875417U (en) * 2016-08-15 2017-01-11 陕西建工第一建设集团有限公司 Construction structures is connected with pre -buried straight screw sleeve to rearmounted girder iron muscle
CN106759873A (en) * 2017-03-25 2017-05-31 河北合创建筑节能科技有限责任公司 A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN206328864U (en) * 2016-11-30 2017-07-14 上海建工二建集团有限公司 Assembled beam-column node structure
CN206607753U (en) * 2017-03-14 2017-11-03 中国华冶科工集团有限公司 After pour beam steel anchor
CN107326810A (en) * 2017-08-03 2017-11-07 武汉理工大学 The reserved grout hole connection method of precast assembly bridge pier
CN107447857A (en) * 2017-07-12 2017-12-08 东南大学 The replaceable power consumption connection component of beam-ends of assembly concrete framework
CN206784739U (en) * 2017-05-16 2017-12-22 沈阳卫德住宅工业化科技有限公司 A kind of new reinforcing steel bar connection grout sleeve
CN206844314U (en) * 2017-05-10 2018-01-05 福建璟榕工程建设发展有限公司 A kind of new prefabricated assembled bean column node
CN206928526U (en) * 2017-05-04 2018-01-26 河北建筑工程学院 A kind of half grout sleeve of bar connecting
CN107700361A (en) * 2017-09-28 2018-02-16 上海应用技术大学 A kind of dumb-bell shape grout sleeve and the method that assembling construction is carried out with the grout sleeve

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205875417U (en) * 2016-08-15 2017-01-11 陕西建工第一建设集团有限公司 Construction structures is connected with pre -buried straight screw sleeve to rearmounted girder iron muscle
CN206328864U (en) * 2016-11-30 2017-07-14 上海建工二建集团有限公司 Assembled beam-column node structure
CN206607753U (en) * 2017-03-14 2017-11-03 中国华冶科工集团有限公司 After pour beam steel anchor
CN106759873A (en) * 2017-03-25 2017-05-31 河北合创建筑节能科技有限责任公司 A kind of new prefabricated integral frame structure prefabricated post is constructed with prefabricated beam connecting node
CN206928526U (en) * 2017-05-04 2018-01-26 河北建筑工程学院 A kind of half grout sleeve of bar connecting
CN206844314U (en) * 2017-05-10 2018-01-05 福建璟榕工程建设发展有限公司 A kind of new prefabricated assembled bean column node
CN206784739U (en) * 2017-05-16 2017-12-22 沈阳卫德住宅工业化科技有限公司 A kind of new reinforcing steel bar connection grout sleeve
CN107447857A (en) * 2017-07-12 2017-12-08 东南大学 The replaceable power consumption connection component of beam-ends of assembly concrete framework
CN107326810A (en) * 2017-08-03 2017-11-07 武汉理工大学 The reserved grout hole connection method of precast assembly bridge pier
CN107700361A (en) * 2017-09-28 2018-02-16 上海应用技术大学 A kind of dumb-bell shape grout sleeve and the method that assembling construction is carried out with the grout sleeve

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
卢家森: "《装配整体式混凝土框架实用设计方法》", 31 July 2016, 湖南大学出版社 *
周起敬: "《混凝土结构构造手册(第二版)》", 31 December 1999, 中国建筑工业出版社 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109267700A (en) * 2018-10-18 2019-01-25 上海宝冶集团有限公司 A kind of assembled beam-column node area reinforcing bar arrangement
CN109267700B (en) * 2018-10-18 2020-08-14 上海宝冶集团有限公司 Assembled beam column node area reinforcing bar structure of arranging
CN109322388A (en) * 2018-11-13 2019-02-12 深圳大学 A kind of assembled beam-column node structure positioned at plastic zone energy dissipation
CN109322388B (en) * 2018-11-13 2024-03-22 深圳大学 Assembly type beam column node structure located in plastic area for earthquake resistance and energy consumption
CN111236423A (en) * 2020-01-06 2020-06-05 三箭建设工程集团有限公司 Semi-dry type connecting joint of frame beam and column and construction method thereof
CN113684922A (en) * 2021-09-27 2021-11-23 南通市建设工程质量监督站 Weather-proof structure of assembled component connecting interface and construction method
CN115354759A (en) * 2022-07-26 2022-11-18 中国航空规划设计研究总院有限公司 Connecting joint of prefabricated steel reinforced concrete column and prefabricated reinforced concrete beam and construction method
CN115354759B (en) * 2022-07-26 2023-04-14 中国航空规划设计研究总院有限公司 Prefabricated steel reinforced concrete column-prefabricated reinforced concrete beam connecting joint and construction method

Similar Documents

Publication Publication Date Title
CN108625477A (en) A kind of assembled beam-column node and its construction method
CN107795010B (en) Precast beam column joint and construction method thereof
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN104775516B (en) Field connecting method among prefabricated reinforced concrete columns
CN110439137A (en) Prefabricated panel, wall and prefabricated panel production method, precast wall body construction method
CN105134009B (en) Sill coping concrete structure of frame structure infilled wall and construction method
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
CN105926771B (en) A kind of the interior joint connection structure and its construction method of prefabricated integral frame column beam
CN109296066A (en) Assembly concrete beam column sleeve combination connecting node
CN109235662A (en) A kind of column board connecting equipment comprising multiple shear connector
CN108265824A (en) A kind of high ductility concrete beam and column node of assembled and connection method
CN108086488A (en) Assembled frame-shear structure wall splitlevel connection structure and assembling method
CN209260897U (en) Assembly concrete beam column sleeve combination connecting node
CN208105477U (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L shape connecting node
CN207260378U (en) A kind of assembled frame-shear structure curved scissors type combines keyway connection structure
CN109881776A (en) A kind of assembling prefabricated reinforced concrete tubular column structure and construction method
CN114215090A (en) Construction method of raft and compression pile in closed space
CN106592759A (en) Assembly type reinforced concrete frame beam column joint and preparation method
CN109056520A (en) A kind of bolt connection of prefabricated overhead guardrail board
CN109267585A (en) Assembled prismoid shaped basis and rod structure and assembly method
CN108265823A (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L-shaped connecting node
CN106337530B (en) A kind of construction of frame beam seams stifled construction method
CN105839851B (en) Using the construction method for the prefabricated frame trestle that segmentation connection is formed
CN108104310A (en) Assembled frame-shear structure column splitlevel connection structure and assembling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181009

RJ01 Rejection of invention patent application after publication