CN108612346A - GIS intelligence dust-free operation methods - Google Patents

GIS intelligence dust-free operation methods Download PDF

Info

Publication number
CN108612346A
CN108612346A CN201810454951.4A CN201810454951A CN108612346A CN 108612346 A CN108612346 A CN 108612346A CN 201810454951 A CN201810454951 A CN 201810454951A CN 108612346 A CN108612346 A CN 108612346A
Authority
CN
China
Prior art keywords
gis
dust
skeleton
tarpaulin
free operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810454951.4A
Other languages
Chinese (zh)
Inventor
陶鸿飞
潘继飞
顾祖良
屠建国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaoxing Jianyuan Electric Group Co Ltd
Shaoxing Daming Power Construction Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Shaoxing Jianyuan Electric Group Co Ltd
Shaoxing Daming Power Construction Co Ltd
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaoxing Jianyuan Electric Group Co Ltd, Shaoxing Daming Power Construction Co Ltd, Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Shaoxing Jianyuan Electric Group Co Ltd
Priority to CN201810454951.4A priority Critical patent/CN108612346A/en
Publication of CN108612346A publication Critical patent/CN108612346A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H1/00Buildings or groups of buildings for dwelling or office purposes; General layout, e.g. modular co-ordination or staggered storeys
    • E04H1/12Small buildings or other erections for limited occupation, erected in the open air or arranged in buildings, e.g. kiosks, waiting shelters for bus stops or for filling stations, roofs for railway platforms, watchmen's huts or dressing cubicles
    • E04H1/1277Shelters for decontamination
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B3/00Apparatus specially adapted for the manufacture, assembly, or maintenance of boards or switchgear
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B1/2403Connection details of the elongated load-supporting parts
    • E04B2001/2406Connection nodes
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B2001/2466Details of the elongated load-supporting parts

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Tents Or Canopies (AREA)

Abstract

This application involves a kind of GIS intelligences dust-free operation method, belong to the special purpose building technical field that site operation or installation are carried out using civil engineering technology.By track installation in position both sides to be installed, the removable engine-bed slid along is set in orbit, skeleton is mounted on removable engine-bed, and in skeleton periphery and top fitting isolation tarpaulin, dust-free operation space is formed, GIS tube passages are arranged in the isolation tarpaulin direction along ng a path, and the GIS tube passages are through the corresponding two side walls of isolation tarpaulin, GIS pipelines to be installed enter dust-free operation space by one end of GIS tube passages, and are stretched out through the other end;After being installed at one, removable engine-bed drives skeleton and isolation tarpaulin thereon to move, and carries out the installation of GIS pipelines next time.The application is applied to the dustless installation of intelligence of GIS, has many advantages, such as good airproof performance, moves, is highly practical.

Description

GIS intelligence dust-free operation methods
Technical field
This application involves a kind of GIS intelligences dust-free operation method, belongs to and site operation is carried out using civil engineering technology Or the special purpose building technical field of installation.
Background technology
Cubicle Gas-Insulated Switchgear GIS(Gas Insulatedmetal-enclosed Switchgear)It is Using sulfur hexafluoride (SF6) gas is using the air under the atmospheric pressure as the metal enclosed switch of dielectric without being set It is standby.
Compared with traditional equipment, GIS has used insulation performance and the excellent sulfur hexafluoride (SF of arc extinction performance6) gas conduct Insulation and arc-extinguishing medium, and High-Voltage Electrical Appliances and insulating part are sealed in grounded metal cylinder, have that floor space is small, element is whole It seals not by environmental disturbances, operational reliability is high, installs the advantages that rapid, operating cost is low, without electromagnetic interference.
However, installing operating mode as a kind of typical outdoor continuous equipment, the unit that GIS installations are related to is more, peace The dress period is long, and installation process is influenced very big by outside environmental elements.
Related data counts and operating experience shows that the failure of GIS device mostly occurs within new equipment puts into operation 1 year, and one As the 1st year operation when, equipment failure rate be 0.53 time/interval, and then drop within the 2nd year 0.06 time/interval, tend to later flat Surely.
With regard to its failure reason analysis, accounts for about the 26% of GIS total failares derived from failure caused by manufactory, is derived from installation Caused by failure account for about the 40% of GIS total failares, account for about GIS total failares derived from failure caused by design 7%, be derived from other reasons Caused by failure account for about the 27% of GIS total failares and analyzed from data, GIS device is to lead to equipment in the problems in installation The sensible factor of failure needs strictly to avoid.
Installation environment is an important factor for influencing GIS device installation quality, and GIS device installation has ratio to site environment Higher requirement.
《1000kV High-Voltage Electrical Appliances(GIS, HGIS, disconnecting switch, arrester)Construction and acceptance specification rule》(GB 50836- 2013)Clear stipulaties:Cubicle Gas-Insulated Switchgear(GIS)In-site installation should in no dust storm, without sleet, air phase Humidity is less than under conditions of 80% and is carried out, and effective dust-proof, moisture preventive measure should be taken;The dustproof room built should meet production Product specification of technical file.
GIS device installation under normal circumstances should be between -10 DEG C to 40 DEG C of environment temperature, no dust storm, without sleet, air phase Humidity is less than under conditions of 80% and is carried out, cleanliness factor should be at million grades or more.When 220 kilovolts or more open air GIS installations, one As should set up dust-proof shed, temperature, humidity, cleanliness factor are monitored in real time;The GIS device installation of extra-high voltage open air should generally use Being made by manufacturers or users formula workshop carries out real-time control to temperature, humidity, cleanliness factor(At 10-25 DEG C, humidity is small for temperature control in workshop In 70%, cleanliness factor is at million grades or more), realize batch production installation.
Fixed dust-free workshop is current most common dustproof room form.Fixed dust-free workshop, although in anti-dust performance And have some superiority in stability, but install and remove the time and need the cost time long, economic cost is relatively high.Therefore, For GIS device installing engineering, fixed dust-free workshop cannot meet the requirement of duration of a project and benefit;Compared to fixation Formula dust-free workshop, mobile dust-free workshop can be adjusted flexibly, build with remove the used time it is shorter, be more suitable in GIS device erector It is used in journey.But mobile dust-free workshop needs to realize that structure moves and dust-proof effect simultaneously, this is a bigger skill Art problem, and not all mobile workshop can meet the needs of GIS device installing engineering.
The dustless installation air film workshops GIS are another common dust-free workshops, use air film as main structure body, internal Facility is simple, but integrally closed is poor, and structure lacks enough stability, and dust-proof effect cannot reach requirement, actually makes Desired effect can not be realized in.
Based on this, the application is made.
Invention content
For the existing drawbacks described above of existing GIS installations, the application provides a kind of mobile GIS intelligences nothing of practicality Dirt operational method, the influence to avoid outside environmental elements to GIS installing engineerings ensure GIS device installation quality, while being also Ensure duration of a project and Project Benefit.
To achieve the above object, the technical solution that the application takes is as follows:
GIS intelligence dust-free operation methods, by track installation in position both sides to be installed, what setting slid along in orbit can Mobile engine base, skeleton are mounted on removable engine-bed, and in skeleton periphery and top fitting isolation tarpaulin, it is empty to form dust-free operation Between, GIS tube passages are arranged in the isolation tarpaulin direction along ng a path, which runs through the corresponding two side walls of isolation tarpaulin, GIS pipelines to be installed enter dust-free operation space by one end of GIS tube passages, and are stretched out through the other end;It waits for installing at one Bi Hou, removable engine-bed drive skeleton and isolation tarpaulin thereon to move, carry out the installation of GIS pipelines next time.
Further, as preferred:
The skeleton is assembling frame structure.It is furthermore preferred that the skeleton is by several groups skeleton unit disposed in parallel It constitutes, each skeleton unit includes an at least column, a top beam, is at least connected with part, two be arranged in pairs column point Top beam both sides are occupied, and are attached with connector between top beam, are controlled into line space with tie-beam between adjacent skeleton unit. It is furthermore preferred that being provided at least one crossbeam between the pair of column, controlled into line space by crossbeam between column.It is described Connector be arcuate structure, rounding off is formed between top beam and column.The top beam is domes, and preferably Inverted v-shaped structure, arcuate structure or similar structures.The connector is towards top beam, connector towards column, column towards even Fitting, top beam towards connector one end be both provided with link block, to realize the dress of connector and top beam, connector and column Match.The application is under the demand for considering GIS device installing engineering, using aluminum alloy frame as skeleton, the top of skeleton unit Beam can be completed with connector prior to ground, after the isolation tarpaulin of good corresponding part to be installed, be lifted by crane using crane i.e. reachable To precalculated position;And crossbeam, tie-beam and column are sequentially installed, combination forms aluminium alloy truss module, you can installation is complete Skeleton agent structure, equipment frame, Airshower chamber frame are in place.The main part of the program is Spliced type light-high-strength aluminium alloy The skeleton that tube frame is constituted, it is whole by multiple removable independent small workshops which forms workshop(That is skeleton unit)Combination and At meeting stable structure and slim and graceful requirement.Meanwhile whether top beam, column or crossbeam, tie-beam even connector etc. Structural elements can use standardized module, installation remove, is easy to maintenance, and the Component composition mode of wherein top beam is more, with It well adapts to roof of different shapes and builds needs, modular component can also be taken by adjusting to adapt to different size workshop It builds, realizes component recycling afterwards in project that can be, improve the workshops GIS usage economy.
The isolation tarpaulin is PC membrane materials, thickness 0.5-1mm.The application is using thickness in the high-strength of 0.5 ~ 1mm PC materials are spent as tarpaulin, meet the closure requirement in the workshops GIS, while the partition plate phase used with conventional fixed-type workshop Than high-strength PC material has more advantages in transport, installation, keeping etc..Investigation result shows, high-strength PC material tension Intensity is larger, fire resistance is fabulous, and anti-aging property is good, has good processability, disclosure satisfy that subsequent project pair The requirement of tarpaulin material recycling.The application is under the demand for considering GIS device installing engineering, using high-strength PC material For be isolated tarpaulin, at the top of skeleton and around respectively fitting installation ceiling, workshop main body, that is, complete isolation tarpaulin it is in place, by Cleaner and workshop integrated combination.It is furthermore preferred that the isolation tarpaulin further includes having wind to drench channel.
The inboard wall of skeleton is provided with fixed frame, and commonly used equipment such as dust removal machine, clarifier etc. is carried out as equipment frame It is fixed;Travelling frame is set with wind leaching channel corresponding position, for disposing wind leaching channel and Airshower chamber.GIS dust-free workshops need Serial equipment is supported, including the equipment such as dust removal machine, Airshower chamber, and conventional mobile workshop, which is typically chosen, to be independently arranged, but workshop is moved During dynamic, autonomous device can influence workshop mobile space and sealing performance.And fixed frame is arranged in the application on inboard wall of skeleton, Equipment, Airshower chamber is integrated with operation room, realize integration movement.GIS dust-free workshops need Airshower chamber because volume compared with Greatly, it can not complete built in entirety, Scheme Choice disposes packaged type frame in workshop inlet setting Airshower chamber, with general frame It is combined, to realize Airshower chamber and workshop synchronizing moving.In Airshower chamber and workshop main body junction, Scheme Choice uses PC tarpaulins It is flexible coupling, realizes qualified sealing effect.
The removable engine-bed includes pedestal and pulley, and pedestal top is connect with skeleton, several pulleys are installed in lower part, Moveable roller is installed on track, and drives it to be slided along track by driver, and then opposite with moving base and its upper skeleton The sliding of track.It is furthermore preferred that the pulley is mounted on pedestal lower part by connecting rod, link tilt is inwardly arranged, to ensure The installation of pulley and track is stablized.Pulley clamp it is in orbit, and can relative orbit movement, you can realize that the whole of workshop moves It is dynamic, workshop mobile route can be preferably controlled, relatively efficiently avoids workshop because pedestal offset occurs in moving process The possibility of excessive deformation and the predetermined mobile route that shifts, when realizing the mobile demand in the workshops GIS, moving member(I.e. Pulley)Below pedestal, the mobility and sealing and dustproof in operation room are also taken into account, outside environmental elements pair have been completely cut off The influence of GIS installing engineerings meets requirement of the GIS installing engineerings to construction environment.Traction is provided on the pedestal to connect Mouthful, for being connect with hoist engine or driver, interface is drawn on pedestal, unified drawing is carried out in conjunction with hoist engine or other drivers It is dynamic, it realizes the effect of mechanical-assisted workshop movement, larger facility is provided for workshop movement.
On erection sequence, main flow has the following steps in the dust-free operation room of above structure:
1)The installation of track and removable engine-bed:In precalculated position attachment rail to be installed, removable engine-bed is in place.
GIS intelligence dust-free operations workshop considers GIS device installing engineering demand, uses the dustless peaces of mobile GIS Scheme between entrucking, using aluminum alloy frame as skeleton, high-strength PC material is isolation tarpaulin, by cleaner and workshop one Change combination, realize that workshop moves integrally by track and movable base, while having taken into account mobility and sealing and dustproof performance, Completely cut off influence of the outside environmental elements to GIS installing engineerings, meets requirement of the GIS installing engineerings to construction environment.
Assembling frame structure, seal isolation part is used to use high-strength PC membrane material, basic courses department in this programme structure Divide the form for having used track and mobile foundation to combine.
2)Ceiling assembles:The ceiling of isolation tarpaulin is completed on ground in advance, it is ensured that after leakproofness, recycles crane etc. Facility is lifted by crane, precalculated position is lifted to.
3)Workshop agent structure installation:According to workshop or the demand of operation occasion, each component part of skeleton is subjected to group It closes, workshop agent structure that installation is complete, and equipment frame, movable framework is in place.
4)Tarpaulin installation is isolated:It is bonded installation workshop main body respectively in the side of skeleton, and ensures GIS tube passages and track Direction is consistent, and it is consistent with the movable framework on skeleton that wind drenches channel.In wind leaching channel and workshop main body junction, it is preferable to use PC tarpaulins are flexible coupling, and realize qualified sealing effect.
The application forms skeleton by structure of aluminum alloy frame, using high-strength PC material as isolation tarpaulin, the two combination It is formed and moves GIS dust-frees assembly shop, which takes into account outside the ability that reply scene is adjusted flexibly and good isolation The ability of portion's such environmental effects, with relevant device no-float, interior layout is reasonable, is provided for GIS device installing engineering The working environment of high standard has ensured GIS device installation engineering quality.The aluminum alloy junction that the GIS operations room of above structure uses Structure module and PC tarpaulins improve the usage economy of GIS dust-free workshops, it can be achieved that recycling.The project have accumulated GIS without The construction experience in dirt workshop, solves serial problem, can be that the later workshops GIS construction is offered reference.
Therefore, said program, which is formed by GIS intelligence dust-free operation methods, realizes the demand of three aspects:
a)Take into account removable and anti-dust performance:It is suitable to assign it for the cooperation of above-mentioned GIS operations room skeleton and removable engine-bed, track The mobility of installation environment is answered, while skeleton assigns its qualified envelope with the setting that tarpaulin, fixed frame, movable framework is isolated Closing property can realize effective isolation to external environment, achieve the effect that dust-proof, waterproof.
b)Topology layout is reasonable:Under the premise of structure is moveable, ensure workshop structure reliability and stability;GIS vehicles Between it is internal should have sufficient space, construction requirement need to be met, it is rationally distributed.
c)It is economical and practical:The workshops GIS should meet cost-effectiveness requirement, and cost is reasonable, and later stage use, maintenance cost are reasonable;Vehicle Between component should be able to realize recycling.
Description of the drawings
Fig. 1 is the stereoscopic schematic diagram of the first structure of the embodiment of the present application middle skeleton;
Fig. 2 is the side schematic view of the first structure of the embodiment of the present application middle skeleton;
Fig. 3 is the schematic top plan view of the first structure of the embodiment of the present application middle skeleton;
Fig. 4 is the stereoscopic schematic diagram of second of structure of the embodiment of the present application middle skeleton;
Fig. 5 is the stereoscopic schematic diagram at another visual angle of second of structure of the embodiment of the present application middle skeleton;
Fig. 6 is the side schematic view of second of structure of the embodiment of the present application middle skeleton;
Fig. 7 is the stereoscopic schematic diagram of the first structure of isolation tarpaulin in the embodiment of the present application;
Fig. 8 is the perspective elevation of the first structure of isolation tarpaulin in the embodiment of the present application;
Fig. 9 is the side schematic view of the first structure of isolation tarpaulin in the embodiment of the present application;
Figure 10 is the stereoscopic schematic diagram that second of structure of tarpaulin is isolated in the embodiment of the present application;
Figure 11 is the perspective elevation that second of structure of tarpaulin is isolated in the embodiment of the present application;
Figure 12 is the side schematic view that second of structure of tarpaulin is isolated in the embodiment of the present application;
Figure 13 is the stereoscopic schematic diagram of the third structure of isolation tarpaulin in the embodiment of the present application;
Figure 14 is the perspective elevation of the third structure of isolation tarpaulin in the embodiment of the present application;
Figure 15 is the side schematic view of the third structure of isolation tarpaulin in the embodiment of the present application.
Figure label:1. skeleton;1a. skeleton units;11. column;12. top beam;13. connector;14. connection Beam;15. crossbeam;16. link block;17. crane hook;18. travelling frame;2. tarpaulin is isolated;21. ceiling;211. hanging Fill angle;22. workshop main body;23. wind drenches channel;24. GIS tube passages;241. tapered channel;25. daylighting window;3. rail Road;4. removable engine-bed;41. pedestal;42. pulley;43. connecting rod;44. drawing interface;5. GIS pipelines.
Specific implementation mode
Embodiment 1
Track 3 is mounted on position both sides to be installed, edge is arranged on the track 3 by the present embodiment GIS intelligence dust-free operation methods Its removable engine-bed 4 slided, skeleton 1 are mounted on removable engine-bed 4, and in 1 periphery of skeleton and top fitting isolation tarpaulin 2, dust-free operation space is formed, isolation tarpaulin 2 is along 3 direction of track setting GIS tube passages 24, and the GIS tube passages 24 are through isolation 2 corresponding two side walls of tarpaulin, GIS pipelines 5 to be installed enter dust-free operation space by one end of GIS tube passages 24, and pass through The other end stretches out;After being installed at one, removable engine-bed 4 drives skeleton 1 and isolation tarpaulin 2 thereon to move, into The installation of capable GIS pipelines 5 next time.
Wherein, the dust-free room formed in above-mentioned operation process includes skeleton 1, isolation tarpaulin 2, track 3 and moves Engine base 4, in conjunction with Fig. 1, removable engine-bed 4 is arranged in 1 bottom of skeleton, and removable engine-bed 4 is slidably mounted on track 3, and tarpaulin 2 is isolated Fitting is installed on 1 outer wall of skeleton, and for being sealed installation to the GIS device in skeleton 1, removable engine-bed 4 is slided along track 3 It is dynamic, that is, drive the isolation tarpaulin 2 on skeleton 1 and skeleton 1 thereon to move.The GIS operations room of above structure, skeleton 1 with can The cooperation of mobile engine base 4, track 3, assigns its mobility for adapting to installation environment, while skeleton 1 and setting that tarpaulin 2 is isolated Its qualified closure is assigned, effective isolation can be realized to external environment, achieve the effect that dust-proof, waterproof.
To realize that more using effects, said program can also add as follows:
In conjunction with Fig. 1-Fig. 6, skeleton 1 is assembling frame structure.
As a kind of concrete scheme of assembling frame structure, skeleton 1 is by several groups skeleton unit 1a structures disposed in parallel At each skeleton unit 1a includes 11, top beams 12 of an at least column, is at least connected with part 13, two be arranged in pairs 12 both sides of the separation top beam of column 11, and be attached with connector 13 between top beam 12, with even between adjacent skeleton unit 1a Beam 14 is connect to control into line space.
Said program can also be preferably arranged to:Be provided at least one crossbeam 15 between one column 11, column 11 it Between by crossbeam 15 into line space control.
Said program can also be preferably arranged to:Connector 13 is arcuate structure, is formed between top beam 12 and column 11 Rounding off.
Said program can also be preferably arranged to:Top beam 12 is domes, and preferably inverted v-shaped structure, arc knot Structure or similar structures.
Said program can also be preferably arranged to:Connector 13 is towards top beam 12, connector 13 towards column 11, column 11 It is both provided with link block 16 towards one end of connector 13, top beam 12 towards connector 13, which may be selected to be sheet Structure, corresponding link block 16 is stitched together, then is fixed in a manner of bolt, screw etc., you can realize connector 13 with The assembly of top beam 12, connector 13 and column 11.
The application is under the demand for considering GIS device installing engineering, using aluminum alloy frame as skeleton 1, skeleton list The top beam 12 of first 1a can be completed with connector 13 prior to ground, after the isolation tarpaulin 2 of good corresponding part to be installed, using hanging Vehicle lifting can reach precalculated position(Such as the crane hook 17 being arranged in Fig. 4-Fig. 6);And crossbeam 15, tie-beam 14 and column 11 It sequentially installs, combination forms aluminium alloy truss module, you can skeleton agent structure that installation is complete.The main part of the program is can The skeleton 1 that spliced light-high-strength aluminium-alloy pipe frame is constituted, it is whole by multiple removable independent which forms workshop Small workshop(That is skeleton unit 1a)It is composed, meets stable structure and slim and graceful requirement.Meanwhile whether top beam 12, column The structural elements such as 11 or crossbeam 15, tie-beam 14 even connector 13 can use standardized module, install, remove, Easy to maintenance, the Component composition mode of wherein top beam 12 is more, and needs, modularization are built to well adapt to roof of different shapes Component can also be built by adjusting to adapt to different size workshop, in project that can be afterwards realize component recycling, carry The high workshops GIS usage economy.
To realize that more using effects, said program can also add as follows:Isolation tarpaulin 2 is PC films Material, thickness 0.5-1mm.The application uses thickness, as tarpaulin, to meet the workshops GIS in the high-strength PC material of 0.5 ~ 1mm Closure requirement, while compared with the partition plate that conventional fixed-type workshop uses, high-strength PC material is in transport, installation, guarantor Pipe etc. has more advantages.Investigation result shows that high-strength PC Tensile strength is larger, fire resistance is fabulous, anti-aging It is functional, there is good processability, disclosure satisfy that the requirement that subsequent project reuses tarpaulin material.The application Under the demand for considering GIS device installing engineering, use high-strength PC material for tarpaulin 2 is isolated, in the top of skeleton 1 and week Fitting installation respectively is enclosed, that is, the in place of isolation tarpaulin is completed, by cleaner and workshop integrated combination.
Said program can also be preferably provided with as follows:
In conjunction with Fig. 7-Figure 15, isolation tarpaulin 2 includes ceiling 21, workshop main body 22, wind leaching channel 23 and GIS tube passages 24, ceiling 21 fittings are installed on 1 top of skeleton(That is the top beam 12 of skeleton 1,13 position of connector), workshop main body 22 fitting be installed on On periphery other than 1 top of skeleton(Each position i.e. where column 11, tie-beam 14, crossbeam 15), ceiling 21 and workshop main body 22 are an integral structure, and wind leaching channel 23 and GIS tube passages 24 are opened in respectively on 22 different lateral of workshop main body, and GIS is managed Channel 24 is consistent with 3 direction of track, and runs through 21 corresponding two wall of workshop main body in the direction.
Wherein:Lifting angle 211 is provided on ceiling 21, to facilitate the installation of isolation tarpaulin 2.Angle 211 is lifted to can be selected such as Fig. 7-Fig. 9 either outwardly projecting horn structure or the wedge angle knot being recessed inwardly as illustrated in figs. 13-15 as shown in figs. 10-12 Structure, to be considered in GIS device installing engineering the case where adapting to shop locations fine tuning, to the use demand of crane equipment.This Shen The flexibility characteristics that please utilize PC materials, use for reference the concept of automobile handle of gear dirt-proof boot, and setting lifting angle 211, forms at ceiling 21 The ceiling structure of taper may be implemented being finely adjusted for multi-angle, provide certain adjustment space while ensureing sealing, with Site error is adapted to, in the case of control workshop specification, scheme is used using lifting angle 211, is reserved at the lifting angle 211 The crane hook 17 as shown in Fig. 4-6 and Fig. 7-15 realizes the effect for lifting work outside workshop in crane participation workshop, substitutes vehicle Between internal driving, economically realize slinger's work energy in workshop.The isolation tarpaulin of the structure can realize a front and back left side Right each 1 meter, each 3 meters of position change up and down, the reserved space of abundance is provided for the movement of crane hook, keeps lifting work suitable Profit carries out.
Said program can also be preferably provided with as follows:In conjunction with Fig. 9, Figure 12, Figure 15, GIS tube passages 24 are by workshop main body 22 Inner wall extends outwardly, and forms interior big outer small tapered channel 241.The tapered channel 241 corresponds to GIS pipelines 5 and crosses workshop main body 22 position realizes pipeline and moves relatively, while ensureing the sealing performance in workshop using material flexibility.
Said program can also be preferably provided with as follows:In conjunction with Fig. 7-Figure 15, workshop main body 22(Referring to respective view)Or Ceiling 21(It is not shown in figure)On be provided with transparent daylighting window 25, introduce natural light outside source, it is convenient to construct in the daytime, reduce Sense of depression in workshop.
To realize that more using effects, said program can also add fixed frame and travelling frame as follows 18:1 inner wall of skeleton is provided with fixed frame, and the fixation of commonly used equipment such as dust removal machine, clarifier etc. is carried out as equipment frame;Skeleton 1 Entrance(Channel 23 is drenched corresponding to wind)Place's setting travelling frame 18, for disposing Airshower chamber.GIS dust-free workshops need series to set It is standby to support, including the equipment such as dust removal machine, Airshower chamber, conventional mobile workshop, which is typically chosen, to be independently arranged, but workshop moving process In, autonomous device can influence workshop mobile space and sealing performance.And fixed frame is arranged in the application on inboard wall of skeleton, will set Standby, Airshower chamber is integrated with operation room, realizes integration movement.The Airshower chamber that GIS dust-free workshops need is because volume is larger, nothing Method is completed built in entirety, and Scheme Choice disposes packaged type frame in workshop inlet setting Airshower chamber, is mutually tied with general frame It closes, to realize Airshower chamber and workshop synchronizing moving.In Airshower chamber and 22 junction of workshop main body, Scheme Choice is soft using PC tarpaulins Qualified sealing effect is realized in connection.
To realize that more using effects, said program can also add as follows:In conjunction with Fig. 1, removable motivation Seat 4 includes pedestal 41 and pulley 42,41 top of pedestal and skeleton 1(Column 11)Several pulleys 42 are installed in connection, lower part, sliding It takes turns 42 active cards to be loaded on track 3, and by driver(It is not shown in figure)It is driven to be slided along track 3, and then with moving base 41 And the sliding of its 1 relative orbit 3 of upper skeleton.It is furthermore preferred that in conjunction with Fig. 6, pulley 42 is mounted on by connecting rod 43 under pedestal 41 Portion, 43 inwardly angled setting of connecting rod, to ensure that pulley 42 and the installation of track 3 are stablized.Pulley 42 clamps on the track 3, and can Relative orbit 3 moves, you can realizes the overall movement in workshop, can preferably control workshop mobile route, relatively efficiently avoid Workshop because the possibility of excessive deformation and the predetermined mobile route that shifts occurs in moving process for pedestal offset, When realizing the mobile demand in the workshops GIS, moving member(That is pulley 42)Positioned at 41 lower section of pedestal, the removable of operation room has also been taken into account Dynamic property and sealing and dustproof, have completely cut off influence of the outside environmental elements to GIS installing engineerings, have met GIS installing engineerings to applying The requirement of work environment.
Said program can also be further arranged:It is provided with traction interface 44 on pedestal 41, is used for and hoist engine or drive Dynamic device connection, draws interface 44 on pedestal 41, carries out unified pulling in conjunction with hoist engine or other drivers, realizes mechanical-assisted The effect of workshop movement provides larger facility for workshop movement.
The square proximate matter that 300mm × 300mm can be used using cross sectional dimensions for the frame that scheme uses makes, construction weight About 5.5kg/ meters, estimated overall weight is at 1000 kilograms or so after this project installs work, and in conjunction with external cable wind rope, structure is whole 6 grades of body wind loading rating, meets stable structure and slim and graceful requirement.Meanwhile whether top beam 12, column 11 or crossbeam 15, even Standardized module can be used by connecing the even structural elements such as connector 13 of beam 14, be divided into tie-beam 14(2 meters, 3 meters), crossbeam 15(1 meter, 2 meters, 3 meters), column 11(1 meter, 2 meters, 3 meters), top beam 12(Arch or herringbone beam can be used, such as curved section, top Section, middle node, column lengthen block), totally four classes, closes 12 kinds of modules, and installation removes, is easy to maintenance, wherein the component groups of top beam 12 Conjunction mode is more, and needs are built to well adapt to roof of different shapes.The workshop that project uses at present is 8m × 8m × 6m's Specification meets project construction demand, adjustment is not necessarily in same scene.Meanwhile modularizing member can be by adjusting to adapt to not Same specification workshop is built, and is realized component recycling afterwards in project that can be, is improved the workshops GIS usage economy.
The above content is the preferred embodiments of combination the invention to further detailed made by provided technical solution Describe in detail bright, and it cannot be said that the invention specific implementation is confined to these above-mentioned explanations, for the affiliated technology of the invention For the those of ordinary skill in field, without departing from the concept of the premise of the invention, several simple deductions can also be made Or replace, it all shall be regarded as belonging to the protection domain of the invention.

Claims (10)

1.GIS intelligence dust-free operation methods, it is characterised in that:By track installation in position both sides to be installed, set in orbit The removable engine-bed slid along is set, skeleton is mounted on removable engine-bed, and tarpaulin is isolated in skeleton periphery and top fitting, Dust-free operation space is formed, GIS tube passages are arranged in the isolation tarpaulin direction along ng a path, and the GIS tube passages are through isolation tarpaulin Corresponding two side walls, GIS pipelines to be installed enter dust-free operation space by one end of GIS tube passages, and are stretched through the other end Go out;After being installed at one, removable engine-bed drives skeleton and isolation tarpaulin thereon to move, and carries out GIS next time The installation of pipeline.
2. GIS intelligences dust-free operation method as described in claim 1, it is characterised in that:The skeleton is put down by several groups The skeleton unit of row setting is constituted, and each skeleton unit includes an at least column, a top beam, is at least connected with part, in pairs The two columns separation top beam both sides being arranged, and be attached with connector between top beam, with even between adjacent skeleton unit Beam is connect to control into line space.
3. GIS intelligences dust-free operation method as claimed in claim 2, it is characterised in that:It is arranged between the pair of column There is at least one crossbeam, is controlled into line space by crossbeam between column.
4. GIS intelligences dust-free operation method as claimed in claim 2, it is characterised in that:The connector is arc knot Structure forms rounding off between top beam and column.
5. GIS intelligences dust-free operation method as claimed in claim 2, it is characterised in that:The connector towards top beam, One end of connector towards column, column towards connector, top beam towards connector is both provided with link block, to realize connector With the assembly of top beam, connector and column.
6. GIS intelligences dust-free operation method as described in claim 1, it is characterised in that:The isolation tarpaulin is PC films Material, thickness 0.5-1mm.
7. GIS intelligences dust-free operation method as described in claim 1, it is characterised in that:The isolation tarpaulin side wall is also It is provided with wind leaching channel.
8. GIS intelligences dust-free operation method as claimed in claim 7, it is characterised in that:The inboard wall of skeleton is provided with Fixed frame is used as equipment frame;Travelling frame is set with wind leaching channel corresponding position, for disposing wind to drench channel.
9. GIS intelligences dust-free operation method as described in claim 1, it is characterised in that:The removable engine-bed includes Pedestal and pulley, pedestal top are connect with skeleton, several pulleys are installed in lower part, and moveable roller is installed on track, and by driving Dynamic device drives it to be slided along track, and then the sliding with moving base and its upper skeleton relative orbit.
10. GIS intelligences dust-free operation method as claimed in claim 9, it is characterised in that:It is provided with and leads on the pedestal Draw interface, for being connect with hoist engine or driver.
CN201810454951.4A 2018-05-14 2018-05-14 GIS intelligence dust-free operation methods Pending CN108612346A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810454951.4A CN108612346A (en) 2018-05-14 2018-05-14 GIS intelligence dust-free operation methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810454951.4A CN108612346A (en) 2018-05-14 2018-05-14 GIS intelligence dust-free operation methods

Publications (1)

Publication Number Publication Date
CN108612346A true CN108612346A (en) 2018-10-02

Family

ID=63663174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810454951.4A Pending CN108612346A (en) 2018-05-14 2018-05-14 GIS intelligence dust-free operation methods

Country Status (1)

Country Link
CN (1) CN108612346A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114172060A (en) * 2021-02-20 2022-03-11 李松 Dust-proof transition room for GIS room equipment to enter and exit and use method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07150816A (en) * 1993-11-30 1995-06-13 Mitsubishi Electric Corp Dust prevention assembling house
CN201601415U (en) * 2010-01-26 2010-10-06 葛洲坝集团机电建设有限公司 Dustproof and damp-proof device for multi-interface mobile GIS equipment
CN106368457A (en) * 2016-11-01 2017-02-01 山东电力建设第工程公司 Mobile sandblast dust suppression workshop
CN107448020A (en) * 2017-09-14 2017-12-08 青海送变电工程公司 A kind of transformer station's GIS device installation is removable, pin-connected panel dust-proof shed
CN107724726A (en) * 2017-10-12 2018-02-23 宁波送变电建设有限公司 A kind of dust-free operation method based on dust-proof operation canopy
CN107946995A (en) * 2017-12-05 2018-04-20 国家电网公司 A kind of dustproof room installed and safeguarded for GIS

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07150816A (en) * 1993-11-30 1995-06-13 Mitsubishi Electric Corp Dust prevention assembling house
CN201601415U (en) * 2010-01-26 2010-10-06 葛洲坝集团机电建设有限公司 Dustproof and damp-proof device for multi-interface mobile GIS equipment
CN106368457A (en) * 2016-11-01 2017-02-01 山东电力建设第工程公司 Mobile sandblast dust suppression workshop
CN107448020A (en) * 2017-09-14 2017-12-08 青海送变电工程公司 A kind of transformer station's GIS device installation is removable, pin-connected panel dust-proof shed
CN107724726A (en) * 2017-10-12 2018-02-23 宁波送变电建设有限公司 A kind of dust-free operation method based on dust-proof operation canopy
CN107946995A (en) * 2017-12-05 2018-04-20 国家电网公司 A kind of dustproof room installed and safeguarded for GIS

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114172060A (en) * 2021-02-20 2022-03-11 李松 Dust-proof transition room for GIS room equipment to enter and exit and use method thereof

Similar Documents

Publication Publication Date Title
CN103147585B (en) All-weather GIS mounting shed
CN209896529U (en) Waterproof anticorrosive cubical switchboard with shock-absorbing function
CN106522592A (en) Mobile armor hanging dustproof shed for assembling of GIS
CN101053131A (en) Transformer substation
CN108612346A (en) GIS intelligence dust-free operation methods
CN208385838U (en) Modular assembly formula dust guard
US9230734B2 (en) U-shaped iron core transporting/assembling tank
CN207863532U (en) Mobile purification installation workshop
CN107946995B (en) A dirt proof chamber for GIS installation and maintenance
CN108412241A (en) GIS intelligence dust-free operations room
CN207176922U (en) A kind of modular architectural
CN207039045U (en) A kind of high-pressure and low-pressure preassembled transformer station
CN208380176U (en) Taper tarpaulin
CN208674726U (en) A kind of landscape type underground box change
CN109193416B (en) Drag type mobile substation
CN101275454A (en) Upper rigidity contact net electric subway integral elevating translational type interval partition door
CN208006949U (en) A kind of sky iron train
CN201549794U (en) Clean room for outdoor installation of high-voltage switch gear
CN213878761U (en) Movable dustproof shed for GIS installation
CN213174408U (en) Novel steel construction building roof structure
CN103579931A (en) Compact type transformer substation
CN207518099U (en) A kind of back opening door prefabricated cabin with inspection channel
CN207039039U (en) A kind of novel high-pressure low pressure preassembled transformer station
CN207598088U (en) A kind of power sunroof for dustproof room
CN205355591U (en) Concatenation formula box substation and box -type substation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002

RJ01 Rejection of invention patent application after publication