CN108612296A - Builder's jack steel pipe locating support and its application method - Google Patents

Builder's jack steel pipe locating support and its application method Download PDF

Info

Publication number
CN108612296A
CN108612296A CN201810550663.9A CN201810550663A CN108612296A CN 108612296 A CN108612296 A CN 108612296A CN 201810550663 A CN201810550663 A CN 201810550663A CN 108612296 A CN108612296 A CN 108612296A
Authority
CN
China
Prior art keywords
steel
pedestal
rack body
locating support
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810550663.9A
Other languages
Chinese (zh)
Inventor
施群凯
焦宝余
惠小军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201810550663.9A priority Critical patent/CN108612296A/en
Publication of CN108612296A publication Critical patent/CN108612296A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/18Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by cantilevers or other provisions mounted in openings in the building, e.g. window openings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions

Abstract

The present invention relates to Construction of Steel Structure ancillary equipment fields, specifically builder's jack steel pipe locating support, it is characterized in that:Including pedestal and rack body, wherein pedestal is rectangular steel plates, opens up two circular holes at the both ends of rectangular steel plates and a reinforcing bar is arranged in the center upright of steel plate;The rack body includes rectangular in cross-section and the girder steel pedestal in bottom opening, in the outer wall at girder steel pedestal both ends and the central bore of inner wall and nut is respectively set and a bolt is threaded through in described two nuts.This steel pipe locating support is recyclable, be not necessarily to welding in installation or removal, therefore not will produce electric spark, flue gas etc., so as to improve the safety of entire scaffold installation operation while making scaffold installation operation more environmentally protective.

Description

Builder's jack steel pipe locating support and its application method
Technical field
The present invention relates to Construction of Steel Structure ancillary equipment fields, specifically builder's jack steel pipe locating support and its use Method.
Background technology
In builder's jack construction, scaffold upright rod steel pipe is stood on I-steel, and steel pipe slides in order to prevent, is needed A reinforcing bar brachycephaly is welded on I-steel, pole steel tube entangles this section of reinforcing bar when then setting up scaffold.And reinforcement welding Position be the scaffold size that is designed after being installed according to I-steel to determine.Therefore some problems are caused:1, welding needs Want power supply and equipment, when operation generates electric spark and air pollution, and when power failure can not weld;2, the Later Zhou Dynasty, one of the Five Dynasties is removed when scaffold to go to When another scaffolding work, since the size of scaffold design is not necessarily identical with a upper engineering, welded on I-steel Spacer bar position need cut after welded again in new position again;3, the spacer bar welded is one section of bar dowel head, Since the presence of this section of reinforcing bar causes I-steel not stack closely after I-steel recycling, the parking space of I-steel is influenced.
Invention content
It is an object of the invention to overcome drawbacks described above, a kind of builder's jack steel pipe locating support is provided.
In order to achieve the above object, the invention is realized in this way:
A kind of builder's jack steel pipe locating support, including pedestal and rack body, wherein pedestal is rectangular steel plates, in rectangle The both ends of steel plate open up two circular holes and a reinforcing bar are arranged in the center upright of steel plate;The rack body includes that section is in square Shape and girder steel pedestal in bottom opening, in the outer wall at girder steel pedestal both ends and the central bore of inner wall and are respectively set nut simultaneously A piece bolt is threaded through in described two nuts.
The application method of the builder's jack steel pipe locating support, including
Step 1, the upper surface that pedestal is placed in I-steel,
Step 2, mobile base are so that the center of reinforcing bar thereon is at scaffold standpipe design position;
Rack body is inserted in I-steel by step 3;
Step 4, mobile rack body are so that the center of rack body is in the center of the vertical reinforcing bar of pedestal;Step 5, by spiral shell Bolt passes through the circular hole on nut and pedestal steel plate, tightens bolt until rack body is closely fixed with I-steel;
Step 6, installation scaffold steel tube poles, set up scaffold;At this time since holder has been fixed, bolt has passed through pedestal Eyelet so that pedestal is also fixed, therefore scaffold upright rod steel pipe bottom is also at stationary state, plays the anti-skidding work of upright bar With.
This steel pipe locating support is recyclable, is not necessarily to welding in installation or removal, therefore not will produce electricity Spark, flue gas etc., so as to improve the safety of entire scaffold installation operation while making scaffold installation Operation is more environmentally protective.
Description of the drawings
Fig. 1 is the structural schematic diagram of pedestal in this locating support.
Fig. 2 is the structural schematic diagram of rack body in this locating support.
Fig. 3 is the use state diagram of this locating support.
Specific implementation mode
It is further illustrated the present invention below by way of specific embodiment.
A kind of builder's jack steel pipe locating support as shown in Figure 1 and Figure 2, including pedestal 1 and rack body 2, wherein bottom Seat 1 is rectangular steel plates, opens up two circular holes at the both ends of rectangular steel plates and a reinforcing bar 11 is arranged in the center upright of steel plate;Institute It includes rectangular in cross-section and the girder steel pedestal 21 in bottom opening to state rack body 2, in the outer wall at 21 both ends of girder steel pedestal and interior The central bore of wall is simultaneously respectively set nut 22 and a bolt 23 is threaded through in described two nuts 22.
As shown in figure 3, the application method of the builder's jack steel pipe locating support, including
Step 1, the upper surface that pedestal 1 is placed in I-steel 3,
Step 2, mobile base 1 are so that the center of reinforcing bar 11 thereon is at scaffold standpipe design position;
Rack body 2 is inserted in I-steel 3 by step 3;
Step 4, mobile rack body 2 are so that the center of rack body 2 is in the center of 1 vertical reinforcing bar 11 of pedestal;
Bolt 23 is passed through the circular hole on 1 steel plate of nut 22 and pedestal by step 5, tightens bolt 23 until rack body 2 and I-shaped Steel 3 closely fixes;
Step 6, installation scaffold steel tube poles, set up scaffold;At this time since holder has been fixed, bolt has passed through pedestal Eyelet so that pedestal is also fixed, therefore scaffold upright rod steel pipe bottom is also at stationary state, plays the anti-skidding work of upright bar With.
This steel pipe locating support is recyclable, is not necessarily to welding in installation or removal, therefore not will produce electricity Spark, flue gas etc., so as to improve the safety of entire scaffold installation operation while making scaffold installation Operation is more environmentally protective.

Claims (2)

1. a kind of builder's jack steel pipe locating support, it is characterized in that:Including pedestal and rack body, wherein pedestal is rectangle Steel plate opens up two circular holes at the both ends of rectangular steel plates and a reinforcing bar is arranged in the center upright of steel plate;The rack body Including rectangular in cross-section and in the girder steel pedestal of bottom opening, in the outer wall at girder steel pedestal both ends and the central bore of inner wall and divide Nut and a bolt She Zhi not be threaded through in described two nuts.
2. the application method of builder's jack steel pipe locating support described in claim 1, it is characterized in that:Including
Step 1, the upper surface that pedestal is placed in I-steel,
Step 2, mobile base are so that the center of reinforcing bar thereon is at scaffold standpipe design position;
Rack body is inserted in I-steel by step 3;
Step 4, mobile rack body are so that the center of rack body is in the center of the vertical reinforcing bar of pedestal;Step 5, by spiral shell Bolt passes through the circular hole on nut and pedestal steel plate, tightens bolt until rack body is closely fixed with I-steel;
Step 6, installation scaffold steel tube poles, set up scaffold;At this time since holder has been fixed, bolt has passed through pedestal Eyelet so that pedestal is also fixed, therefore scaffold upright rod steel pipe bottom is also at stationary state, plays the anti-skidding work of upright bar With.
CN201810550663.9A 2018-05-31 2018-05-31 Builder's jack steel pipe locating support and its application method Pending CN108612296A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810550663.9A CN108612296A (en) 2018-05-31 2018-05-31 Builder's jack steel pipe locating support and its application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810550663.9A CN108612296A (en) 2018-05-31 2018-05-31 Builder's jack steel pipe locating support and its application method

Publications (1)

Publication Number Publication Date
CN108612296A true CN108612296A (en) 2018-10-02

Family

ID=63664578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810550663.9A Pending CN108612296A (en) 2018-05-31 2018-05-31 Builder's jack steel pipe locating support and its application method

Country Status (1)

Country Link
CN (1) CN108612296A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4387568B2 (en) * 2000-08-21 2009-12-16 光洋機械産業株式会社 Temporary scaffold members such as overhang brackets
CN202969894U (en) * 2012-12-24 2013-06-05 中建海峡建设发展有限公司 Base of overhanging scaffolding vertical rod
CN203050076U (en) * 2013-01-08 2013-07-10 福建四海建设有限公司 Scaffold upright rod combination-type locating device
CN203684642U (en) * 2013-12-05 2014-07-02 中国建筑第六工程局有限公司 Quick positioning device for profile steel builder's jack upright
CN205276846U (en) * 2015-06-05 2016-06-01 中国十七冶集团有限公司 Fixing device of builder's jack pole setting
CN205531283U (en) * 2016-02-05 2016-08-31 黄石市砼锚五金机电设备有限公司 Scaffold puts up I -steel bracing of encorbelmenting power of getting and pole setting positioner
CN205822759U (en) * 2016-05-26 2016-12-21 中建海峡建设发展有限公司 Scaffold upright rod anti-slip positioning device
CN206829586U (en) * 2017-05-09 2018-01-02 上海绿地建设(集团)有限公司 Overhanging type steel pipe scaffold vertical rod base stand location buckle

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4387568B2 (en) * 2000-08-21 2009-12-16 光洋機械産業株式会社 Temporary scaffold members such as overhang brackets
CN202969894U (en) * 2012-12-24 2013-06-05 中建海峡建设发展有限公司 Base of overhanging scaffolding vertical rod
CN203050076U (en) * 2013-01-08 2013-07-10 福建四海建设有限公司 Scaffold upright rod combination-type locating device
CN203684642U (en) * 2013-12-05 2014-07-02 中国建筑第六工程局有限公司 Quick positioning device for profile steel builder's jack upright
CN205276846U (en) * 2015-06-05 2016-06-01 中国十七冶集团有限公司 Fixing device of builder's jack pole setting
CN205531283U (en) * 2016-02-05 2016-08-31 黄石市砼锚五金机电设备有限公司 Scaffold puts up I -steel bracing of encorbelmenting power of getting and pole setting positioner
CN205822759U (en) * 2016-05-26 2016-12-21 中建海峡建设发展有限公司 Scaffold upright rod anti-slip positioning device
CN206829586U (en) * 2017-05-09 2018-01-02 上海绿地建设(集团)有限公司 Overhanging type steel pipe scaffold vertical rod base stand location buckle

Similar Documents

Publication Publication Date Title
CN204327103U (en) A kind of reaction frame started for tunneling shield
CN203867158U (en) Cantilever type scaffold structure with positioning plug for fixation
CN205531283U (en) Scaffold puts up I -steel bracing of encorbelmenting power of getting and pole setting positioner
CN108612296A (en) Builder's jack steel pipe locating support and its application method
CN206352340U (en) Connecting node between precast concrete column and pedestal
CN103206075A (en) Suspension platform for construction of steel reinforced concrete cantilever structure
CN202936996U (en) Wall connecting piece for scaffold
CN206245709U (en) A kind of outrigger wall-connecting piece
CN203145430U (en) Detachable anchor ring structure for fixing cantilever beam
CN110630035A (en) Steel column supporting structure for bottom of reinforced concrete floor beam
CN202447878U (en) Simple aligning line rack for installation centre line of detachable equipment
CN214117483U (en) Steel pipe mobile positioning pile for building engineering cantilever beam scaffold erection
CN205276846U (en) Fixing device of builder's jack pole setting
CN208202527U (en) Overhang the outer bearing apparatus of I-steel external scaffolding head step upright bar footing positioning
CN203222981U (en) Suspended platform for steel reinforced concrete cantilever structure construction
CN204199323U (en) For the positioning screw hole mould of pre-embedded bolt quick position
CN210104727U (en) Mechanical connection structure
JP2007009447A (en) Demolition method for steel tower supported stack
CN203867164U (en) Cantilever type scaffold structure with positioning steel pipe
CN210134635U (en) Device for connecting cantilever scaffold section steel and scaffold upright rod
CN203795841U (en) Building template early-demounting device
CN203638044U (en) Fixing clamp for ship glass steel tube
CN204609345U (en) A kind of full dismounting bean column node temporary support lattice column device
CN206903185U (en) Pre-buried board-like carrier setting bolt structure
CN214531985U (en) Tool joint for mounting large steel pipe stand column

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002

RJ01 Rejection of invention patent application after publication