CN108612100A - A method of anchor cable is handled using churning driven - Google Patents

A method of anchor cable is handled using churning driven Download PDF

Info

Publication number
CN108612100A
CN108612100A CN201810328302.XA CN201810328302A CN108612100A CN 108612100 A CN108612100 A CN 108612100A CN 201810328302 A CN201810328302 A CN 201810328302A CN 108612100 A CN108612100 A CN 108612100A
Authority
CN
China
Prior art keywords
anchor cable
shield
churning driven
construction
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810328302.XA
Other languages
Chinese (zh)
Inventor
潘茜
林湘
周灿朗
邓嘉宁
于清平
丁建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan Rail Transit Design & Research Institute Co Ltd
Original Assignee
Foshan Rail Transit Design & Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan Rail Transit Design & Research Institute Co Ltd filed Critical Foshan Rail Transit Design & Research Institute Co Ltd
Priority to CN201810328302.XA priority Critical patent/CN108612100A/en
Publication of CN108612100A publication Critical patent/CN108612100A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Abstract

The invention discloses a kind of methods handling anchor cable using churning driven, include the following steps:A, during subway shield tunnel construction, when encountering existing anchor cable (2), the anchor cable (2) is cut off with churning driven (1), discharges the tension stress of the anchor cable (2);Part in the anchor cable (2) is taken out of by churning driven (1), and other two sections of anchor cables after cutting off form free end and remain in the earth formation;B, after churning driven (1) construction, rock stratum (3) is backfilled using C20 concrete, soil layer (4) is backfilled using M5 cement mortar;C, carry out shield-tunneling construction again, shield driving by when, select suitable boring parameter, will be squeezed to the soil at both sides of shield as the anchor cable of free end, realize tunneling construction of the shield by anchor cable section.The method for handling anchor cable using churning driven of the present invention, will not have an impact surrounding building, and the duration is shorter, engineering cost is relatively low.

Description

A method of anchor cable is handled using churning driven
Technical field
The present invention relates to technical field of tunnel construction, and in particular to a method of anchor cable is handled using churning driven.
Background technology
With the rapid development of cities in China rail traffic, in urban rail transit shield work progress often Encounter various underground obstacles.Currently, most cities skyscraper is equipped with basement, urban construction basement encloses Protection structure largely uses the form of cable bolting, this constructs to urban rail transit shield and generates large effect.
And for underground anchor rope processing it is current domestic occur similar in the case of be also it is more, processing method difference it is larger but Substantially be to clear up in advance anchor cable, take method it is common there is pipe-following drilling set to follow the example of, artificial digging pile segmentation pull out Method, chute forming machine crawl method, full-sleeve slewing drilling machine patterning method etc., and the interaction between shield driving and anchor cable is ground Study carefully less;The good and bad index of evaluation anchor cable processing construction is construction period, the influence to surrounding enviroment and engineering cost;It is common Pipe-following drilling set follow the example of the basement side wall that need to abolish existing building, be affected to existing building;Artificial digging pile point Method that section is pulled out, chute forming machine crawl method, full-sleeve slewing drilling machine patterning method construction area area are big and long in time limit, engineering cost It is high.
Since churning driven is directly constructed in subway shield tunnel construction range, and rotary drilling rig footprint is smaller, uses Churning driven processing anchor cable will not have an impact surrounding building, and the duration is shorter, and engineering cost is relatively low, and applicability is wide, because This, there is an urgent need for designing a kind of completely new processing scheme coordinated using churning driven and shield machine, to handle anchor cable.
Invention content
The object of the present invention is to provide a kind of methods handling anchor cable using churning driven, will not be generated to surrounding building It influences, and the duration is shorter, engineering cost is relatively low.
To achieve the above object, a kind of method that anchor cable is handled using churning driven provided by the present invention, including walk as follows Suddenly:
A, during subway shield tunnel construction, when encountering existing anchor cable (2), the anchor cable is cut off with churning driven (1) (2), the tension stress of the anchor cable (2) is discharged;Part in the anchor cable (2) is taken out of by churning driven (1), and after cutting off other two Section anchor cable forms free end and remains in the earth formation;
B, after churning driven (1) construction, rock stratum (3) are backfilled using C20 concrete, M5 is used to soil layer (4) Cement mortar is backfilled;
C, carry out shield-tunneling construction again, shield driving by when, select suitable boring parameter, will be as the anchor of free end Rope is squeezed to the soil at both sides of shield, realizes tunneling construction of the shield by anchor cable section.
In the above-mentioned method for handling anchor cable using churning driven, in the step (a), churning driven (1) is in ground construction.
The present invention has the advantages that compared with prior art:
Since churning driven is directly constructed in subway shield tunnel construction range, and rotary drilling rig footprint is smaller, uses Churning driven processing anchor cable will not have an impact surrounding building, and the duration is shorter, and engineering cost is relatively low, and applicability is wide;This Although part construction risk, by whole anchor cables in range, is transferred to shield machine pick by inventive method without fully erased shield Into in the process, but it is flexible with rotary digging pile layout, and quantities is few, and cost is controllable, rotary drilling rig machine source is sufficient, speed of application Soon, stake position positioning accuracy is high, anchor cable cut off situation it is controllable, using mud off, the advantages that construction safety risk is controllable, be suitble to anchor The processing of rope is constructed.
Description of the drawings
Fig. 1 is a kind of construction schematic diagram of method handling anchor cable using churning driven of the embodiment of the present invention.
Wherein, 1, churning driven;2, anchor cable;3, rock stratum;4, soil layer.
Specific implementation mode
With reference to the accompanying drawings and examples, the specific implementation mode of the present invention is described in further detail.Implement below Example is not limited to the scope of the present invention for illustrating the present invention.
As shown in Figure 1, a kind of method handling anchor cable using churning driven provided by the present invention, includes the following steps:
A, during subway shield tunnel construction, when encountering existing anchor cable 2, the anchor cable 2 is cut off with churning driven 1, is discharged The tension stress of the anchor cable 2;Part in the anchor cable 2 is taken out of by churning driven 1, and other two sections of anchor cables after cutting off form freedom It holds and remains in the earth formation;
B, after churning driven 1 is constructed, rock stratum 3 is backfilled using C20 concrete, M5 cement bonded sands are used to soil layer 4 Slurry is backfilled;
C, carry out shield-tunneling construction again, shield driving by when, select suitable boring parameter, will be as the anchor of free end Rope is squeezed to the soil at both sides of shield, realizes tunneling construction of the shield by anchor cable section.
Preferably, in the step (a), churning driven 1 is in ground construction.
To sum up, the present invention has the advantages that compared with prior art:
Since churning driven is directly constructed in subway shield tunnel construction range, and rotary drilling rig footprint is smaller, uses Churning driven processing anchor cable will not have an impact surrounding building, and the duration is shorter, and engineering cost is relatively low, and applicability is wide;This Although part construction risk, by whole anchor cables in range, is transferred to shield machine pick by inventive method without fully erased shield Into in the process, but it is flexible with rotary digging pile layout, and quantities is few, and cost is controllable, rotary drilling rig machine source is sufficient, speed of application Soon, stake position positioning accuracy is high, anchor cable cut off situation it is controllable, using mud off, the advantages that construction safety risk is controllable, be suitble to anchor The processing of rope is constructed.
It the above is only the preferred embodiment of the present invention, it is noted that those skilled in the art are come It says, without departing from the technical principles of the invention, several improvement and replacement can also be made, these improve and replace and also answer It is considered as protection scope of the present invention.

Claims (2)

1. a kind of method handling anchor cable using churning driven, which is characterized in that include the following steps:
A, during subway shield tunnel construction, when encountering existing anchor cable (2), the anchor cable (2) is cut off with churning driven (1), is released Put the tension stress of the anchor cable (2);Part in the anchor cable (2) is taken out of by churning driven (1), and other two sections of anchor cables after cutting off It forms free end and remains in the earth formation;
B, after churning driven (1) construction, rock stratum (3) are backfilled using C20 concrete, M5 cement is used to soil layer (4) Mortar is backfilled;
C, carry out shield-tunneling construction again, shield driving by when, select suitable boring parameter, will be squeezed as the anchor cable of free end It is depressed into the soil at both sides of shield, realizes tunneling construction of the shield by anchor cable section.
2. as described in claim 1 using the method for churning driven processing anchor cable, which is characterized in that in the step (a), rotary digging (1) is bored in ground construction.
CN201810328302.XA 2018-04-12 2018-04-12 A method of anchor cable is handled using churning driven Pending CN108612100A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810328302.XA CN108612100A (en) 2018-04-12 2018-04-12 A method of anchor cable is handled using churning driven

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810328302.XA CN108612100A (en) 2018-04-12 2018-04-12 A method of anchor cable is handled using churning driven

Publications (1)

Publication Number Publication Date
CN108612100A true CN108612100A (en) 2018-10-02

Family

ID=63659799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810328302.XA Pending CN108612100A (en) 2018-04-12 2018-04-12 A method of anchor cable is handled using churning driven

Country Status (1)

Country Link
CN (1) CN108612100A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110630271A (en) * 2019-09-09 2019-12-31 中国电建集团铁路建设有限公司 Construction method for water-rich sand layer shield to penetrate through steel pipe soil nail area
CN111851484A (en) * 2020-07-30 2020-10-30 深圳市工勘岩土集团有限公司 Method for cutting off semi-invasive prestressed anchor cable in supporting pile by rotary drilling rig
CN111926821A (en) * 2020-07-13 2020-11-13 北京城建勘测设计研究院有限责任公司 Construction method of novel slope protection pile
CN112145210A (en) * 2020-08-25 2020-12-29 广州市市政工程设计研究总院有限公司 Anchor cable group removing method for invading shield or pipe-jacking tunnel section
CN113266362A (en) * 2021-05-25 2021-08-17 中铁四局集团第三建设有限公司 Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN113266392A (en) * 2021-05-25 2021-08-17 中铁四局集团第三建设有限公司 Pipe jacking construction method for penetrating through existing anchor cable group
CN113513014A (en) * 2021-04-26 2021-10-19 中铁四局集团有限公司 Anchor cable treatment and stratum reinforcement integrated method adopting triaxial mixing pile machine

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851922A (en) * 2010-06-17 2010-10-06 昆明捷程桩工有限责任公司 Method for eliminating underground anchor rope/rod by using all casing drill
CN105201515A (en) * 2015-09-09 2015-12-30 泰安市岱宗机电科技开发有限公司 Anchor cable dismantling method based on shield operation area
CN106437798A (en) * 2016-09-23 2017-02-22 广东省基础工程集团有限公司 Pretreatment method for anchor cable group penetrating through shield driving fracture surface
CN206785388U (en) * 2017-05-18 2017-12-22 中国建筑第八工程局有限公司 Anchor cable removes system in a kind of tunnel
CN107829753A (en) * 2017-09-30 2018-03-23 中铁第四勘察设计院集团有限公司 Underground anchor rope remove device and sweep-out method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101851922A (en) * 2010-06-17 2010-10-06 昆明捷程桩工有限责任公司 Method for eliminating underground anchor rope/rod by using all casing drill
CN105201515A (en) * 2015-09-09 2015-12-30 泰安市岱宗机电科技开发有限公司 Anchor cable dismantling method based on shield operation area
CN105822313A (en) * 2015-09-09 2016-08-03 泰安市岱宗机电科技开发有限公司 Method and device for removing obstacle foreign matter in shield section based on transverse channel
CN106437798A (en) * 2016-09-23 2017-02-22 广东省基础工程集团有限公司 Pretreatment method for anchor cable group penetrating through shield driving fracture surface
CN206785388U (en) * 2017-05-18 2017-12-22 中国建筑第八工程局有限公司 Anchor cable removes system in a kind of tunnel
CN107829753A (en) * 2017-09-30 2018-03-23 中铁第四勘察设计院集团有限公司 Underground anchor rope remove device and sweep-out method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张志冰: ""软弱地层盾构穿越锚索区域施工技术"", 《石家庄铁路职业技术学院学报》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110630271A (en) * 2019-09-09 2019-12-31 中国电建集团铁路建设有限公司 Construction method for water-rich sand layer shield to penetrate through steel pipe soil nail area
CN110630271B (en) * 2019-09-09 2020-11-20 中国电建集团铁路建设有限公司 Construction method for water-rich sand layer shield to penetrate through steel pipe soil nail area
CN111926821A (en) * 2020-07-13 2020-11-13 北京城建勘测设计研究院有限责任公司 Construction method of novel slope protection pile
CN111851484A (en) * 2020-07-30 2020-10-30 深圳市工勘岩土集团有限公司 Method for cutting off semi-invasive prestressed anchor cable in supporting pile by rotary drilling rig
CN112145210A (en) * 2020-08-25 2020-12-29 广州市市政工程设计研究总院有限公司 Anchor cable group removing method for invading shield or pipe-jacking tunnel section
CN113513014A (en) * 2021-04-26 2021-10-19 中铁四局集团有限公司 Anchor cable treatment and stratum reinforcement integrated method adopting triaxial mixing pile machine
CN113266362A (en) * 2021-05-25 2021-08-17 中铁四局集团第三建设有限公司 Top pipe cover excavation construction method for penetrating through existing dense anchor cable area
CN113266392A (en) * 2021-05-25 2021-08-17 中铁四局集团第三建设有限公司 Pipe jacking construction method for penetrating through existing anchor cable group
CN113266362B (en) * 2021-05-25 2022-04-12 中铁四局集团第三建设有限公司 Top pipe cover excavation construction method for penetrating through existing dense anchor cable area

Similar Documents

Publication Publication Date Title
CN108612100A (en) A method of anchor cable is handled using churning driven
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN110344400A (en) The hard rock pore-forming construction technology of churning driven opportunity
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN105041322A (en) Method and system for reinforcing hole for push bench to go in and out
CN103603342A (en) Construction method of ultra-long bored concrete pile with large-diameter casing combination
KR102288770B1 (en) Horizontal directional drilling method strengthening driving force
CN103046931A (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN209958343U (en) Connecting joint for connecting reinforced concrete cast-in-place piles
CN114320313B (en) Air-pushing traction type push bench escaping construction method
CN109208594B (en) Treatment method for steel casing sinking meeting boulder, steel casing structure and drilled pile
CN102733390A (en) Method for removing underground waste anchor cable/anchor rod
JP6319935B2 (en) Tubing pile driving method
KR101066296B1 (en) Rock cutting method using boring lid
CN109944251A (en) The drawing hole construction method that soft rock stratum steel sheet pile is squeezed into
CN106337418A (en) Supporting structure and supporting method of deep foundation pit in narrow area
KR102267676B1 (en) A method of construction for temporary retaining wall and sheating work cup using its method
CN109555127A (en) A kind of construction for the flush type multimedium built pile that drills
CN103967000A (en) Rotary excavating pile construction method in combined construction
CN208039236U (en) It is a kind of belong to underground pile connect wall construction method at wall equipment
CN106677242A (en) Engineering ship for underwater tunnel and construction method of engineering ship
KR101237749B1 (en) Propulsion unit head that is used in shield method
CN106837343A (en) Push pipe goes out the construction method of hole second consolidation
CN112324441A (en) Construction method for removing underground shield segments by full-slewing drilling machine
JPS6332930B2 (en)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181002