CN108597629A - A kind of arrangement of nuclear plant safety workshop - Google Patents

A kind of arrangement of nuclear plant safety workshop Download PDF

Info

Publication number
CN108597629A
CN108597629A CN201810240596.0A CN201810240596A CN108597629A CN 108597629 A CN108597629 A CN 108597629A CN 201810240596 A CN201810240596 A CN 201810240596A CN 108597629 A CN108597629 A CN 108597629A
Authority
CN
China
Prior art keywords
workshop
row
layers
ground
aerial part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810240596.0A
Other languages
Chinese (zh)
Inventor
杜广
许克凤
李海冰
陈元初
陈昊阳
徐国飞
李昭清
赵丹峰
陈巧英
程丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Nuclear Power Engineering Co Ltd
Original Assignee
China Nuclear Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Nuclear Power Engineering Co Ltd filed Critical China Nuclear Power Engineering Co Ltd
Priority to CN201810240596.0A priority Critical patent/CN108597629A/en
Publication of CN108597629A publication Critical patent/CN108597629A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21DNUCLEAR POWER PLANT
    • G21D1/00Details of nuclear power plant
    • G21D1/02Arrangements of auxiliary equipment
    • GPHYSICS
    • G21NUCLEAR PHYSICS; NUCLEAR ENGINEERING
    • G21DNUCLEAR POWER PLANT
    • G21D1/00Details of nuclear power plant
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin

Abstract

The present invention relates to a kind of arrangements of nuclear plant safety workshop, including A row workshop and B row workshops;A row workshop and B row workshop include aerial part and under ground portion;The mechanical equipment area of redundancy series facilities is set to the under ground portion of the under ground portion and the B row workshop of the A row workshop;The electrical instrument control of redundancy series facilities and plenum area are set to the aerial part of the A row workshop and the B row workshop includes aerial part;The aerial part of the aerial part of the A row workshop and the B row workshop is respectively arranged at reactor building both sides.The beneficial effects of the present invention are:The present invention influences another series by the avoidable internal disaster that is physically isolated completely of safe workshop A row and safe workshop B row by a series; separated using subregion arrangement, space or redundancy facility and critical facility are separated and are protected by the method for physical barrier; it ensure that the independence between facility, improve reliability, safety and the economy of power plant.

Description

A kind of arrangement of nuclear plant safety workshop
Technical field
The present invention relates to nuclear island structures, and in particular to a kind of arrangement of nuclear plant safety workshop.
Background technology
To meet three generations's Nuclear Safety technical standard, safe workshop is the completely new workshop newly set up, and relates generally to one A little Special safety facilities include containment spray system (CSP), safety injection system (RSI), Reactor cavity flooding system (CIS) and answer Anxious boron injected system (REB), component cooling water system (WCC), electrical building chilled water system (WEC) equipment and pipeline, with And electrical equipment, accumulator, instrument control facility and ventilation equipment etc..
The safe workshop of the prior art does not have redundancy facility or redundancy facility interrelated, entity be not completely every From when a situation arises for safe workshop, unit and safety and reliability being caused to reduce.
Invention content
In view of the deficiencies in the prior art, the object of the present invention is to provide a kind of arrangement knots of nuclear plant safety workshop Structure, can be in the case where the safe workshop in side breaks down and can not work, and the safe workshop in the other side can normally execute safe work( Energy.
Technical scheme is as follows:
A kind of arrangement of nuclear plant safety workshop, including A row workshop and B row workshops;The A row workshop and the B Row workshop respectively arranges a set of redundancy series facilities;
The A row workshop and the B row workshop include aerial part and under ground portion;
The mechanical equipment area of the redundancy series facilities is set to the under ground portion of the A row workshop and the B row workshop Under ground portion;The electrical instrument control of the redundancy series facilities and plenum area are set to aerial part and the institute of the A row workshop It includes aerial part to state B row workshop;
The aerial part of the aerial part of the A row workshop and the B row workshop is respectively arranged at reactor building both sides.
Further, the under ground portion of the arrangement of above-mentioned nuclear plant safety workshop, the A row workshop includes three Layer, aerial part include five layers;The under ground portion of the B row workshop includes six layers including three layers, aerial part.
Further, the arrangement of above-mentioned nuclear plant safety workshop, in the under ground portion of the A row workshop:
F3/B3 is equipped between emergent boron note pump, between middle pressure safety injection pump, peace spray between heat exchanger, between low pressure safety injection pump, heap Between chamber water filling cooling pump, peace spray pump between, between chemical addition system equipment box between pipeline valve;There is boron note case in two layers of the underground Between, between middle pressure safety injection pump motor, peace spray pump heat exchanger between, low pressure peace note valve operation and motor between, Reactor cavity flooding cooling pump Between valve operation and motor, peace spray valve operation and motor between, between chemical addition system equipment box between pipeline valve;Describedly Next layer has between boron note case, between equipment hoisting, ventilation equipment computer room and cable shaft;
In the aerial part of the A row workshop:
Ground floor is equipped between ventilation equipment computer room, equipment hoisting successively, equipment removal path and cable shaft;Describedly Upper two layers be equipped with successively between low pressure disk cabinet cable, ventilation equipment computer room and cable shaft;Three layers of the ground is equipped with low pressure disk cabinet Between and ventilation equipment computer room;Four layers of the ground has between middle platen cabinet cable and ventilation equipment computer room;Five layers of the ground is equipped with Between middle platen cabinet and ventilation equipment computer room;
In the under ground portion of the B row workshop:
F3/B3 is equipped between emergent boron note pump, between middle pressure safety injection pump, peace spray between heat exchanger, between low pressure safety injection pump, heap Between chamber water filling cooling pump, peace spray pump between, between chemical addition system equipment box between pipeline valve;There is boron note case in two layers of the underground Between, between middle pressure safety injection pump motor, peace spray pump heat exchanger between, low pressure peace note valve operation and motor between, Reactor cavity flooding cooling pump Between valve operation and motor, peace spray valve operation and motor between, between chemical addition system equipment box between pipeline valve;Describedly Next layer has between boron note case, between equipment hoisting, ventilation equipment computer room and cable shaft;
In the aerial part of the B row workshop:
Ground floor is equipped between ventilation equipment computer room, equipment hoisting successively, equipment removal path and cable shaft;On the ground two Layer is equipped between accumulator and ventilation equipment computer room;On the ground three layers be equipped with accumulator disk cabinet between and ventilation equipment computer room;Four layers on the ground Equipped between mesolow disk cabinet cable, between accumulator and ventilation equipment computer room;On the ground five layers be equipped with mesolow disk cabinet between, accumulator disk Between cabinet and ventilation equipment computer room;On the ground six layers be equipped between cable, reactor protection system rack room, instrument control electric room and logical Wind devices computer room.
Further, the roof of the arrangement of above-mentioned nuclear plant safety workshop, the A row workshop and B row workshops point The pressuring machine and induced-draft fan that She Zhi not be connect with the ventilation equipment computer room.
Further, the arrangement of above-mentioned nuclear plant safety workshop, each area of the A row workshop and B row workshops Domain is symmetrical arranged.
Further, the arrangement of above-mentioned nuclear plant safety workshop, the A row workshop and the B row workshop it is every Layer is equipped with independent staircase, escalator, channel and reactor building bonding pad.
Further, the arrangement of above-mentioned nuclear plant safety workshop, the workshop A row and workshop B are classified as antidetonation I classes Reinforced concrete structure, seismic acceleration value 0.3g.
Further, the arrangement of above-mentioned nuclear plant safety workshop, reactor building, fuel plant, electrical building, The workshop A row and workshop B row share same bottom plate.
Beneficial effects of the present invention are as follows:
The present invention can avoid internal disaster by one by safe workshop A row and being physically isolated completely for safe workshop B row Series influences another series, is separated using subregion arrangement, space or the method for physical barrier by redundancy facility and important is set It applies and is separated and protects, ensure that the independence between facility, improve reliability, safety and the economy of power plant.
Description of the drawings
Fig. 1 is the general arrangement of nuclear plant safety workshop F3/B3 of the present invention;
Fig. 2 is the general arrangement of two layers of nuclear plant safety workshop of the present invention underground;
Fig. 3 is the general arrangement of nuclear plant safety workshop basement one of the present invention;
Fig. 4 is the general arrangement of nuclear plant safety workshop ground floor of the present invention;
Fig. 5 is the general arrangement of nuclear plant safety workshop F2/B2 of the present invention;
Fig. 6 is the general arrangement of three layers of nuclear plant safety workshop of the present invention ground;
Fig. 7 is the general arrangement of four layers of nuclear plant safety workshop of the present invention ground;
Fig. 8 is the general arrangement of five layers of nuclear plant safety workshop of the present invention ground;
Fig. 9 is the general arrangement of six layers of nuclear plant safety workshop of the present invention ground.
Specific implementation mode
The present invention is described in detail below with reference to the accompanying drawings and embodiments.
To avoid commercial aircraft impact disaster, meeting Safety Redundancy design and single failure criteria, related system and equipment It is divided to A, B row to be arranged in two completely self-contained workshops, forms safe workshop (NL) and safe workshop (NR).It is specific and Speech, the arrangement of nuclear plant safety workshop provided by the invention, including A row workshop (i.e. NL) and B row workshop (i.e. NR);It is described A row workshop and the B row workshop respectively arrange a set of redundancy series facilities;The A row workshop and the B row workshop include on the ground Part and under ground portion;The mechanical equipment area of the redundancy series facilities is set to the under ground portion of the A row workshop and the B The under ground portion of row workshop;The electrical instrument control of the redundancy series facilities and plenum area are set to the overground part of the A row workshop Divide and the B row workshop includes aerial part;The aerial part of the aerial part of the A row workshop and the B row workshop point It is not set to reactor building both sides.
In the present embodiment, the under ground portion of the A row workshop includes five layers including three layers, aerial part;B row factory The under ground portion in room includes six layers including three layers, aerial part.In this way, safe workshop provided in this embodiment can be divided by its absolute altitude It realizes engineered safety system using two completely self-contained mill constructions for nine arrangement layers independently of each other and is kept completely separate, this Kind arrangement can be in the case where side workshop breaks down and can not work, and other side workshop can normally execute security function.
As shown in Figure 1, for the floor plan of F3/B3.This layer of A Leie time be equipped with NL010, NL011, NL012, The room NL013, NL014, NL015, NL016, NL017, NL071, NL073, NL083, NL085;B row be arranged with NR020, The room NR021, NR022, NR023, NR024, NR025, NR026, NR027, NR072, NR074, NR082, NR084, NR086.
NL010 and NR020 is that an emergent boron note pump is respectively equipped between emergent boron note pumps;NL011 and NR021 pacifies for middle pressure It is respectively arranged in one between note pump and presses safety injection pump;NL012 and NR022 is that a peace spray heat friendship is respectively arranged between pacifying spray heat exchanger Parallel operation;NL013 and NR023 is respectively arranged a low pressure safety injection pump between low pressure safety injection pump;NL014 and NR024 is Reactor cavity flooding A Reactor cavity flooding cooling pump is respectively arranged between cooling pump;NL015 and NR025 be peace spray pump between be respectively arranged one peace spray pump, NL016 arranges a chemistry addition pump between chemical addition system equipment box, and NR026 is spare room;NL017 and NR027 are Pipeline valve is respectively arranged between pipeline valve.NL071 and NR072 is channel;NL073 and NR074 is reactor building bonding pad; NL083, NR082, NR084 are staircase;NL085 and NR086 is escalator.
As shown in Fig. 2, for the floor plan of two layers of underground.This layer of A Leie time be equipped with NL110, NL111, NL112, The room NL113, NL114, NL115, NL116, NL117, NL171, NL173, NL183, NL185;B row be arranged with NR120, The room NR121, NR122, NR123, NR124, NR125, NR126, NR127, NR172, NR174, NR182, NR184, NR186.
NL110 and NR120 is respectively equipped with a boron note case between boron note case;NL111 and NR121 respectively with NL011 and NR021, which communicates to be respectively arranged in one between middle pressure safety injection pump, presses safety injection pump;NL112 and NR122 respectively with NL012 and NR022 It communicates and is respectively arranged a peace spray heat exchanger between peace spray heat exchanger;NL113 and NR123 be low pressure peace note valve operation and Be respectively arranged between motor low pressure safety injection pump motor and;NL114 and NR124 is between Reactor cavity flooding cooling pump valve operation and motor It is respectively arranged the motor and valve of Reactor cavity flooding cooling pump;NL115 and NR125 is to be respectively arranged between peace spray valve operation and motor Pacify the valve of spray pump and motor, NL116 arrange a chemistry addition case between chemical addition system equipment box, NR126 is pipeline Relevant pipeline and valve are arranged between valve;NL117 and NR127 are respectively arranged pipeline valve between pipeline valve.NL171 and NR172 is channel;NL173 and NR174 is reactor building bonding pad;NL183, NR182, NR184 are staircase;NL185 and NR186 is escalator.
As shown in figure 3, for the floor plan of basement one.This layer of A Leie time be equipped with NL210, NL212, NL213, The room NL214, NL215, NL216, NL217, NL271, NL273, NL283, NL285, NL290, NL291;B row are arranged with The room NR220, NR222, NR223, NR224, NR225, NR226, NR227, NR272, NR274, NR282, NR284, NR286.
NL210 and NR220 is communicated with NL110 and NR120 be respectively arranged a boron note case between boron note case respectively;NL212、 NL213, NL214, NL215, NL271 and NR222, NR223, NR224, NR225, NR272 are respectively arranged between equipment hoisting Hole for hoist is used for lifting underlying device;NL216 and NR226 is ventilation equipment division of room ventilation equipment;NL290 and NL291 Cable is arranged for cable shaft;NL217 and NR227 is spare room;NL273 and NR274 is reactor building bonding pad; NL283, NR282, NR284 are staircase;NL285 and NR286 is escalator.
As shown in figure 4, being ground floor floor plan;
This layer of A Leie time be equipped with NL310, NL313, NL314, NL315, NL317, NL371, NL373, NL383, NL385, The room NL390, NL391;B row be arranged with NR320, NR323, NR324, NR325, NR327, NR370, NR372, NR374, The room NR382, NR384, NR386.
NL310 and NR321, which is ventilation equipment division of room, ventilation equipment and air hose;NL313、NL314、NL315、/ NR323, NR324, NR325 are equipped with hole for hoist between equipment hoisting and arrange crane, and the equipment of lower two layers is by herein Hole for hoist lifting is in place;NL317/NR327 is that equipment is between repairing;NL371/NR370 is equipment removal path;NL373/NR374 For reactor building bonding pad;NL390 and NL391 is the relevant cables that cable shaft arranges instrument control;NL383、NR382、 NR384 is staircase;NL385 and NR386 is escalator.
As shown in figure 5, being F2/B2 floor plan;
This layer of A Leie time be equipped with NL410, NL411, NL412, NL413, NL414, NL471, NL473, NL483, NL485, The room NL490, NL491;B row be arranged with NR420, NR421, NR422, NR423, NR424, NR425, NR472, NR474, The room NR482, NR484, NR486.
NL410, NL411, NL413, NL414 are disposed with low pressure disk cabinet cable between low pressure disk cabinet cable;NL412 is ventilation Equipment machine room is disposed with ventilation equipment;NL490, NL491 are that cable shaft is disposed with cable;NR420、NR421、NR423、 NR424, NR425 set between accumulator and are disposed with accumulator;NR422, which is ventilation equipment division of room, ventilation equipment;NL471 and NR472 is channel;NL473 and NR474 is reactor building bonding pad;NL483, NR482, NR484 are staircase;NL485 and NR486 is escalator.
As shown in fig. 6, being three layer plane layout drawings of ground;
This layer of A Leie time is equipped with NL510, NL511, NL512, NL513, NL514, NL571, NL573, NL583, NL585 Room;B row be arranged with NR520, NR521, NR522, NR523, NR524, NR525, NR572, NR574, NR582, NR584, The rooms NR586.
NL510, NL511, NL513, NL514 are disposed with low pressure disk cabinet between low pressure disk cabinet;NL512 and NR522 is ventilation Equipment machine room is disposed with ventilation equipment;NR520, NR521, NR524, NR525 are disposed with accumulator disk cabinet between accumulator disk cabinet; NL571 and NR572 is channel;NL573 and NR574 is reactor building bonding pad;NL583, NR582, NR584 are staircase; NL585 and NR586 is escalator.
As shown in fig. 7, being four layer plane layout drawings of ground;
This layer of A Leie time is equipped with NL610, NL611, NL612, NL613, NL614, NL671, NL673, NL683, NL685 Room;B row be arranged with NR620, NR621, NR622, NR623, NR624, NR625, NR626, NR672, NR674, NR682, The room NR684, NR686.
NL610, NL611, NL613, NL614 are disposed with middle platen cabinet cable between middle platen cabinet cable;NL612 and NR622, NR623, NR626, which are ventilation equipment division of room, has ventilation equipment and pipeline, NR620, NR624 electric for mesolow disk cabinet Mesolow disk cabinet cable is disposed between cable;NR621, NR625 are disposed with accumulator between accumulator;NL671 and NR672 is logical Road;NL673 and NR674 is reactor building bonding pad;NL683, NR682, NR684 are staircase;NL685 and NR686 is electricity Between ladder.
As shown in figure 8, being five layer plane layout drawings of ground;
This layer be A row workshops top layer successively be equipped with NL710, NL711, NL712, NL713, NL714, NL771, NL773, The room NL783, NL785;B row be arranged with NR720, NR721, NR722, NR723, NR724, NR725, NR726, NR772, The room NR774, NR782, NR784, NR786.
NL710, NL711, NL713, NL714 are disposed with middle platen cabinet between middle platen cabinet;NL712 and NR722 is ventilation Equipment machine room, which is set, is disposed with ventilation equipment, and NR720, NR724 are disposed with mesolow disk cabinet between mesolow disk cabinet;NR721、 NR723, NR725, NR726 are disposed with accumulator disk cabinet between accumulator disk cabinet;NL771 and NR772 is channel;NL773 and NR774 is reactor building bonding pad;NL783, NR782, NR784 are staircase;NL785 and NR786 is escalator.
As shown in figure 9, being six layer plane layout drawings of ground;
This layer of A be classified as this layer of B in roof row equipped with NR820, NR821, NR822, NR823, NR824, NR825, NR826, The room NR872, NR874, NR882, NR884, NR886, this layer are the top layer of B row workshops.
NR820 is disposed with cable between cable;NR821, NR822 are that reactor protection system rack room is disposed with reactor Protect system cabinet;NR823, NR824 are that instrument control electric room is disposed with instrument control electronic equipment;NR825, NR826 are ventilation Equipment machine room is disposed with ventilation equipment;NR872 is channel;NR874 is reactor building bonding pad;NR882, NR884 are stair Between;NR886 is escalator;Roof is disposed with the pressuring machine and induced-draft fan being connect with the ventilation equipment computer room.
In above-described embodiment, each region of the A row workshop and B row workshops is symmetrical arranged, the A row workshop and described Every layer of B row workshops is equipped with independent staircase, escalator, channel and reactor building bonding pad.
Further, the workshop A row and workshop B are classified as the reinforced concrete structure of antidetonation I classes, seismic acceleration value 0.3g;Reactor building, fuel plant, electrical building, workshop A row and workshop B row share same bottom plate, enhance The shock resistance of workshop.
Engineered safeguards features and associated safety system in workshop can guarantee that power plant allows reactor to be in the state of accident Stably and controllable state can reduce the temperature and pressure in core temperature and reactor building, ensure pressure vessel not burn through, protect Demonstrate,prove the integrality and leakproofness of containment.
In conclusion this implementation example by the way of solid shield is meeting code requirement, it is ensured that each system work(in workshop Under the premise of energy, corresponding device is reasonably arranged in workshop;Utilize the method for subregion arrangement, space separation or physical barrier Redundancy facility and critical facility are separated and are protected, ensure that the independence between facility, improves the reliability of power plant; Sanitation and hygiene area is set simultaneously, divides radioactivity control zone, designer channel and equipment hoisting hole in region.The present embodiment A kind of layout design method of the nuclear plant safety workshop provided can be widely applied to three generations's nuclear power generating sets.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art God and range.If in this way, belonging to the model of the claims in the present invention and its equivalent technology to these modifications and changes of the present invention Within enclosing, then the present invention is also intended to include these modifications and variations.

Claims (8)

1. a kind of arrangement of nuclear plant safety workshop, it is characterised in that:Including A row workshop and B row workshops;A row factory Room and the B row workshop respectively arrange a set of redundancy series facilities;
The A row workshop and the B row workshop include aerial part and under ground portion;
The mechanical equipment area of the redundancy series facilities is set to the ground of the under ground portion and the B row workshop of the A row workshop Lower part;The electrical instrument control of the redundancy series facilities and plenum area are set to the aerial part and B row of the A row workshop Workshop includes aerial part;
The aerial part of the aerial part of the A row workshop and the B row workshop is respectively arranged at reactor building both sides.
2. the arrangement of nuclear plant safety workshop as described in claim 1, it is characterised in that:The underground of the A row workshop Part includes five layers including three layers, aerial part;The under ground portion of the B row workshop includes six layers including three layers, aerial part.
3. the arrangement of nuclear plant safety workshop as claimed in claim 2, it is characterised in that:The underground of the A row workshop In part:
F3/B3 is equipped between emergent boron note pump, between middle pressure safety injection pump, between peace spray heat exchanger, between low pressure safety injection pump, heap chamber notes Water cooling pump between, peace spray pump between, between chemical addition system equipment box between pipeline valve;Two layers of the underground has between boron note case, Between middle pressure safety injection pump motor, peace spray pump heat exchanger between, low pressure peace note valve operation and motor between, Reactor cavity flooding cool down pump valve Operation and motor between, peace spray valve operation and motor between, between chemical addition system equipment box between pipeline valve;It is describedly next Layer has between boron note case, between equipment hoisting, ventilation equipment computer room and cable shaft;
In the aerial part of the A row workshop:
Ground floor is equipped between ventilation equipment computer room, equipment hoisting successively, equipment removal path and cable shaft;The ground two Layer is equipped with successively between low pressure disk cabinet cable, ventilation equipment computer room and cable shaft;Three layers of the ground be equipped between low pressure disk cabinet and Ventilation equipment computer room;Four layers of the ground has between middle platen cabinet cable and ventilation equipment computer room;Five layers of the ground is equipped with middle pressure Between disk cabinet and ventilation equipment computer room;
In the under ground portion of the B row workshop:
F3/B3 is equipped between emergent boron note pump, between middle pressure safety injection pump, between peace spray heat exchanger, between low pressure safety injection pump, heap chamber notes Water cooling pump between, peace spray pump between, between chemical addition system equipment box between pipeline valve;Two layers of the underground has between boron note case, Between middle pressure safety injection pump motor, peace spray pump heat exchanger between, low pressure peace note valve operation and motor between, Reactor cavity flooding cool down pump valve Operation and motor between, peace spray valve operation and motor between, between chemical addition system equipment box between pipeline valve;It is describedly next Layer has between boron note case, between equipment hoisting, ventilation equipment computer room and cable shaft;
In the aerial part of the B row workshop:
Ground floor is equipped between ventilation equipment computer room, equipment hoisting successively, equipment removal path and cable shaft;F2/B2 is set Have between accumulator and ventilation equipment computer room;On the ground three layers be equipped with accumulator disk cabinet between and ventilation equipment computer room;It is equipped with for four layers on the ground Between mesolow disk cabinet cable, between accumulator and ventilation equipment computer room;On the ground five layers be equipped with mesolow disk cabinet between, between accumulator disk cabinet With ventilation equipment computer room;On the ground six layers be equipped between cable, reactor protection system rack room, instrument control electric room and ventilation are set Standby host room.
4. the arrangement of nuclear plant safety workshop as claimed in claim 3, it is characterised in that:The A row workshop and B row factory The pressuring machine and induced-draft fan being connect with the ventilation equipment computer room is respectively set in the roof in room.
5. the arrangement of the nuclear plant safety workshop as described in claim 1-4 is any, it is characterised in that:The A row workshop It is symmetrical arranged with each region of B row workshops.
6. the arrangement of the nuclear plant safety workshop as described in claim 1-4 is any, it is characterised in that:The A row workshop It is equipped with independent staircase, escalator, channel and reactor building bonding pad with every layer of the B row workshop.
7. the arrangement of the nuclear plant safety workshop as described in claim 1-4 is any, it is characterised in that:The workshop A row The reinforced concrete structure of antidetonation I classes, seismic acceleration value 0.3g are classified as with workshop B.
8. the arrangement of the nuclear plant safety workshop as described in claim 1-4 is any, it is characterised in that:Reactor building, Fuel plant, electrical building, workshop A row and workshop B row share same bottom plate.
CN201810240596.0A 2018-03-22 2018-03-22 A kind of arrangement of nuclear plant safety workshop Pending CN108597629A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810240596.0A CN108597629A (en) 2018-03-22 2018-03-22 A kind of arrangement of nuclear plant safety workshop

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810240596.0A CN108597629A (en) 2018-03-22 2018-03-22 A kind of arrangement of nuclear plant safety workshop

Publications (1)

Publication Number Publication Date
CN108597629A true CN108597629A (en) 2018-09-28

Family

ID=63627058

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810240596.0A Pending CN108597629A (en) 2018-03-22 2018-03-22 A kind of arrangement of nuclear plant safety workshop

Country Status (1)

Country Link
CN (1) CN108597629A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371933A (en) * 2018-11-23 2019-02-22 中国电建集团成都勘测设计研究院有限公司 Underground workshop ventilating system
CN110047606A (en) * 2019-03-01 2019-07-23 中国核电工程有限公司 A kind of arragement construction of fuel for nuclear power plant workshop
CN110043099A (en) * 2019-03-26 2019-07-23 中国核电工程有限公司 A kind of nuclear power plant resists the simplification means of defence and system of commercial big aircraft impact
CN110067428A (en) * 2019-03-26 2019-07-30 中国核电工程有限公司 A kind of nuclear power plant resists the means of defence and system of commercial big aircraft impact
CN111081403A (en) * 2019-10-09 2020-04-28 中国核电工程有限公司 Layout design method of nuclear power station personnel passing factory building
CN111599501A (en) * 2020-04-20 2020-08-28 中国核电工程有限公司 Arrangement method of nuclear waste liquid system of nuclear auxiliary plant of nuclear power station
CN113314238A (en) * 2021-05-10 2021-08-27 中国核电工程有限公司 Three-generation nuclear power station reactor factory building, arrangement method thereof and nuclear power station

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104047448A (en) * 2014-06-13 2014-09-17 长江勘测规划设计研究有限责任公司 Annular-structure construction layout for underground nuclear power station nuclear island cavern group
CN104060859A (en) * 2014-06-13 2014-09-24 长江勘测规划设计研究有限责任公司 Construction layout of underground nuclear power station nuclear island workshop underground grotto group vertical to depth direction of mountain body
CN104131714A (en) * 2014-06-30 2014-11-05 中国核电工程有限公司 Method for arranging first span of nuclear power station steam turbine plant
EP2814038A1 (en) * 2012-07-19 2014-12-17 Serbex Tecnología y Valores, S.L. Nuclear power plant, safety system with fuse element and gravity elevator
CN105569384A (en) * 2015-12-15 2016-05-11 中广核工程有限公司 Arrangement structure of single-pile nuclear island main workshop of nuclear power station
CN107137837A (en) * 2017-05-24 2017-09-08 长江勘测规划设计研究有限责任公司 Underground nuclear plant fire compartment design method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2814038A1 (en) * 2012-07-19 2014-12-17 Serbex Tecnología y Valores, S.L. Nuclear power plant, safety system with fuse element and gravity elevator
CN104047448A (en) * 2014-06-13 2014-09-17 长江勘测规划设计研究有限责任公司 Annular-structure construction layout for underground nuclear power station nuclear island cavern group
CN104060859A (en) * 2014-06-13 2014-09-24 长江勘测规划设计研究有限责任公司 Construction layout of underground nuclear power station nuclear island workshop underground grotto group vertical to depth direction of mountain body
CN104131714A (en) * 2014-06-30 2014-11-05 中国核电工程有限公司 Method for arranging first span of nuclear power station steam turbine plant
CN105569384A (en) * 2015-12-15 2016-05-11 中广核工程有限公司 Arrangement structure of single-pile nuclear island main workshop of nuclear power station
CN107137837A (en) * 2017-05-24 2017-09-08 长江勘测规划设计研究有限责任公司 Underground nuclear plant fire compartment design method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙琳: "核电常规岛主厂房下沉式布置方案经济性分析", 《科技信息》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371933A (en) * 2018-11-23 2019-02-22 中国电建集团成都勘测设计研究院有限公司 Underground workshop ventilating system
CN109371933B (en) * 2018-11-23 2024-02-27 中国电建集团成都勘测设计研究院有限公司 Underground powerhouse ventilation system of hydropower station
CN110047606A (en) * 2019-03-01 2019-07-23 中国核电工程有限公司 A kind of arragement construction of fuel for nuclear power plant workshop
CN110043099A (en) * 2019-03-26 2019-07-23 中国核电工程有限公司 A kind of nuclear power plant resists the simplification means of defence and system of commercial big aircraft impact
CN110067428A (en) * 2019-03-26 2019-07-30 中国核电工程有限公司 A kind of nuclear power plant resists the means of defence and system of commercial big aircraft impact
CN110043099B (en) * 2019-03-26 2021-09-17 中国核电工程有限公司 Simplified protection method and system for nuclear power plant to resist commercial large airplane collision
CN110067428B (en) * 2019-03-26 2021-09-17 中国核电工程有限公司 Protection method and system for nuclear power plant to resist commercial large airplane collision
CN111081403A (en) * 2019-10-09 2020-04-28 中国核电工程有限公司 Layout design method of nuclear power station personnel passing factory building
CN111081403B (en) * 2019-10-09 2023-12-22 中国核电工程有限公司 Layout design method for personnel passing factory buildings of nuclear power station
CN111599501B (en) * 2020-04-20 2022-11-25 中国核电工程有限公司 Arrangement method of nuclear waste liquid system of nuclear auxiliary plant of nuclear power station
CN111599501A (en) * 2020-04-20 2020-08-28 中国核电工程有限公司 Arrangement method of nuclear waste liquid system of nuclear auxiliary plant of nuclear power station
CN113314238B (en) * 2021-05-10 2023-10-24 中国核电工程有限公司 Three-generation nuclear power station reactor plant, arrangement method thereof and nuclear power station
CN113314238A (en) * 2021-05-10 2021-08-27 中国核电工程有限公司 Three-generation nuclear power station reactor factory building, arrangement method thereof and nuclear power station

Similar Documents

Publication Publication Date Title
CN108597629A (en) A kind of arrangement of nuclear plant safety workshop
CN103850483B (en) A kind of nuclear power plant main building group's method for arranging
CN110047606A (en) A kind of arragement construction of fuel for nuclear power plant workshop
Kostov et al. Safety assessment of A92 reactor building for large commercial aircraft crash
JP2011252800A (en) Nuclear reactor building
CN105569384A (en) Arrangement structure of single-pile nuclear island main workshop of nuclear power station
JP6271158B2 (en) Reactor auxiliary equipment cooling equipment
CN108193906A (en) A kind of nuclear island factory building arrangement
CN203652977U (en) Lift car falling energy dissipation protection device
CN207078146U (en) Air traffic transportation system
Kakodkar Evolution of nuclear reactor containments in India: Addressing the present day challenges
CN108842836A (en) A kind of counter weight device of engineering pile foundation detection ballast test
CN111599501B (en) Arrangement method of nuclear waste liquid system of nuclear auxiliary plant of nuclear power station
CN105390169A (en) Underground nuclear island workshop of deeply buried nuclear power station
JP6618847B2 (en) Safety measures for multi-layer ground building
CN107098234A (en) Many elevator untied simulated techniques and equipment
CN106340330B (en) A kind of underground nuclear power station main building group step layout design method
CN106375501B (en) Terminal
CN203821619U (en) Fire-proof blocking structure used in interlayer hole of shaft
CN104279360B (en) A kind of magnetic induction explosion valve system designed based on foreign intervention
CN204076944U (en) The special cellular board of a kind of many sandwich shelter
CN110067428B (en) Protection method and system for nuclear power plant to resist commercial large airplane collision
CN110043099B (en) Simplified protection method and system for nuclear power plant to resist commercial large airplane collision
CN104443442B (en) Protecting structure and setting method of space product
Moon et al. Development of the APR+ Auxiliary Building General Arrangement (GA)

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination