CN108560561A - A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment - Google Patents

A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment Download PDF

Info

Publication number
CN108560561A
CN108560561A CN201810336657.3A CN201810336657A CN108560561A CN 108560561 A CN108560561 A CN 108560561A CN 201810336657 A CN201810336657 A CN 201810336657A CN 108560561 A CN108560561 A CN 108560561A
Authority
CN
China
Prior art keywords
foundation pit
lifted
mechanical equipment
integrated
collection support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810336657.3A
Other languages
Chinese (zh)
Inventor
孔维强
Original Assignee
孔维强
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 孔维强 filed Critical 孔维强
Priority to CN201810336657.3A priority Critical patent/CN108560561A/en
Publication of CN108560561A publication Critical patent/CN108560561A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Abstract

A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment, constructed for city integrated piping lane.The organic machine of three gantry cranes is combined with girder steel, forms rectangular frame, iron plate is installed at surrounding and top;It is moved on spandrel girder by skid beam and is hung to precast concrete module in foundation pit from ground;Universal driving wheel is installed under three gantry crane column legs;On the ground, remaining four groups of driving wheel is in foundation pit for two groups of driving wheels of foremost;Vibration hammer is arranged in the front end of equipment, and fender pile is squeezed into below ground before excavation;Equipment using runner bucket continuously excavate and transported the soil dug out with conveyer belt;It is sieved equipped with electronic dregs in transmission end of tape, screening sorting processing is carried out to dregs;The crane column leg of back is articulated and connected with main body, can together be removed related column leg in turning.

Description

A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment
One, technical field
The present invention relates to a kind of mechanical equipment, the grooving of collection underground pipe gallery foundation pit, branch in the enclosed space can be realized Crater wall function is protected in one, and the function of concrete pipe gallery module can be lifted simultaneously.
Two, technical background
Currently, conventional underground pipe gallery construction all uses excavator to excavate bright ditch, fender pile supporting crater wall is manually laid, then Using the form of construction work of crane lifting precast concrete module.Common process excavates bright ditch using excavator influences environment, work Efficiency has low;Artificial laying fender pile needs multi agent cooperation that could complete;Crane lifting operation needs Special crane parking stall, occupies construction Place is unfavorable for the construction operation in urban congestion region.
Three, invention content
Problem to be solved:
It is an object of the present invention to provide a kind of mechanical equipments, construct for city integrated piping lane.For realize its function need solve with Lower problem:1, it is to meet environmental requirement, needs to carry out excavation of foundation pit operation in the enclosed space, this requires equipment shapes to advise It is whole, to install coffer;2, it is to reduce construction site, needs to carry out lifting operation using gantry crane;3, in order to ensure to set It is standby to be moved forward according to installation progress, it needs that driving wheel is arranged;4, it is to guarantee smoothly by prefabricated piping lane module from ground Face is hung in foundation pit, and equipment is needed to have supporting member in ground and foundation pit simultaneously;5, it is to ensure Excavation Process safety, It needs to complete fender pile supporting operation before excavation;6, it is to improve excavation speed, needs to use " excavation-conveying " inline process Carry out excacation;7, need the dregs Screening Treatment that will be dug out after the completion of lifting, using satisfactory dregs it is reserved as time It bankets;8, foundation pit narrow space, equipment turning is inconvenient, needs to take measures to reduce equipment turning radius.
Solution
The object of the present invention is achieved like this, with girder steel by 3 gantry crane organic assemblings, forms rectangular frame, surrounding and Top is installed by iron plate;Not only can be with closed operation region, but also Active workings can be saved;By skid beam, movement will be pre- on spandrel girder Concrete modular processed is hung to from ground in foundation pit;One group of universal driving wheel is installed under each column leg of 3 gantry cranes, to realize The mobile turning function of equipment;On the ground, remaining 4 groups of postposition driving wheel is placed in foundation pit preposition 2 groups of driving wheels, and height difference can be with It is adjusted according to cutting depth;Vibration hammer is set in the front end of equipment, fender pile can be squeezed into ground while advancing Hereinafter, carrying out security protection for follow-up excavation;The mud that equipment using runner bucket continuously excavate and will be dug out with conveyer belt Soil transports immediately;It is sieved equipped with electronic dregs in transmission end of tape, screening sorting processing is carried out to dregs, satisfactory dregs stays It is used as backfill down;2 groups of driving wheels of back are articulated and connected by column leg and main body, can related column leg is together in turning It removes, only stays a pair of driving wheels in foundation pit, turning radius of the equipment in foundation pit can be reduced.
Four, it illustrates
Attached drawing 1 is a kind of collection Support of Foundation Pit Excavation and is lifted on integrated mechanical equipment front view;
Attached drawing 2 is a kind of collection Support of Foundation Pit Excavation and is lifted on integrated mechanical equipment top view;
Attached drawing 3 is a kind of collection Support of Foundation Pit Excavation and is lifted on integrated mechanical equipment side view;
Attached drawing 4 is a kind of collection Support of Foundation Pit Excavation and is lifted on integrated mechanical equipment axonometric drawing;
Attached drawing 5 is runner bucket enlarged drawing in Fig. 4;
In figure:1 girder steel;2 gantry cranes;3 skid beams;4 spandrel girders;The universal driving wheel of 5 postpositions;6 preposition universal driving wheels;7 vibrations Hammer;8 runner buckets;9 conveyer belts;10 hinged links;11 electronic dregs sieves.
Five, specific implementation mode
In figure 4, the organic machine of three gantry cranes (2) is combined with girder steel (1), forms rectangular frame, surrounding and top Portion is installed by iron plate;It is moved on spandrel girder (4) by skid beam (3) and is hung to installation module in foundation pit from ground;3 gantry cranes (2) universal driving wheel is installed under column leg;On the ground, remaining four groups of postposition driving wheel (5) is in foundation pit for two groups of front driving wheels (6) Interior, height difference can be adjusted according to cutting depth;Equipment front end setting vibration hammer (7), fender pile squeeze into ground with Under, carry out security protection for follow-up excavation;Equipment using runner bucket (8) continuously excavate and will be dug out with conveyer belt (9) Soil transport;It is equipped with electronic dregs in transmission end of tape and sieves (11), screening sorting processing, satisfactory slag are carried out to dregs Soil gives over to backfill;The crane column leg of back is articulated and connected (10) with main body, can together be removed related column leg in turning, It only stays a pair of driving wheels in foundation pit, reduces turning radius.

Claims (9)

1. a kind of collection Support of Foundation Pit Excavation and being lifted on integrated mechanical equipment;By gantry crane, skid beam, spandrel girder, universal drive Driving wheel, vibration hammer, runner bucket, conveyer belt composition;Its characteristic use girder steel by three gantry cranes, vibration hammer, runner bucket, Conveyer belt, electronic dregs sieve are integrated into a whole.
2. collection Support of Foundation Pit Excavation according to claim 1 and be lifted on integrated mechanical equipment, it is characterized in that surrounding and It is closed with iron plate at top.
3. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that using girder steel Three gantry cranes are integrated into a whole.
4. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that using girder steel Vibration hammer and gantry crane are integrated into a whole.
5. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that using girder steel Runner bucket is integrated into a whole with gantry crane.
6. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that conveyer belt It is integrated into a whole with gantry crane.
7. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that by electronic Dregs sieve is integrated into a whole with gantry crane.
8. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that front two A driving wheel has height difference with remaining four groups.
9. collection Support of Foundation Pit Excavation according to claim 1 and integrated mechanical equipment is lifted on, it is characterized in that rear portion two A driving wheel supporting leg is articulated and connected with main body.
CN201810336657.3A 2018-04-16 2018-04-16 A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment Withdrawn CN108560561A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810336657.3A CN108560561A (en) 2018-04-16 2018-04-16 A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810336657.3A CN108560561A (en) 2018-04-16 2018-04-16 A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment

Publications (1)

Publication Number Publication Date
CN108560561A true CN108560561A (en) 2018-09-21

Family

ID=63535153

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810336657.3A Withdrawn CN108560561A (en) 2018-04-16 2018-04-16 A kind of collection Support of Foundation Pit Excavation and it is lifted on integrated mechanical equipment

Country Status (1)

Country Link
CN (1) CN108560561A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5040921A (en) * 1989-10-13 1991-08-20 Torok Frank J Segmented tunnel system
CN105714851A (en) * 2016-02-29 2016-06-29 济南轨道交通集团有限公司 Integrated construction device for assembly type underground diaphragm wall or precast pile and cast-in-place underground station and construction method adopting same
CN106088149A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 A kind of mechanization rapid constructing method of precast splice type underground gallery
CN107724425A (en) * 2017-09-19 2018-02-23 中建科技有限公司深圳分公司 The mechanized construction equipment and construction method of a kind of prefabricated pipe gallery

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5040921A (en) * 1989-10-13 1991-08-20 Torok Frank J Segmented tunnel system
CN105714851A (en) * 2016-02-29 2016-06-29 济南轨道交通集团有限公司 Integrated construction device for assembly type underground diaphragm wall or precast pile and cast-in-place underground station and construction method adopting same
CN106088149A (en) * 2016-08-05 2016-11-09 中交第二航务工程局有限公司 A kind of mechanization rapid constructing method of precast splice type underground gallery
CN107724425A (en) * 2017-09-19 2018-02-23 中建科技有限公司深圳分公司 The mechanized construction equipment and construction method of a kind of prefabricated pipe gallery

Similar Documents

Publication Publication Date Title
CN103981898B (en) A kind of inverse underground engineering construction method done of overall open cut node
CN103291308B (en) For boom-type roadheader and the method for tunnel construction of constructing tunnel
JP4184400B2 (en) Construction method of underground structure
KR100209103B1 (en) Excavator for forming underground continuous wall
CN101338678B (en) Supporting arch hidden digging top-down construction method
CN104074199B (en) Underwater bearing platform construction method
JP3284047B2 (en) Construction method of underground diaphragm wall
CN103938617B (en) A kind of ultra-deep underground continuous wall and construction method thereof
CN102392648A (en) Method for building subway station by expansively digging large-diameter shield tunnel
CN102691300B (en) Construction method of foundation pit earthwork
KR20040097967A (en) Construction method of three arch excavation tunnel
US4696607A (en) Slurry trench method and apparatus for constructing underground walls
CN102505706A (en) Method for building subway station
CN102720140A (en) Large-span prestress concrete continuous beam deepwater pier construction process
US5957624A (en) Apparatus and method for in Situ installation of underground containment barriers under contaminated lands
CN103628885A (en) Tunnel exit cover-excavation construction method of Ultra-shadow buried tunnel
CN104131829B (en) A kind of solid filling coal mining hydraulic supporting building and withdrawing frame method
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN205024740U (en) Civil engineering uses multi -functional excavating machinery
CN105155579A (en) Construction method for penetrating existing underground passage in open cutting of subway foundation pit
CN101922293A (en) Method for installing waterproof steel plate in construction of underground tunnel
CN106869936A (en) It is a kind of to be suitable to the surface mining new method of steep slope topography
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
EP0407934B1 (en) Method for executing monolithic continuous straights or circular structural walls and a machine for realizing such a method
CN104727324B (en) Irregular basement construction method for supporting

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20180921

WW01 Invention patent application withdrawn after publication