CN101775821B - Device and method for vertically transporting earthwork by reverse construction method - Google Patents

Device and method for vertically transporting earthwork by reverse construction method Download PDF

Info

Publication number
CN101775821B
CN101775821B CN 200910311140 CN200910311140A CN101775821B CN 101775821 B CN101775821 B CN 101775821B CN 200910311140 CN200910311140 CN 200910311140 CN 200910311140 A CN200910311140 A CN 200910311140A CN 101775821 B CN101775821 B CN 101775821B
Authority
CN
China
Prior art keywords
floor
conveyer belt
earthwork
negative
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200910311140
Other languages
Chinese (zh)
Other versions
CN101775821A (en
Inventor
贺小村
马宁
王剑峰
朱燕
赵俭学
陈娣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Divison Group Huajiang Construction Co Ltd
China Construction First Divison Group Huazhong Construction Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Divison Group Huajiang Construction Co Ltd
China Construction First Divison Group Huazhong Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Divison Group Huajiang Construction Co Ltd, China Construction First Divison Group Huazhong Construction Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN 200910311140 priority Critical patent/CN101775821B/en
Publication of CN101775821A publication Critical patent/CN101775821A/en
Application granted granted Critical
Publication of CN101775821B publication Critical patent/CN101775821B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a device and a method for vertically transporting earthwork by a reverse construction method, which belong to the field of civil construction. In the device, segmental belt-type conveyor belts are adopted as earthwork transporting tools in a deep foundation pit; the conveyor belts pass through reserved holes of floor slabs on each floor; and the earthwork is transported to a dump truck obliquely from the bottom to the top by the conveyor belts. The device is formed by connecting independently segmented and obliquely arranged belt-type conveyor belts end to end; and each floor is provided with at least one conveyor belt which consists of an electric motor, a conveyor belt rack, an unloading tank, a scraping plate, a roller wheel, a roller wheel shaft bracket, a belt, a feeding funnel and an emergency brake device. The device and the method for vertically transporting the earthwork by the reverse construction method can effectively increase the earth volume in single vertical transport, effectively improve excavation efficiency, reduce excavation machines, reduce excavation cost, and simultaneously, reduce the influence of the construction of underground excavation on the simultaneous construction of an upper structure to the minimum.

Description

Reverse construction earthwork vertical transferring apparatus and method
Technical field
The present invention relates to the device and method of deep foundation ditch earthwork transportation in a kind of construction work.
Background technology
At present, when the deep foundation ditch reverse construction, the key of restriction duration is a cubic metre of earth travelling speed.Most of contrary working method engineering adopts high-front shovel, and crawler belt grab bucket shovel machine or straddle truck directly are unearthed from the shoveling hole.The long-armed digging machine on limit, hole or crawler belt grab bucket shovel machine need turn round operation when promoting dress soil owing to be unearthed, and needs bigger running space, and big machinery and vehicle need be gone up floor.The mode of more than being unearthed mainly is fit to have the basement excavation of annex, perhaps the half contrary engineering of doing.
When overground part take up an area of with under ground portion take up an area of about the same when big because the restriction of first floor floor height, have only when under ground portion cut the earth finish after, just can carry out the construction of overground part, very big to the duration influence like this.
Summary of the invention
The invention provides a kind of reverse construction earthwork vertical transferring apparatus and method, solve that existing earthwork construction shoveling inefficiency, digging machine are huge, shoveling cost height, the technical problem that can not carry out the superstructure construction simultaneously.
For achieving the above object, the present invention adopts following technical scheme:
This reverse construction earthwork vertical transporting method, it adopts the instrument of the belt-type conveyer belt of merogenesis as deep foundation ditch earthwork transportation, conveyer belt passes from the reservation hole of each floor plate, and the earthwork is directly transported on the ground tipping truck through conveyer belt, and concrete construction sequence is as follows:
Step 1: at first carry out the construction of space enclosing structure, pile foundation and the intermediolateral column in deep foundation pit construction place;
Step 2: the open cut earthwork on construction ground, the construction of clay model method ± 0The floor of layer, ± 0Reserve the hole on the floor of layer, arrange the conveyer belt of the first floor, will ± 0The earthwork that layer excavates ± 0Layer is transported on the tipping truck on ground through conveyer belt;
Step 3: when ± 0The structural strength of floor plate reaches at 100% o'clock, removes ± 0The floor plate is reserved the template and the cleaning at place, hole, the hole is local cuts the earth downwards from reserving, reserve lower floor's digging face, to the negative one deck conveyer belt of the oblique continued access of negative one deck, the earthwork that divides the negative one deck of section tunneling, horizontal spreading conveyer belt is to the work plane of cutting the earth, to be transported on the tipping truck on ground in the earthwork that negative one deck excavates, simultaneously, with the floor of the negative one deck of clay model method construction, floor at negative one deck is reserved the hole, construction F2/B2 floor;
Step 4: when the floor slab structure intensity of negative one deck reaches 100%, remove the floor of negative one deck and reserve hole place's template and cleaning, toward the negative two layers of conveyer belt of negative two layers of oblique continued access, divide the section tunneling negative two layers of earthwork, horizontal spreading conveyer belt will be transported on the tipping truck on ground in the earthwork of negative two layers of excavation to the work plane of cutting the earth, simultaneously, the floor that the construction of clay model method is negative two layers is reserved the hole at negative two layers floors, and construction is three floor plates on the ground;
Step 5: repeat above-mentioned steps three to step 4, until being excavated to the basement bottom board place.
The reverse construction earthwork vertical transferring apparatus that described method adopted, form by the independent segmented belt-type conveyer belt head and the tail continued access that is obliquely installed, has one section conveyer belt at least at each floor, described belt-type conveyer belt comprises motor, running roller, running roller pedestal, belt, conveyer belt frame and elevating hopper, and elevating hopper is positioned at the afterbody of belt-type conveyer belt.
The angle of inclination of described conveyer belt is less than 19 degree.
The inclination conveyer belt of described each floor and the continued access of horizontal spreading conveyer belt.
Reverse construction earthwork vertical transporting method of the present invention and device can be according to total earth volumes of basement, and the budget shoveling duration calculates the amount of being unearthed every day, and the individual layer area is divided into some unearthed districts, and each district sets up one to overlap independently conveyer belt vertical transit system.
The conveyer belt vertical transit system is constituted jointly by the conveyer belt of independent merogenesis, and every joint length does not wait from 8 meters-20 meters, according to floor height, the openings position flexible arrangement, box out on the floor is that 2 meters wide * 4 are meter long just enough, but double as ventilation hole, hole is placed ladder and done personnel's passage up and down.
Soil in bulk is evenly distributed on very long being with, and is little to the pressure of each strong point, do not have impact load, do not need the extra in addition floor design of reinforcement that increases.
Compared with prior art the present invention has following beneficial effect:
1. because conveyer belt can directly arrive the shoveling work plane of basement by spreading, excavator can with the earthwork of excavating directly overturning on conveyer belt, therefore, do not need basement to turn over to refute digging machine to turn over haul volume, reduced the process of cutting the earth and lightering.Can increase substantially shoveling efficient.
2. the required dimension of opening of conveyer belt is less, and is favourable to horizontal support structure.
3. adopt the conveyer belt vertical transport to replace ± 0The large-scale lifting earth loader tool such as the straddle truck of the big rotary space of the needs on the floor, long-armed digging machine etc.Therefore, the above and below ground structure can be constructed simultaneously, can effectively accelerate the duration.
4. the power owing to conveyer belt is electricity, and a large amount of digging machines of former method are diesel, and the environmental protection energy-saving and emission-reduction have also been produced sizable benefit.
5. after the employing carousel transmission scheme, the muck haulage vehicle is not gone up floor, and beam slab does not need to strengthen design, has reduced amount of reinforcement.
6. but the present invention's overground part and under ground portion are constructed simultaneously, effectively increase the earth volume of single vertical transport, effectively improve shoveling efficient, reduce digging machine, reduce the shoveling cost, the influence that underground excavation and construction is constructed simultaneously to superstructure eases down to minimum degree, has shortened the duration significantly.
Description of drawings
Fig. 1 makes shoveling step conveyer belt for the present invention is contrary and arranges schematic diagram;
Fig. 2 is the structure diagram of 8 meters long conveyer belts of the present invention;
Fig. 3 is a conveyer belt cross-sectional view of the present invention;
Reference numeral: 1- ± 0The floor of layer; The floor of the negative one deck of 2-; The floor that 3-is negative two layers; The floor that 4-is negative three layers; The 5-basement bottom board; 6-F2/B2 floor; 7-is three floor plates on the ground; 8-is four floor plates on the ground; 9-is five floor plates on the ground; The 10-pile foundation; 11- ± 0Layer conveyer belt; 12-bears one deck conveyer belt; 13-bears two layers of conveyer belt; 14-bears three layers of conveyer belt; 15-bears four layers of conveyer belt; The 16-motor; The 17-running roller; 18-running roller pedestal; The 19-belt; 20-conveyer belt frame; The 21-elevating hopper.
The specific embodiment
The present invention will be further described below in conjunction with accompanying drawing 1-3:
With underground four layers is example:
The general colum network size of engineering is 8 meters * 16 meters, 140 meters * 70 meters of building sizes.According to duration and total Earthwork Calculation, be divided into 3 sections, about 50 meters long of each section is provided with one respectively and overlaps independently conveyer belt system.
Referring to shown in Figure 1, reverse construction earthwork vertical transporting method of the present invention, it adopts the instrument of the belt-type conveyer belt of merogenesis as earthwork vertical transport, by the technical reservation hole on each floor plate conveyer belt is installed, the earthwork is directly received on the tipping truck of road by conveyer belt, and its concrete construction sequence is as follows:
Step 1: at first carry out the construction of place enclosed structure, pile foundation and intermediolateral column;
Step 2: the levelling of the land open cut earthwork, the construction of clay model method ± 0The floor 1 of layer is reserved the hole, arranges ± 0Layer conveyer belt 11 is used for the oblique tipping truck that is transported on the road;
Step 3: when ± 0 Floor 1 structural strength of layer reaches at 100% o'clock, remove hole place's template and cleaning, floor 2 toward negative one deck connects oblique negative one deck conveyer belt 12,2 cubic metres of earth on the floor of the negative one deck of branch section tunneling, horizontal spreading conveyer belt are to the work plane of cutting the earth, and the floor 2 of one deck is born in the construction of clay model method, reserve the hole, hole place digs dark 3 meters in the part, and cutting the earth to lower floor provides in advance the scope of operation, the F2/B2 floor 6 of constructing on the ground;
Step 4: when floor 2 structural strengths of negative one deck reach 100%, remove hole place's template and cleaning, connect oblique negative two layers of conveyer belt 13 toward negative one deck, divide the section tunneling negative two layers of earthwork, horizontal spreading conveyer belt is to the work plane of cutting the earth, and two layers floor 3 is born in the construction of clay model method, reserve the hole, hole place digs dark 3 meters in the part, and cutting the earth to lower floor provides in advance the scope of operation, and construction is three floor plates 7 on the ground;
Step 5: when negative two layers floor 3 structural strengths reach 100%, repeat top step, connect oblique negative three layers of conveyer belt 14, negative three layers of excavation, three layers floor 4 is born in construction, and construction is four floor plates 8 on the ground.
Step 6: when negative three layers floor 4 structural strengths reach 100%, repeat top step, connect oblique negative four layers of conveyer belt 15, negative four layers of excavation, construction basement bottom board 5, the five floor plates 9 on the ground of constructing.
Vertical transferring apparatus that said method adopts is constituted jointly by the belt-type conveyer belt of independent merogenesis setting, and the ramp angle control of floor gap conveyer belt adopts steel pipe scaffold to install; Conveyer belt is made up of motor 16, conveyer belt frame 20, unloading groove, scraper plate, running roller 17, running roller pedestal 18, belt 19, elevating hopper 21 and the device of bringing to a halt.Motor 16, unloading groove, scraper plate, elevating hopper 21, bring to a halt device and running roller 17, running roller pedestal 18 are separately positioned on two ends, the left and right sides and medium position on the conveyer belt frame 20, belt 19 is placed on the running roller 17 of 20 of conveyer belt frames, for the conveyer belt ramp angle that the earthwork is not glided is 18 degree.
Referring to Fig. 2, shown in Figure 3, the conveyer belt main body is a conveyer belt frame 20, the belt 19 thickness 7-8mm of conveyer belt, and wide 650mm can widen as required.Each conveyer belt is joined a unloading groove, two each and every one scraper plates, running roller pedestal 18, upper and lower running roller 17 several.Each conveyer belt is furnished with the independent motor 16 and the device of bringing to a halt, and motor power (output) is 3kw.Conveyer belt length is less than 10 meters, and is then non-dismountable, if its length greater than 10 meters, then can be assembled.The conveyer belt technical performance is as follows: conveyer belt is used to transport soil in bulk, the maximal density of soil: 1.3t/m 3Theoretical capacity: 60m 3/ h (80t/h); Speed: 1m/s.
More than be a kind of exemplary embodiments of the present invention, enforcement of the present invention is not limited thereto.

Claims (4)

1. reverse construction earthwork vertical transporting method, it is characterized in that: the belt-type conveyer belt that adopts segmentation is as deep foundation ditch earthwork vehicle, conveyer belt passes from the reservation hole of each floor plate, cubic metre of earth on the oblique from bottom to top tipping truck of transporting to ground of conveyer belt, concrete construction sequence is as follows:
Step 1: at first carry out the construction of supporting and protection structure, pile foundation (10) and the intermediolateral column in deep foundation pit construction place;
Step 2: the open cut earthwork on construction ground, the construction of clay model method The floor of layer, The floor (1) of layer go up to be reserved the hole, arranges the conveyer belt of the first floor, will The earthwork that layer excavates is transported on the tipping truck on ground through conveyer belt (11);
Step 3: when
Figure 663967DEST_PATH_IMAGE001
The structural strength of floor plate (1) reaches at 100% o'clock, removes
Figure 606515DEST_PATH_IMAGE001
The floor plate is reserved the template and the cleaning at place, hole, the hole is local cuts the earth downwards from reserving, reserve lower floor's digging face, to the negative one deck conveyer belt (12) of the oblique continued access of negative one deck, the earthwork that divides the negative one deck of section tunneling, horizontal spreading conveyer belt is to the work plane of cutting the earth, to be transported on the tipping truck on ground in the earthwork that negative one deck excavates, simultaneously, with the floor (2) of the negative one deck of clay model method construction, floor (2) at negative one deck is reserved the hole, construction F2/B2 floor (6);
Step 4: when the floor (2) of negative one deck when structural strength reaches 100%, remove the floor (2) of negative one deck and reserve hole place's template and cleaning, toward the negative two layers of conveyer belt (13) of negative two layers of oblique continued access, divide the section tunneling negative two layers of earthwork, horizontal spreading conveyer belt will be transported on the tipping truck on ground in the earthwork of negative two layers of excavation to the work plane of cutting the earth, simultaneously, the floor (3) that the construction of clay model method is negative two layers is reserved the hole at negative two layers floors (3), and construction is three floor plates (7) on the ground;
Step 5: repeat above-mentioned steps three to step 4, locate until being excavated to basement bottom board (5).
2. reverse construction earthwork vertical transferring apparatus that the described method of claim 1 is adopted, it is characterized in that: form by the independent segmented belt-type conveyer belt head and the tail continued access that is obliquely installed, has one section conveyer belt at least at each floor, described belt-type conveyer belt comprises motor (16), running roller (17), running roller pedestal (18), belt (19), conveyer belt frame (20) and elevating hopper (21), and elevating hopper (21) is positioned at the afterbody of belt-type conveyer belt.
3. reverse construction earthwork vertical transferring apparatus according to claim 2 is characterized in that: the angle of inclination of described conveyer belt is less than 19 degree.
4. reverse construction earthwork vertical transferring apparatus according to claim 2 is characterized in that: the inclination conveyer belt of described each floor and the continued access of horizontal spreading conveyer belt.
CN 200910311140 2009-12-10 2009-12-10 Device and method for vertically transporting earthwork by reverse construction method Expired - Fee Related CN101775821B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200910311140 CN101775821B (en) 2009-12-10 2009-12-10 Device and method for vertically transporting earthwork by reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200910311140 CN101775821B (en) 2009-12-10 2009-12-10 Device and method for vertically transporting earthwork by reverse construction method

Publications (2)

Publication Number Publication Date
CN101775821A CN101775821A (en) 2010-07-14
CN101775821B true CN101775821B (en) 2011-06-08

Family

ID=42512393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200910311140 Expired - Fee Related CN101775821B (en) 2009-12-10 2009-12-10 Device and method for vertically transporting earthwork by reverse construction method

Country Status (1)

Country Link
CN (1) CN101775821B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102758441A (en) * 2011-04-23 2012-10-31 中国建筑第四工程局有限公司 Relay unearthing method and structure for deep foundation pit platform under reverse construction condition
CN104695497B (en) * 2014-12-30 2019-11-22 无锡三和重工机械有限公司 The upper native machine construction technology of large-scale earth and rock works
CN104790406B (en) * 2015-03-26 2016-08-24 中国建筑第八工程局有限公司 Basement is inverse to be made engineering earthwork level and has bad luck method
CN106608491A (en) * 2015-10-22 2017-05-03 中铁二局集团有限公司 Adjustable conveying belt muck discharging method for high-slope-ratio entrance and exit channel
CN105257304B (en) * 2015-11-19 2018-05-25 宋明富 Huge vertical shield machine
CN106347934B (en) * 2016-08-30 2018-12-28 上海市基础工程集团有限公司 Binary combines chain type earthwork perpendicular lifting apparatus
CN107090838A (en) * 2017-06-21 2017-08-25 贵州省水利水电勘测设计研究院 A kind of generous amount of accumulation body cuts the constructing structure and method of slope back-pressure
CN107459001B (en) * 2017-08-27 2023-05-26 保利新联爆破工程集团有限公司 Manual hole digging pile soil outlet lifting device
CN108729449A (en) * 2018-05-22 2018-11-02 四川城凯特建设工程有限公司 A kind of construction method and deep basal pit soil transport device of deep basal pit
CN109915164B (en) * 2019-03-01 2020-06-19 中铁十四局集团有限公司 Soil body transferring method for tunnel contact channel
CN111549846B (en) * 2020-04-30 2021-09-24 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing treatment
CN112281939A (en) * 2020-10-21 2021-01-29 上海建工二建集团有限公司 Reverse construction method long-distance soil taking and carrying integrated equipment and construction method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1948633A (en) * 2005-10-14 2007-04-18 上海市第七建筑有限公司 Tray type excarvating contrary construction method
CN101255702A (en) * 2008-02-29 2008-09-03 刘志宏 Method for mining construction of inverse practicing project using carriageway method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1948633A (en) * 2005-10-14 2007-04-18 上海市第七建筑有限公司 Tray type excarvating contrary construction method
CN101255702A (en) * 2008-02-29 2008-09-03 刘志宏 Method for mining construction of inverse practicing project using carriageway method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
JP特开平11-152768A 1999.06.08
JP特开平9-195312A 1997.07.29
黄钽,邵凯平,戴文龙,蔡卫祥.逆作法在杭州环北丝绸服装城的应用.《施工技术》.2009,(第9期),第57-59页. *

Also Published As

Publication number Publication date
CN101775821A (en) 2010-07-14

Similar Documents

Publication Publication Date Title
CN101775821B (en) Device and method for vertically transporting earthwork by reverse construction method
CN104775817A (en) All-negative pressure continuous-mining continuous-filling step-by-step replacement mining method for coal underneath cities and towns, industrial buildings, railways and other buildings
CN101713191B (en) Device and method used for excavating foundation pit deep earthwork
CN101434358A (en) Elevator for deep foundation pit excavation by inverse construction method, and excavation system and method
CN102691300A (en) Construction method of foundation pit earthwork
CN105887889A (en) Excavation construction method for super-wide low-permeability silty deep foundation pit
CN102060199B (en) Transportation method for constructing high mountain building
CN107524141B (en) Construction method of cast-in-situ bored pile of rock soil foundation
CN109339096A (en) A kind of construction integrated constructing device of pipe gallery open cut precast assembly and its construction method
CN109812271B (en) Construction method for shield-crossing limited box culvert
CN106245652B (en) A kind of construction method of deep foundation pit earthwork digging near a river
CN201339209Y (en) Top-down construction earth excavation earth-moving device
WO2016155657A1 (en) Movable cofferdam open-cutting method
CN210530844U (en) A dregs conveyer that is used for undermining construction heavy grade to dive section of digging
CN111350520A (en) Underground water drainage system for underground excavation tunnel in water-rich sandy gravel stratum and construction method thereof
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology
CN110821508A (en) Rock mining device and method for penetrating through surrounding rock of broken zone
CN201334293Y (en) Hoist and excavation construction system used for deep foundation pit excavation using top-down method
CN112459834B (en) Water collecting well, counter-slope tunnel and counter-slope tunnel drainage method
CN111852554B (en) Rapid trenching method for large water inrush quantity pit open-pit mine small-block full-section deep one-time blasting
CN103154434A (en) Closed trench tunnels
CN105952449A (en) Novel dry-type stoping method for tailings in tailing pond
CN206554118U (en) City integrated piping lane protects self-propelled laydown machine certainly
CN213775379U (en) Construction system for small-section ultra-long water delivery tunnel in hard rock stratum
JP6276300B2 (en) Open shield method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110608

Termination date: 20131210