CN108520361A - Process task management method, device and computer readable storage medium - Google Patents

Process task management method, device and computer readable storage medium Download PDF

Info

Publication number
CN108520361A
CN108520361A CN201810323817.0A CN201810323817A CN108520361A CN 108520361 A CN108520361 A CN 108520361A CN 201810323817 A CN201810323817 A CN 201810323817A CN 108520361 A CN108520361 A CN 108520361A
Authority
CN
China
Prior art keywords
process task
node
engineering
planned time
procedure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810323817.0A
Other languages
Chinese (zh)
Inventor
马天正
唐洪凯
冯丰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wanyi Technology Co Ltd
Original Assignee
Wanyi Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wanyi Technology Co Ltd filed Critical Wanyi Technology Co Ltd
Priority to CN201810323817.0A priority Critical patent/CN108520361A/en
Publication of CN108520361A publication Critical patent/CN108520361A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations

Abstract

The invention discloses a kind of methods of process task management, including:Engineering project is established according to process template, includes multistage node in the engineering project, and includes procedure-node in the multistage node;Project data is received, and according to the procedure-node generation process task in the project data and the engineering project;The planned time of the process task is obtained, and the planned time of the multistage node is set according to the planned time of the process task;The process task provided with planned time is associated with preset person liable, the process task is managed for the person liable.The invention also discloses a kind of process task management device and computer readable storage mediums.The present invention includes the process task scheduling of multistage node, the planned time of setting process task by formulating, and generation process task is simultaneously assigned to related personnel, provides the high management method of structuring degree, to ensure the smooth development of project under construction and orderly carry out.

Description

Process task management method, device and computer readable storage medium
Technical field
The present invention relates to field of engineering technology more particularly to a kind of process task management method, process task management devices And computer readable storage medium.
Background technology
In the technical field of the project management of engineering, there are some Project Management Softwares from the formulation project plan, prison Control and item controlled progress, to show project risk etc. many-sided to ensure the overall progress of project and the information of project management process Change.
The building engineering field segmented under engineering project, the building structure complexity that is related to due to architectural engineering is various, relates to And items it is various, work progress link is numerous and it is more to check and accept object type, need a set of structuring degree compared with The process task scheduling that actual architectural engineering plan can be split into clear layer and be easily managed by high management method, and show Some Project Management Softwares can not meet the needs of such management process task well.
The above is only used to facilitate the understanding of the technical scheme, and is not represented and is recognized that the above is existing skill Art.
Invention content
The main purpose of the present invention is to provide a kind of management method of process task, process task management device and calculating Machine readable storage medium storing program for executing, it is intended to solve in the prior art that can not actual engineering project to be split into level clear for Project Management Software It is clear and be easily managed process task scheduling the technical issues of.
To achieve the above object, the present invention provides a kind of management method of process task, the manager of the process task Method includes the following steps:
Engineering project is established according to process template, comprising multistage node in the engineering project, and the multistage node In include procedure-node;
Project data is received, and is appointed according to the procedure-node generation process in the project data and the engineering project Business;
The planned time of the process task is obtained, and according to the planned time of the process task setting multistage section The planned time of point;
The process task provided with planned time is associated with preset person liable, for the person liable to institute Process task is stated to be managed.
Preferably, described established before engineering project step according to process template and project data includes:
Obtain the hierarchical relationship between multistage node and each node;
Obtain the examination object of the procedure-node;
According to the examination object generation process template of the hierarchical relationship and the procedure-node between each node.
Preferably, the reception project data, and according to the procedure-node in the project data and the engineering project Generation process task step includes:
Obtain the examination object of the procedure-node;
According to the process task of the procedure-node checked and accepted object and generate corresponding types.
Preferably, include after the examination object step for obtaining the procedure-node:
Obtain the acceptance criteria of the procedure-node;
Work is generated according to the examination object of hierarchical relationship, the procedure-node between each node and acceptance criteria Sequence template.
Preferably, the reception project data, and according to the procedure-node in the project data and the engineering project Include after generation process task step:
It receives Engineering Planning Document and generates instruction;
Instruction is generated according to the Engineering Planning Document and generates Engineering Planning Document to be edited, for editing the process The planned time of task.
Preferably, described to obtain the planned time of the process task, and set according to the planned time of the process task The planned time step for setting the multistage node includes:
The Engineering Planning Document edited is obtained, the Engineering Planning Document edited includes the process task Planned time information;
The planned time of the multistage node is set according to the planned time information of the process task.
Preferably, which is characterized in that the planned time for obtaining the process task, and according to the process task Planned time includes after the planned time step of the multistage node is arranged:
Receive the instruction of uniform delay process task scheduling time;
The number of days of uniform delay is obtained from the instruction of the uniform delay process task scheduling time;
Postpone the planned time of the process task according to the number of days of the uniform delay.
In addition, to achieve the above object, the present invention also provides the process task management device, which includes:It deposits Reservoir, processor and it is stored in the process task management program that can be run on the memory and on the processor, it is described Process task management program realizes the step of management method of process task as described above when being executed by the processor.
In addition, to achieve the above object, the present invention also proposes a kind of computer readable storage medium, which is characterized in that institute The management program that process task is stored on computer readable storage medium is stated, the management program of the process task is by processor The step of management method of process task as described above is realized when execution.
Management method, device and the computer readable storage medium for a kind of process task that the embodiment of the present invention proposes, root Engineering project is established according to process template, includes multistage node in the engineering project, and includes process in the multistage node Node;Project data is received, and according to the procedure-node generation process task in the project data and the engineering project;It obtains When taking the planned time of the process task, and the plan of the multistage node being set according to the planned time of the process task Between;The process task provided with planned time is associated with preset person liable, for the person liable to the work Sequence task is managed.
The present invention based on process template by formulating the process task scheduling for including multiple hierarchy nodes, setting process task Planned time in the works is based on complete process task scheduling generation process task, and process task assignment is blamed to related The person of leting people provides the management method that a kind of structuring degree is high and feedback is closed and assists construction responsible person's management project construction The process task at scene, to ensure the smooth development of project under construction and orderly carry out.
Description of the drawings
Fig. 1 is the terminal structure schematic diagram for the hardware running environment that the embodiment of the present invention is related to;
Fig. 2 is the flow diagram of process task management method first embodiment of the present invention;
Fig. 3 is the flow diagram of process task management method second embodiment of the present invention;
Fig. 4 is the flow diagram of process task management method 3rd embodiment of the present invention.
The embodiments will be further described with reference to the accompanying drawings for the realization, the function and the advantages of the object of the present invention.
Specific implementation mode
It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not intended to limit the present invention.
The primary solutions of the embodiment of the present invention are:Engineering project is established according to process template, in the engineering project Including multistage node, and include procedure-node in the multistage node;Receive project data, and according to the project data and Procedure-node generation process task in the engineering project;The planned time of the process task is obtained, and according to the work The planned time of the multistage node is arranged in the planned time of sequence task;By provided with planned time the process task with it is pre- If person liable association, the process task is managed for the person liable.
Since in the prior art, the Project Management Software structuring degree of building field is low, not to miscellaneous special Industry and construction link carry out orderly classification and rational fractionation, can not be suitable for the pipe of different types of construction projects Reason.
The present invention provides a solution, by formulating the process task for including multiple hierarchy nodes based on process template Plan, the planned time in setting process task scheduling are based on complete process task scheduling generation process task, and by process Task assignment gives related responsibility personnel, provides the management method that a kind of structuring degree is high and feedback is closed and construction is assisted to be responsible for The process task at personal management project construction scene, to ensure the smooth development of project under construction and orderly carry out.
As shown in Figure 1, the terminal structure schematic diagram for the hardware running environment that Fig. 1, which is the embodiment of the present invention, to be related to.
Terminal of the embodiment of the present invention is the device of process task management.
As shown in Figure 1, the device may include:Processor 1001, such as CPU, communication bus 1002, memory 1003. Wherein, communication bus 1002 is for realizing the connection communication between these components.Memory 1003 can be high-speed RAM storage Device can also be stable memory (non-volatile memory), such as magnetic disk storage.Memory 1003 is optional It can also be the storage device independently of aforementioned processor 1001.
It will be understood by those skilled in the art that the restriction of the not structure paired terminal of terminal structure shown in Fig. 1, can wrap It includes than illustrating more or fewer components, either combines certain components or different components arrangement.
As shown in Figure 1, as may include operating system and process in a kind of memory 1003 of computer storage media Task management program.
In device shown in Fig. 1, processor 1001 can be used for calling the process task pipe stored in memory 1003 Program is managed, and executes following operation:
Engineering project is established according to process template, comprising multistage node in the engineering project, and the multistage node In include procedure-node;
Project data is received, and is appointed according to the procedure-node generation process in the project data and the engineering project Business;
The planned time of the process task is obtained, and according to the planned time of the process task setting multistage section The planned time of point;
The process task provided with planned time is associated with preset person liable, for the person liable to institute Process task is stated to be managed.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
Obtain the hierarchical relationship between multistage node and each node;
Obtain the examination object of the procedure-node;
According to the examination object generation process template of the hierarchical relationship and the procedure-node between each node.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
Obtain the examination object of the procedure-node;
According to the process task of the procedure-node checked and accepted object and generate corresponding types.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
Obtain the acceptance criteria of the procedure-node;
Work is generated according to the examination object of hierarchical relationship, the procedure-node between each node and acceptance criteria Sequence template.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
It receives Engineering Planning Document and generates instruction;
Instruction is generated according to the Engineering Planning Document and generates Engineering Planning Document to be edited, for editing the process The planned time of task.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
The Engineering Planning Document edited is obtained, the Engineering Planning Document edited includes the process task Planned time information;
The planned time of the multistage node is set according to the planned time information of the process task.
Further, processor 1001 can call the process task management program stored in memory 1003, also execute It operates below:
Receive the instruction of uniform delay process task scheduling time;
The number of days of uniform delay is obtained from the instruction of the uniform delay process task scheduling time;
Postpone the planned time of the process task according to the number of days of the uniform delay.
With reference to Fig. 2, first embodiment of the invention provides a kind of method of process task management, the method includes:
Step S10 establishes engineering project according to process template, includes multistage node in the engineering project, and described It include procedure-node in multistage node.
Process type in engineering project is various, and the profession and examination object type involved by process are also very much, process mould The tissue and displaying that a kind of mode of structuring classifies to numerous processes are provided in plate.
By taking the process template of architectural engineering as an example, which includes level-one profession node, two-level node, three-level work Sequence node is father and son's hierarchical relationship between adjacent level, such as the father node that level-one profession node is two-level node, two-level node For the father node of three-level procedure-node.Level-one profession node be electromechanics, civil engineering, finishing, garden build with this five, milestone, wherein in Journey upright stone tablet only has two-level node, does not have three-level procedure-node.The particular content for being included further according to profession based on level-one profession node Carry out thinner classification obtain the two-level node under two-level node, such as milestone node include basis goes into operation, admission card obtains, Engineering reaches presell condition, milestone node 1, milestone node 2 and actual handing over.Include under two-level node is three-level process Node, procedure-node are the minimum construction cell for having in construction work independent construction condition and complete construction object.Such as Two-level node under level-one electromechanical speciality node includes pipeline set aside pre-embedded engineering, dispatch from foreign news agency and high-low pressure power engineering and forceful electric power work Journey, the procedure-node under two-level node heavy current engineering include obtaining dispatch from foreign news agency power supply plan.
Engineering project is established according to above-mentioned operation template, is just contained in entire engineering project in obtained engineering project The engineering duty type to be completed specifically carries out tissue and the exhibition of all engineering duties in a manner of multistage father and son's node Show wherein including procedure-node in multistage node, i.e., have the minimum task unit of independent carry out condition and examination in engineering.
Step S20 receives project data, and is generated according to the procedure-node in the project data and the engineering project Process task.
Project data includes the related data of the scale and specification for the objective for implementation for illustrating engineering project.Such as it builds Project data includes number by stages, building information, gardens information, fire compartment information for including by stages each etc..According to work It is only needed into one comprising the engineering duty type to be completed in entire engineering project in the engineering project that sequence template is established Step according in engineering project procedure-node and engineering project data determine which specific process is completed in engineering project Task.
It illustrates how to be generated according to the procedure-node of architectural engineering data and architectural engineering in the works by taking architectural engineering as an example Process task.For example the project data of certain architectural engineering shows that the engineering included one to three phase, first stage of the project includes three buildings, often Building includes 32 floor.Include secondary body work in the engineering project established according to process template, under level-one Civil Specialities node Cheng Jiedian is total to three process under the secondary body engineering node comprising A, B, the C checked and accepted by layer.According to a phase in the project data Data, the process task of the first stage of the project ultimately generated includes:32 A processes in total of 32 floor of one phase the first building are appointed Business, 32 B processes tasks, 32 C process tasks;32 A processes tasks, the 32 B works in total of 32 floor in one building of phase second Sequence task, 32 C process tasks;32 A processes tasks in total of 32 floor in one phase third building, 32 B processes tasks, 32 C process tasks.The second phase of the engineering generates with rule of the process task of three phases also as.
Step S30 obtains the planned time of the process task, and institute is arranged according to the planned time of the process task State the planned time of multistage node.
In the present embodiment, the various functions of process task management are realized in a complete software systems, including aforementioned Engineering project is established according to process template, receives project data and according to the work in the project data and the engineering project Sequence node generation process task.
There are many modes for obtaining the process task scheduling time for software systems;Setting interface can be provided, used by obtaining The setting process task scheduling time command that family is sent obtains the process task scheduling time;It can also will be established according to process template Preliminary project plan preserve and at editable file and export, when Engineering Planning Document editor's completion plan after, then will compile The Engineering Planning Document input system collected is to obtain the process task scheduling time.
It is that engineering project is more since process task is the construction task unit that can not continue segmentation minimum in engineering project The node of lowest hierarchical level in grade node, under the direct upper layer node for obtaining process task when the plan of each process task Between after, the planned time of the direct upper layer node is the union of section of each process task time, more than the direct upper layer node The planned time of node is calculated with identical rule.
The process task provided with planned time is associated with, for the responsibility by step S40 with preset person liable Personnel are managed the process task.
In the whole life cycle existing for engineering project, process task experience generates, implements, checks and accepts and terminates four ranks Section, corresponding related responsibility personnel are administrative staff, construction personnel, inspector and administrative staff respectively.Process task is by pipe After reason personnel generate according to above-mentioned steps, be assigned to construction personnel, inspector and other need to be concerned about the process task The administrative staff of progress.Construction personnel understands the specific location of construction, condition by the relevant information for the process task being assigned And task definition, set process task status to when completing process task " construction is completed " state so that inspector and When be notified and carry out an acceptance inspection to the process task;Inspector is after the examination for completing the process task by process task status It is set as " check and accept and complete " state, so that administrative staff are notified and set " " end " the process task status in time State.
In the present embodiment, by formulating the process task scheduling for including multiple hierarchy nodes, setting based on process template Planned time in process task scheduling is based on complete process task scheduling generation process task, and by process task assignment Related responsibility personnel are given, the management method that a kind of structuring degree is high and feedback is closed is provided and assists construction responsible person's management The process task at project construction scene, to ensure the smooth development of project under construction and orderly carry out.
Further, with reference to Fig. 3, second embodiment of the invention provides a kind of process task management based on first embodiment Method, the present embodiment include before step S10:
Step S50 obtains the hierarchical relationship between multistage node and each node.
For engineering, the need that all process steps classification of task hierarchical is shown could be met by needing multistage node is arranged It asks.Such as the setting of level-one profession node, two-level node and three-level procedure-node can meet the classification of most of architectural engineering Layering manifestation demand.It is arranged if some engineerings also include the node of more father and son's levels under professional node, needs to set The node of more levels is set, needs to obtain the hierarchical relationship comprising between all hierarchy nodes and node at different levels at this time.
Step S60 obtains the examination object of the procedure-node.
According to the examination object type of the setting instruction setting process node of user.It is common such as in building engineering field Examination object type include by stages, Lou Dong, anti-windburn area and garden zoning etc..Interface, which can also be provided, allows user according to project The acceptance criteria of codes and standards setting process node.
Further, it is also possible to according to the demand of project management, provide interface allow user setting plan node, vivid node and its The distribution of weight, the setting of these nodes will directly affect the statistics of vivid progress report and plan image;This can be arranged respectively The control node of process cannot be deleted as the node of a pressure management and control for Project Manager.
Step S70 generates work according to the examination object of hierarchical relationship and the procedure-node between each node Sequence template.
The profession and process for including due to different types of engineering are all distinct, can be different types of engineering subcontract Different process templates is established for reference.Even same type of engineering, not according to the scene condition of engineering concrete application Together, it or due to occurring newly-increased process based on the new market demand, is required for based on the fixed process template provided to it In nodes at different levels carry out necessary adjustment.A node pool can be established, including first nodes, two-level node, three-level process The nodes at different levels such as node and examination item.According to the variation of engineer application scene and the market demand, constantly to the node in node pool Increased and is deleted.After tentatively establishing engineering project according to fixed process template, based on the node pool to engineering Node in drawing is adjusted.
After establishing preliminary engineering project by reference above-mentioned operation template, the examination object of procedure-node is obtained, And according to the process task of procedure-node checked and accepted object and generate corresponding types.It is introduced according to procedure-node by taking architectural engineering as an example Check and accept object generate corresponding types process task detailed process.
1) procedure-node that object is checked and accepted with Lou Dongwei obtains the building plan of current process, according to building building in the works Number generate the process task of equal number of building type;
2) it is the procedure-node for checking and accepting object with floor, the building plan of current process is obtained, according to building building in the works Number, the floor number in every building, generate the process task of the identical floor type of sum;
3) it is the procedure-node for checking and accepting object with room, the building plan of current process is obtained, according to building building in the works Number, the room number in every building, generate the process task of the identical room type of sum;
4) it is the procedure-node for checking and accepting object with facade, the building plan of current process is obtained, according to building building in the works Number, the number of every building facade, generate the process task of the identical facade type of sum;
5) with by stages, fire compartment, garden zoning or pile foundation number be to check and accept the procedure-node of object, obtain current process By stages or subregion plan, according to by stages or the plan of subregion, generating equal number of type by stages, divisional type or stake in the works The process task of base type.
In the present embodiment, hierarchical relationship between multistage node and each node is obtained, procedure-node is tested It receives the information such as object and establishes process template according to these information, provide the high process template of structuring degree for engineering The formulation drawn improves the efficiency for formulating operationpiston.
Further, with reference to Fig. 4, third embodiment of the invention is based on first or second embodiments and provides a kind of process task The method of management, the present embodiment include after step S20:
Step S80 receives Engineering Planning Document and generates instruction.
Step S90 generates instruction according to the Engineering Planning Document and generates Engineering Planning Document to be edited, for editor The planned time of the process task.
After establishing preliminary engineering project according to process template, it is also necessary to obtain the plan of process task in engineering project Time can just ultimately generate the process task that can assign implementation and tracking.Due to some engineering projects especially construction project scale It is very big, cause the number of the process task in engineering project very huge, each process is appointed manually if relying only on user The planned time of business is configured, and workload is very big and error-prone.It, can be with so system is needed to provide a kind of interface Engineering project is exported in a manner of file, is realized to engineering by third-party software program or software tool by user The planned time of process task carries out the setting of batch in drawing.Such as it can be by Engineering Planning Document with the format of EXCEL file Output, user can use the process task time in the function batch editorial project project documentation that EXCEL softwares carry.
Simultaneity factor provides interface, so that user imports edited Engineering Planning Document.System imports text by user The operation of part obtains the Engineering Planning Document edited, when the Engineering Planning Document edited includes the plan of the process task Between information, the planned time of multistage node is arranged according to the planned time information of process task system.
With the progress of engineering, it is often necessary to be adjusted to the planned time of the process portion task in engineering project. User can select directly to change in turn manually in systems according to the size of process task number scale to be adjusted, or Selection output Engineering Planning Document is simultaneously edited, edits the mode imported again after the completion.Process for having generated business datum The planned time of task is then restricted to change.
In order to simplify operation, when to carry out uniform delay to the planned time of process task, system passes through user interface The instruction for receiving the uniform delay process task scheduling time obtains unified from the instruction of uniform delay process task scheduling time The number of days of delay, and postpone according to the number of days of uniform delay the planned time of the process task.
In the present embodiment, engineering project text to be edited is generated by generating instruction according to the Engineering Planning Document Part, for editing the planned time of the process task, the mode for compatibility a variety of setting process task scheduling times provides Unified interface keeps the setting of engineering project time more flexible efficiently.
The present invention also provides a kind of process task management device, which includes:It memory, processor and is stored in described On memory and the process task management program that can run on the processor, the process task management program is by the place Manage the step of realizing the process task management method when device executes.
In addition, the embodiment of the present invention also proposes a kind of computer readable storage medium, the computer readable storage medium On be stored with process task management program, the process task is realized when the process task management program is executed by processor The step of management method.
It should be noted that herein, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that process, method, article or system including a series of elements include not only those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or system institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including this There is also other identical elements in the process of element, method, article or system.
The embodiments of the present invention are for illustration only, can not represent the quality of embodiment.
Through the above description of the embodiments, those skilled in the art can be understood that above-described embodiment side Method can add the mode of required general hardware platform to realize by software, naturally it is also possible to by hardware, but in many cases The former is more preferably embodiment.Based on this understanding, technical scheme of the present invention substantially in other words does the prior art Going out the part of contribution can be expressed in the form of software products, which is stored in one as described above In storage medium (such as ROM/RAM, magnetic disc, CD), including some instructions use so that a station terminal equipment (can be mobile phone, Computer, server, air conditioner or network equipment etc.) execute method described in each embodiment of the present invention.
It these are only the preferred embodiment of the present invention, be not intended to limit the scope of the invention, it is every to utilize this hair Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills Art field, is included within the scope of the present invention.

Claims (9)

1. a kind of management method of process task, which is characterized in that the management method of the process task includes the following steps:
Engineering project is established according to process template, includes multistage node in the engineering project, and wrapped in the multistage node Containing procedure-node;
Project data is received, and according to the procedure-node generation process task in the project data and the engineering project;
The planned time of the process task is obtained, and the multistage node is arranged according to the planned time of the process task Planned time;
The process task provided with planned time is associated with preset person liable, for the person liable to the work Sequence task is managed.
2. the management method of process task as described in claim 1, which is characterized in that described according to process template and engineering number Include according to before establishing engineering project step:
Obtain the hierarchical relationship between multistage node and each node;
Obtain the examination object of the procedure-node;
According to the examination object generation process template of the hierarchical relationship and the procedure-node between each node.
3. the management method of process task as claimed in claim 2, which is characterized in that the reception project data, and according to Procedure-node generation process task step in the project data and the engineering project includes:
Obtain the examination object of the procedure-node;
According to the process task of the procedure-node checked and accepted object and generate corresponding types.
4. the management method of process task as claimed in claim 2, which is characterized in that described to obtain testing for the procedure-node Receiving object step includes later:
Obtain the acceptance criteria of the procedure-node;
According to the examination object and acceptance criteria generation process mould of hierarchical relationship, the procedure-node between each node Plate.
5. the management method of process task as described in claim 1, which is characterized in that the reception project data, and according to Include after procedure-node generation process task step in the project data and the engineering project:
It receives Engineering Planning Document and generates instruction;
Instruction is generated according to the Engineering Planning Document and generates Engineering Planning Document to be edited, for editing the process task Planned time.
6. the management method of process task as claimed in claim 5, which is characterized in that the meter for obtaining the process task It draws the time, and the planned time step that the multistage node is arranged according to the planned time of the process task includes:
The Engineering Planning Document edited is obtained, the Engineering Planning Document edited includes the meter of the process task Draw temporal information;
The planned time of the multistage node is set according to the planned time information of the process task.
7. such as the management method of claim 1 to 6 any one of them process task, which is characterized in that described to obtain the work The planned time of sequence task, and according to the planned time of the process task be arranged the multistage node planned time step it After include:
Receive the instruction of uniform delay process task scheduling time;
The number of days of uniform delay is obtained from the instruction of the uniform delay process task scheduling time;
Postpone the planned time of the process task according to the number of days of the uniform delay.
8. a kind of managing device of process task, which is characterized in that described device includes:Memory, processor and it is stored in institute State the management program for the process task that can be run on memory and on the processor, the management program quilt of the process task The step of management method of the process task as described in any one of claim 1 to 7 is realized when the processor executes.
9. a kind of computer readable storage medium, which is characterized in that be stored with process on the computer readable storage medium and appoint It is realized such as any one of claim 1 to 7 institute when the management program of the management program of business, the process task is executed by processor The step of process task management method stated.
CN201810323817.0A 2018-04-10 2018-04-10 Process task management method, device and computer readable storage medium Pending CN108520361A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810323817.0A CN108520361A (en) 2018-04-10 2018-04-10 Process task management method, device and computer readable storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810323817.0A CN108520361A (en) 2018-04-10 2018-04-10 Process task management method, device and computer readable storage medium

Publications (1)

Publication Number Publication Date
CN108520361A true CN108520361A (en) 2018-09-11

Family

ID=63431113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810323817.0A Pending CN108520361A (en) 2018-04-10 2018-04-10 Process task management method, device and computer readable storage medium

Country Status (1)

Country Link
CN (1) CN108520361A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109345103A (en) * 2018-09-25 2019-02-15 北京地厚云图科技有限公司 Process receipt control method and storage medium
CN109615252A (en) * 2018-12-14 2019-04-12 万翼科技有限公司 The monitoring method and device of project
CN109858870A (en) * 2018-12-24 2019-06-07 万翼科技有限公司 A kind of event management method, system and a kind of storage device
CN109886576A (en) * 2019-02-20 2019-06-14 司空科技股份有限公司 Task management method, device and storage medium are delivered in digitlization
CN111242457A (en) * 2020-01-07 2020-06-05 中国建筑第八工程局有限公司 Construction technology management system and method
CN111340320A (en) * 2018-12-18 2020-06-26 西安海平方网络科技有限公司 Work plan determination method and device, computer equipment and storage medium
CN111626531A (en) * 2019-02-28 2020-09-04 贵阳海信网络科技有限公司 Risk control method, device, system and storage medium
CN112884455A (en) * 2021-03-26 2021-06-01 中车青岛四方机车车辆股份有限公司 Task plan processing system, method and device
CN113344477A (en) * 2021-08-05 2021-09-03 捷尔杰(天津)设备有限公司 Task synchronization control method and device, electronic equipment and computer storage medium
CN113807730A (en) * 2021-09-28 2021-12-17 重庆允成互联网科技有限公司 Work order generation method, system, equipment and storage medium based on discrete management

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101266669A (en) * 2008-05-06 2008-09-17 广州市中联创通电脑有限公司 Project process workflow based on plan template and its implementation method
CN102096849A (en) * 2009-12-15 2011-06-15 苏州铭星软件科技有限公司 Flow management design method based on network program
CN107680003A (en) * 2016-08-01 2018-02-09 北京地厚云图科技有限公司 The node tree generation method and device of project supervision task
CN107688922A (en) * 2016-08-04 2018-02-13 北京地厚云图科技有限公司 Project supervision task processing method and device based on node tree
CN107784447A (en) * 2017-11-06 2018-03-09 国家电网公司 A kind of overall process prison based on triple early warning makes closed loop management system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101266669A (en) * 2008-05-06 2008-09-17 广州市中联创通电脑有限公司 Project process workflow based on plan template and its implementation method
CN102096849A (en) * 2009-12-15 2011-06-15 苏州铭星软件科技有限公司 Flow management design method based on network program
CN107680003A (en) * 2016-08-01 2018-02-09 北京地厚云图科技有限公司 The node tree generation method and device of project supervision task
CN107688922A (en) * 2016-08-04 2018-02-13 北京地厚云图科技有限公司 Project supervision task processing method and device based on node tree
CN107784447A (en) * 2017-11-06 2018-03-09 国家电网公司 A kind of overall process prison based on triple early warning makes closed loop management system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
乔非编著: "《钢铁企业能源管理模型与系统节能技术》", 31 December 2016, 同济大学出版社 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109345103A (en) * 2018-09-25 2019-02-15 北京地厚云图科技有限公司 Process receipt control method and storage medium
CN109615252A (en) * 2018-12-14 2019-04-12 万翼科技有限公司 The monitoring method and device of project
CN111340320B (en) * 2018-12-18 2023-09-22 西安海平方网络科技有限公司 Work plan determining method, apparatus, computer device, and storage medium
CN111340320A (en) * 2018-12-18 2020-06-26 西安海平方网络科技有限公司 Work plan determination method and device, computer equipment and storage medium
CN109858870A (en) * 2018-12-24 2019-06-07 万翼科技有限公司 A kind of event management method, system and a kind of storage device
CN109886576B (en) * 2019-02-20 2023-04-07 司空定制家居科技有限公司 Digital delivery task management method, device and storage medium
CN109886576A (en) * 2019-02-20 2019-06-14 司空科技股份有限公司 Task management method, device and storage medium are delivered in digitlization
CN111626531A (en) * 2019-02-28 2020-09-04 贵阳海信网络科技有限公司 Risk control method, device, system and storage medium
CN111626531B (en) * 2019-02-28 2023-09-05 贵阳海信网络科技有限公司 Risk control method, apparatus, system and storage medium
CN111242457A (en) * 2020-01-07 2020-06-05 中国建筑第八工程局有限公司 Construction technology management system and method
CN112884455A (en) * 2021-03-26 2021-06-01 中车青岛四方机车车辆股份有限公司 Task plan processing system, method and device
CN113344477A (en) * 2021-08-05 2021-09-03 捷尔杰(天津)设备有限公司 Task synchronization control method and device, electronic equipment and computer storage medium
CN113807730A (en) * 2021-09-28 2021-12-17 重庆允成互联网科技有限公司 Work order generation method, system, equipment and storage medium based on discrete management

Similar Documents

Publication Publication Date Title
CN108520361A (en) Process task management method, device and computer readable storage medium
KR102184182B1 (en) Project/Task Intelligent Goal Management Method and Platform based on Super Tree
Zhang et al. Process-oriented framework to improve modular and offsite construction manufacturing performance
Son et al. Simulation-based shop floor control: formal model, model generation and control interface
KR101860276B1 (en) 3D piping design support program device applied to smart plant collaboration system
Liu et al. Restoration of power distribution systems with multiple data centers as critical loads
CN102096849A (en) Flow management design method based on network program
Ayinla et al. Process waste analysis for offsite production methods for house construction: A case study of factory wall panel production
Laipple et al. Generic data model for semiconductor manufacturing supply chains
CN107169180A (en) A kind of power grid regulation model center system of two-stage deployment
CN110401556A (en) A kind of method and apparatus of IDC computer room cable visualization Automatic dispatching
Ham et al. BIM based construction project case analysis for facility life cycle management from the perspective of the client
CN112434978A (en) Efficient office room allocation method and system
Hobbs et al. Harnessing the power of virtual reality–the potential for VR as a virtual integrated environment for project development in construction
Gupta et al. Levelling resources of a construction project by various softwarebasedleveling tool
Sanvido Towards a process based information architecture for construction
Hazeyama et al. Workload management facilities for software project management
Zhang et al. 4D visualization of construction site management
CN115965207B (en) Resource allocation method, system and storage medium
Wang et al. CIM modeling for market management systems
JP3695410B2 (en) Production technology management method and apparatus therefor
Sweat et al. Multi-factory capacity planning in semiconductor assembly and test manufacturing with multiple-chip products
KR100217234B1 (en) Working management method using cad
KR20240016734A (en) System and method for managing modular construction project schedule
Dawood et al. The virtual construction site (VIRCON): a decision support system for construction planning

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180911