CN108518204A - A kind of gap gas lift liquid drainage gas production control method and system - Google Patents

A kind of gap gas lift liquid drainage gas production control method and system Download PDF

Info

Publication number
CN108518204A
CN108518204A CN201810230249.XA CN201810230249A CN108518204A CN 108518204 A CN108518204 A CN 108518204A CN 201810230249 A CN201810230249 A CN 201810230249A CN 108518204 A CN108518204 A CN 108518204A
Authority
CN
China
Prior art keywords
gas
pressure
liquid drainage
production
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810230249.XA
Other languages
Chinese (zh)
Other versions
CN108518204B (en
Inventor
王仪
鲜乾坤
朱文忠
薛加勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan University of Science and Engineering
Original Assignee
Sichuan University of Science and Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan University of Science and Engineering filed Critical Sichuan University of Science and Engineering
Priority to CN201810230249.XA priority Critical patent/CN108518204B/en
Publication of CN108518204A publication Critical patent/CN108518204A/en
Application granted granted Critical
Publication of CN108518204B publication Critical patent/CN108518204B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/12Methods or apparatus for controlling the flow of the obtained fluid to or in wells
    • E21B43/121Lifting well fluids
    • E21B43/122Gas lift
    • E21B43/123Gas lift valves
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/06Measuring temperature or pressure

Abstract

The invention discloses a kind of gap gas lift liquid drainage gas production control method and systems, including:Based on oil pressure, the casing pressure variation characteristic during Wellbore of Gas Wells hydrops, using acquire in real time oil pressure, casing pressure data, automatically determine the intermittent gaslift liquid discharging gas producing gas injection opening time;Oil pressure, the casing pressure variation characteristic of well head are discharged to by gaslift based on Wellbore of Gas Wells hydrops, using acquire in real time oil pressure, casing pressure data, automatically determine intermittent gaslift liquid discharging gas producing gas injection and shut down the time;It is empirically determined existing insufficient by gas recovery teacher to solve existing gaslift intermittent time and gas injection time, realize intermittent gaslift liquid discharging gas producing manipulation automation, intelligence, it realizes that intermittent gaslift liquid discharging gas producing scene is unattended, effectively improves intermittent gaslift liquid discharging gas producing efficiency and benefit.

Description

A kind of gap gas lift liquid drainage gas production control method and system
Technical field
The present invention relates to exploitation of oil-gas field automatic fields, and in particular, to a kind of gap gas lift liquid drainage gas production controlling party Method and system.
Background technology
Intermittent gaslift is a kind of major way of low yield natural gas well liquid discharging gas producing, injects high pressure from annular space by intermittence Gas enters oil pipe by gas lift valve or oil pipe foot, thus by pit shaft institute hydrops body (generally condensate or water flooding) It is taken out of from oil pipe, and then restores gas well deliverability.Gaslift intermittent time and gas injection time are generally rule of thumb true by gas recovery teacher Fixed, intermittent gaslift manipulation is manually completed by gas production operative employee.
Invention content
The present invention provides a kind of gap gas lift liquid drainage gas production control method and systems, when solving existing gaslift interval Between and gas injection time by gas recovery teacher it is empirically determined caused by it is insufficient, realize that the manipulation of intermittent gaslift liquid discharging gas producing is automatic Change, is intelligent, realizing that intermittent gaslift liquid discharging gas producing scene is unattended, effectively improve intermittent gaslift liquid discharging gas producing efficiency and effect Benefit.
Present invention is primarily based on tubing pressure during Wellbore of Gas Wells hydrops and gas lift liquid drainage and casing pressure variation characteristics Rule, it is proposed that a kind of intermittent gaslift liquid discharging gas producing intelligent optimization algorithm, and then devise a set of intermittent gaslift liquid discharging gas producing intelligence It can control device system.With the application of the invention, intermittent gaslift liquid discharging gas producing manipulation automation, intelligent, realization interval may be implemented Gas lift liquid drainage gas production scene is unattended, effectively improves intermittent gaslift liquid discharging gas producing efficiency and benefit.
When gas well gas production is less than entrained liquid threshold, liquid will slip aggregation from air-flow, and gradually be converged to shaft bottom Poly-, the averag density of oily tube fluid will be stepped up, and when shaft bottom, hydrops is gathered to a certain extent, hydrops will to annular carrying, Oil jacket annulus liquid level is caused to increase.Three ranks generally are divided by hydrops process to the influence degree of gas well yield according to wellbore effusion Section:Slight hydrops, moderate hydrops, severe hydrops.In the slight hydrops stage, refer to wellbore effusion and occur over just in oil pipe, there are no Shaft bottom forms a large amount of aggregations, and there are no hydrops for oil jacket annular space, at this point, gas well yield is barely affected, shaft bottom production stream pressure dimension It is fixed to keep steady, and casing pressure maintains to stablize, and oil pressure gradually declines, and oil jacket pressure difference gradually increases;Moderate hydrops stage, wellbore effusion have been opened Beginning largely assembles in shaft bottom, and oil jacket annular space gradually begins with hydrops, but without stable liquid level, at this point, gas well yield starts Decline, production stream pressure in shaft bottom is begun to decline, and casing pressure gradually declines with oil pressure, and oil jacket pressure difference is basicly stable certain fluctuation;Severe Hydrops stage, oil jacket annulus liquid level rise, and yield, which declines, to be accelerated, and tubing pressure, set pressure pressure decline and accelerate, and finally result in gas well It stops production.Therefore, gas lift liquid drainage Best Times in gap are preferable in slight hydrops later stage and moderate hydrops early stage, on the one hand, can To prevent wellbore effusion from influencing gas well yield;On the other hand, gas lift liquid drainage efficiency can be improved.
Gas lift liquid drainage refers to by injecting high pressure gas to annular space, enters oil pipe by oil pipe foot or gas lift valve, pass through raising Oil pipe interior air-flow speed takes the liquid in pit shaft to ground out of, meanwhile, the higher well section of liquid holdup on the spot can also be reduced Liquid holdup, and then reduce fluid column static pressure.During gas lift liquid drainage, as wellbore effusion is gradually discharged to ground, oil pipe Interior average fluid density will gradually reduce, according to U-tube principle, in the case where gas injection pressure remains unchanged, tubing pressure It will be stepped up;After wellbore effusion is completely exhausted out pit shaft, since pit shaft is without hydrops, the average fluid density base in oil pipe Originally it remains unchanged, according to U-tube principle, in the case where gas injection pressure keeps stablizing, tubing pressure will keep stablizing.Therefore, Gas lift liquid drainage dwell time can be to avoid invalid gas injection when should be wellbore effusion and being completely exhausted out pit shaft.
1, the required real-time data collection of intermittent gaslift liquid discharging gas producing intelligent control includes mainly:Well mouth oil pipe pressure (abbreviation oil pressure), oil pipe temperature, casing pressure (abbreviation casing pressure), bushing temperature, oil pipe produced gas Inlet pressure (abbreviation back pressure), Casing injection gas comes pressure (abbreviation gas injection pipeline pressure), pneumatic diaphragm control valve open state detection (control injection high pressure gas Body switchs).Wherein oil pressure, casing pressure, pneumatic diaphragm control valve open state are automatically controlled for real-time intelligent, and other data are used for Gas recovery well production monitoring.The pneumatic diaphragm control valve open state testing requirements response time is not less than 1 millisecond, other parameters detection Time interval is not less than 5 seconds.
2, intermittent gaslift liquid discharging gas producing gas injection opening time intelligent optimization algorithm, such as Fig. 1.In the gas injection down periods, gas well Blowing band liquid produces, since gas well gas production is less than pit shaft entrained liquid threshold, wellbore effusion process:(1) the oil pipe hydrops stage, Wellbore effusion is constantly assembled in oil pipe, at this time production stream pressure, casing pressure it is basicly stable, gas well yield by keep stablize, oil pressure with It is more and more and be gradually reduced hydrops in oil pipe, the pressure difference of casing pressure and oil pressure is gradually increased.(2) the shaft bottom hydrops stage, with The continuous intensification of wellbore effusion, wellbore bottom will gradually form stable hydrops, at this point, production stream pressure will be stepped up, casing pressure by Step declines, and gas well yield is begun to decline, and oil pressure continues to decline, the pressure difference kept stable of casing pressure and oil pressure.(3) annular space hydrops In the stage, with the further intensification of wellbore effusion, shaft bottom is stablized hydrops liquid level and is constantly risen, and pin top oil jacket ring is stepped into Sky, this stage gas well yield is by rapid decrease or even stop-spraying.Casing pressure, oil pressure gradually decline, and the pressure difference of casing pressure and oil pressure is protected substantially It is fixed to keep steady.The best time that intermittent gaslift liquid discharging gas producing gas injection is opened stablizes the first of hydrops between oil pipe hydrops latter stage to shaft bottom Phase.Based on the oil pressure during Wellbore of Gas Wells hydrops, casing pressure changing rule feature, using acquire in real time oil pressure, casing pressure data, The intermittent gaslift liquid discharging gas producing gas injection opening time is automatically determined by the intelligent optimization algorithm of intelligent controller.Specific algorithm is such as Under:
1) calibration is given with production production Q in gas wellgUnder the conditions of, the reasonable pressure value P of casing pressure when no shaft bottom hydropsc.Calibration side There are two types of methods, and (1) one is, after gas lift liquid drainage between the blowing time started section average casing pressure value, the time started, segment length generally took 0.5 ~1 hour.(2) it second is that, is calculated by Wellbore Flow simulation, rational proration QgWhen correspond to production stream pressure PwfSubtract casing sky Air column pressure Pcgs
2) there is the permitted maximum casing pressure drop value Δ P of certain hydrops in calibration shaft bottomzcmax, scaling method is:(1) first First, calibration allows minimum gas production Qgmin, generally take with production gas production Qg70~90%,.(2) then, pass through thermally coupled flow The corresponding minimum gas production Q of permission is calculated in IPR modelgminCorresponding production stream Pwfmax.(3) finally, maximum set drop of pressure It is worth Δ PzcmaxEqual to casing hydrops section head of liquid PclsSubtract (Pwfmax-Pwf)。
3) the permitted maximum value Δ P of oil jacket pressure difference during the production of calibration blowing hydropszctmax, embody gap gaslift Liquid discharging gas producing hydrops severity allowed, oil jacket pressure difference is bigger, and hydrops is more serious in oil pipe.
4) casing pressure with oil pressure difference DELTA P of calibration blowing hydrops production phasezct(t) variation tendency.In oil pipe hydrops rank Section, casing pressure are gradually increased with the variation of oil pressure difference, and after initially forming stable hydrops to shaft bottom, casing pressure tends to be steady with oil pressure difference It is fixed.For the data monitored in real time with oil pressure due to casing pressure due to various because that will cause to fluctuate, pressure difference also will be fluctuation.In order to disappear Except the tendency judgement error that the numerical fluctuations of real time monitoring are brought, the difference DELTA P of obtained casing pressure and oil pressure will be detected in real timezct (t) time series rolling average processing is carried out.The sampling period of Real-time Monitoring Data is set as T, n times of T is moved for unit Dynamic average computation, n can distinguish 5 or 10 or 20.Tendency judgement is carried out by linear fit, if slope KznIt is increasing, is showing to change Comparatively fast;Slope tends to 0, shows to tend towards stability.5) the calibration blowing hydrops production phase continues minimum Tzmin, maximum time Tzmax.Root T is determined according to the comprehensive analysis to gas well items Testing indexzmin、Tzmax
6) from being sprayed onto certainly, the judgement of gas injection opening time is accurate to survey intermittent gaslift liquid discharging gas producing:Terminated as starting point with last time gaslift, Current time casing pressure drop value Δ P is calculated separately based on real-time collected oil pressure, casing pressure valuezc(t);Oil jacket pressure difference Δ Pzct (t);Time series oil jacket pressure difference rolling average changes slope kzn(t);Blowing duration Tz(t);Following three criterions are any When one establishment, then start gas lift liquid drainage automatically:
(1) if T (t)>Tzmax, show that the blowing hydrops production time is more than and demarcate allowed maximum duration, need to open at this time Dynamic gas lift liquid drainage;
(2) if Δ Pzc(t)>ΔPzcmax, and Tz(t)>Tzmin, show that blowing hydrops causes oil jacket pressure difference to be more than calibration and permits Perhaps maximum value then needs to start gas lift liquid drainage;
(3) if kzn(t)>kzmax, and Tz(t)>Tzmin, oil jacket pressure difference change rate be significantly greater than demarcate permitted maximum value, It then needs to start gas lift liquid drainage;
3, time intelligence optimization algorithm, such as Fig. 2 are shut down in the gas injection of intermittent gaslift liquid discharging gas producing.Gas lift liquid drainage process, first, note Enter high pressure gas to replace the hydrops of oil jacket annular space into oil pipe by pin (or gas lift valve), oil jacket pressure difference gradually increases at this time Greatly;Then, the hydrops in oil pipe is replaced to well head and is discharged by injection high pressure gas, and oil jacket pressure difference keeps stablizing at this time;After again, with It the liquid in oil pipe and pit shaft is gradually discharged, oily liquid in pipe is fewer and fewer, and oil jacket pressure difference gradually decreases;Finally, with hydrops All discharge pit shafts, oil jacket pressure difference keep stablizing.The oil pressure of well head is discharged to by gaslift based on Wellbore of Gas Wells hydrops, casing pressure changes Law characteristic, using acquire in real time oil pressure, casing pressure data, by the intelligent optimization algorithm of intelligent controller automatically determine interval The time is shut down in gas lift liquid drainage gas production gas injection.Specific algorithm is as follows:
1) calibration gas lift liquid drainage enumerates the minimum oil jacket pressure difference Δ P of wellbore effusion completelyglctmin.The value can pass through gas Wellbore Flow simulation calculating is lifted to acquire, according to U-tube principle, in the case where pit shaft does not have hydrops, oil jacket pressure difference Δ Pctmin Equal to the air column pressure P in annular spacecgs+ annular air injection frictional resistance Pcfg+ pin gas lift valve (if having) chock pressure difference PctpGas in+oil pipe Body frictional resistance PtgsAir column pressure P in oil pipetfg
2) casing pressure and oil pressure difference DELTA P during calibration gas lift liquid drainageglct(t) variation tendency.In order to eliminate real time monitoring The tendency judgement error that numerical fluctuations are brought will detect the difference DELTA P of obtained casing pressure and oil pressure in real timeglct(t) time is carried out Sequence rolling average is handled.The sampling period of Real-time Monitoring Data is set as T, n times of T carries out rolling average calculating for unit, n3Can value be generally 5,10 or 20.Tendency judgement, k are carried out by linear fitglnSlope is to bear then to be judged to reducing;If kgln It is approximately 0, then is judged to stablizing.
3) calibration gas lift liquid drainage gas production minimum, maximum gas injection duration.According to the synthesis to gas well items Testing index Analysis determines gas lift liquid drainage gas production minimum, maximum allowable gas injection duration Tglmin、Tglmax
4) judgement of intermittent gaslift liquid discharging gas producing gas injection duration is accurate surveys:Using this gaslift opening point as starting point, based on real When collected oil pressure, casing pressure value calculate separately current time oil jacket pressure difference Δ Pglct(t);Time series oil jacket pressure difference moves Mean change slope kgln(t);Gaslift duration Tgl(t);Any one establishment of following three criterions, then need to be automatically closed Gas lift liquid drainage, gas well are switched to the blowing production phase:
(1) if, Tgl(t)>Tglmax, the gas lift liquid drainage time, which is more than, demarcates permitted maximum time, shows that gas lift liquid drainage is complete At, need at this time close gas lift liquid drainage, automatically switch to the blowing production phase;
(2) if, Pglct(t)<ΔPglctmin, and Tgl(t)>Tglmin, oil jacket pressure difference, which drops to, demarcates institute's permissible value, shows gaslift Drain is completed, and is needed to close gas lift liquid drainage at this time, is automatically switched to the blowing production phase.
(3) if, kgln(t)<kglmin, and Tgl(t)>Tglmin, oil jacket pressure difference change rate tends to be steady, and shows that gas lift liquid drainage is complete At, need at this time close gas lift liquid drainage, automatically switch to the blowing production phase;
4, gas lift liquid drainage intelligence control system in gap forms, such as Fig. 3, (1) real-time detection senses unit:By tubing pressure, Casing pressure sensor is constituted;(2) automatic execution unit:It is made of controllable diaphragm control valve and its attachment, it is general to choose pneumatically Diaphragm control valve, control air source directly take gas from proof wellhead oil casing annular space by acquiring connector, pass through pressure reducing valve, filter, electricity After magnet valve open and close power gas is provided to pneumatic diaphragm control valve.Intelligent controller to solenoid valve by exporting control signal.(3) Intelligent controller, is the core cell of gap gas lift liquid drainage gas production, and inside has real-time data collection interface, automatic executive device to connect Mouthful, live control panel interface, data remote interface, intelligent optimization calculator and the resistance of other attachmentes at.(4) live operation control surface Plate, the system of offer are shown and manipulation data input;(5) power-supply system, be intelligent controller, detecting sensor, automatic executive device, Live control panel provides power supply.
One or more technical solution provided by the present application, has at least the following technical effects or advantages:
Realize intermittent gaslift liquid discharging gas producing manipulation automation, intelligent, the unmanned value in realization intermittent gaslift liquid discharging gas producing scene It keeps, effectively improves intermittent gaslift liquid discharging gas producing efficiency and benefit.
Description of the drawings
Attached drawing described herein is used for providing further understanding the embodiment of the present invention, constitutes one of the application Point, do not constitute the restriction to the embodiment of the present invention;
Fig. 1 is that intermittent gaslift liquid discharging gas producing well blowing hydrops production phase intelligent control operation principle is illustrated in the application Figure;
Fig. 2 is that intermittent gaslift liquid discharging gas producing well gas lift liquid drainage production phase intelligent control operation principle is illustrated in the application Figure;
Fig. 3 is intermittent gaslift liquid discharging gas producing well Structure of intelligent control system schematic diagram in the application.
Specific implementation mode
Intermittent gaslift is a kind of major way of low yield natural gas well liquid discharging gas producing, injects high pressure from annular space by intermittence Gas enters oil pipe by gas lift valve or oil pipe foot, thus by pit shaft institute hydrops body (generally condensate or water flooding) It is taken out of from oil pipe, and then restores gas well deliverability.Current gaslift intermittent time and gas injection time are generally by gas recovery teacher according to warp Determination is tested, intermittent gaslift manipulation is manually completed by gas production operative employee.Present invention is primarily based on Wellbore of Gas Wells hydrops and gas lift liquid drainages Tubing pressure and casing pressure variation characteristic rule in the process, it is proposed that a kind of intermittent gaslift liquid discharging gas producing intelligent optimization method, And then devise a set of intermittent gaslift liquid discharging gas producing intelligent control device system.With the application of the invention, intermittent gaslift row may be implemented Liquid gas production manipulation automation, intelligence, realize that intermittent gaslift liquid discharging gas producing scene is unattended, effectively improve intermittent gaslift drain Gas production efficiency and benefit.
To better understand the objects, features and advantages of the present invention, below in conjunction with the accompanying drawings and specific real Mode is applied the present invention is further described in detail.It should be noted that in the case where not conflicting mutually, the application's Feature in embodiment and embodiment can be combined with each other.
Many details are elaborated in the following description to facilitate a thorough understanding of the present invention, still, the present invention may be used also Implemented with being different from the other modes being described herein in range using other, therefore, protection scope of the present invention is not by under The limitation of specific embodiment disclosed in face.
The present invention is based on collect oil pressure, casing pressure data in real time, it is proposed that a set of intelligent decision intermittent gaslift liquid discharging gas producing Hydrops degree algorithm during well blowing, which is embedded into intelligent controller, you can realizes intermittent gaslift liquid discharging gas producing intelligence It can, automatically turn on gas lift liquid drainage control.Using the algorithm, gas well self-energy can be applied to carry out hydrops production to greatest extent, It can reach and be required with production, moreover it is possible to injected gas volume is reduced, to improve intermittent gaslift liquid discharging gas producing efficiency and benefit.
Hydrops deciding degree method one proposed by the present invention, be utilized wellbore effusion the oil pressure of different phase, casing pressure it Between difference changing character, using time scale rolling average slope computational methods carry out intelligent decision, reality can be eliminated When monitoring fluctuation uncertain influenced on what tendency judgement was brought.The difference DELTA P of obtained casing pressure and oil pressure will be detected in real timezct (t) time series rolling average processing is carried out.The sampling period of Real-time Monitoring Data is set as T, n times of T is moved for unit Dynamic average computation, n desirable 5,10 or 20, concrete condition rule of thumb determines.Tendency judgement is carried out by linear fit, if quasi- Close slope KznIt is larger, it is determined as that variation is apparent;If close to 0, it is judged to stablizing.
Hydrops deciding degree method two proposed by the present invention, judgement Δ is carried out using maximum difference between oil pressure and casing pressure Pzctmax.Oil jacket allows maximum differential pressure to be obtained to gas well plug-ging production process tracking comprehensive analysis by gas recovery teacher.If Pzct(t) >ΔPzctmax, then show that hydrops is serious, needs gas lift liquid drainage.
Hydrops deciding degree method three proposed by the present invention, is judged using wellbore effusion stage casing pressure drop value. It is calculated by the flow simulating in the gas well plug-ging production process of backstage, incorporates experience into estimation, obtain gas well blowing hydrops production Permitted maximum casing pressure drop value Δ P in the processzcmax.It calculates first, in no hydrops rational proration QgCorresponding set Pressure value Pc1.Then it calculates, the hydrops of permission produces minimum gas production QgminWhen (generally take with production gas production Qg70~90%, It is specific value, empirically determined) corresponding to and Pc2.Maximum casing pressure drop value Δ Pzcmax=Pc1-Pc2.If Δ Pzc(t)>Δ Pcmax, then show that hydrops is serious, needs gas lift liquid drainage.
Hydrops deciding degree method four proposed by the present invention is analyzed by gas recovery teacher according to the historical trace to gas well It arrives, permitted minimum, the largest production time T of hydrops productionzmin、Tzmax.If Tz(t)<Tzmin, show that gas well plug-ging is not serious; Tz(t)>Tzmax, show that gas well plug-ging is serious.
The present invention proposes intermittent gaslift liquid discharging gas producing, and from being sprayed onto certainly, the judgement of gas injection opening time is accurate to survey:With last time gaslift knot Beam is starting point, and current time casing pressure drop value Δ P is calculated separately based on real-time collected oil pressure, casing pressure valuezc(t);Oil jacket pressure Difference DELTA Pzct(t);Time series oil jacket pressure difference rolling average changes slope kzn(t);Blowing duration Tz(t);It is following three When any one establishment of criterion, then start gas lift liquid drainage automatically:
(1) if T (t)>Tzmax, show that the blowing hydrops production time is more than and demarcate allowed maximum duration, need to open at this time Dynamic gas lift liquid drainage;
(2) if Δ Pzc(t)>ΔPzcmax, and Tz(t)>Tzmin, show that blowing hydrops causes oil jacket pressure difference to be more than calibration and permits Perhaps maximum value then needs to start gas lift liquid drainage;
(3) if kzn(t)>kzmax, and Tz(t)>Tzmin, oil jacket pressure difference change rate be significantly greater than demarcate permitted maximum value, It then needs to start gas lift liquid drainage;
The present invention is based on collect oil pressure, casing pressure data in real time, it is proposed that a set of intelligent decision intermittent gaslift liquid discharging gas producing Well gas lift liquid drainage Method Of Accomplishment, this method is embedded into intelligent controller, you can realizes intermittent gaslift liquid discharging gas producing intelligently, certainly It is dynamic to close lift-gas injection control.Using the algorithm, it can be precisely controlled gas injection time, injected gas volume is avoided to waste, to improve Intermittent gaslift liquid discharging gas producing efficiency and benefit.
Gas lift liquid drainage proposed by the present invention completes determination method one, and oil pressure, set of the pit shaft drain in different phase is utilized Difference changing character between pressure carries out intelligent decision using different time scales rolling average slope computational methods, can The uncertainty that tendency judgement is brought is influenced with eliminating monitoring fluctuation in real time.The difference of obtained casing pressure and oil pressure will be detected in real time It is worth Δ Pglct(t) time series rolling average processing is carried out.The sampling period of Real-time Monitoring Data is set as T, n times of T is single Position carries out rolling average calculating, and n desirable 5,10 or 20, concrete condition rule of thumb determines.Trend is carried out by linear fit Judgement, if fit slope kglnIt is larger, then it is determined as that variation is apparent;If kglnIt levels off to 0, is then judged to stablizing.
Gas lift liquid drainage proposed by the present invention completes determination method two, is judged using minimal difference between oil pressure and casing pressure ΔPglctmin.Oil jacket allows minimum differntial pressure to be obtained to gas well drain production process tracking comprehensive analysis by gas recovery teacher.If Pglct (t)<ΔPglctmin, then show that hydrops is drained, can switch to the production of blowing hydrops.
Gas lift liquid drainage proposed by the present invention completes determination method three, is gone through according to gas well gas lift liquid drainage by gas recovery teacher History trace analysis obtains, gas lift liquid drainage gas production minimum, maximum allowable gas injection duration Tglmin、Tglmax.If Tgl(t)<Tglmin, Show that gas lift liquid drainage does not complete;Tgl(t)>Tglmax, show that gas well gas lift liquid drainage has been completed.
The present invention proposes the quasi- survey of intermittent gaslift liquid discharging gas producing gas injection duration judgement:It is with this gaslift opening point Point calculates separately current time oil jacket pressure difference Δ P based on real-time collected oil pressure, casing pressure valueglct(t);Time series oil It covers pressure difference rolling average and changes slope kgln(t);Gaslift duration Tgl(t);Any one establishment of following three criterions, then need Gas lift liquid drainage is automatically closed, gas well is switched to the blowing production phase:
(1) if, Tgl(t)>Tglmax, the gas lift liquid drainage time, which is more than, demarcates permitted maximum time, shows that gas lift liquid drainage is complete At, need at this time close gas lift liquid drainage, automatically switch to the blowing production phase;
(2) if, Pglct(t)<ΔPglctmin, and Tgl(t)>Tglmin, oil jacket pressure difference, which drops to, demarcates institute's permissible value, shows gaslift Drain is completed, and is needed to close gas lift liquid drainage at this time, is automatically switched to the blowing production phase.
(3) if, kgln(t)<kglmin, and Tgl(t)>Tglmin, oil jacket pressure difference change rate tends to be steady, and shows that gas lift liquid drainage is complete At, need at this time close gas lift liquid drainage, automatically switch to the blowing production phase;
The present invention is based on the production of blowing hydrops, the gas lift liquid drainage productions during intermittent gaslift liquid discharging gas producing set forth above Stage hydrops and drain intelligent decision algorithm, it is proposed that a set of enforceable intermittent gaslift liquid discharging gas producing intelligence control system dress It sets, which is made of 7 parts:
1 real-time detection senses unit:In addition to intelligent control other than tubing pressure necessarily, casing pressure on-line checking, In order to realize to gas well liquid loading situation overall monitor, it is also necessary to increase gas injection system pressure and temperature, surface production pipeline back pressure With temperature, the parameters on-line real-time measuremen such as gas injection rate metering, the metering of production tolerance, production liquid (oil, water) metering,.
2 automatic execution units:It is made of controllable diaphragm control valve and its attachment, generally chooses pneumatic diaphragm control valve, Control air source directly takes gas by acquiring connector from proof wellhead oil casing annular space, by after pressure reducing valve, filter, solenoid valve to pneumatic thin Film control valve provides power gas source.Intelligent controller to solenoid valve by exporting control signal.
3 intelligent controllers, are the core cells of gap gas lift liquid drainage gas production, and there is real-time data collection interface, automatic in inside Actuator interface, live control panel interface, data remote interface, intelligent optimization calculator and the resistance of other attachmentes at.
4 live control panels, the system of offer are shown and manipulation data input;
5 data remote communication modules realize that on-line monitoring and control information uploads, long-range model parameter and operating parameter are returned It passes, communication modes can be wireless GPRS, WIFI or wired optical cable, connection etc..
6 remote monitoring systems monitor intermittent gaslift liquid discharging gas producing production status, and intelligent control model parameter inputs, remotely Manipulate data input;
7 power-supply systems are intelligent controller, detecting sensor, automatic executive device, data remote communication module, scene behaviour It controls the field devices such as panel and power supply is provided, power source can be ground electrical power line, accumulator, solar energy etc..
What the part in the application met is described as follows:
Qg, calibration gives in gas well matches production yield, m3/d;Pc, the reasonable pressure value of casing pressure when no shaft bottom hydrops, MPa;Δ Pzcmax, there are the permitted maximum casing pressure drop value of certain hydrops, MPa in calibration shaft bottom;ΔPzctmax, demarcate blowing drain production period Between the permitted maximum value of oil jacket pressure difference, MPa;ΔPzc(t), oil jacket pressure difference monitor value during blowing drain production, MPa;kzn (t), the Fitting Calculation obtains oil jacket pressure differential deltap P during blowing drain productionzc(t) rolling average variation tendency slope, MPa/d; kzmax, demarcate oil jacket pressure difference rolling average variation slope boundary value during blowing, MPa/d;Tzmin、Tzmax, demarcate blowing and continue most Short, maximum duration, d;ΔPglct(t), oil jacket pressure difference monitor value, MPa during gas lift liquid drainage;ΔPglctmin, it is complete to demarcate gas lift liquid drainage Enumerate the minimum oil jacket pressure difference after wellbore effusion, MPa entirely;kgln(t), the rolling average of oil jacket pressure difference changes during gas lift liquid drainage Trend slope, MPa/d;kglmin, oil jacket pressure difference rolling average variation tendency slope minimum defines value during demarcating gas lift liquid drainage, MPa/d;Tglmin、Tglmax, calibration gas lift liquid drainage gas production minimum allowable gas injection duration minimum, maximum value, d;Pwf, rationally match Produce QgWhen correspond to production stream pressure, MPa;Pcgs, rational proration QgWhen correspond to casing air column pressure, MPa;Qgmin, calibration permission is most Low yield tolerance, m3/d;Pwfmax, allow the production stream pressure corresponding to minimum gas production;Pcls, allow casing hydrops head of liquid, MPa;Pcfg, annular air injection frictional resistance when gaslift, MPa;Pctp, pin gas lift valve chock pressure difference when gaslift, MPa;Ptgs, oil when gaslift Gas frictional resistance, MPa in pipe;Ptfg, air column pressure in oil pipe when gaslift.
Intermittent gaslift liquid discharging gas producing Structure of intelligent control system proposed by the invention and principle as shown in Figure 1, Figure 2, Fig. 3
In the blowing hydrops production phase, oil pressure, casing pressure are persistently monitored, it is automatic to calculate based on the model parameter that backstage provides Blowing hydrops critical parameter is surveyed, intelligence using intermittent gaslift liquid discharging gas producing gas injection opening time comprehensive judgement standard proposed by the present invention It is capable of determining whether to need to be switched to the gas lift liquid drainage production phase, if then exporting gas lift liquid drainage open command, be beaten by solenoid valve Pneumatic diaphragm control valve is opened to realize that gas lift liquid drainage produces, otherwise continues to the production of blowing hydrops.
In the gas lift liquid drainage production phase, oil pressure, casing pressure are persistently monitored, it is automatic to calculate based on the model parameter that backstage provides Gas lift liquid drainage completes critical parameter, judges quasi- survey, intelligence using the intermittent gaslift liquid discharging gas producing gas injection duration proposed by the present invention It is capable of determining whether that needing to be switched to the blowing hydrops production phase is closed if then exporting gas lift liquid drainage out code by solenoid valve Pneumatic diaphragm control valve is closed to realize that gaslift is closed, otherwise continues to gas lift liquid drainage production.
Although preferred embodiments of the present invention have been described, it is created once a person skilled in the art knows basic Property concept, then additional changes and modifications may be made to these embodiments.So it includes excellent that the following claims are intended to be interpreted as It selects embodiment and falls into all change and modification of the scope of the invention.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art God and range.In this way, if these modifications and changes of the present invention belongs to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (11)

1. a kind of gap gas lift liquid drainage gas production control method, which is characterized in that the method includes:
Based on oil pressure, the casing pressure variation characteristic during Wellbore of Gas Wells hydrops, using acquire in real time oil pressure, casing pressure data, from The dynamic opening time for determining intermittent gaslift liquid discharging gas producing gas injection;
Oil pressure, the casing pressure variation characteristic of well head are discharged to by gaslift based on Wellbore of Gas Wells hydrops, using oil pressure, the set acquired in real time Data are pressed, the production time that intermittent gaslift liquid discharging gas producing gas injection closure, suspension, merger and conversion is blowing is automatically determined.
2. gas lift liquid drainage gas production control method in gap according to claim 1, which is characterized in that automatically determine intermittent gaslift It the opening time of liquid discharging gas producing gas injection, specifically includes:
Calibration is given with production production Q in gas wellgUnder the conditions of, the reasonable pressure value P of casing pressure when no shaft bottom hydropsc;Calibration shaft bottom has one The permitted maximum casing pressure drop value Δ P of constant volume liquidzcmax;Demarcate the permitted maximum value Δ P of oil jacket pressure differencezctmax;Using movement The method of average calculates, oil jacket pressure differential deltap Pzc(t) variation tendency slope kzn(t), calibration hydrops allows to change slope boundary value kzmax; Calibration gas lift liquid drainage gas production blowing continues shortest time Tzmin, maximum duration Tzmax
From being sprayed onto certainly, the judgement of gas injection opening time is accurate to survey intermittent gaslift liquid discharging gas producing:Terminated as starting point with last time gaslift, based on real When collected oil pressure, casing pressure value calculate separately current time casing pressure drop value Δ Pzc(t);Oil jacket pressure difference Δ Pzct(t);When Between sequence oil jacket pressure difference rolling average change slope kzn(t);Blowing duration Tz(t);Following three criterions any one at Immediately, then start gas lift liquid drainage automatically:
If 1) T (t)>Tzmax, show that the blowing hydrops production time is more than and demarcate allowed maximum duration, need to start gaslift at this time Drain;
If 2) Δ Pzc(t)>ΔPzcmax, and Tz(t)>Tzmin, it is permitted to show that blowing hydrops causes oil jacket pressure difference to be more than calibration Maximum value then needs to start gas lift liquid drainage;
If 3) kzn(t)>kzmax, and Tz(t)>Tzmin, oil jacket pressure difference change rate, which is more than, demarcates permitted maximum value, then needs to open Dynamic gas lift liquid drainage.
3. gas lift liquid drainage gas production control method in gap according to claim 1, which is characterized in that automatically determine intermittent gaslift Liquid discharging gas producing gas injection closure, suspension, merger and conversion is the production time of blowing, is specifically included:
Calibration gas lift liquid drainage enumerates the minimum oil jacket pressure difference Δ P after wellbore effusion completelyglctmin;It is calculated using the method for moving average, Casing pressure and oil pressure difference DELTA Pglct(t) variation tendency kgln(t), calibration gas lift liquid drainage enumerates the oil jacket pressure after wellbore effusion completely Poor minimum change slope kglmin;Demarcate gas lift liquid drainage gas production minimum allowable gas injection duration Tglmin, maximum time Tglmax
The judgement of intermittent gaslift liquid discharging gas producing gas injection duration is accurate to survey:Using this gaslift opening point as starting point, based on acquisition in real time To oil pressure, casing pressure value calculate separately current time oil jacket pressure difference Δ Pglct(t);Time series oil jacket pressure difference rolling average becomes Change slope kgln(t);Gaslift duration Tgl(t);Any one establishment of following three criterions then needs that gaslift row is automatically closed Liquid, gas well are switched to the blowing production phase:
If 1), Tgl(t)>Tglmax, the gas lift liquid drainage time, which is more than, demarcates permitted maximum time, shows that gas lift liquid drainage is completed, this When need close gas lift liquid drainage, automatically switch to the blowing production phase;
If 2), Pglct(t)<ΔPglctmin, and Tgl(t)>Tglmin, oil jacket pressure difference, which drops to, demarcates institute's permissible value, shows gas lift liquid drainage It completes, needs to close gas lift liquid drainage at this time, automatically switch to the blowing production phase;
If 3), kgln(t)<kglmin, and Tgl(t)>Tglmin, show that gas lift liquid drainage is completed, need to close gas lift liquid drainage at this time, automatically It is switched to the blowing production phase.
4. gas lift liquid drainage gas production control method in gap according to claim 2, which is characterized in that calibration gives in gas well matches Produce production QgUnder the conditions of, the reasonable pressure value P of casing pressure when no shaft bottom hydropsc, there are two types of scaling methods, the first:After gas lift liquid drainage Between the blowing time started section average casing pressure value;Second:It is calculated by Wellbore Flow simulation, rational proration QgWhen correspond to Production stream pressure PwfSubtract casing air column pressure Pcgs
5. gas lift liquid drainage gas production control method in gap according to claim 2, which is characterized in that there is a constant volume in calibration shaft bottom The permitted maximum casing pressure drop value Δ P of liquidzcmax, scaling method is:First, calibration allows minimum gas production Qgmin;Then, The corresponding minimum gas production Q of permission is calculated by thermally coupled flow IPR modelgminCorresponding production stream presses Pwfmax;Finally, most Big casing pressure drop value Δ PzcmaxEqual to casing hydrops section head of liquid PclsSubtract (Pwfmax-Pwf)。
6. gas lift liquid drainage gas production control method in gap according to claim 2, which is characterized in that calibration casing pressure and oil pressure are poor It is worth Δ Pzct(t) variation tendency will detect the difference DELTA P of obtained casing pressure and oil pressure in real timezct(t) it is flat to carry out time series movement It handles, sets the sampling period of Real-time Monitoring Data as T, n times of T carries out rolling average calculating for unit, and the value of n is 5 Or 10, tendency judgement is carried out by linear fit.
7. gas lift liquid drainage gas production control method in gap according to claim 3, which is characterized in that calibration gas lift liquid drainage is complete Enumerate the minimum oil jacket pressure difference Δ P of wellbore effusionglctminIt is acquired by the calculating of gaslift pit shaft flow simulating, is not accumulated in pit shaft In the case of liquid, oil jacket pressure difference Δ PctminEqual to the air column pressure P in annular spacecgs+ annular air injection frictional resistance Pcfg+ pin gas lift valve Chock pressure difference PctpGas frictional resistance P in+oil pipetgsAir column pressure P in oil pipetfg
8. gas lift liquid drainage gas production control method in gap according to claim 3, which is characterized in that calibration casing pressure and oil pressure are poor It is worth Δ Pglct(t) variation tendency will detect the difference DELTA P of obtained casing pressure and oil pressure in real timeglct(t) time series movement is carried out Average treatment sets the sampling period of Real-time Monitoring Data as T, and n times of T carries out rolling average calculating for unit, and the value of n is 5 or 10, tendency judgement is carried out by linear fit.
9. a kind of gap gas lift liquid drainage gas production control system, which is characterized in that the system comprises:
Real-time detection senses unit, including tubing pressure, casing pressure sensor, real-time detection senses unit is for acquiring gap Gas lift liquid drainage gas production production status parameter, and the parameter is transmitted to intelligent controller, intelligent controller will be based on detection in real time The parameter of perception carries out operation, output intelligent control instruction;
Automatic execution unit, including controllable diaphragm control valve and its attachment, automatic execution unit are used for intelligent controller institute is defeated The gas injection that the instruction gone out is converted to gap gaslift is shut down and is automatically brought into operation, if instruction is blowing, production is switched to gas lift liquid drainage state, Diaphragm control valve can then be crossed and open gas injection channel, to pit shaft gas injection, gas well is kept to be in gas lift liquid drainage state;If instruction is gaslift Drain is switched to blowing production status, then by the control valve of film, closes gas injection channel, and gas well is kept to be in blowing production shape State;
Intelligent controller, the real-time status parameter for receiving real-time detection senses unit transmission, generates manipulation instruction, and will refer to Order sends automatic execution unit to and realizes automatic manipulation;
Live control panel is shown and manipulation data input for providing system;
Power-supply system, for being provided for intelligent controller, real-time detection senses unit, automatic execution unit, live control panel Power supply.
10. gas lift liquid drainage gas production control system in gap according to claim 9, which is characterized in that the system also includes:
Data remote communication module uploads for realizing system on-line monitoring and control information, long-range model parameter and manipulation are joined Number passback;
Remote monitoring system, for monitoring intermittent gaslift liquid discharging gas producing production status, the input of Controlling model parameter, remote control number According to input.
11. gas lift liquid drainage gas production control system in gap according to claim 9, which is characterized in that
In the blowing hydrops production phase, oil pressure, casing pressure are persistently monitored, based on the model parameter that backstage provides, calculates blowing automatically Hydrops critical parameter is surveyed using intermittent gaslift liquid discharging gas producing gas injection opening time comprehensive judgement standard, it is determined whether needs are switched to The gas lift liquid drainage production phase, if then exporting gas lift liquid drainage open command, by solenoid valve open pneumatic diaphragm control valve to It realizes gas lift liquid drainage production, otherwise continues to the production of blowing hydrops;
In the gas lift liquid drainage production phase, oil pressure, casing pressure are persistently monitored, based on the model parameter that backstage provides, calculates gaslift automatically Critical parameter is completed in drain, judges accurate survey using the intermittent gaslift liquid discharging gas producing gas injection duration, it is determined whether needs are switched to The blowing hydrops production phase, if then exporting gas lift liquid drainage out code, by solenoid valve close pneumatic diaphragm control valve to It realizes that gaslift is closed, otherwise continues to gas lift liquid drainage production.
CN201810230249.XA 2018-03-20 2018-03-20 Intermittent gas lift liquid drainage gas production control method and system Active CN108518204B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810230249.XA CN108518204B (en) 2018-03-20 2018-03-20 Intermittent gas lift liquid drainage gas production control method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810230249.XA CN108518204B (en) 2018-03-20 2018-03-20 Intermittent gas lift liquid drainage gas production control method and system

Publications (2)

Publication Number Publication Date
CN108518204A true CN108518204A (en) 2018-09-11
CN108518204B CN108518204B (en) 2020-01-21

Family

ID=63432900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810230249.XA Active CN108518204B (en) 2018-03-20 2018-03-20 Intermittent gas lift liquid drainage gas production control method and system

Country Status (1)

Country Link
CN (1) CN108518204B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209305A (en) * 2018-11-13 2019-01-15 中国石油化工股份有限公司江汉油田分公司石油工程技术研究院 A kind of gas well Intelligent Plunger mining device and construction method
CN110318715A (en) * 2019-07-03 2019-10-11 四川轻化工大学 A kind of plunger auxiliary intermittent gaslift liquid discharging gas producing control system and control method
CN110593820A (en) * 2019-08-07 2019-12-20 中国石油天然气股份有限公司 Liquid drainage and gas production device and gas well liquid drainage method
CN111472733A (en) * 2020-06-03 2020-07-31 中测测控(西安)研究院有限公司 Intelligent intermittent drainage gas production system and control method thereof
CN111832232A (en) * 2020-07-20 2020-10-27 森诺科技有限公司 Technical method for diagnosing and identifying accumulated liquid in pipeline
CN112459748A (en) * 2020-11-05 2021-03-09 中国石油天然气股份有限公司 Single-point high-pressure gas lift drainage and gas increase process system and method
CN113027382A (en) * 2020-08-18 2021-06-25 陕西中良智能科技有限公司 Machine learning device, intermittent gas well switching intelligent control system and control method
CN114412427A (en) * 2020-10-12 2022-04-29 北京星油科技有限公司 Gas lift and production integrated oil and gas exploitation system
CN114673473A (en) * 2022-04-22 2022-06-28 托普威尔石油技术股份公司 Plunger gas lift control system and control method thereof
CN115492573A (en) * 2022-11-21 2022-12-20 西南石油大学 Dynamic determination method for stratum inflow of plunger gas lift well

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5871048A (en) * 1997-03-26 1999-02-16 Chevron U.S.A. Inc. Determining an optimum gas injection rate for a gas-lift well
US20090173494A1 (en) * 2003-12-30 2009-07-09 Schlumberger Technology Corporation System and method to interpret distributed temperature sensor data and to determine a flow rate in a well
CN104806229A (en) * 2015-04-01 2015-07-29 西南石油大学 Plunger gas-lift drainage/gas production logging system and control method thereof
CN105089537A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Simple plunger piston device of gas well mouth and gas well gas production method
CN105888608A (en) * 2014-12-05 2016-08-24 西安金立石油科技有限公司 Intelligent control plunger gas lift water drainage and gas recovery system and realizing method thereof
CN206928940U (en) * 2017-07-14 2018-01-26 中国石油化工股份有限公司 A kind of downhole intelligent controls plunger airlift unit

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5871048A (en) * 1997-03-26 1999-02-16 Chevron U.S.A. Inc. Determining an optimum gas injection rate for a gas-lift well
US20090173494A1 (en) * 2003-12-30 2009-07-09 Schlumberger Technology Corporation System and method to interpret distributed temperature sensor data and to determine a flow rate in a well
CN105089537A (en) * 2014-05-14 2015-11-25 中国石油天然气股份有限公司 Simple plunger piston device of gas well mouth and gas well gas production method
CN105888608A (en) * 2014-12-05 2016-08-24 西安金立石油科技有限公司 Intelligent control plunger gas lift water drainage and gas recovery system and realizing method thereof
CN104806229A (en) * 2015-04-01 2015-07-29 西南石油大学 Plunger gas-lift drainage/gas production logging system and control method thereof
CN206928940U (en) * 2017-07-14 2018-01-26 中国石油化工股份有限公司 A kind of downhole intelligent controls plunger airlift unit

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
田宝: "柱塞气举排水采气工艺关键技术研究", 《全国优秀硕士学位论文全文数据库工程科技Ⅰ辑》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109209305A (en) * 2018-11-13 2019-01-15 中国石油化工股份有限公司江汉油田分公司石油工程技术研究院 A kind of gas well Intelligent Plunger mining device and construction method
CN109209305B (en) * 2018-11-13 2023-10-13 中国石油化工股份有限公司 Intelligent plunger drainage and production device for gas well and construction method
CN110318715A (en) * 2019-07-03 2019-10-11 四川轻化工大学 A kind of plunger auxiliary intermittent gaslift liquid discharging gas producing control system and control method
CN110593820A (en) * 2019-08-07 2019-12-20 中国石油天然气股份有限公司 Liquid drainage and gas production device and gas well liquid drainage method
CN111472733A (en) * 2020-06-03 2020-07-31 中测测控(西安)研究院有限公司 Intelligent intermittent drainage gas production system and control method thereof
CN111832232A (en) * 2020-07-20 2020-10-27 森诺科技有限公司 Technical method for diagnosing and identifying accumulated liquid in pipeline
CN113027382A (en) * 2020-08-18 2021-06-25 陕西中良智能科技有限公司 Machine learning device, intermittent gas well switching intelligent control system and control method
CN113027382B (en) * 2020-08-18 2023-02-10 陕西中良智能科技有限公司 Machine learning device, intermittent gas well switching intelligent control system and control method
CN114412427A (en) * 2020-10-12 2022-04-29 北京星油科技有限公司 Gas lift and production integrated oil and gas exploitation system
CN114412427B (en) * 2020-10-12 2023-11-14 北京星油科技有限公司 Gas lift and production integrated oil gas exploitation system
CN112459748A (en) * 2020-11-05 2021-03-09 中国石油天然气股份有限公司 Single-point high-pressure gas lift drainage and gas increase process system and method
CN114673473A (en) * 2022-04-22 2022-06-28 托普威尔石油技术股份公司 Plunger gas lift control system and control method thereof
CN115492573A (en) * 2022-11-21 2022-12-20 西南石油大学 Dynamic determination method for stratum inflow of plunger gas lift well

Also Published As

Publication number Publication date
CN108518204B (en) 2020-01-21

Similar Documents

Publication Publication Date Title
CN108518204A (en) A kind of gap gas lift liquid drainage gas production control method and system
CN106285572B (en) Control device and its control method are taken out between a kind of pumping unit intelligence
CN110318715B (en) Plunger-assisted intermittent gas lift liquid drainage and gas production control system and control method
CN104196506B (en) Injection and production parameter joint debugging method, device and system for SAGD single well set
CN112861423B (en) Data-driven water-flooding reservoir optimization method and system
CN111472733B (en) Intelligent intermittent drainage gas production system and control method thereof
CN104100241B (en) A kind of definite hyposmosis oil well is taken out the method for system rationally
US20200277844A1 (en) Apparatus and methods for operating gas lift wells
CN110847894B (en) Method for determining flow pressure of underground throttling gas well
CN112580851A (en) Cluster well site pumping unit well group peak-staggering well-opening pumping row scheduling method
CN111364941B (en) Shale gas well wellhead pressure control method and control system thereof
CN110928215B (en) Intelligent control system and control method for oilfield water mixing pipe network
CN103835687A (en) Method and device for controlling SAGD well steam injection flow
CN113027387B (en) Oil well interval pumping control system and method
CN202023738U (en) Rotating speed intelligent control system for oil-immersed screw pump
CN112943179B (en) Plunger gas lift production system optimization control method
CN107989599A (en) The low-consumption wireless communication system and method for a kind of circuit die meter
CN102393631B (en) Lubricating oil temperature control system based on fuzzy control
CN209494552U (en) A kind of well plunger control system
CN110988305A (en) Automatic water pumping test device and implementation method
Liang et al. Fuzzy immune algorithm based remote wireless transmission for Throttled PID control strategy
CN112882381B (en) Self-optimizing decision control system of electric submersible pump
CN109594983B (en) Constant-current injection and in-situ stress test monitoring system for coal bed gas injection pressure drop well testing
CN110043228A (en) A kind of oil pumping unit well field intelligent management work station
CN113027382B (en) Machine learning device, intermittent gas well switching intelligent control system and control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant