CN108491967A - One kind being suitable for the automatic pre-judging method of dispatching automation main station failure - Google Patents
One kind being suitable for the automatic pre-judging method of dispatching automation main station failure Download PDFInfo
- Publication number
- CN108491967A CN108491967A CN201810211229.8A CN201810211229A CN108491967A CN 108491967 A CN108491967 A CN 108491967A CN 201810211229 A CN201810211229 A CN 201810211229A CN 108491967 A CN108491967 A CN 108491967A
- Authority
- CN
- China
- Prior art keywords
- failure
- main station
- dispatching automation
- automation main
- judging method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0635—Risk analysis of enterprise or organisation activities
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/04—Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
The present invention relates to the technical fields of failure anticipation, being suitable for the automatic pre-judging method of dispatching automation main station failure more particularly, to one kind.One kind being suitable for the automatic pre-judging method of dispatching automation main station failure, wherein includes the following steps:S1. with the device and system of third party role, according to the abstract fault category of summary;S2. it by parallelizations, standardization, automations such as the emergent failure that need to manually dispose anticipation, confirmations, with the hardware structure for meeting system operation demand of customization, avoids using reliability weak spot caused by common computer hardware equipment;S3. it with the software systems of customization, is interacted with operating system, database, application system difference depth, fully identifies each fault category of dispatching automation main station system, the active isolation that takes measures, Disposal Measures.
Description
Technical field
The present invention relates to the technical fields of failure anticipation, being suitable for the event of dispatching automation main website more particularly, to one kind
Hinder automatic pre-judging method.
Background technology
Dispatching automation main station system failure in power grid day-to-day operation, emergency worker must efficiently hold within the time of restriction
Row failure is studied and judged.The uncertainty of " personnel are in place ", " technical ability is in place " these elements is easy to cause troubleshooting not in time or expands
Greatly, threaten the safe and stable operation of system, it is therefore necessary to by the method for operation maintenance personnel failure judgement and empirical routines, be
Systemization is applied to dispatching automation main station system failure and quickly studies and judges.And existing dispatching automation main station system key node
Equal redundant configuration can accomplish the fault self-checking of limited extent based on the software systems of itself, but Master Station Software system is die certainly
Barrier checks failure of the module for relatively deep, such as:Operating system grade failure, database table level failure, process deadlock grade failure,
Key node restart automatically after using it is not actuated, after system down quick black starting-up etc. can cause the failure of greater risk there are still
Blind area or powerless processing.
Invention content
The present invention is at least one defect overcome described in the above-mentioned prior art, is provided a kind of suitable for dispatching automation master
The automatic pre-judging method of station failure, it is efficient and stable.
The technical scheme is that:One kind being suitable for the automatic pre-judging method of dispatching automation main station failure, wherein including
Following steps:
S1. with the device and system of third party role, according to the abstract fault category of summary;
S2. by parallelizations, standardization, automations such as the emergent failure that need to manually dispose anticipation, confirmations, it is with meeting for customization
The hardware structure of system operation demand is avoided using reliability weak spot caused by common computer hardware equipment;
S3. it with the software systems of customization, is interacted with operating system, database, application system difference depth, fully identification scheduling
Automate each fault category of main station system, the active isolation that takes measures, Disposal Measures.
Compared with prior art, advantageous effect is:The present invention eliminates uncertain factor related with people in troubleshooting,
Steadily and surely, the emergent failure in part for rapidly, efficiently studying and judging scheduling station system, promotes the event of power network schedule automation main station system
Barrier processing intelligence, automation level and power network schedule automation main station system troubleshooting efficiency, it is ensured that system is effectively propped up
Power network safety operation is supportted, the generation of dispatch automated system failure event can be effectively prevented.
Specific implementation mode
One kind being suitable for the automatic pre-judging method of dispatching automation main station failure, wherein includes the following steps:
S1. with the device and system of third party role, according to the abstract fault category of summary;
S2. by parallelizations, standardization, automations such as the emergent failure that need to manually dispose anticipation, confirmations, it is with meeting for customization
The hardware structure of system operation demand is avoided using reliability weak spot caused by common computer hardware equipment;
S3. it with the software systems of customization, is interacted with operating system, database, application system difference depth, fully identification scheduling
Automate each fault category of main station system, the active isolation that takes measures, Disposal Measures.
The present invention gives full play to scheduling station system hardware and software advantage, and failure is studied and judged early warning operation automation.
Obviously, the above embodiment of the present invention be only to clearly illustrate example of the present invention, and not be pair
The restriction of embodiments of the present invention.For those of ordinary skill in the art, may be used also on the basis of the above description
To make other variations or changes in different ways.There is no necessity and possibility to exhaust all the enbodiments.It is all this
All any modification, equivalent and improvement etc., should be included in the claims in the present invention made by within the spirit and principle of invention
Protection domain within.
Claims (1)
1. one kind being suitable for the automatic pre-judging method of dispatching automation main station failure, which is characterized in that include the following steps:
S1. with the device and system of third party role, according to the abstract fault category of summary;
S2. by parallelizations, standardization, automations such as the emergent failure that need to manually dispose anticipation, confirmations, it is with meeting for customization
The hardware structure of system operation demand is avoided using reliability weak spot caused by common computer hardware equipment;
S3. it with the software systems of customization, is interacted with operating system, database, application system difference depth, fully identification scheduling
Automate each fault category of main station system, the active isolation that takes measures, Disposal Measures.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810211229.8A CN108491967A (en) | 2018-03-14 | 2018-03-14 | One kind being suitable for the automatic pre-judging method of dispatching automation main station failure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810211229.8A CN108491967A (en) | 2018-03-14 | 2018-03-14 | One kind being suitable for the automatic pre-judging method of dispatching automation main station failure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108491967A true CN108491967A (en) | 2018-09-04 |
Family
ID=63339325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810211229.8A Pending CN108491967A (en) | 2018-03-14 | 2018-03-14 | One kind being suitable for the automatic pre-judging method of dispatching automation main station failure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108491967A (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202565022U (en) * | 2011-12-16 | 2012-11-28 | 北京市电力公司 | Fault monitoring system capable of monitoring fault of electric power dispatching automation device |
CN104218676A (en) * | 2014-09-02 | 2014-12-17 | 广东电网公司茂名供电局 | Intelligent warning system and method for power dispatching automation master station |
CN105488610A (en) * | 2015-11-23 | 2016-04-13 | 国网山东省电力公司信息通信公司 | Fault real-time analysis and diagnosis system and method for power application system |
-
2018
- 2018-03-14 CN CN201810211229.8A patent/CN108491967A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202565022U (en) * | 2011-12-16 | 2012-11-28 | 北京市电力公司 | Fault monitoring system capable of monitoring fault of electric power dispatching automation device |
CN104218676A (en) * | 2014-09-02 | 2014-12-17 | 广东电网公司茂名供电局 | Intelligent warning system and method for power dispatching automation master station |
CN105488610A (en) * | 2015-11-23 | 2016-04-13 | 国网山东省电力公司信息通信公司 | Fault real-time analysis and diagnosis system and method for power application system |
Non-Patent Citations (1)
Title |
---|
林冠强: ""调度自动化主站运行监视系统的设计与实现"", 《中国优秀硕士论文全文数据库》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103473710B (en) | A kind of failure sorted processing method concentrating operational system | |
CN104821894B (en) | A kind of in-orbit autonomous management system of satellite and autonomous management method | |
CN108710544B (en) | Process monitoring method of database system and rail transit comprehensive monitoring system | |
CN111224818B (en) | Road side unit alarming method and device, electronic equipment and storage medium | |
CN109728979A (en) | Automatic warning system and method suitable for information O&M comprehensive supervision platform | |
US20180190403A1 (en) | Plant operation system and plant operation method | |
CN101222742A (en) | Alarm self-positioning and self-processing method and system for mobile communication network guard system | |
CN107658980A (en) | A kind of analysis method and system for being used to check power system monitor warning information | |
CN113066247A (en) | Intelligent monitoring system for operation of power distribution room based on cloud edge cooperation | |
CN108491967A (en) | One kind being suitable for the automatic pre-judging method of dispatching automation main station failure | |
KR102400956B1 (en) | A Bidirectional Control System for Power Facility | |
CN207748684U (en) | One kind managing system based on Internet of Things intelligent remote monitoring fault diagnosis | |
CN102999785A (en) | Integrated analysis method for process risk assessment | |
CN116505658A (en) | Abnormal defect alarm module of extended power distribution automation master station system | |
CN109308062A (en) | A kind of production equipment monitoring network integrated system | |
RU82048U1 (en) | STRUCTURED MONITORING AND MANAGEMENT SYSTEM FOR BUILDING AND STRUCTURE ENGINEERING SYSTEMS - SMIS | |
KR102235061B1 (en) | Safe-shutdown equipment operator action management system in case of fire at nuclear power plant | |
CN106789182A (en) | The detection points-scoring system and implementation method of the automatic assessment device of power plant's hierarchical protection | |
CN108249243B (en) | A kind of elevator Internet of Things fault recognition method | |
Wu et al. | Research on Public Safety Management under the Application of Big Data and Internet of Things | |
CN110255321A (en) | Elevator safety network supervision method based on Internet of Things | |
JP5477194B2 (en) | Communication network control management system and method | |
Spósito | Just a human error…? Case study of a condensate vessel explosion | |
Uesako | STAMP applied to Fukushima Daiichi nuclear disaster and the safety of nuclear power plants in Japan | |
CN113452142B (en) | Remote monitoring and restarting device and method for automatic equipment at station end |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |