CN108487462A - Reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process - Google Patents

Reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process Download PDF

Info

Publication number
CN108487462A
CN108487462A CN201810250217.6A CN201810250217A CN108487462A CN 108487462 A CN108487462 A CN 108487462A CN 201810250217 A CN201810250217 A CN 201810250217A CN 108487462 A CN108487462 A CN 108487462A
Authority
CN
China
Prior art keywords
main reinforcement
length
column
antidetonation
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810250217.6A
Other languages
Chinese (zh)
Other versions
CN108487462B (en
Inventor
詹焕辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Media Career Academy
Original Assignee
Jiangxi Media Career Academy
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Media Career Academy filed Critical Jiangxi Media Career Academy
Priority to CN201810250217.6A priority Critical patent/CN108487462B/en
Publication of CN108487462A publication Critical patent/CN108487462A/en
Application granted granted Critical
Publication of CN108487462B publication Critical patent/CN108487462B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Abstract

The invention belongs to technical field of buildings and disclose reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process realizes component and fitting or work as follows that this method need to be completed:It cuts 5d (vertical muscle diameter) bar dowels and is welded with main reinforcement patch, determines main reinforcement La(LaE) length and inflection point and bend etc..The cutting 5d (vertical muscle diameter) bar dowel and the advantages of welding, making full use of construction waste material, play mechanical anchor is pasted with main reinforcement, need to ensure weldquality;The calculating main reinforcement La(LaE) length inflection point and bends, main reinforcement L with determininga(LaE) length can foreshorten to 0.6 Lab(0.6LabE), be conducive to convenience and the flexibility of site operation.By the implementation of the above construction method, improves the vertical muscle of beam straight anchor length in column and be not less than 0.4Lab(0.4LabE) condition limitation defect;Improve the defect of main reinforcement anchoring process unicity present situation in bean column node;It avoids inconvenient phenomenon of constructing, consumes waste material, it is not only energy saving but also save trouble.

Description

Reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process
Technical field
Patent of the present invention relates generally to reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process belongs to building skill Art field..
Background technology
According to the requirement of building structure construction specification and design, concrete and rebar can be effectively bonded together, and be played Go out respective advantage, benefited for the mankind, reaches our research and use purpose.So reinforcing bar can with coagulation local soil type integrator, It has to the anchorage length for having enough in concrete, and competence exertion goes out the effect of its tension, and otherwise concrete and rebar must It will detach, can not work together, i.e., destroying occurs in component.
In engineering design, for frame middle layer end node, beam longitudinal reinforcement is in the anchoring at Column border node position, when adopting With beam muscle 900When bending anchoring, it is desirable that the vertical muscle of beam stretches into straight anchor length in column and is not less than 0.4Lab (0.4LabE), this parameter is closed It is to column cross-section size, the diameter of anchor bar and strength grade, concrete strength and reinforcing bar type etc..And in putting into practice, often Appearance local location stretches into straight anchor length in column there are the vertical muscle of beam and is less than 0.4Lab (0.4LabE), the processing of usual such situation Method is that muscle replacement will be indulged in beam is minor diameter, but this way often occurs that number of steel bars is excessive at bean column node, sometimes The construction of concrete at bean column node can be seriously affected, on the other hand as what is replaced is the elongated muscle of beam, that is, there is taking for reinforcing bar It connects, while many inconvenience is brought to construction, increase the workload of construction arrangement of reinforcement, and waste steel..
Invention content
The technical problem to be solved in the present invention overcomes existing defect, provides reinforcing bar in a kind of concrete frame node (Antidetonation)Anchoring process, by using the method for pasting weldering dowel in main reinforcement side, anchoring overall length is La (LaE).This anchoring process, The vertical muscle for improving beam stretches into straight anchor length in column and must not drop below 0.4Lab (0.4LabE) condition limitation defect;Additionally by Using this anchoring process, the excessive phenomenon of number of steel bars at bean column node is avoided because of caused by Reinforcement Replacement, while also avoiding Therefore the inconvenient phenomenon of construction caused by, reduces construction arrangement of reinforcement workload, and consumption construction site some extra reinforcing bars are short Head, it is not only energy saving but also save trouble, and increase construction site and handle the flexibility of such anchoring matters, while can effectively solve background The problems in technology.
In order to solve the above technical problem, the present invention provides the following technical solutions:
Mainly there is provided a kind of for reinforcing bar in concrete frame node by the present invention(Antidetonation)Anchoring process realizes this method The need component and fitting that installation is complete or work include:It calculates and measures and cutting 5d (vertical muscle diameter) bar dowel, bar dowel and main reinforcement Patch weldering calculates main reinforcement La(LaE) length with determine inflection point, bending main reinforcement(900), installation and binding main reinforcement etc..The meter It calculates and measures and cut long 5d (vertical muscle diameter) bar dowel, be to have to do a job in a kind of mechanism anchorage method, it is long 5d (vertical muscle diameter) bar dowel is the accessory of such anchorage style can utilize steel bar stress end using such anchorage style Anchor head increases anchoring bearing capacity to the local squeezing action of concrete;The bar dowel head is welded with main reinforcement patch, is that will cut Good bar dowel head is welded with main reinforcement, is a kind of way of mechanical anchor, in order to ensure certain anchoring bearing capacity, is needed Control certain straight anchor length and welding quality;The calculating main reinforcement La(LaE) length with determine inflection point, be by La (LaE) require to determine the total anchorage length of main reinforcement, by code requirement, when using mechanical anchor length, main reinforcement La(LaE) length 0.6 L can be foreshortened toab (0.6LabE), i.e. anchorage length correction factor ζa0.6 is can be taken as, and according to column cross-section size, column The factors such as muscle diameter determine the inflection point of main reinforcement;The bending main reinforcement(900), according to fixed inflection point, to main reinforcement reality Apply 900Bending;The installation and binding main reinforcement, are that the main reinforcement that will have been bent is placed into corresponding position, and fixes.
As a preferred technical solution of the present invention, the calculating simultaneously measures and cuts 5d (vertical muscle diameter) bar dowel, leads to It crosses and uses bar dowel head, take full advantage of the waste material of construction site, it is not only energy saving but also save trouble, change Fei Weibao, reduces investment outlay into This.
As a preferred technical solution of the present invention, the bar dowel is welded with main reinforcement patch, is a kind of mechanical anchor side Formula increases anchoring bearing capacity to the local squeezing action of concrete using steel bar stress end anchor head, therefore to control certain Straight anchor length and welding quality.
As a preferred technical solution of the present invention, the calculating main reinforcement La(LaE) length with determine inflection point, Use such mechanical anchor mode, main reinforcement La(LaE) length can foreshorten to 0.6 Lab (0.6LabE), i.e. anchorage length Correction factor ζa0.6 is can be taken as, the flexibility that construction site handles such anchoring matters, and energy saving and province are not only increased Thing.
As a preferred technical solution of the present invention, the bending main reinforcement(900), it is to be more than 0.2L because existingab (0.2LabE) length main reinforcement can not straight anchor in column, can only be handled by bent anchor, while also increasing such anchorage style Safety stock.
Compared with prior art, using technical solutions according to the invention, it can reach following advantageous effect:
1, weldering mechanical anchor is pasted with unilateral side using such bent anchor and is combined mode, the vertical muscle for improving prior art central sill stretches into column Interior straight anchor length must not drop below 0.4Lab (0.4LabE) condition limitation defect.
2, the bar dowel head that long 5d is welded using unilateral patch is improved waste material live in the prior art and is unable to fully close Reason uses, and the defect that main reinforcement anchor type is single.
3, weldering mechanical anchor is pasted with unilateral side using such bent anchor and is combined mode, main reinforcement La(LaE) length can shorten To 0.6 Lab (0.6LabE), between two kinds of anchorage styles in existing technology, improves and handle such anchoring thing in the prior art The defect that suitable underaction, expense material are taken a lot of work again.
4, weldering mechanical anchor is pasted with unilateral side using such bent anchor and is combined mode, improve anchorage style peace in the prior art Not high enough defect is laid in entirely.
Description of the drawings
Attached drawing is used for a further understanding of the present invention, and a part for constitution instruction, the specific reality with the present invention It applies mode to be used to explain the present invention together, not be construed as limiting the invention.
In the accompanying drawings:
Fig. 1 is reinforcing bar in a kind of concrete frame node described in the specific embodiment of the invention(Antidetonation)Anchoring process is flat Face figure;
Fig. 2(1-1 sectional views)It is reinforcing bar in a kind of concrete frame node described in the specific embodiment of the invention(It is anti- Shake)Sectional view in anchoring process plan view.
Figure label:1、5d(Vertical muscle diameter)Bar dowel is welded with vertical muscle patch;2, beam upper longitudinal bar;3, beam upper longitudinal bar inflection point; 4, concrete column;5, beams of concrete.
Specific implementation mode
The preferred embodiment of the present invention is illustrated below in conjunction with attached drawing, it should be understood that preferred tool described herein Body embodiment is only for the purpose of illustrating and explaining the present invention and is not intended to limit the present invention.
Embodiment:It please refers to Fig.1, Fig. 2(1-1 sectional views), the present invention is reinforcing bar in a kind of concrete frame node(Antidetonation) Anchoring process realizes component and fitting or work as follows that this method need to be completed:It calculates and measures and cutting 5d (vertical muscle diameter) short steel Muscle(1), bar dowel and main reinforcement patch weld(2), calculate main reinforcement La(LaE) length inflection point and bend with determining(3), peace in beam column Dress and binding main reinforcement(4)(5).The calculating simultaneously measures and cutting 5d (vertical muscle diameter) bar dowel(1), take full advantage of construction The waste material at scene, it is not only energy saving but also save trouble, change Fei Weibao, cost of reducing investment outlay, and change construction site and applied about anchoring The monistic present situation of work mode;The bar dowel is welded with main reinforcement patch(2), be conducive to steel bar stress end anchor head to concrete Local squeezing action increases anchoring bearing capacity, therefore to control certain straight anchor length and welding quality, is a kind of mechanical anchor Gu mode;The calculating main reinforcement La(LaE) length inflection point and bend with determining(3), use such mechanical anchor side Formula, main reinforcement La(LaE) length can foreshorten to 0.6 Lab (0.6LabE), i.e. anchorage length correction factor ζa0.6 is can be taken as, It is not only advantageous to the easy for construction and flexibility of construction site, and energy saving and save trouble;Installation is led with binding in the beam column Muscle(4)(5), it is the work that main reinforcement binding has to complete in beam column, is conducive to the movement for preventing main reinforcement position.
By the implementation of the above construction method, the vertical muscle for improving beam stretches into straight anchor length in column and must not drop below 0.4Lab (0.4LabE) condition limitation defect;Additionally by this anchoring process is used, improve in site operation about in bean column node The monistic defect of main reinforcement anchoring process;Also avoid simultaneously therefore caused by the inconvenient phenomenon of construction, reduce construction arrangement of reinforcement Workload consumes some extra reinforcing bar brachycephaly of construction site, not only energy saving but also save trouble, and increases construction site and handle such anchor Gu the flexibility of matters.
Finally it should be noted that:The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, still may be used With technical scheme described in the above embodiments is modified or equivalent replacement of some of the technical features. All spirit in the present invention within principle, made by any modification, equivalent replacement, correction etc., should be included in of the invention Within protection domain.

Claims (5)

1. reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process realizes component and fitting or work that this method need to be completed It is as follows:It calculates and measures and cutting 5d (vertical muscle diameter) bar dowel(1), bar dowel and main reinforcement patch weld(2), calculate main reinforcement La(LaE) Length inflection point and bend with determining(3), installation and binding main reinforcement in beam column(4)(5).It is characterized in that beam upper longitudinal bar It stretches into straight anchor length in column and is less than 0.4Lab (0.4LabE)。
2. reinforcing bar in a kind of concrete frame node according to claim 1(Antidetonation)Anchoring process, it is characterised in that main Muscle end uses the mechanical anchor method of unilateral patch weldering, pastes a length of 5d of bar dowel of weldering(Main reinforcement diameter).
3. reinforcing bar in a kind of concrete frame node according to claim 1(Antidetonation)Anchoring process, it is characterised in that beam Total anchorage length of the top main reinforcement in column is 0.6Lab (0.6LabE)。
4. reinforcing bar in a kind of concrete frame node according to claim 1(Antidetonation)Anchoring process, it is characterised in that beam Top main reinforcement away from column inner edge distance is after bending in column:Wide-the 60mm of column.
5. reinforcing bar in a kind of concrete frame node according to claim 1(Antidetonation)Anchoring process, it is all the present invention's Spirit within principle, made by any modification, equivalent replacement, correction etc., should all be included in the protection scope of the present invention.
CN201810250217.6A 2018-03-26 2018-03-26 Anchoring method for steel bars in concrete frame node Expired - Fee Related CN108487462B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810250217.6A CN108487462B (en) 2018-03-26 2018-03-26 Anchoring method for steel bars in concrete frame node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810250217.6A CN108487462B (en) 2018-03-26 2018-03-26 Anchoring method for steel bars in concrete frame node

Publications (2)

Publication Number Publication Date
CN108487462A true CN108487462A (en) 2018-09-04
CN108487462B CN108487462B (en) 2020-09-01

Family

ID=63337484

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810250217.6A Expired - Fee Related CN108487462B (en) 2018-03-26 2018-03-26 Anchoring method for steel bars in concrete frame node

Country Status (1)

Country Link
CN (1) CN108487462B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339228A (en) * 2018-10-10 2019-02-15 湖南大学 A kind of bolt fastening structure of full prefabricated concrete structure bean column node
CN113006279A (en) * 2021-03-19 2021-06-22 山东建筑大学 Inorganic adhesive composite bamboo-wood structure middle beam-column connection node, frame structure and method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0617483A (en) * 1992-07-03 1994-01-25 Taisei Corp Composite beam
JPH10292483A (en) * 1997-04-15 1998-11-04 Mitsui Constr Co Ltd Fixing method of beam reinforcement
CN1386941A (en) * 2002-05-09 2002-12-25 张晓萌 Method for lapped joint or anchoring of reinforcing bars in reinforced concrete member
JP2004316322A (en) * 2003-04-18 2004-11-11 Takenaka Komuten Co Ltd Construction method of column-beam skeleton by precast concrete member
CN202187283U (en) * 2011-07-20 2012-04-11 天津市市政工程设计研究院 Structure of combined beam-concrete beam combined section
CN103061452A (en) * 2012-08-16 2013-04-24 杨众 Anti-seismic prestressed precast beam
CN203716304U (en) * 2013-08-20 2014-07-16 浙江精工钢结构集团有限公司 Flat-plate type embedded part
CN104131631A (en) * 2014-08-15 2014-11-05 重庆大学 Structure of top layer end node of anti-seismic framework and construction method of structure
CN204475530U (en) * 2015-01-06 2015-07-15 北京艾梦海洋科技有限公司 A kind of horizontal anchor structure of reinforcing bar short distance of new concrete beam
CN105239670A (en) * 2015-09-28 2016-01-13 沈阳建筑大学 Non-planar beam-wall connection structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0617483A (en) * 1992-07-03 1994-01-25 Taisei Corp Composite beam
JPH10292483A (en) * 1997-04-15 1998-11-04 Mitsui Constr Co Ltd Fixing method of beam reinforcement
CN1386941A (en) * 2002-05-09 2002-12-25 张晓萌 Method for lapped joint or anchoring of reinforcing bars in reinforced concrete member
JP2004316322A (en) * 2003-04-18 2004-11-11 Takenaka Komuten Co Ltd Construction method of column-beam skeleton by precast concrete member
CN202187283U (en) * 2011-07-20 2012-04-11 天津市市政工程设计研究院 Structure of combined beam-concrete beam combined section
CN103061452A (en) * 2012-08-16 2013-04-24 杨众 Anti-seismic prestressed precast beam
CN203716304U (en) * 2013-08-20 2014-07-16 浙江精工钢结构集团有限公司 Flat-plate type embedded part
CN104131631A (en) * 2014-08-15 2014-11-05 重庆大学 Structure of top layer end node of anti-seismic framework and construction method of structure
CN204475530U (en) * 2015-01-06 2015-07-15 北京艾梦海洋科技有限公司 A kind of horizontal anchor structure of reinforcing bar short distance of new concrete beam
CN105239670A (en) * 2015-09-28 2016-01-13 沈阳建筑大学 Non-planar beam-wall connection structure

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339228A (en) * 2018-10-10 2019-02-15 湖南大学 A kind of bolt fastening structure of full prefabricated concrete structure bean column node
CN113006279A (en) * 2021-03-19 2021-06-22 山东建筑大学 Inorganic adhesive composite bamboo-wood structure middle beam-column connection node, frame structure and method
CN113006279B (en) * 2021-03-19 2022-05-06 山东建筑大学 Inorganic adhesive composite bamboo-wood structure middle beam-column connection node, frame structure and method
WO2022193405A1 (en) * 2021-03-19 2022-09-22 山东建筑大学 Beam-column connection joint in inorganic adhesive composite bamboo-wood structure, and framework structure and method

Also Published As

Publication number Publication date
CN108487462B (en) 2020-09-01

Similar Documents

Publication Publication Date Title
CN208396036U (en) A kind of connecting node of profile steel concrete column and reinforced beam
CN201474166U (en) Concrete column for thin-walled steel section composite steel tube
CN108487462A (en) Reinforcing bar in a kind of concrete frame node(Antidetonation)Anchoring process
CN103174098B (en) A kind of reinforcement means of steel reinforced concrete punishment single slab bearing
CN105756365B (en) A kind of method of rapid reinforcement beams of concrete
CN203096945U (en) Novel panel point of concrete-filled steel tubular column, reinforced concrete beam having bonding pre-stressing force and ring beam
CN202913337U (en) Prestress combination box girder composed of concrete frange plates and corrugated steel webs
CN108978988A (en) A kind of superimposed sheet composite roof truss and preparation method
CN202359742U (en) Steel bar locator with reinforced masonry structure
CN204001810U (en) A kind of Covered with Angles encloses cover and reinforces section steel concrete column-steel girder node device after fire
CN103216085B (en) A kind of removable lining self-bearing type reinforcement bar truss mould plate
CN110273362A (en) A kind of orthogonal U-shaped steel floorings
CN103452331B (en) Shear strengthening of concrete beam method
CN206428966U (en) Deformation joint template of shear wall structure
CN209129250U (en) A kind of superimposed sheet composite roof truss
CN210049428U (en) Sandwich heat-insulating steel concrete composite pipe structure
CN202324349U (en) Integral type welding hooping for L-shaped edge member of shear wall
CN207700064U (en) A kind of Precast T-Beam reinforcing steel bar-binding bench
CN208056445U (en) A kind of prestressed cored slab
CN204370695U (en) Building L-type wall limb welding hooping structure
CN207419714U (en) A kind of new fixed steel tie bar embedded part steel plate structure
CN207673040U (en) It a kind of three face of increasing section beam encloses set and reinforces ring beam U hoop constructions
CN207988381U (en) A kind of structure that steel is marked time
CN206562770U (en) A kind of building in the style of the ancients cornice template
CN206263478U (en) Reinforcing bar length control mechanism when steel reinforcement cage is welded on seam welder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200901