CN108411797A - Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction - Google Patents

Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction Download PDF

Info

Publication number
CN108411797A
CN108411797A CN201810138842.1A CN201810138842A CN108411797A CN 108411797 A CN108411797 A CN 108411797A CN 201810138842 A CN201810138842 A CN 201810138842A CN 108411797 A CN108411797 A CN 108411797A
Authority
CN
China
Prior art keywords
arch
amount
deflection
catenary
vault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810138842.1A
Other languages
Chinese (zh)
Other versions
CN108411797B (en
Inventor
杨雨厚
罗月静
刘家耀
尹平阳
卓小丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Transportation Research and Consulting Co Ltd
Original Assignee
Guangxi Transportation Research and Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Transportation Research and Consulting Co Ltd filed Critical Guangxi Transportation Research and Consulting Co Ltd
Priority to CN201810138842.1A priority Critical patent/CN108411797B/en
Publication of CN108411797A publication Critical patent/CN108411797A/en
Application granted granted Critical
Publication of CN108411797B publication Critical patent/CN108411797B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F17/00Digital computing or data processing equipment or methods, specially adapted for specific functions
    • G06F17/10Complex mathematical operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/10Numerical modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2119/00Details relating to the type or aim of the analysis or the optimisation
    • G06F2119/06Power analysis or power optimisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Geometry (AREA)
  • Structural Engineering (AREA)
  • Mathematical Optimization (AREA)
  • Mathematical Analysis (AREA)
  • Computational Mathematics (AREA)
  • Pure & Applied Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Data Mining & Analysis (AREA)
  • Mathematical Physics (AREA)
  • Evolutionary Computation (AREA)
  • Algebra (AREA)
  • Databases & Information Systems (AREA)
  • Software Systems (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses vault amount of deflection control methods in a kind of Catenary arch arch springing increasing section strengthening construction, structure basic parameter value is obtained according to design drawing, with catenary line approximate substitution catenary, the amount of deflection of crown section when calculating function unit power at Catenary arch arbitrary section, the reinforcing segment length that is determined by arrangement and method for construction and the side's amount for needing casting concrete calculate vault amount of deflection at this time, and field measurement vault amount of deflection is compared with the amount of deflection for calculating determination;The method is used for constant section catenary fixed arch.Relative to presently the most common FInite Element, the present invention can coordinate scientific calculator real-time control at the construction field (site), has the advantages that the defects of easy to operate and be easily achieved, to overcome that calculate the time caused by the FInite Element generally used now long, parameter affecting laws can not be directly acquired.Meanwhile analytic expression directly reflects the mechanical relationship between vault deflection value and each parameter of structure in the present invention, is conducive to assurance of the engineer to Design of Reinforcement and arrangement and method for construction.

Description

Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction
Technical field
The invention belongs to bridge structure strengthening construction process control fields more particularly to a kind of increase of Catenary arch arch springing to cut Vault amount of deflection control method in the strengthening construction of face.
Background technology
Arch bridge has a long history in China, embodies the standard of construction of Bridges in Our Country.Arch is both structure and building, It is favored by people.China has built large number of arch bridge since the establishment of the nation, however, with the raising of social industrial level, hands over The increase of logical load, and influenced by factors such as the low degenerations with bridge material status of former design standard, that built in the past is very much Arch bridge has become four classes or five class bridges, these bridges urgently rebuild by maintenance and reinforcement or dismounting.From economic benefit angle analysis, for The bridge that can be transformed, the method using maintenance and reinforcement are more preferably to select.
According to《Highway bridge and culvert construction technique normalizing》(JTG/T F50-2011) the 15.13rd trifle content:" Arch Bridge Construction mistake Cheng Shiying carries out process control to it, should ensure that stability, deformation and internal force of the arch structure in construction work are in peace always In gamut.For large span arch bridge, construction process control should be carried out by the regulation of specification;For Medium and small span arch bridge, can adopt The method for taking relative ease easy carries out Construction control ".The maintenance and reinforcement of arch bridge need to equally meet the code requirement, especially Medium and small span arch bridge researches and develops a kind of easy-to-use construction safety control method right and wrong often with there is engineering practical value.
Invention content
The technical problem to be solved in the present invention is to provide a kind of Catenary arch arch springing increases easy to operate, being easily achieved to cut Vault amount of deflection control method in the strengthening construction of face, to ensure arch bridge in carrying out arch springing increasing section construction structure safety with And determine rational strengthening construction scheme.
In order to solve the above technical problems, the present invention uses following technical scheme:
Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction obtains structure base according to design drawing This parameter value, with catenary line approximate substitution catenary, the amount of deflection of crown section when calculating function unit power at Catenary arch section x V (x), the reinforcing segment length n determined by arrangement and method for construction and the side amount V of casting concrete is needed to calculate vault amount of deflection at this time, will showed Field actual measurement vault amount of deflection is compared with determining amount of deflection is calculated;The method is used for constant section catenary fixed arch.
Vault amount of deflection control method in above-mentioned Catenary arch arch springing increasing section strengthening construction, includes the following steps:
The first step obtains structure basic parameter value, including across footpath l, rise f, arch axis coefficient m, catenary by design drawing Equation variable k, arch elastic modulus E and arch section bending resistance the moment of inertia I;
Second step obtains the arch constant a of equivalent catenary line with catenary line approximate substitution catenary using dichotomy;
Third walks, and is x-axis along span of arch diameter direction using vault as origin (0,0), and rise direction is that v axis establishes coordinate system, Obtain under this coordinate system at the x of Catenary arch section vault amount of deflection v (x) when function unit power;
4th step is determined by arrangement and method for construction when arch springing uses Enlargement of Section strengthening construction and reinforces segment length n and need to pour The side amount V for building concrete determines that the amount of deflection h, V of vault at this time are that total side of both sides concreting measures, i.e., in [- l/2 ,-l/2+ N] and [l/2-n, l/2] range in effect vertical uniform load γ V/2n, γ be the unit weight of concrete;
5th step shows through field measurement vault amount of deflection if actual measurement amount of deflection, which is less than in the 4th step, calculates determining amount of deflection Arch deformation is in the controllable state of safety always during arch springing casting concrete, otherwise, is in uncontrollable state.
Vault amount of deflection v (x) is calculated as follows:
V (x)=f (x)-k1f1(x)-k2f2(x)-k3f3(x)
In formula:
k1=c111
k2=c222
k3=c333
The amount of deflection h of vault is calculated as follows:
For in existing Catenary arch arch springing increasing section strengthening construction vault amount of deflection control there are the problem of, inventor builds Vault amount of deflection control method in a kind of Catenary arch arch springing increasing section strengthening construction has been found, structure base is obtained according to design drawing This parameter value, with catenary line approximate substitution catenary, the amount of deflection of crown section when calculating function unit power at Catenary arch section x V (x), the reinforcing segment length n determined by arrangement and method for construction and the side amount V of casting concrete is needed to calculate vault amount of deflection at this time, will showed Field actual measurement vault amount of deflection is compared with determining amount of deflection is calculated;The method is used for constant section catenary fixed arch.Relative to current The most commonly used FInite Element, the present invention have the advantages that it is easy to operate and be easily achieved, can be by means of scientific calculator Scene obtains the size of the vault amount of deflection under different concreting side's amounts, and obtains influence of the structural parameters to vault amount of deflection Rule, whether quickly and accurately assess arch deformation in arch springing increase strengthened section construction can really realize reality in safe range When control on the spot avoid causing permanent damage to structure convenient for pinpointing the problems and solving the problems, such as in time at the scene.It overcomes It is long to calculate the time caused by the FInite Element that generally uses now, the defects of can not directly acquiring parameter affecting laws.Meanwhile Analytic expression directly reflects the mechanical relationship between vault deflection value and each parameter of structure in the present invention, is conducive to engineer to reinforcing The assurance of design and construction scheme.
Description of the drawings
Fig. 1 is the method for the present invention flow chart.
Fig. 2 is the calculation flow chart of the catenary line arch constant a of equivalent substitution catenary.
The calculating schematic diagram of vault amount of deflection when Fig. 3 is function unit power at the x of catenary ream less arch section.
The calculating schematic diagram of vault amount of deflection when Fig. 4 is catenary ream less arch arch springing increasing section strengthening construction.
Specific implementation mode
Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction, the method for constant section catenary without Hinged arch specifically includes following steps:
The first step obtains structure basic parameter value, including across footpath l, rise f, arch axis coefficient m, catenary by design drawing Equation variable k, arch elastic modulus E and arch section bending resistance the moment of inertia I;
Second step obtains the arch constant a of equivalent catenary line with catenary line approximate substitution catenary using dichotomy;
Third walks, and is x-axis (to the left for just) along span of arch diameter direction using vault as origin (0,0), rise direction is v axis (downwards for just) establishes coordinate system, obtains under this coordinate system at the x of Catenary arch section vault amount of deflection v (x) when function unit power;
Vault amount of deflection v (x) is calculated as follows:
V (x)=f (x)-k1f1(x)-k2f2(x)-k3f3(x)
In formula:
k1=c111
k2=c222
k3=c333
4th step is determined by arrangement and method for construction when arch springing uses Enlargement of Section strengthening construction and reinforces segment length n (in x-axis Projected length) and need casting concrete side amount V (both sides arch springing concrete symmetrically pours, V be both sides concreting it is total Side's amount), i.e., (γ is concrete to effect vertical uniform load γ V/2n in [- l/2 ,-l/2+n] and [l/2-n, l/2] range Unit weight), and determine the amount of deflection h of vault at this time;
The amount of deflection h of vault is calculated as follows:
5th step shows through field measurement vault amount of deflection if actual measurement amount of deflection, which is less than in the 4th step, calculates determining amount of deflection Arch deformation is in the controllable state of safety always during arch springing casting concrete, otherwise, is in uncontrollable state, need to stop It only constructs, analyzes and find out reason, should take safety measures or adjust when necessary concreting process.
The above method is also applicable for variable cross-section catenary ream less arch, and only cross sectional moment of inertia I is the function of x.
For ease of understanding, it is elaborated below for crucial second step, third step and the 4th step.
For Catenary arch, because the integral along its arch does not have explicit expression, see formula (1), thus in deformation or Generally use straight line, circular arc line or catenary line carry out approximate substitution catenary when the calculating such as internal force, and the integral of these curve of approximation is equal With compact expression, formula (2)~formula (4) is seen respectively
sDs=x (2)
sDs=sinh (x/a)/a (4)
In formula (1)~formula (4), s is arch path of integration;F (x) is integrand;X is that coordinate origin is located at vault Coordinate along across footpath direction;L is across footpath;F is rise;M is the arch axis coefficient of Catenary arch;K is catenary equation variable,R is the radius of skene arch;A is catenary line arch parameter.
Relative to straight line and circular arc line, catenary line is then closer to catenary, and therefore, the present invention is approximate using catenary line Substitute catenary.Using vault as under the coordinate system of origin, catenary line equation is:
As long as adjusting parameter a so that the curve newly built and former arch axis curve are close as possible, then along Catenary arch axis Integral can be obtained the higher Approximate Explicit Solution of precision.The solution of parameter a can utilize dichotomy.According to Catenary arch perimeter strip Part has been apparent from following formula establishment:
Equation can be obtained as a result,
The value that parameter a can be obtained in formula (7) is solved using dichotomy, flow chart is shown in attached drawing 2.For convenience, unit across footpath is listed Under the corresponding a values of common ratio of rise to span, refer to table 1.
The value of the corresponding parameter a of common ratio of rise to span under 1 unit across footpath of table
Ratio of rise to span 1/3 1/4 1/5 1/6 1/7 1/8 1/9 1/10
a 0.421166 0.537160 0.655863 0.776289 0.897848 1.020178 1.143053 1.266324
On the basis of encircleing equivalent substitution Catenary arch with catenary line, when deriving function unit power at Catenary arch section x The Deflection Formula of crown section:
(1) thinking is calculated
Deflection line is solved using static(al) method, unit force P is acted at arbitrary section b, crown section is solved and scratches Degree influences line.According to elastic center method, fixed arch under unit force effect is converted to the statically determinate structure of redundant force, such as attached drawing 3 Shown, catenary equation y=f [cosh (2xk/l) -1]/(m-1), arch section bending stiffness is EI,For arch axis tangent line and level Wire clamp angle, redundant force include moment of flexure x1, axle power x2, shear x3, elastic center is y away from vault distances.To seek crown section amount of deflection, Illusory load need to be acted in the position, and internal force of the basic structure under all load actions is listed in table 2.
Basic structure internal force under 2 all load actions of table
(2) redundant force calculates
By basic mechanical principle, finds out basic structure (attached drawing 3) redundant force under unit force effect and be to solve for before encircleing amount of deflection It carries.Catenary, the simplification integrated to curve according to formula (4) are substituted with catenary line, it can be deduced that redundant force influences line computation formula, Solution procedure and formula are listed in table 3.
3 redundant force of table calculates
Note:Δ1p、Δ2p、Δ3pTo act on left half across pushing away card by unit force, when unit force act on right half across when, Δ1pAnd Δ2pStill take left half across respective value, Δ3pIt takes corresponding left partly across -1 times of value.
(3) solution of vault deflection value
Such as attached drawing 3, the amount of deflection Δ of O points when basic structure B point function unit power and redundant forceOFor:
ΔOOp+x1ΔO1+x2ΔO2+x3ΔO3 (8)
Each meaning of parameters and calculation formula are listed in table 4 in formula (8).
The calculating of 4 vault amount of deflection of table
By formula (8), table 3 and table 4, the amount of deflection v (x) of crown section is when obtaining function unit power at the x of Catenary arch section:
V (x)=f (x)-k1f1(x)-k2f2(x)-k3f3(x) (9)
In formula:
k1=c111 (14)
k2=c222 (15)
k3=c333 (16)
Wherein, coefficient k1、k2And k3Each parameter value in calculating formula is calculated by following formula:
(4) Example Verification
Divide by taking 2 constant section catenary fixed arch as an example for the vault amount of deflection calculating formula accuracy that the verification present invention derives Not Cai Yong FInite Element and the method for the present invention calculate, and judge that formula of the present invention calculates mistake on the basis of Finite element analysis results Difference.
Example 1, span of arch diameter 117.5m, rise 22.158m, arch axis coefficient 1.347, section bending stiffness 9552.1994kNm2, function unit concentrated force (1kN) on arch;Example 2, arch axis coefficient 2.240, other parameters are the same as example 1.This Invention formula calculates and FEM calculation crown section deflection value comparative situation is listed in table 5.
52 example exemplary value contrast tables of table
Note:Amount of deflection is upwards for just, downward is negative in table.
As can be seen from Table 5, formula calculating of the present invention is differed with Finite element analysis results maximum is no more than 3.60%, verification Formula of the present invention calculates the accuracy of constant section catenary fixed arch crown section amount of deflection.On this basis, by attached drawing 4, root According to arrangement and method for construction, casting concrete side's amount is V in [- l/2 ,-l/2+n] and [l/2-n, l/2] range, that is, applies evenly load When γ V/2n, the amount of deflection h of vault is:

Claims (4)

1. vault amount of deflection control method in a kind of Catenary arch arch springing increasing section strengthening construction, it is characterised in that according to design drawing Paper obtains structure basic parameter value, with catenary line approximate substitution catenary, encircles when calculating function unit power at Catenary arch section x The amount of deflection v (x) of top section, the reinforcing segment length n determined by arrangement and method for construction and the side amount V of casting concrete is needed to calculate arch at this time Amount of deflection is pushed up, field measurement vault amount of deflection is compared with determining amount of deflection is calculated;The method is used for constant section catenary fixed arch.
2. vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction according to claim 1, special Sign is to include the following steps:
The first step obtains structure basic parameter value, including across footpath l, rise f, arch axis coefficient m, catenary equation by design drawing Variable k, arch elastic modulus E and arch section bending resistance the moment of inertia I;
Second step obtains the arch constant a of equivalent catenary line with catenary line approximate substitution catenary using dichotomy;
Third walks, and is x-axis along span of arch diameter direction using vault as origin (0,0), rise direction is that v axis establishes coordinate system, is obtained Vault amount of deflection v (x) when function unit power at the x of Catenary arch section under this coordinate system;
4th step is determined by arrangement and method for construction when arch springing uses Enlargement of Section strengthening construction and reinforces segment length n and need to pour mixed The side amount V of solidifying soil determines that the amount of deflection h, V of vault at this time are that total side of both sides concreting measures, i.e., at [- l/2 ,-l/2+n] and Effect vertical uniform load γ V/2n in [l/2-n, l/2] range, γ are the unit weight of concrete;
5th step shows encircleing through field measurement vault amount of deflection if actual measurement amount of deflection, which is less than in the 4th step, calculates determining amount of deflection Arch deformation is in the controllable state of safety always during foot casting concrete, otherwise, is in uncontrollable state.
3. vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction according to claim 2, special Sign is that vault amount of deflection v (x) is calculated as follows:
V (x)=f (x)-k1f1(x)-k2f2(x)-k3f3(x)
In formula:
k1=c111
k2=c222
k3=c333
4. vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction according to claim 2, special Sign is that the amount of deflection h of vault is calculated as follows:
CN201810138842.1A 2018-02-09 2018-02-09 Method for controlling arch crown deflection in reinforcing construction of increasing section of catenary arch springing Active CN108411797B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810138842.1A CN108411797B (en) 2018-02-09 2018-02-09 Method for controlling arch crown deflection in reinforcing construction of increasing section of catenary arch springing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810138842.1A CN108411797B (en) 2018-02-09 2018-02-09 Method for controlling arch crown deflection in reinforcing construction of increasing section of catenary arch springing

Publications (2)

Publication Number Publication Date
CN108411797A true CN108411797A (en) 2018-08-17
CN108411797B CN108411797B (en) 2020-07-31

Family

ID=63127197

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810138842.1A Active CN108411797B (en) 2018-02-09 2018-02-09 Method for controlling arch crown deflection in reinforcing construction of increasing section of catenary arch springing

Country Status (1)

Country Link
CN (1) CN108411797B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371804A (en) * 2018-09-22 2019-02-22 胡常福 A kind of empty stomach Deck Arch Bridges optimal distance and its determining method
CN110387806A (en) * 2019-07-31 2019-10-29 中交路桥北方工程有限公司 A kind of restressed beam slab deflection deformation control method
CN111041969A (en) * 2019-12-31 2020-04-21 深圳市桥博设计研究院有限公司 Large-span combined arch bridge based on bending design theory and design and construction method
CN112560321A (en) * 2020-12-29 2021-03-26 重庆交通大学 Calculation method for ring-divided segmented pouring length of concrete wrapped outside arch ring of stiffened framework concrete arch bridge

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005071266A (en) * 2003-08-27 2005-03-17 Chuo Fukken Consultants Co Ltd Structure maintenance support method using performance update model, and structure maintenance support apparatus using performance update model
CN101525108A (en) * 2009-03-18 2009-09-09 上海三一科技有限公司 Method and device for reducing over-high deflection in amplitude changing process of caterpillar-band crane arm support
CN103821080A (en) * 2014-02-24 2014-05-28 南阳理工学院 Girder deflection control device of simply supported girder bridge
CN105040904A (en) * 2015-07-13 2015-11-11 涂建维 Method for designing fiber reinforce plastic (FRP) reinforced concrete beam for controlling crack width and deflection
CN205188792U (en) * 2015-07-29 2016-04-27 广西交通科学研究院 Prefabricated internal prestressing force steel and concrete composite simply supported girder bridge of assembling of fish belly wave form steel web
CN205228391U (en) * 2015-12-24 2016-05-11 成都上甲光电科技有限公司 Bridge amount of deflection monitoring system based on visible light imaging technique
CN205421992U (en) * 2016-03-02 2016-08-03 叶香雄 Floor reinforced structure that bearing capacity is not enough
CN205618058U (en) * 2016-03-21 2016-10-05 深圳广田装饰集团股份有限公司 Building grid deflection control structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005071266A (en) * 2003-08-27 2005-03-17 Chuo Fukken Consultants Co Ltd Structure maintenance support method using performance update model, and structure maintenance support apparatus using performance update model
CN101525108A (en) * 2009-03-18 2009-09-09 上海三一科技有限公司 Method and device for reducing over-high deflection in amplitude changing process of caterpillar-band crane arm support
CN103821080A (en) * 2014-02-24 2014-05-28 南阳理工学院 Girder deflection control device of simply supported girder bridge
CN105040904A (en) * 2015-07-13 2015-11-11 涂建维 Method for designing fiber reinforce plastic (FRP) reinforced concrete beam for controlling crack width and deflection
CN205188792U (en) * 2015-07-29 2016-04-27 广西交通科学研究院 Prefabricated internal prestressing force steel and concrete composite simply supported girder bridge of assembling of fish belly wave form steel web
CN205228391U (en) * 2015-12-24 2016-05-11 成都上甲光电科技有限公司 Bridge amount of deflection monitoring system based on visible light imaging technique
CN205421992U (en) * 2016-03-02 2016-08-03 叶香雄 Floor reinforced structure that bearing capacity is not enough
CN205618058U (en) * 2016-03-21 2016-10-05 深圳广田装饰集团股份有限公司 Building grid deflection control structure

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371804A (en) * 2018-09-22 2019-02-22 胡常福 A kind of empty stomach Deck Arch Bridges optimal distance and its determining method
CN110387806A (en) * 2019-07-31 2019-10-29 中交路桥北方工程有限公司 A kind of restressed beam slab deflection deformation control method
CN111041969A (en) * 2019-12-31 2020-04-21 深圳市桥博设计研究院有限公司 Large-span combined arch bridge based on bending design theory and design and construction method
CN111041969B (en) * 2019-12-31 2021-11-26 深圳市桥博设计研究院有限公司 Large-span combined arch bridge based on bending design theory and design and construction method
CN112560321A (en) * 2020-12-29 2021-03-26 重庆交通大学 Calculation method for ring-divided segmented pouring length of concrete wrapped outside arch ring of stiffened framework concrete arch bridge

Also Published As

Publication number Publication date
CN108411797B (en) 2020-07-31

Similar Documents

Publication Publication Date Title
CN108411797A (en) Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction
CA2679645C (en) A method and machine for the lowering of a track
CN110502855B (en) Method for identifying damage of uniform-section continuous beam with support reaction influence line curvature
CN108416116A (en) Vault ballast method for determination of amount when arch springing increasing section reinforces parabolic arch
CN203229865U (en) Clamping-groove type bridge pier shaft steel bar positioning device
CN107014541B (en) Based on the modified grade generation hinged beam model cable force measurement method of linear model
CN108460197A (en) Spandrel construction based on deformation amount controlling dismounts Scheme Optimum Seeking Methods
CN105184393A (en) Auxiliary path restoration method under complex path
CN109214099B (en) Arch rib steel pipe positioning and construction method
CN111337212A (en) Method for measuring maximum deflection of simply supported beam based on corner under unknown state
CN108089938A (en) Method for processing abnormal data and device
CN101555961A (en) Construction method of arch pipeline support and hanger laser positioning
CN107908879A (en) A kind of concrete beam bridge fatigue behaviour appraisal procedure
CN108487087A (en) Vault ballast water volume in water tank real-time control method when arch springing is reinforced
CN208456625U (en) A kind of tunnel lining trolley automatic measurement regulating device
CN104999061B (en) Constant-volume casting control method and system for tilting type casting machine
CN108487088A (en) Catenary arch spandrel construction rationally dismounts process and determines method
DE102015008113A1 (en) Manufacturing device and manufacturing method for producing a less unbalanced fan blade
CN108894120A (en) Arch ring transformation safe judgment method in spandrel construction disassembly process
CN108505432B (en) Evaluation method without diaphragm plate concrete hollow tall pier and thin wall
Miller A method for the determination of converging factors, applied to the asymptotic expansions for the parabolic cylinder functions
CN109930456B (en) Method for determining reinforcement rate control index of double-layer continuous reinforced concrete pavement
CN204679016U (en) Stirrup spacing survey instrument
Relf LIV. An electrical method for tracing stream lines in the two-dimensional motion of a perfect fluid
CN206289475U (en) CRTSI type ballastless track bed board template elevation calibration controllers

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant