CN205618058U - A building grid deflection control structure - Google Patents

A building grid deflection control structure Download PDF

Info

Publication number
CN205618058U
CN205618058U CN201620213023.5U CN201620213023U CN205618058U CN 205618058 U CN205618058 U CN 205618058U CN 201620213023 U CN201620213023 U CN 201620213023U CN 205618058 U CN205618058 U CN 205618058U
Authority
CN
China
Prior art keywords
grid
control structure
deflection control
hanger
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201620213023.5U
Other languages
Chinese (zh)
Inventor
沈尧
赵晓晖
方志仁
柳林
杨洪春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Grandland Group Co ltd
Original Assignee
Shenzhen Grandland Decoration Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Grandland Decoration Group Co Ltd filed Critical Shenzhen Grandland Decoration Group Co Ltd
Priority to CN201620213023.5U priority Critical patent/CN205618058U/en
Application granted granted Critical
Publication of CN205618058U publication Critical patent/CN205618058U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

The utility model relates to a building grid amount of deflection control structure, including grid frame (1), install a plurality of grids (2) that arrange in proper order on grid frame (1), grid frame (1) is by a set of relative first C type groove (3) and a set of relative second C type groove (4) end to end connection constitution square frame, the both ends of each grid (2) are fixed in on the first C type groove (3) at both ends through first screw (5); the pull cable (6) sequentially penetrates through a through hole (8) matched with each grating (2), and two ends of the pull cable (6) are fixed on second C-shaped grooves (4) at two ends through bolts (9); each grid (2) is clamped between two corresponding hoops (7) on the inhaul cable (6). The utility model has the characteristics of the construction is simple, practice thrift the cost, do not influence pleasing to the eye.

Description

一种建筑物格栅挠度控制结构A building grid deflection control structure

技术领域 technical field

本实用新型涉及建筑装饰领域,尤其是涉及一种建筑物格栅挠度控制结构。 The utility model relates to the field of architectural decoration, in particular to a structure for controlling the deflection of a building grid.

背景技术 Background technique

格栅在建筑施工、设计装潢等领域均有广泛的用途,可用于天花板、墙壁或围篱等结构上,其在装饰及功能上都别具特色。 Gratings are widely used in the fields of construction, design and decoration, and can be used on structures such as ceilings, walls or fences. They are unique in both decoration and function.

如今根据建筑物设计需求,安装格栅的洞口尺寸越来越大,因而所需格栅也越做越长,长宽比越做越大。但格栅长宽比变大后,在格栅自重或竖向风荷载方向的作用下,格栅会承受较大的力,长期承受较大的力容易使格栅产生永久形变,影响美观度。现有技术中,为了防止长条格栅挠度不足,施工人员采用将格栅打断后,在格栅上增加强筋,以减少格栅形变,但此方法施工较复杂,且影响格栅的美观装饰效果;另外,有的解决方法是将格栅本身的尺寸进行加宽加厚处理,以增强其自身的抗形变能力,但此方法会增加材料用量,从而增加成本。 Nowadays, according to the design requirements of buildings, the size of the opening for installing the grille is getting larger and larger, so the required grille is getting longer and longer, and the aspect ratio is getting bigger and bigger. However, when the aspect ratio of the grid becomes larger, the grid will bear a large force under the action of the grid's own weight or the direction of the vertical wind load. Long-term exposure to a large force will easily cause permanent deformation of the grid and affect the aesthetics. . In the prior art, in order to prevent the insufficient deflection of the long grid, the construction personnel interrupted the grid and added strong ribs to the grid to reduce the deformation of the grid, but this method is more complicated to construct and affects the stability of the grid. Beautiful decorative effect; In addition, some solutions are to widen and thicken the size of the grid itself to enhance its own resistance to deformation, but this method will increase the amount of materials and thus increase the cost.

实用新型内容 Utility model content

本实用新型要解决的技术问题是提供一种建筑物格栅挠度控制结构,具有施工简单、节约成本、不影响美观的特点。 The technical problem to be solved by the utility model is to provide a building grid deflection control structure, which has the characteristics of simple construction, cost saving and no influence on the appearance.

为了解决上述技术问题,本实用新型提供一种建筑物格栅挠度控制结构,包括格栅外框、安装于格栅外框上的依次排列的若干格栅,所述格栅外 框为由一组相对的第一C型槽和一组相对的第二C型槽首尾连接组成的方框,每条所述格栅的两端通过第一螺钉固定于两端的第一C型槽上;还包括拉索和若干定位用卡箍,所述拉索依次穿过每条格栅上适配的通孔,所述拉索的两端通过螺栓固定于两端的第二C型槽上;每条所述格栅(2)卡置于所述拉索上的对应两个卡箍之间。 In order to solve the above technical problems, the utility model provides a building grid deflection control structure, which includes a grid frame and a number of grids arranged in sequence installed on the grid frame. The grid frame is composed of a A set of opposite first C-shaped slots and a set of opposite second C-shaped slots are connected end-to-end to form a square frame, and the two ends of each grid are fixed on the first C-shaped slots at both ends by first screws; It includes a cable and a number of clamps for positioning, the cable passes through the through holes adapted on each grid in turn, and the two ends of the cable are fixed on the second C-shaped grooves at both ends by bolts; each The grid (2) is clamped between two corresponding clips on the cable.

作为优选方式,所述格栅与卡箍的中间垫有开口软垫片。 As a preferred manner, an open soft gasket is placed between the grille and the clamp.

作为优选方式,所述软垫片是防腐材料所制。 As a preferred manner, the soft gasket is made of anti-corrosion material.

作为优选方式,所述通孔位于格栅的中间或侧边。 As a preferred manner, the through holes are located in the middle or side of the grid.

作为优选方式,所述拉索是可承力的钢拉索。 As a preferred manner, the stay cables are load-bearing steel stay cables.

作为优选方式,所述通孔或拉索的数量为一条或多条。 As a preferred manner, the number of said through holes or cables is one or more.

作为优选方式,两条所述第一C型槽的和两条所述第二C型槽的开口端卡扣于相应的适配的第一挂架和第二挂架上,所述第一挂架和第二挂架通过第二螺钉固定在基体的相应面上。 As a preferred manner, the opening ends of the two first C-shaped slots and the two second C-shaped slots are buckled on the corresponding adapted first hanger and second hanger, and the first The hanger and the second hanger are fixed on corresponding surfaces of the base body by second screws.

作为优选方式,所述第一C型槽和所述第二C型槽是铝材料制。 As a preferred manner, the first C-shaped groove and the second C-shaped groove are made of aluminum material.

作为优选方式,所述第一挂架和所述第二挂架的周围填装有用于加固和防水的岩浆。 As a preferred manner, the surroundings of the first hanger and the second hanger are filled with magma for reinforcement and waterproofing.

本实用新型涉及一种建筑物格栅挠度控制结构,与现有设计相比,其优点在于:首先,在格栅上设置通孔,并在通孔中穿入拉索,通过格栅上下两面的定位卡箍将格栅固定于拉索上合适的位置,拉索分担了部分格栅自重和风荷载的作用力,从而控制了格栅挠度,既不影响格栅整体的美观,又施工简单,节约成本。 The utility model relates to a building grid deflection control structure. Compared with the existing design, the utility model has the following advantages: firstly, a through hole is arranged on the grid, and a cable is inserted into the through hole to pass through the upper and lower sides of the grid. The positioning clamps fix the grille at a suitable position on the cable, and the cable shares part of the grille’s own weight and the force of the wind load, thereby controlling the deflection of the grille, which does not affect the overall appearance of the grille and is easy to construct. save costs.

进一步地,在卡箍和格栅之间垫有开口软垫片,在卡箍固定格栅的前提下避免了卡箍对格栅的磨损,增加了格栅的使用寿命,当开口软垫片磨损严 重时,从开口软垫片的开口处接口直接拆下,方便更换,特定环境下,开口软垫片采用防腐材料制成,防止其被腐蚀。格栅上通孔位置可以在中间或其它有效位置,灵活性强;拉索采用钢拉索,由于钢拉索硬度可靠,做成较小的尺寸也可以满足受力要求,从而不影响整体格栅的美观;为了更好地控制格栅的挠度,可以在格栅上开始多个通孔和使用多条拉索。格栅外框采用常规的铝制方通,取材方便。 Further, a soft opening gasket is placed between the clamp and the grid, which avoids the wear of the clamp on the grid under the premise that the clamp fixes the grid, and increases the service life of the grid. When the soft opening gasket When the wear is serious, it can be directly removed from the opening of the opening soft gasket for easy replacement. Under certain circumstances, the opening soft gasket is made of anti-corrosion materials to prevent it from being corroded. The position of the through hole on the grid can be in the middle or other effective positions, and the flexibility is strong; the steel cable is used for the cable, and because the hardness of the steel cable is reliable, it can be made into a smaller size to meet the force requirements, so as not to affect the overall grid. The aesthetics of the grid; in order to better control the deflection of the grid, it is possible to start multiple holes and use multiple cables on the grid. The grille frame is made of conventional aluminum square, which is easy to obtain.

附图说明 Description of drawings

图1为本实用新型建筑物格栅挠度控制结构纵向截面示意图。 Fig. 1 is a schematic diagram of a longitudinal section of a building grid deflection control structure of the present invention.

图2为本实用新型建筑物格栅挠度控制结构横向截面示意图。 Fig. 2 is a schematic cross-sectional view of the grid deflection control structure of the utility model.

图3为本实用新型建筑物格栅挠度控制结构局部放大图。 Fig. 3 is a partially enlarged view of the grid deflection control structure of the utility model.

图4为本实用新型建筑物格栅挠度控制结构中卡箍的截面示意图。 Fig. 4 is a schematic cross-sectional view of the hoop in the grid deflection control structure of the utility model.

图5为本实用新型建筑物格栅挠度控制结构中软垫片示意图。 Fig. 5 is a schematic diagram of the soft gasket in the grid deflection control structure of the utility model.

附图标记如下: The reference signs are as follows:

1-格栅外框、2-格栅、3-第一C型槽、4-第二C型槽、5-第一螺钉、6-拉索、7-卡箍、8-通孔、9-螺栓、10-软垫片、11-第一挂架、12-第二挂架、13-第二螺钉13、14-基体。 1-Grille frame, 2-Grille, 3-First C-shaped slot, 4-Second C-shaped slot, 5-First screw, 6-Layer cable, 7-Clamp, 8-Through hole, 9 -bolt, 10-soft gasket, 11-first hanger, 12-second hanger, 13-second screw 13, 14-substrate.

具体实施方式 detailed description

如图1-2所示,本实用新型涉及一种建筑物格栅挠度控制结构,包括由一组相对的第一C型槽3和一组相对的第二C型槽4首尾连接组成的格栅外框1、安装于格栅外框1上的依次排列的若干格栅2、穿过格栅通孔8的拉索6和若干用于定位格栅的卡箍7。 As shown in Figure 1-2, the utility model relates to a building grid deflection control structure, which includes a grid consisting of a set of opposite first C-shaped grooves 3 and a set of opposite second C-shaped grooves 4 connected end to end. The grille frame 1, several grilles 2 arranged in sequence installed on the grille frame 1, the cables 6 passing through the grille through holes 8, and several hoops 7 for positioning the grilles.

每条格栅2的两端通过第一螺钉5固定于两端的第一C型槽3上,在每条格栅2挠度不够的的中间或其它有效位置,例如格栅2的侧边,开设一个或多个通孔8,相应数量的所述拉索6依次穿过通孔8,从而将若干格栅2穿置于拉索6上,所述拉索6的两端通过螺栓9固定于两端的第二C型槽4上。第一C型槽3和第二C型槽4组成的格栅外框1采用铝制材料,方便取材,经济实用,所组成的格栅外框1的形状可以是方形或菱形或其他形状,以增添装饰效果;拉索6采用钢拉索,强度可靠,采用较小的尺寸即可满足承力要求,不影响美观。 The two ends of each grid 2 are fixed on the first C-shaped groove 3 at both ends by the first screw 5, and in the middle or other effective positions where the deflection of each grid 2 is not enough, such as the side of the grid 2, set One or more through holes 8, the corresponding number of said stay cables 6 pass through the through holes 8 in turn, so as to put several grids 2 on the stay cables 6, and the two ends of the stay cables 6 are fixed on the on the second C-shaped groove 4 at both ends. The grid outer frame 1 composed of the first C-shaped groove 3 and the second C-shaped groove 4 is made of aluminum material, which is convenient to obtain materials, economical and practical, and the shape of the formed grid outer frame 1 can be square or rhombus or other shapes, To increase the decorative effect; the cable 6 is a steel cable with reliable strength, and a smaller size can meet the load-bearing requirements without affecting the appearance.

如图2-5所示,将多个卡箍7套置于拉索6上,使每条格栅2卡于两个卡箍7之间,在卡箍7和格栅2之间插入开口软垫片10,移动卡箍7,使其靠紧开口软垫片10后,拧紧卡箍7上的螺栓,以将格栅2固定在拉索6上合适的位置,拉索6分担了部分格栅2自重和风荷载的作用力,从而控制了格栅2挠度,既不影响格栅整体的美观,又施工简单,节约成本;开口软垫片10可以避免卡箍7对格栅2的直接磨损,并且开口设计方便开口软垫片10的更换,特定环境下,可采用防腐蚀材料制作。 As shown in Figure 2-5, put a plurality of clamps 7 on the cable 6, so that each grid 2 is clamped between two clamps 7, and an opening is inserted between the clamps 7 and the grid 2 Soft gasket 10, move the clamp 7 to make it close to the opening soft gasket 10, then tighten the bolts on the clamp 7 to fix the grid 2 at a suitable position on the cable 6, and the cable 6 shares part of the The self-weight of the grille 2 and the force of the wind load control the deflection of the grille 2, which does not affect the overall appearance of the grille, and is simple in construction and saves costs; Wear and tear, and the opening design facilitates the replacement of the opening soft gasket 10. Under certain circumstances, it can be made of anti-corrosion materials.

如图1-2所示,两条第一C型槽3的和两条第二C型槽4的开口端适配地卡扣于相应的第一挂架11和第二挂架12上,所述第一挂架11和第二挂架12通过第二螺钉13固定在基体14的相应面上。 As shown in Figure 1-2, the opening ends of the two first C-shaped slots 3 and the two second C-shaped slots 4 are fitly snapped onto the corresponding first hanger 11 and the second hanger 12, The first hanger 11 and the second hanger 12 are fixed on corresponding surfaces of the base 14 by second screws 13 .

在所述第一挂架11和所述第二挂架12的周围填装岩浆,达到加固和防水的作用。 Fill magma around the first hanger 11 and the second hanger 12 to achieve reinforcement and waterproofing.

Claims (9)

1. a building grid amount of deflection control structure, including grid housing (1), the some grids (2) being arranged in order being installed on grid housing (1), described grid housing (1) is to be connected, by the second C-shaped channel (4) that one group of relative first C-shaped channel (3) is relative with a group, the square frame formed from beginning to end, the two ends of every described grid (2) are fixed in first C-shaped channel (3) at two ends by the first screw (5), it is characterized in that: also include drag-line (6) and some location clip (7), described drag-line (6) sequentially passes through the upper adaptive through hole (8) of every bar grating (2), the two ends of described drag-line (6) are fixed in second C-shaped channel (4) at two ends by bolt (9);Between two clips (7) of correspondence that every described grid (2) is placed on described drag-line (6).
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described grid (2) is lined with opening cushion film (10) with the centre of clip (7).
A kind of building grid amount of deflection control structure the most according to claim 2, it is characterised in that: described cushion film (10) is that anti-corrosion material is made.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described through hole (8) is positioned at centre or the side of grid (2).
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: described drag-line (6) is can the steel cable of load.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterised in that: the quantity of described through hole (8) or drag-line (6) is one or more.
A kind of building grid amount of deflection control structure the most according to claim 1, it is characterized in that: the opening with two described second C-shaped channel (4) of two described first C-shaped channel (3) is snapped on corresponding adaptive the first hanger (11) and the second hanger (12), and described first hanger (11) and the second hanger (12) are fixed in the respective face of matrix (14) by the second screw (13).
A kind of building grid amount of deflection control structure the most according to claim 1 and 2, it is characterised in that: described first C-shaped channel (3) and described second C-shaped channel (4) they are aluminum systems.
A kind of building grid amount of deflection control structure the most according to claim 7, it is characterised in that: the surrounding of described first hanger (11) and described second hanger (12) is filled with for reinforcing and waterproof magma.
CN201620213023.5U 2016-03-21 2016-03-21 A building grid deflection control structure Expired - Lifetime CN205618058U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620213023.5U CN205618058U (en) 2016-03-21 2016-03-21 A building grid deflection control structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620213023.5U CN205618058U (en) 2016-03-21 2016-03-21 A building grid deflection control structure

Publications (1)

Publication Number Publication Date
CN205618058U true CN205618058U (en) 2016-10-05

Family

ID=57031033

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620213023.5U Expired - Lifetime CN205618058U (en) 2016-03-21 2016-03-21 A building grid deflection control structure

Country Status (1)

Country Link
CN (1) CN205618058U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411797A (en) * 2018-02-09 2018-08-17 广西交通科学研究院有限公司 Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108411797A (en) * 2018-02-09 2018-08-17 广西交通科学研究院有限公司 Vault amount of deflection control method in Catenary arch arch springing increasing section strengthening construction

Similar Documents

Publication Publication Date Title
CN106969208A (en) A kind of gate antidetonation suspension and support
CN211143452U (en) An assembled ceiling structure
CN106838467A (en) A kind of suspension rod and fastener for being applied to antidetonation suspension and support
CN205618058U (en) A building grid deflection control structure
CN113530071A (en) Assembled letter hangs furred ceiling mounting structure
KR102399727B1 (en) the slab reinforcement equipment for noise between floors and the slab structure using the same
CN108104335A (en) A kind of cladding system of the assembled flexible of curtain wall
CN203605170U (en) Lamp installing suspension cable hooking clamp
CN213897510U (en) Cable membrane butt-joint tensioning structure and large-span cable membrane storage space
CN206555564U (en) A kind of suspension rod and fastener applied to antidetonation suspension and support
WO2010001478A1 (en) Fence
CN211007176U (en) Anti-seismic shear wall
CN208856818U (en) A tower crane anchoring device
JP5925098B2 (en) Seismic ceiling structure
CN215888880U (en) Assembled letter hangs furred ceiling mounting structure
CN205791306U (en) Cable testing bridge heavy duty suspension bracket
CN214941960U (en) Stone installation device for building outer wall
KR102532942B1 (en) Finishing material for a ceiling of building
CN109025079A (en) A new type of safety protection structure for alloy roof
KR102247640B1 (en) Anti-seismic reinforcing structure for preventing collapse of a masonry wall and a finishing structure for preventing collapse of the masonry wall having the same
KR20120111825A (en) Fixing device of lightweight steel for underground double wall
CN209816864U (en) Prestressed I-shaped supporting pile
CN209163149U (en) Curtain wall installs system
CN106088514A (en) A kind of stone material dry suspending slabstone fixed structure with high anti-seismic function
KR20030077050A (en) House framing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee after: SHENZHEN GRANDLAND GROUP Co.,Ltd.

Address before: 518000 Guangdong, Shenzhen, Luohu District, Yanhe Road 1003, Beijing capital east 1~2 level.

Patentee before: SHENZHEN GRANDLAND DECORATION GROUP Co.,Ltd.

CP01 Change in the name or title of a patent holder
CX01 Expiry of patent term

Granted publication date: 20161005

CX01 Expiry of patent term