CN108396871A - The assembled toilet and its installation method being easily installed - Google Patents
The assembled toilet and its installation method being easily installed Download PDFInfo
- Publication number
- CN108396871A CN108396871A CN201810460719.1A CN201810460719A CN108396871A CN 108396871 A CN108396871 A CN 108396871A CN 201810460719 A CN201810460719 A CN 201810460719A CN 108396871 A CN108396871 A CN 108396871A
- Authority
- CN
- China
- Prior art keywords
- keel
- metope
- waterproof
- riser
- bottom plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 44
- 238000000034 method Methods 0.000 title claims abstract description 15
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 67
- 238000005452 bending Methods 0.000 claims description 44
- 230000007246 mechanism Effects 0.000 claims description 23
- 238000009499 grossing Methods 0.000 claims description 17
- 239000000758 substrate Substances 0.000 claims description 14
- 239000011468 face brick Substances 0.000 claims description 12
- 238000005476 soldering Methods 0.000 claims description 12
- 210000004243 sweat Anatomy 0.000 claims description 12
- 230000005674 electromagnetic induction Effects 0.000 claims description 9
- 238000010438 heat treatment Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 7
- 238000013003 hot bending Methods 0.000 claims description 7
- 239000010959 steel Substances 0.000 claims description 7
- 238000003466 welding Methods 0.000 claims description 6
- 230000005611 electricity Effects 0.000 claims description 5
- 239000003292 glue Substances 0.000 claims description 4
- 229920001903 high density polyethylene Polymers 0.000 claims description 4
- 239000004700 high-density polyethylene Substances 0.000 claims description 4
- 238000007689 inspection Methods 0.000 claims description 3
- 230000002045 lasting effect Effects 0.000 claims description 3
- 239000011465 paving brick Substances 0.000 claims description 3
- 210000000988 bone and bone Anatomy 0.000 claims 2
- 238000010586 diagram Methods 0.000 description 12
- 238000010276 construction Methods 0.000 description 6
- 238000005516 engineering process Methods 0.000 description 4
- 239000012943 hotmelt Substances 0.000 description 3
- 206010037660 Pyrexia Diseases 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- 239000011083 cement mortar Substances 0.000 description 2
- 239000000835 fiber Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 239000003351 stiffener Substances 0.000 description 2
- 206010057855 Hypotelorism of orbit Diseases 0.000 description 1
- 239000004677 Nylon Substances 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 239000000956 alloy Substances 0.000 description 1
- 229910045601 alloy Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 229910003460 diamond Inorganic materials 0.000 description 1
- 239000010432 diamond Substances 0.000 description 1
- 229920006351 engineering plastic Polymers 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 229920001778 nylon Polymers 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/343—Structures characterised by movable, separable, or collapsible parts, e.g. for transport
- E04B1/34315—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
- E04B1/34321—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts mainly constituted by panels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/343—Structures characterised by movable, separable, or collapsible parts, e.g. for transport
- E04B1/34315—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts
- E04B1/34326—Structures characterised by movable, separable, or collapsible parts, e.g. for transport characterised by separable parts mainly constituted by longitudinal elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Sanitary Device For Flush Toilet (AREA)
Abstract
The invention discloses a kind of assembled toilets and its installation method being easily installed, this assembled toilet includes the steelframe being arranged in toilet, flexible water disk, precast floor and co-layer draining pipe, the steelframe is arranged on the upside of toilet earth's surface, the precast floor includes the first precast floor and the second precast floor, first precast floor is fixed on the upside of the keel of steelframe, the flexible water disk is arranged on the upside of the first precast floor, and second precast floor is arranged on the upside of the waterproof bottom plate of flexible water disk;The main pipeline of co-layer draining pipe is fixed on the upside of toilet earth's surface and below keel, and the subtube of co-layer draining pipe sequentially passes through the first precast floor, flexible water disk and the second precast floor from the bottom up and water inlet is located above the second precast floor.This assembled toilet and its installation method improve the installation effectiveness of toilet, reduce the installation difficulty and installation cost of toilet.
Description
Technical field
The present invention relates to assembled architecture technical field, be specifically related to a kind of assembled toilet being easily installed and its
Installation method.
Background technology
It being sharply increased with the continuous development of society with population, assembled builds the mainstream for slowly becoming and building,
In it is most important be house construction, toilet is built an essential part as assembled-type house and is also increasingly received
Concern.In recent years, assembled toilet had obtained significant progress, but the installation and decoration process of existing assembled toilet
Construction technology that is complicated and needing profession, time installation period is long, and therefore, existing assembled toilet has the following problems:
1, installation effectiveness is low;2, installation difficulty is high;3, installation cost is high.
Invention content
For deficiencies of the prior art, it is an object of the invention to propose that a kind of assembled being easily installed is defended
Between life and its installation method, this assembled toilet and its installation method reduce the installation cost and installation difficulty of toilet,
Improve the installation effectiveness of toilet.
For this purpose, technical solution of the present invention is:A kind of flexible water disk, including steelframe, flexible water disk, precast floor and
Co-layer draining pipe, the steelframe, flexible water disk, precast floor and co-layer draining pipe are arranged in toilet;The steel
Frame is arranged on the upside of toilet earth's surface, and steelframe includes keel, vertical supporting frame and cross-brace frame;The keel, which constitute one jiao, to be had
In netted, the vertical supporting frame is used to support keel and adjusts keel height for the rectangular platform of notch and the keel in rectangular platform
Degree, the cross-brace frame are fixed on the keel on four side of rectangular platform to prevent keel from being moved relative to metope;The assembled
Floor includes the first precast floor and the second precast floor, and first precast floor is fixed on the upside of keel;It is described
Flexible water disk is arranged on the upside of the first precast floor, and flexible water disk includes bottom plate and riser, the floor level setting
And it is jaggy rectangular-shaped in one jiao, discharge outlet is provided on bottom plate, the riser is located at around bottom plate, bottom plate and riser one
It is molded and constitutes the case shape of upper opening;Second precast floor is arranged on the upside of the bottom plate of flexible water disk;Same layer
The main pipeline of drainpipe is fixed on the upside of toilet earth's surface and below keel, the subtube of co-layer draining pipe from the bottom up according to
It is secondary to pass through the first precast floor, flexible water disk and the second precast floor and water inlet is located on the second precast floor
Side.
Steelframe, flexible water disk, the first precast floor of this assembled toilet (are used to support flexible water disk, prevent
Only flexible water disk deforms) and the second precast floor be convenient for in-site installation, be not necessarily to cement mortar, it is clean environmentally friendly, not only realize
Co-layer draining, it is easy for construction, it interferes few under upstairs house, improves residence comfort, and also reduce the material of toilet
Cost, installation cost and installation difficulty improve the installation effectiveness of toilet.
Further, second precast floor includes that substrate, positioning net, positioning card and face brick, the positioning net are in
It is rectangular-shaped and be fixed on upper surface of base plate, it is clamped between adjacent positioning net;The positioning card includes the first positioning card and second
Positioning card, first positioning, which fixes, is scheduled on positioning net middle part, and second positioning, which fixes, is scheduled on positioning net four corners, the face
Brick positions card and the locking position of the second positioning by adjacent first and is bonded in positioning on the net.
Further, the vertical supporting frame includes L-shaped spine support frame, main tee supporting rack and cross keel branch
Support, the L-shaped spine support frame, main tee supporting rack and cross spine support frame include bending part, support column and height
Regulating mechanism is spent, the bending part is fixed on the upper head of support column and is bolted with keel, the height adjustment mechanism
The lower end head of support column is fixed on to adjust the vertical supporting height of support column and bending part;The bending part includes being located at L
The L-shaped bending part on shape spine support frame top, positioned at main tee supporting rack top T shapes bending part and be located at cross keel
The cross bending part on supporting rack top, the L-shaped bending part include L-shaped bottom plate and the riser perpendicular to L-shaped bottom plate, L-shaped bottom
Plate and riser collectively form the L-shaped keel link slot of opening upwards, are all provided on the riser of two ends of L-shaped keel link slot
It is equipped with the keel fixing bolt of connection keel;The T shapes bending part includes T shapes bottom plate and the riser perpendicular to T shape bottom plates, T shapes
Bottom plate and riser collectively form the main tee link slot of opening upwards, on the riser of three ends of main tee link slot
It is provided with the keel fixing bolt of connection keel;The cross bending part includes cross bottom plate and perpendicular to cross bottom plate
Riser, cross bottom plate and riser collectively form the cross keel link slot of opening upwards, close to cross keel connection
The keel fixing bolt of connection keel is both provided on the riser of four ends of slot.
Further, the height adjustment mechanism include height fixing nut, height adjusting pads piece, height locking nut and
Height adjustment bolt, the height fixing nut are fixedly connected with support column lower end head, the height adjusting pads piece and height
Locking nut is successively set on the downside of height fixing nut, and the height adjustment bolt includes head and threaded portion, and height is adjusted
The threaded portion of bolt sequentially passes through height locking nut, height adjusting pads piece and height fixing nut, the height from the bottom up
Locking nut and height fixing nut are adapted with the threaded portion of height adjustment bolt.
Further, the cross-brace frame includes wall face supporting beam and metope retaining mechanism, on the wall face supporting beam
Portion is fixedly connected with keel, and the metope retaining mechanism is arranged in the lower part of wall face supporting beam to prevent keel from being moved with respect to metope
It is dynamic;The metope retaining mechanism includes that metope fixing nut, metope adjusting gasket, metope locking nut and metope smooth bolt,
Wall face supporting beam lower part is provided perpendicular to the metope smoothing bolt mounting holes of metope, and the metope fixing nut is fixed on
Metope is smoothed on the wall face supporting beam of the remote metope side of bolt mounting holes, and the metope adjusting gasket and metope locking nut are set successively
Set the nearly metope side that bolt mounting holes are smoothed in metope;The metope smoothing bolt includes head and threaded portion, and metope smooths spiral shell
The threaded portion of bolt sequentially passes through metope locking nut, metope adjusting gasket, metope smoothing bolt mounting holes and metope from outside to inside
The threaded portion that fixing nut, the metope locking nut and metope fixing nut smooth bolt with metope is adapted.
Further, the keel and support column are square tube, and wall face supporting beam is channel steel.
Further, between adjacent riser by inner corner trim electromagnetism joint angle and the thermofussion welding of external corner electromagnetism joint angle in succession
Connect, the inner corner trim electromagnetism joint angle is located at the interior angle side that adjacent two waterproof risers are constituted, inner corner trim electromagnetism joint angle with it is adjacent
Sweat soldering connection on the upside of two waterproof risers and waterproof bottom plate, it is vertical that the external corner electromagnetism joint angle is located at two adjacent waterproofs
The exterior angle side that plate is constituted, external corner electromagnetism joint angle connect with two adjacent waterproof risers and the equal sweat soldering of waterproof baseplate underside
It connects.
Further, the inner corner trim electromagnetism joint angle includes inner corner trim lower connecting plate, inner corner trim upper junction plate and inner corner trim electromagnetic screen
Face, the inner corner trim lower connecting plate are in isosceles right triangle, are connected under the inner corner trim upper junction plate section is L-shaped and lower end and inner corner trim
Two right-angle sides of fishplate bar are fixedly connected with, and the inner corner trim electromagnetism wire side is arranged in the close of inner corner trim lower connecting plate and inner corner trim upper junction plate
Waterproof riser side;The external corner electromagnetism joint angle includes external corner lower connecting plate, external corner upper junction plate and external corner electromagnetism wire side, described
External corner lower connecting plate is in isosceles right triangle, and the external corner upper junction plate section is L-shaped and lower end and external corner lower connecting plate
Two right-angle sides are fixedly connected with, and the external corner electromagnetism wire side is arranged vertical in the nearly waterproof of external corner lower connecting plate and external corner upper junction plate
Plate side.
Further, the waterproof bottom plate, waterproof riser, inner corner trim lower connecting plate, inner corner trim upper junction plate, external corner lower connecting plate
It is all made of HDPE materials with external corner upper junction plate.
A kind of assembled Toilet Installation method is installed using above-described assembled toilet, including as follows
Step:
Step 1, the size for measuring toilet, according to the size precasting steel frame of toilet;
Step 2, it is laid with same-floor drainage pipeline;
Step 3, steelframe is installed, wherein step 3 includes the following steps:Step 3.1, vertical supporting frame is tentatively adjusted to one
A unified height;Step 3.2, keel are connect with vertical supporting frame;Step 3.3, the keel on adjustment rectangular platform four side with
Spacing between metope;Step 3.4, accurate adjustment vertical supporting frame height makes to be located at same level on the upside of keel;Step 3.5, lead to
Cross-brace frame is crossed to lock the spacing between the keel and metope on four side of rectangular platform;
Step 4, the first precast floor is installed;
Step 5, flexible water disk is installed, wherein step 5 includes the following steps:Step 5.1, it is cut out according to the size of toilet
It cuts flexible web and constitutes the original-shape of flexible water disk, the original-shape of flexible water disk is by integrally formed waterproof bottom plate
It is collectively formed with waterproof riser, the shape of waterproof bottom plate is identical as toilet flat shape, and waterproof riser is located at waterproof bottom plate week
It encloses;Step 5.2, by waterproof riser hot bending, waterproof riser and waterproof bottom plate is made to constitute the case shape of upper opening;Step 5.3, exist
External corner electromagnetism joint angle is placed in exterior angle side that is adjacent and needing the two waterproof risers connected to constitute, adjacent and need two connected
Place inner corner trim electromagnetism joint angle in the interior angle side that waterproof riser is constituted;Step 5.4, with fixture by inner corner trim electromagnetism joint angle, it is adjacent simultaneously
It needs the two waterproof risers connected and external corner electromagnetism joint angle while clamping, inner corner trim electromagnetism joint angle is kept to be connected with external corner electromagnetism
There is lasting clamping force between angle;Step 5.5, to inner corner trim electromagnetism joint angle and external corner electromagnetism joint angle, electromagnetic induction adds simultaneously
Heat waits between the inner corner trim electromagnetic screen surface side of inner corner trim electromagnetism joint angle and two adjacent waterproof risers and waterproof bottom plate upside, sun
Equal sweat soldering between the external corner electromagnetic screen surface side of angle electromagnetism joint angle and two adjacent waterproof risers and waterproof baseplate underside
Stop electromagnetic induction heating after connection;Step 5.6, process discharge outlet, make discharge outlet formed with bottom plate be integrally formed and be open to
Under circular ring shape hot bending portion;Step 5.7, discharge outlet is connect with main drainpipe;Step 5.8, flexible water disk is shelved on school
On cushion layer;
Step 6, the second precast floor is installed, wherein step 6 includes the following steps:Step 6.1, installation base plate;Step
6.2, positioning net fixed substrate upper surface will be clamped by installation positioning net between adjacent positioning net;Step 6.3, by glue for tile
It pours into positioning net, strikes off;Step 6.4, the first positioning is connected to positioning net middle part, the second positioning is connected to positioning
Net four corners;Step 6.5, according to the first positioning card and the second positioning locking position paving brick;
Step 7, safety inspection.
Beneficial effects of the present invention:
1, the steelframe of this assembled toilet, flexible water disk and precast floor are convenient for in-site installation, working procedure letter
It is single, material cost, installation cost and the installation difficulty of toilet are reduced, installation effectiveness (this assembled of toilet is improved
Toilet can largely reduce difficulty of construction, largely shorten the construction period the time, and not have technical difficulty or even ordinary people finishing watching
Oneself can have no the assembled toilet of difficulty after bright book, whole dresses of toilet can be completed in the people one day of actual test two
It repaiies).
2, co-layer draining is realized, it is easy for construction, it is interfered less under upstairs house, improves residence comfort;
3, using flexible water disk, cost is reduced while being easily installed;
4, this assembled toilet is not necessarily to cement mortar, clean environmental protection.
Description of the drawings
Fig. 1 is assembled toilet of the present invention structural schematic diagram;
Fig. 2 is the dimensional structure diagram of flexible water disk of the present invention;
Fig. 3 is the schematic top plan view of flexible water disk of the present invention;
Fig. 4 is enlarged drawing at A in Fig. 3;
Fig. 5 is the schematic elevation view of inner corner trim electromagnetism joint angle of the present invention;
Fig. 6 is the vertical view of Fig. 5;
Fig. 7 is the right view of Fig. 5;
Fig. 8 is the schematic elevation view of external corner electromagnetism joint angle of the present invention;
Fig. 9 is the vertical view of Fig. 8;
Figure 10 is the right view of Fig. 8;
Figure 11 is flexible water disk discharge structure schematic diagram of the present invention;
Figure 12 is the original-shape figure of flexible water disk;
Figure 13 is the dimensional structure diagram of steelframe of the present invention;
Figure 14 is the structural schematic diagram of L-shaped spine support frame of the present invention;
Figure 15 is the structural schematic diagram of main tee supporting rack of the present invention;
Figure 16 is the structural schematic diagram of cross spine support frame of the present invention;
Figure 17 is height adjustment mechanism schematic diagram of the present invention;
Figure 18 is metope retaining mechanism schematic diagram of the present invention;
Figure 19 is the structural schematic diagram of precast floor of the present invention;
Figure 20 is the structural schematic diagram of present invention positioning net;
Figure 21 is the structural schematic diagram of the present invention the second positioning card.
In attached drawing:1- flexible water disks;2- steelframes;The second precast floors of 3-;The first precast floors of 4-;5- same layers are arranged
Water pipe;6- main drainpipes;The toilets 7-;
11- waterproof bottom plates;12- waterproof risers;13- inner corner trim electromagnetism joint angles;14- external corner electromagnetism joint angles;15- hot bendings
Line;16- support tubes;17- electrodes heat elbow;21- keel;22- vertical supporting framves;22a-L shape spine support framves;22b-T shapes
Spine support frame;22c- cross spine support framves;23- cross-brace framves;31- substrates;32- positions net;33- face bricks;34-
One positioning card;The positioning cards of 35- second;51- co-layer draining pipe main pipelines;52- co-layer draining pipe subtubes;53- water-proof plates drain
Pipeline;
111- discharge outlet;131- inner corner trim lower connecting plates;132- inner corner trim upper junction plates;133- inner corner trim electromagnetism wire sides;141- sun
Angle lower connecting plate;142- external corner upper junction plates;143- external corner electromagnetism wire sides;211- lateral keels;212- longitudinal keels;221-L
Shape bending part;222-T shape bending parts;223- cross bending parts;224- support columns;225- height adjustment mechanisms;231- metopes
Supporting beam;232- metope retaining mechanisms;The first card holes of 321-;351- support portions;352- limiting sections;
2211-L shape bottom plates;2221-T shape bottom plates;2231- cross bottom plates;2251- height fixing nuts;2252- height
Adjusting gasket;2253- height locking nuts;2254- height adjustment bolts;2321- metope fixing nuts;2322- metopes are adjusted
Gasket;2323- metope locking nuts;2324- metopes smooth bolt.
Specific implementation mode
The invention will be further described with reference to the accompanying drawings and examples:
As shown in Figure 1, a kind of assembled toilet of the present embodiment, has steelframe 2, flexible water disk 1, precast floor
With co-layer draining pipe 5, above-mentioned steelframe 2, flexible water disk 1, precast floor and co-layer draining pipe 5 are arranged in toilet 7.
As shown in Fig. 1 and Figure 13, in the present embodiment, steelframe 2 is arranged on the upside of 7 earth's surface of toilet, and steelframe 2 has keel
21, vertical supporting frame 22 and cross-brace frame 23, wherein keel 21 are constituted in one jiao of rectangular platform jaggy and rectangular platform
Keel 21 be in square grid shape;22 frame of vertical supporting is used to support keel 21 and adjusts 21 height of keel, and cross-brace frame 23 is solid
It is scheduled on the keel 21 on four side of rectangular platform to prevent keel 21 from being moved relative to 7 metope of toilet.In the present embodiment, rectangular platform
One jiao jaggy is to avoid pipeline or structural column, and in practical application, the keel 21 in rectangular platform can also constitute it
The reticular structure of its shape, such as diamond shape or decorative pattern shape.Precast floor is located on rectangular platform, due to rectangular platform supporting surface
Product is big, precast floor is also just unlikely to deform, and leveling rectangular platform is that is, leveling precast floor, 2 leveling of this steelframe
From the artificial leveling in the gap of keel 21 when rectangular platform, leveling difficulty is low.In use, due to precast floor and keel
21 contacts area are big, are not easy to move horizontally after precast floor stress, and 5 leak of drainpipe and accomodation ground will not be caused to shake
It is dynamic.
As shown in Fig. 1 and Figure 13, in the present embodiment, precast floor includes the first precast floor 4 and the second assembled
Floor 3, the first precast floor 4 are fixed on 21 upside of keel;The setting of flexible water disk 1 is in 4 upside of the first precast floor.This
In embodiment, the first precast floor 4 is used to support flexible water disk 1, prevents flexible water disk 1 from deforming, in practical application, the
Fiber cement board may be used in one precast floor 4.
As depicted in figs. 1 and 2, in the present embodiment, flexible water disk 1 includes waterproof bottom plate 11 and waterproof riser 12, waterproof
Bottom plate 11 is horizontally disposed and jaggy rectangular-shaped in one jiao, and discharge outlet 111, waterproof riser 12 are provided on waterproof bottom plate 11
Around waterproof bottom plate 11, waterproof bottom plate 11 and waterproof riser 12 are integrally formed and constitute the case shape of upper opening;Second dress
It is arranged in 11 upside of waterproof bottom plate of flexible water disk 1 with formula floor 3.Specifically, in the present embodiment, 1 notch of flexible water disk
One jiao be to avoid main drainpipe 6 or structural column and be adapted with steelframe 2.
As shown in Fig. 1 and Figure 13, in the present embodiment, co-layer draining pipe main pipeline 51 is fixed on the upside of 7 earth's surface of toilet simultaneously
Positioned at 21 lower section of keel, co-layer draining pipe subtube 52 sequentially passes through the first precast floor 4, flexible water disk 1 from the bottom up
It is located at 3 top of the second precast floor with the second precast floor 3 and water inlet.
As shown in Fig. 1 and Figure 13, in the present embodiment, vertical supporting frame 22 includes L-shaped spine support frame 22a, main tee branch
Support 22b and cross spine support frame 22c, L-shaped spine support frame 22a, main tee supporting rack 22b and cross keel branch
Support 22c includes bending part, support column 224 and height adjustment mechanism 225, and bending part is fixed on the upper end of support column 224
Portion is simultaneously bolted with keel 21, and height adjustment mechanism 225 is fixed on the lower end head of support column 224 to adjust support column 224
With the vertical supporting height of bending part;Cross-brace frame 23 is fixed on the keel 21 on four side of rectangular platform, cross-brace frame 23
Including wall face supporting beam 231 and metope retaining mechanism 232,231 top of wall face supporting beam is fixedly connected with keel 21, metope locking
Mechanism 232 is arranged in the lower part of wall face supporting beam 231 to prevent keel 21 from being moved relative to metope.In the present embodiment, steelframe 2 passes through
Vertical supporting frame 22 adjusts 21 height of keel, and wherein L-shaped spine support frame 22a is mainly used for supporting the keel at rectangular platform angle
21, main tee supporting rack 22b are mainly used for that the keel 21 at rectangular platform side, cross spine support frame 22c is supported mainly to use
Keel 21 inside support rectangular platform.In the present embodiment, two groups of cross are respectively provided on the keel 21 on four side of nearly metope of steelframe 2
To supporting rack 23, keel 21 and metope horizontal distance are adjusted by cross-brace frame 23 and limit keel 21 and is moved, therefore, steelframe
Structure (overhead system) stability is preferable;Specifically, cross-brace frame 23 is arranged quantity and position will according to toilet and
The shape of keel 21 specifically considers, as long as can the effectively horizontal distance between adjustment keel 21 and metope and after adjustment
Prevent keel 21 from moving.In the present embodiment, which up to 40 years or more, and is dismantled by plastic-spraying antirust treatment, long lifespan
It is convenient.
As shown in Figure 13 to Figure 17, in the present embodiment, bending part includes that the L-shaped positioned at the tops L-shaped spine support frame 22a is rolled over
Comer pieces 221, positioned at the T shapes bending part 222 on the tops main tee supporting rack 22b and positioned at the tops cross spine support frame 22c
Cross bending part 223, L-shaped bending part 221 include L-shaped bottom plate 2211 and the riser perpendicular to L-shaped bottom plate 2211, L-shaped bottom plate
2211 and riser collectively form the L-shaped keel link slots of opening upwards, on the riser of two ends of L-shaped keel link slot
It is provided with the keel fixing bolt of connection keel;T shapes bending part 222 is including T shapes bottom plate 2221 and perpendicular to T shapes bottom plate 2221
Riser, T shapes bottom plate 2221 and riser collectively form the main tee link slot of opening upwards, close to three ends of main tee link slot
The keel fixing bolt of connection keel is both provided on the riser in portion;Cross bending part 223 includes 2231 He of cross bottom plate
Perpendicular to the riser of cross bottom plate 2231, the cross keel that cross bottom plate 2231 and riser collectively form opening upwards connect
Access slot is both provided with the keel fixing bolt of connection keel on the riser of four ends of cross keel link slot.Specifically
Ground, in the present embodiment, in order to keep bending part easy to process, stable structure, L-shaped bending part 221, T shapes bending part 222 and cross
Bending part 223 is integrally formed;In order to alleviate the weight of bending part and be convenient for punch forming, the two of L-shaped bending part 221 are short vertical
Between plate, between 222 circumferentially adjacent and mutually perpendicular riser of T shapes bending part, cross bending part 223 it is circumferentially adjacent
And be both provided with notch between mutually perpendicular riser.In practical application, as needed, bending part can also be by multiple zero
Part welding is composed, and bending part according to actual needs, can also use other shapes, as long as not influencing installation and use i.e.
It can.
As shown in Figure 13 to Figure 17, in the present embodiment, height adjustment mechanism 225 includes height fixing nut 2251, height
Under adjusting gasket 2252, height locking nut 2253 and height adjustment bolt 2254, height fixing nut 2251 and support column 224
End head is fixedly connected, and height adjusting pads piece 2252 and height locking nut 2253 are successively set under height fixing nut 2251
Side, height adjustment bolt 2254 include head and threaded portion, and the threaded portion of height adjustment bolt 2254 sequentially passes through from the bottom up
Height locking nut 2253, height adjusting pads piece 2252 and height fixing nut 2251, height locking nut 2253 and height are solid
Determine nut 2251 to be adapted with the threaded portion of height adjustment bolt 2254.Before adjusting 21 height of keel, height is first unscrewed downwards
Locking nut 2253 is spent, then rotation height adjusting bolt 2254 adjusts 21 height of keel, after keel 21 highly adjust, to
On screw 2253 mother of height locking screw.
As shown in Figure 13 and Figure 18, in the present embodiment, metope retaining mechanism 232 includes metope fixing nut 2321, metope
Adjusting gasket 2322, metope locking nut 2323 and metope smooth bolt 2324, and 231 lower part of wall face supporting beam is provided perpendicular to
The metope of metope smooths bolt mounting holes, and metope fixing nut 2321 is fixed on the wall of the remote metope side of metope smoothing bolt mounting holes
In face supporting beam 231, metope adjusting gasket 2322 and metope locking nut 2323 are successively set on metope smoothing bolt mounting holes
Nearly metope side;It includes head and threaded portion that metope, which smooths bolt 2324, and metope smooths the threaded portion of bolt 2324 from outside to inside
Sequentially pass through metope locking nut 2323, metope adjusting gasket 2322, metope smoothing bolt mounting holes and metope fixing nut
2321, metope locking nut 2323 and metope fixing nut 2321 are adapted with the threaded portion of metope smoothing bolt 2324.This
In embodiment, the metope smoothing bolt 2324 of metope retaining mechanism 232 is abutted with 7 metope of toilet, adjusts keel 21 and metope
Before distance, metope locking nut 2323 is first unscrewed, then rotates metope smoothing bolt 2324 and adjusts keel 21 and metope distance, when
After keel 21 and metope distance adjustment, screwing metope locking nut 2321 prevents keel 21 from moving horizontally.
As shown in Figure 13 to Figure 18, in the present embodiment, height adjustment bolt 2254 and metope smoothing bolt 2324 are all made of
Nylon material.For the ease of attaching nut and bolt, keel 21 and support column 224 are all made of square tube making, wall face supporting beam
231 are made of channel steel.In the present embodiment, height fixing nut 2251 is welded in the square hole on 224 lower end head of support column, high
The lower end of degree fixing nut 2251 is flushed with 224 lower end of support column.
As shown in Figure 13 to Figure 18, in the present embodiment, keel 21 include lateral keel 211 and longitudinal keel 212, wherein horizontal
It is arranged in parallel to keel 211 along rectangular platform length direction, longitudinal keel 212 is vertical with lateral keel 211.The present embodiment
In, the vertical height all same in 212 section of lateral keel 211 and longitudinal keel, the specification of longitudinal keel 212 and be located at grid
The 211 specification all same of lateral keel at shape edge, 211 cross-sectional width of lateral keel being located in square grid shape are more than positioned at grid
211 cross-sectional width of lateral keel of web-like edge;In order to reduce installation error, lateral keel 211 is fixed on transversely keel 211
On all vertical supporting framves 22 of axis direction setting, therefore 211 length of most of lateral keels is grown more than longitudinal keel 212
Degree, longitudinal keel 212 are fixed on two adjacent vertical supporting framves 22.In the present embodiment, in order to which the support for increasing bending part is strong
It spends, in T shapes bending part 222, T shapes bottom plate 2221, which supports the downside at longitudinal keel 212 and is both provided between support column 224, to be added
The stiffener plate of strong structure;In cross bending part 223, cross bottom plate 2231 supports downside and branch at longitudinal keel 212
The stiffener plate of reinforcement structure is both provided between dagger 224.
As shown in Fig. 2 to Figure 10, in the present embodiment, pass through inner corner trim electricity between the adjacent waterproof riser 12 of flexible water disk 1
Magnetic connects angle 13 is connected with 14 sweat soldering of external corner electromagnetism joint angle, and inner corner trim electromagnetism joint angle 13 is located at two adjacent waterproof risers
The 12 interior angle sides constituted, inner corner trim electromagnetism joint angle 13 and the 11 equal thermofussion welding in upside of two adjacent waterproof risers 12 and waterproof bottom plate
Connect in succession, external corner electromagnetism joint angle 14 is located at the exterior angle side that adjacent two waterproof risers 12 are constituted, external corner electromagnetism joint angle 14 with
Adjacent two waterproof risers 12 and the sweat soldering connection of 11 downside of waterproof bottom plate.The adjacent waterproof of this flexible water disk 1 is vertical
Pass through the inner corner trim electromagnetism joint angle 13 positioned at 11 inside of riser and the external corner electromagnetism joint angle 14 on the outside of riser between plate 12
Sweat soldering connects, easy to operate, when operation inner corner trim electromagnetism joint angle 13 and external corner electromagnetism joint angle 14 are placed after use
Electromagnetic welding equipment electromagnetic induction heating, installation difficulty is low, and not only water resistance is good for this flexible water disk 1, but also can
Differ to avoid thickness everywhere, shape is overall beautiful.In practical application, inner corner trim and external corner and flexible water disk can also be used
The mode of 1 bonding.
As shown in Fig. 5 to Figure 10, in the present embodiment, inner corner trim electromagnetism joint angle 13 is including on inner corner trim lower connecting plate 131, inner corner trim
Connecting plate 132 and inner corner trim electromagnetism wire side 133, inner corner trim lower connecting plate 131 are in isosceles right triangle, and inner corner trim upper junction plate 132 is disconnected
Face is L-shaped and lower end and two right-angle sides of inner corner trim lower connecting plate 131 are fixedly connected with, and inner corner trim electromagnetism wire side 133 is arranged in inner corner trim
The nearly riser side of lower connecting plate 131 and inner corner trim upper junction plate 132;External corner electromagnetism joint angle 14 includes external corner lower connecting plate 141, sun
Angle upper junction plate 142 and external corner electromagnetism wire side 143, external corner lower connecting plate 141 are in isosceles right triangle, external corner upper junction plate
142 sections are L-shaped and lower end and two right-angle sides of external corner lower connecting plate 141 are fixedly connected with, and the setting of external corner electromagnetism wire side 143 exists
The nearly riser side of external corner lower connecting plate 141 and external corner upper junction plate 142.In the present embodiment, inner corner trim electromagnetism wire side 133 and external corner electricity
Magnetic wire side 143 is made of wire electrode, and after electromagnetic induction heating, wire electrode fever makes inner corner trim electromagnetism joint angle 13, external corner electromagnetism
Joint angle 14 is connect with 1 sweat soldering of flexible water disk respectively.For the ease of installation, waterproof bottom plate 11, waterproof riser 12, inner corner trim
Lower connecting plate 131, inner corner trim upper junction plate 132, external corner lower connecting plate 141 and external corner upper junction plate 142 are all made of HDPE materials.For
The upper end of good appearance, inner corner trim upper junction plate 132 and external corner upper junction plate 142 is flushed with 12 upper end of waterproof riser.
As shown in figure 11, in the present embodiment, for the ease of the discharge outlet 111 and water-proof plate drainage pipeline of flexible water disk 1
53 connect and prevent leak, discharge outlet 111 to be equipped with circular ring shape hot bending portion integrally formed with waterproof bottom plate 11 and that Open Side Down.
As shown in figure 11, a kind of flexible water disk discharge structure of the present embodiment has discharge outlet 111, support tube 16, electricity
The waterproof bottom plate 11 of very hot molten elbow 17 and water-proof plate drainage pipeline 53, discharge outlet 111 and flexible water disk 1 is integrally formed and is in
The annular shape extended downwardly, 16 lower part of support tube are located in discharge outlet 111, and 16 lower end of support tube is flushed with 111 lower end of discharge outlet
And upper end exceeds 111 upper end of discharge outlet, 16 upper end edge of support tube is circumferentially provided with rhone;Electrode heats 17 upper head of elbow
Inside is provided with electromagnetism wire side, and 111 lower part of discharge outlet is inserted into after electrode hot melt 17 upper head of elbow and heats elbow 17 with electrode
Sweat soldering connects, and water-proof plate drainage pipeline 53 is connected to the lower end head of electrode hot melt elbow 17.This flexible water disk drains
In structure, the waterproof bottom plate 11 of discharge outlet 111 and flexible water disk 1 is integrally formed and in the annular shape extended downwardly, electrode heat
Electromagnetism wire side on the inside of 17 upper head of molten elbow is made of wire electrode, after electromagnetic induction heating electromagnetism wire side, wire electrode fever
Sweat soldering between electrode hot melt elbow 17 and discharge outlet 111 is set to connect, connection difficulty is low, and water resistance is good;Support tube upper end
Surrounding opens up rhone, is convenient to clean sundries and draining.Specifically, discharge outlet 111 and electrode heat elbow 17 in the present embodiment
HDPE materials are all made of, support tube 16 and water-proof plate drainage pipeline 53 are pvc pipe;The discharge outlet 111 of flexible water disk 1 passes through
Water is drained into 5 (not shown) of same layer main drainpipe by water-proof plate drainage pipeline 53.
As shown in figure 19, precast floor 3 includes substrate 31, positioning net 32, positioning card and face brick 33, and positioning net 32 is in square
Shape is simultaneously fixed on 31 upper surface of substrate, is clamped between adjacent positioning net 32;Positioning card includes the first positioning card 34 and second
Positioning card 35, the first positioning card 34 are fixed on 32 middle part of positioning net, and the second positioning card 35 is fixed on positioning 32 four corners of net, face brick
33 are positioned by adjacent the first positioning card 34 and the second positioning card 35 and are bonded on positioning net 32.In the present embodiment, substrate 31
For fiber cement board, positioning net 32 is made of ABS engineering plastics, and in practical application, substrate 31 can also use alloy sheets.
As shown in Fig. 1 and Figure 19, substrate 31 is first fixed on steelframe 32 by this precast floor 3, then will position net 32
Between be clamped and it is fixed on the substrate 31, position after spreading glue for tile on net 32 by the first positioning block 34 and second positioning card 35 with
It positions net 32 to connect, face brick 33 can easily be installed by the first adjacent positioning card 34 and 35 positioning of the second positioning card at this time,
The installation difficulty for reducing face brick 33 improves the installation effectiveness of face brick 33, and the personnel for not needing profession can be by face brick 33
It installs smooth.Specifically, the gap between adjacent tile 33 is filled with jointing agent;In the present embodiment, positioning net 32 and substrate 31
Between using rifle nail be fixedly connected, can also be connected with common nails in practical application, as long as do not influence installation and use.
As shown in Figure 19 to Figure 21, in the present embodiment, 32 middle part of positioning net is provided with the first card hole 321, the first positioning card
34 lower parts are connected in the first card hole 321 and top is beyond 32 upper surface of positioning net, the first positioning 34 lower parts of card and the first card hole
321 are adapted.Second positioning card 35 includes support portion 351 and limiting section 352, and the four corners of positioning net 32 are both provided with bayonet,
Support portion 351 is adapted with bayonet and is connected to the four corners of positioning net 32,351 thickness of support portion and positioning 32 thickness phase of net
Together.Specifically, in the present embodiment, first positioning the 34, first card hole 321 of card and limiting section 352 are cross;Bayonet and support
Portion 352 is rectangular.In practical application, first positioning the 34, first card hole 321 of card and limiting section 352 can also use other shapes
Shape, as long as not influencing installation and use.
As shown in Fig. 1 to Figure 21, a kind of assembled Toilet Installation method includes the following steps:
Step S1 measures the size of toilet, according to the size precasting steel frame 2 of toilet;
Step S2 is laid with same-floor drainage pipeline 5;
Step S3, installs steelframe 2, and wherein step S5 includes the following steps:Step S3.1, the first step of vertical supporting frame 22
Whole to one unified height;Step S3.2, keel 21 are connect with vertical supporting frame 22 (lateral keel 211 can be first connected,
After all lateral keels 211 are connected with corresponding vertical supporting frame 22, longitudinal keel 212 is reconnected);Step S3.3, adjustment
Rectangular platform four while keel 21 and metope between spacing (when preventing rectangular platform four with metope hypotelorism or too far);Step
Rapid S3.4,22 height of accurate adjustment vertical supporting frame make 21 upside of keel be located at same level and (measure keel 21 by horizon rule side
Levelness side adjusts 22 height of vertical supporting frame there are deviation);Step S3.5, by cross-brace frame 23 by rectangular platform four
Spacing locking between the keel 21 and metope on side;
Step S4 installs the first precast floor 4;
Step S5, installation flexible water disk 1, wherein step S5 includes the following steps:Step S5.1, according to the ruler of toilet
It is very little to cut flexible web and constitute the original-shape of flexible water disk 1, the original-shape (Figure 12) of flexible water disk by one at
The waterproof bottom plate 11 and waterproof riser 12 of type collectively form, and the shape of waterproof bottom plate 11 is identical as toilet flat shape, waterproof
Riser 12 is located at around waterproof bottom plate 11;Step S5.2 makes waterproof riser 12 and prevents by waterproof riser 12 along 15 hot bending of hot bending line
Water-bed plate 11 constitutes the case shape of upper opening;Step S5.3, adjacent and to need the two waterproof risers 12 connected to constitute outer
External corner electromagnetism joint angle 14 is placed in angle side, and inner corner trim electricity is placed in interior angle side that is adjacent and needing the two waterproof risers 12 connected to constitute
Magnetic connects angle 13;Step S5.4, with fixture by inner corner trim electromagnetism joint angle 13, adjacent and need the two waterproof risers 12 connected and sun
Angle electromagnetism joint angle 14 is clamped simultaneously, keeps having lasting clamping between inner corner trim electromagnetism joint angle 13 and external corner electromagnetism joint angle 14
Power;Step S5.5 waits for that inner corner trim electromagnetism connects to inner corner trim electromagnetism joint angle 13 and external corner electromagnetism joint angle 14 while electromagnetic induction heating
It connects between 133 side of inner corner trim electromagnetism wire side at angle 13 and two adjacent waterproof risers 12 and the upside of waterproof bottom plate 11, external corner electromagnetism
Equal thermofussion welding between 11 downside of 143 side of external corner electromagnetism wire side of joint angle 14 and two adjacent waterproof risers 12 and waterproof bottom plate
Stop electromagnetic induction heating after connecing in succession;Step S5.6 processes discharge outlet 111, and discharge outlet 111 is made to be formed and waterproof bottom plate 11 1
Circular ring shape body formed and that Open Side Down;Discharge outlet 111 is connect by step S5.7 with main drainpipe 6;Step S5.8, will be flexible
Water-proof plate 1 is shelved on smoothing bed course 4;
Step S6, installs precast floor 3, and wherein step S6 includes the following steps:Step S6.1, installation base plate 31;Step
31 upper surface of positioning 32 fixed substrate of net will be clamped by rapid S6.2, installation positioning net 32 between adjacent positioning net 32;Step
Glue for tile is poured into positioning net 32, is struck off by S6.3;First positioning is blocked 34 and is connected to 32 middle part of positioning net by step S6.4, will
Second positioning card 35 is connected to positioning 32 four corners of net;Step S6.5 blocks 34 and 35 positioning of the second positioning card according to the first positioning
Paving brick 33;
Step S7, safety inspection.
In step S6, substrate 31 and 33 shape of face brick that co-layer draining pipe 5 is in charge of across place are in charge of phase with co-layer draining pipe 5
Adaptation, positioning net 32 herein will manually be cut when installing.
The preferred embodiment of the present invention has been described in detail above.It should be appreciated that those skilled in the art without
It needs creative work according to the present invention can conceive and makes many modifications and variations.Therefore, all technologies in the art
Personnel are available by logical analysis, reasoning, or a limited experiment on the basis of existing technology under this invention's idea
Technical solution, all should be in the protection domain being defined in the patent claims.
Claims (10)
1. a kind of assembled toilet being easily installed, it is characterised in that:Including steelframe, flexible water disk, precast floor and
Co-layer draining pipe, the steelframe, flexible water disk, precast floor and co-layer draining pipe are arranged in toilet;
The steelframe is arranged on the upside of toilet earth's surface, and steelframe includes keel, vertical supporting frame and cross-brace frame;The keel
The keel constituted in one jiao of rectangular platform jaggy and rectangular platform are in netted, and the vertical supporting frame is used to support keel simultaneously
Keel level is adjusted, the cross-brace frame is fixed on the keel on four side of rectangular platform to prevent keel from being moved relative to metope;
The precast floor includes the first precast floor and the second precast floor, and first precast floor is fixed on
On the upside of keel;
The flexible water disk is arranged on the upside of the first precast floor, and flexible water disk includes waterproof bottom plate and waterproof riser,
The waterproof floor level is arranged and is in one jiao jaggy rectangular-shaped, and discharge outlet is provided on waterproof bottom plate, and the waterproof is vertical
Plate is located at around waterproof bottom plate, and waterproof bottom plate and waterproof riser are integrally formed and constitute the case shape of upper opening;
Second precast floor is arranged on the upside of the waterproof bottom plate of flexible water disk;
The main pipeline of co-layer draining pipe is fixed on the upside of toilet earth's surface and below keel, the subtube of co-layer draining pipe from
Under up sequentially pass through the first precast floor, flexible water disk and the second precast floor and water inlet is located at the second assembled
Above floor.
2. assembled toilet according to claim 1, it is characterised in that:Second precast floor include substrate,
Net, positioning card and face brick are positioned, the positioning net is rectangular and is fixed on upper surface of base plate, blocks between adjacent positioning net
It connects;Positioning card includes that the first positioning card and the second positioning block, and first positioning, which fixes, to be scheduled in the middle part of positioning net, and described the
Two positioning, which fix, is scheduled on positioning net four corners, and the face brick is by the first adjacent positioning card and the locking position of the second positioning and is bonded in
Positioning is online.
3. the assembled toilet according to claim 2 being easily installed, it is characterised in that:The vertical supporting frame includes
L-shaped spine support frame, main tee supporting rack and cross spine support frame, the L-shaped spine support frame, main tee supporting rack
Include bending part, support column and height adjustment mechanism with cross spine support frame, the bending part is fixed on support column
Upper head is simultaneously bolted with keel, the height adjustment mechanism be fixed on the lower end head of support column with adjust support column and
The vertical supporting height of bending part;The bending part includes positioned at the L-shaped bending part on L-shaped spine support frame top, positioned at T shape dragons
The T shapes bending part on bone supporting rack top and cross bending part positioned at cross spine support frame top, the L-shaped bending part
The L-shaped keel that riser including L-shaped bottom plate and perpendicular to L-shaped bottom plate, L-shaped bottom plate and riser collectively form opening upwards connect
Slot is both provided with the keel fixing bolt of connection keel on the riser of two ends of L-shaped keel link slot;The T shapes folding
Comer pieces includes T shapes bottom plate and the riser perpendicular to T shape bottom plates, and the main tee that T shapes bottom plate and riser collectively form opening upwards connects
Access slot is both provided with the keel fixing bolt of connection keel on the riser of three ends of main tee link slot;The cross
Shape bending part includes cross bottom plate and the riser perpendicular to cross bottom plate, cross bottom plate and riser collectively form opening to
On cross keel link slot, close to four ends of cross keel link slot riser on be both provided with connection keel dragon
Bone fixation bolt.
4. the assembled toilet according to claim 3 being easily installed, it is characterised in that:The height adjustment mechanism packet
Include height fixing nut, height adjusting pads piece, height locking nut and height adjustment bolt, the height fixing nut and support
Column lower end head is fixedly connected, and the height adjusting pads piece and height locking nut are successively set on the downside of height fixing nut,
The height adjustment bolt includes head and threaded portion, and the threaded portion of height adjustment bolt sequentially passes through height and locks from the bottom up
Nut, height adjusting pads piece and height fixing nut, the height locking nut and height fixing nut adjust spiral shell with height
The threaded portion of bolt is adapted.
5. the assembled toilet according to claim 4 being easily installed, it is characterised in that:The cross-brace frame includes
Wall face supporting beam and metope retaining mechanism, wall face supporting beam top are fixedly connected with keel, and the metope retaining mechanism is set
It sets in the lower part of wall face supporting beam to prevent keel from being moved relative to metope;The metope retaining mechanism include metope fixing nut,
Metope adjusting gasket, metope locking nut and metope smooth bolt, and wall face supporting beam lower part is provided perpendicular to metope
Metope smooths bolt mounting holes, and the metope fixing nut is fixed on the wall face supporting of the remote metope side of metope smoothing bolt mounting holes
Liang Shang, the metope adjusting gasket and metope locking nut are successively set on the nearly metope side of metope smoothing bolt mounting holes;Institute
It includes head and threaded portion to state metope smoothing bolt, and the threaded portion of metope smoothing bolt sequentially passes through metope locking screw from outside to inside
Mother, metope adjusting gasket, metope smoothing bolt mounting holes and metope fixing nut, the metope locking nut and metope fix spiral shell
Female threaded portion that bolt is smoothed with metope is adapted.
6. the assembled toilet according to claim 5 being easily installed, it is characterised in that:The keel and support column are equal
For square tube, wall face supporting beam is channel steel.
7. the assembled toilet according to claim 2 being easily installed, it is characterised in that:Between adjacent waterproof riser
It is connected with external corner electromagnetism joint angle sweat soldering by inner corner trim electromagnetism joint angle, the inner corner trim electromagnetism joint angle is located at adjacent two
The interior angle side that waterproof riser is constituted, inner corner trim electromagnetism joint angle and equal thermofussion welding on the upside of two adjacent waterproof risers and waterproof bottom plate
It connects in succession, the external corner electromagnetism joint angle is located at the exterior angle side that two adjacent waterproof risers are constituted, external corner electromagnetism joint angle and phase
The equal sweat soldering connection of adjacent two waterproof risers and waterproof baseplate underside.
8. the assembled toilet according to claim 7 being easily installed, it is characterised in that:The inner corner trim electromagnetism joint angle
Including inner corner trim lower connecting plate, inner corner trim upper junction plate and inner corner trim electromagnetism wire side, the inner corner trim lower connecting plate is in isosceles right triangle,
The inner corner trim upper junction plate section is L-shaped and lower end and two right-angle sides of inner corner trim lower connecting plate are fixedly connected with, the inner corner trim electricity
The nearly waterproof riser side in inner corner trim lower connecting plate and inner corner trim upper junction plate is arranged in magnetic wire side;The external corner electromagnetism joint angle includes sun
Angle lower connecting plate, external corner upper junction plate and external corner electromagnetism wire side, the external corner lower connecting plate are in isosceles right triangle, the sun
Angle upper junction plate section is L-shaped and lower end and two right-angle sides of external corner lower connecting plate are fixedly connected with, the external corner electromagnetism wire side
Nearly waterproof riser side in external corner lower connecting plate and external corner upper junction plate is set.
9. the assembled toilet according to claim 8 being easily installed, it is characterised in that:The waterproof bottom plate, waterproof
Riser, inner corner trim lower connecting plate, inner corner trim upper junction plate, external corner lower connecting plate and external corner upper junction plate are all made of HDPE materials.
10. a kind of assembled Toilet Installation method, which is characterized in that using the dress as described in claim 7~9 any one
It is installed, is included the following steps with formula toilet:
Step 1, the size for measuring toilet, according to the size precasting steel frame of toilet;
Step 2, it is laid with same-floor drainage pipeline;
Step 3, steelframe is installed, wherein step 3 includes the following steps:Step 3.1, vertical supporting frame is tentatively adjusted to a system
One height;Step 3.2, keel are connect with vertical supporting frame;Step 3.3, the keel and metope on four side of adjustment rectangular platform
Between spacing;Step 3.4, accurate adjustment vertical supporting frame height makes to be located at same level on the upside of keel;Step 3.5, pass through cross
The spacing between the keel and metope on four side of rectangular platform is locked to supporting rack;
Step 4, the first precast floor is installed;
Step 5, flexible water disk is installed, wherein step 5 includes the following steps:Step 5.1, it is cut according to the size of toilet soft
Property coiled material and constitute the original-shape of flexible water disk, the original-shape of flexible water disk is by integrally formed waterproof bottom plate and anti-
Water riser collectively forms, and the shape of waterproof bottom plate is identical as toilet flat shape, and waterproof riser is located at around waterproof bottom plate;Step
Rapid 5.2, by waterproof riser hot bending, waterproof riser and waterproof bottom plate is made to constitute the case shape of upper opening;Step 5.3, adjacent
And external corner electromagnetism joint angle is placed in the exterior angle side for needing the two waterproof risers connected to constitute, adjacent and need two waterproofs connected
Place inner corner trim electromagnetism joint angle in the interior angle side that riser is constituted;Step 5.4, with fixture by inner corner trim electromagnetism joint angle, adjacent and need
Connection two waterproof risers and external corner electromagnetism joint angle clamp simultaneously, holding inner corner trim electromagnetism joint angle and external corner electromagnetism joint angle it
Between have lasting clamping force;Step 5.5, inner corner trim electromagnetism joint angle and external corner electromagnetism joint angle electromagnetic induction heating simultaneously are given, is waited for
Between on the upside of the inner corner trim electromagnetic screen surface side of inner corner trim electromagnetism joint angle and two adjacent waterproof risers and waterproof bottom plate, external corner electromagnetism
Between the external corner electromagnetic screen surface side of joint angle and two adjacent waterproof risers and waterproof baseplate underside after equal sweat soldering connection
Stop electromagnetic induction heating;Step 5.6, discharge outlet is processed, so that discharge outlet is formed and is integrally formed the circle that simultaneously Open Side Down with bottom plate
Annular heat turn of bilge;Step 5.7, discharge outlet is connect with main drainpipe;Step 5.8, flexible water disk is shelved on smoothing bed course
On;
Step 6, the second precast floor is installed, wherein step 6 includes the following steps:Step 6.1, installation base plate;Step 6.2,
Positioning net fixed substrate upper surface will be clamped by installation positioning net between adjacent positioning net;Step 6.3, glue for tile is poured into
In positioning net, strike off;Step 6.4, the first positioning is connected to positioning net middle part, the second positioning is connected to positioning net four
At angle;Step 6.5, according to the first positioning card and the second positioning locking position paving brick;
Step 7, safety inspection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810460719.1A CN108396871A (en) | 2018-05-15 | 2018-05-15 | The assembled toilet and its installation method being easily installed |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810460719.1A CN108396871A (en) | 2018-05-15 | 2018-05-15 | The assembled toilet and its installation method being easily installed |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108396871A true CN108396871A (en) | 2018-08-14 |
Family
ID=63101288
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810460719.1A Pending CN108396871A (en) | 2018-05-15 | 2018-05-15 | The assembled toilet and its installation method being easily installed |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108396871A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020211803A1 (en) * | 2019-04-18 | 2020-10-22 | 林品通 | Assembled device |
CN112878440A (en) * | 2020-10-13 | 2021-06-01 | 南通中慧建筑科技有限公司 | Mobile toilet same-floor drainage system based on BIM |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0481246A2 (en) * | 1990-10-16 | 1992-04-22 | CENTRO ACCIAI S.p.A. | Public lavatory with a self-supporting structure |
CN2725413Y (en) * | 2004-09-07 | 2005-09-14 | 张丽莉 | Assembling type network floor |
KR100670842B1 (en) * | 2006-06-13 | 2007-01-17 | (주)한국환경종합건축사사무소 | Foor pannel for building |
CN202300428U (en) * | 2011-10-28 | 2012-07-04 | 成都市新筑路桥机械股份有限公司 | Trolley for installing tunnel waterproof plate |
CN202442049U (en) * | 2012-03-09 | 2012-09-19 | 山东胜邦塑胶有限公司 | Electromagnetic heating type electric smelting pipe fitting |
CN203867202U (en) * | 2014-06-19 | 2014-10-08 | 中国五冶集团有限公司 | Positioning tool special for steel structure vertical keel of metal curtain wall of large gymnasium |
CN205062922U (en) * | 2015-09-08 | 2016-03-02 | 上海中房建筑设计有限公司 | Installation is with layer drainage system's bathroom |
CN106284911A (en) * | 2016-08-23 | 2017-01-04 | 天元建设集团有限公司 | A kind of assembled raised flooring, assembled space separating system and construction method |
CN107268938A (en) * | 2017-07-31 | 2017-10-20 | 钱浩 | A kind of combined type movement floor |
CN107859275A (en) * | 2017-09-29 | 2018-03-30 | 浙江未来加电子商务有限公司 | Ground pavement structure based on cross positioning assembly parts |
CN108005338A (en) * | 2017-11-30 | 2018-05-08 | 浙江亚厦装饰股份有限公司 | Substrate, substrate floor tile composite module and its assemble method |
-
2018
- 2018-05-15 CN CN201810460719.1A patent/CN108396871A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0481246A2 (en) * | 1990-10-16 | 1992-04-22 | CENTRO ACCIAI S.p.A. | Public lavatory with a self-supporting structure |
CN2725413Y (en) * | 2004-09-07 | 2005-09-14 | 张丽莉 | Assembling type network floor |
KR100670842B1 (en) * | 2006-06-13 | 2007-01-17 | (주)한국환경종합건축사사무소 | Foor pannel for building |
CN202300428U (en) * | 2011-10-28 | 2012-07-04 | 成都市新筑路桥机械股份有限公司 | Trolley for installing tunnel waterproof plate |
CN202442049U (en) * | 2012-03-09 | 2012-09-19 | 山东胜邦塑胶有限公司 | Electromagnetic heating type electric smelting pipe fitting |
CN203867202U (en) * | 2014-06-19 | 2014-10-08 | 中国五冶集团有限公司 | Positioning tool special for steel structure vertical keel of metal curtain wall of large gymnasium |
CN205062922U (en) * | 2015-09-08 | 2016-03-02 | 上海中房建筑设计有限公司 | Installation is with layer drainage system's bathroom |
CN106284911A (en) * | 2016-08-23 | 2017-01-04 | 天元建设集团有限公司 | A kind of assembled raised flooring, assembled space separating system and construction method |
CN107268938A (en) * | 2017-07-31 | 2017-10-20 | 钱浩 | A kind of combined type movement floor |
CN107859275A (en) * | 2017-09-29 | 2018-03-30 | 浙江未来加电子商务有限公司 | Ground pavement structure based on cross positioning assembly parts |
CN108005338A (en) * | 2017-11-30 | 2018-05-08 | 浙江亚厦装饰股份有限公司 | Substrate, substrate floor tile composite module and its assemble method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020211803A1 (en) * | 2019-04-18 | 2020-10-22 | 林品通 | Assembled device |
CN112878440A (en) * | 2020-10-13 | 2021-06-01 | 南通中慧建筑科技有限公司 | Mobile toilet same-floor drainage system based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108425434A (en) | Flexible water disk, flexible water disk processing method and assembled toilet | |
CN108442738A (en) | Assembled toilet and its installation method | |
CN105113671A (en) | Construction method of large conchoidal hyperbolic curtain wall | |
CN210482605U (en) | Building structure movement joint mounting structure | |
CN108396871A (en) | The assembled toilet and its installation method being easily installed | |
CN208718092U (en) | A kind of assembled toilet being easily installed | |
CN110158394A (en) | A kind of concrete ultra-flat terrace cutting-free constructing structure | |
CN108612284A (en) | Aerial steelframe and its installation method | |
CN106437093B (en) | Building decoration concealed installation ceramic tile baseboard structure and construction process thereof | |
CN208578362U (en) | A kind of assembled toilet | |
CN106894583B (en) | A kind of discharge structure and its construction method for ancient building shelter bridge | |
CN102230338A (en) | Prefabricated toilet and construction method and installation method thereof | |
CN108396934A (en) | Precast floor, precast floor installation method and assembled toilet | |
CN111997236A (en) | Slotting and stacking type back bolt stone curtain wall | |
KR101156099B1 (en) | Guide-point of hydroelectricity box for masonry wall and the installation method of hydroelectricity box using it | |
CN217399823U (en) | Indoor appliance drainage connecting disc | |
CN207017442U (en) | A kind of cleaning fixed structure of curved roof | |
CN113638567B (en) | Quick-assembly integral ground system based on descending plate type toilet and construction method | |
KR20160017465A (en) | Heating module board and construction method of heating module board | |
CN111335352B (en) | Positioning and waterproof integrated construction method for roof solar foundation buttress | |
CN208088817U (en) | A kind of easy-to-dismount overhanging type scaffold bolt anchoring assembly | |
CN111749403A (en) | Drainage ditch and deformation joint combined structure and construction method thereof | |
CN101250892A (en) | Hanging device and construction method for light separating-wall hidden installation sanitary equipment | |
CN213452089U (en) | Same-floor drainage and water supply buried pipeline supporting structure | |
CN105350784B (en) | Utilize skirt location technology one-shot forming service sleeve installation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180814 |