CN108386228A - 一种斜井冻结法施工长期监测巷壁应力的方法 - Google Patents
一种斜井冻结法施工长期监测巷壁应力的方法 Download PDFInfo
- Publication number
- CN108386228A CN108386228A CN201810132182.6A CN201810132182A CN108386228A CN 108386228 A CN108386228 A CN 108386228A CN 201810132182 A CN201810132182 A CN 201810132182A CN 108386228 A CN108386228 A CN 108386228A
- Authority
- CN
- China
- Prior art keywords
- freezing
- pressure gauge
- monitoring
- freezing pipe
- soil pressure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
- E21F17/18—Special adaptations of signalling or alarm devices
Abstract
一种斜井冻结法施工长期监测巷壁应力的方法,包括如下步骤:巷道掘进前,利用空气将冻结管内的盐水置换干净,尽量保证冻结管内没有盐水残留;使用煤巷综掘机掘进工作面,将位于巷道范围内的3根冻结管露出来;人工用电焊将3根冻结管截断,将冻结管的上下两端做临时封闭;将正常工作的土压力盒及孔隙水压力计的监测导线绑扎好,从废弃冻结管内提升至地面,将监测线固定好,保护好。本发明可以在地面对井下巷道巷壁应力进行长期监测,不受井下施工环境影响。避免了监测导线穿过隔水板,延伸到巷道内,进而形成一个新的漏水点,保证了巷道井壁的完整性和安全性,最终达到长期对巷壁应力监测的目的。
Description
技术领域
本发明涉及一种长期监测巷壁应力的方法,具体涉及一种斜井冻结法施工长期监测巷壁应力的方法。
背景技术
现有的巷壁应力监测方法一般均为短期的、临时的监测,不能完整的记录巷壁在冻结中、解冻时以及解冻后的应力变化情况,而且一般监测方法的数据收集端都设立在井下,受井下施工环境影响较大。一般监测方法,其监测仪器的导线会穿过一衬与二衬之间的隔水板,形成一个新的漏水点,对巷道的稳定性造成了很大的伤害,甚至有可能导致灾害的发生。
发明内容
为解决上述问题,本发明提供了一种斜井冻结法施工长期监测巷壁应力的方法,可以在地面对井下巷壁应力进行长期监测,不受井下施工环境影响。避免了监测导线穿过隔水板,延伸到巷道内,进而形成一个新的漏水点,保证了巷道井壁的完整性和安全性,最终达到长期对巷壁应力监测的目的。
为实现上述目的,本发明采取的技术方案为:
一种斜井冻结法施工长期监测巷壁应力的方法,包括如下步骤:
步骤1、巷道掘进前,利用空气将冻结管内的盐水置换干净,尽量保证冻结管内没有盐水残留;
步骤2、使用煤巷综掘机掘进工作面,将位于巷道范围内的3根冻结管露出来;
步骤3、人工用电焊将3根冻结管截断,将冻结管的上下两端做临时封闭;
步骤4、检查土压力盒及孔隙水压力计能否正常工作,如正常,则在巷道四周安装土压力盒及孔隙水压力计,确保土压力盒及孔隙水压力计与冻结壁紧密结合在一起,如不正常,需更换土压力盒或孔隙水压力计;
步骤5、将土压力盒及孔隙水压力计的监测导线绑扎好,从废弃冻结管内提升至地面;
步骤6、检查土压力盒及孔隙水压力计能否正常工作,如正常,则将监测线固定好,保护好;如不正常,更换土压力盒或孔隙水压力计,重新按照上述步骤安装。
本发明具有以下有益效果:
数据收集方便,监测周期长,不受监测环境影响,不形成新的漏水点,能够完整的记录巷壁在冻结中、解冻时以及解冻后的应力变化情况,保证了巷道井壁的完整性和安全性,是分析冻结斜井巷壁应力变化规律的一种有效手段。
附图说明
图1为本发明实施例一种斜井冻结法长期监测巷壁应力的方法的平面结构示意图。
图2为图1中A-A的剖面图。
图3为图1中B-B的剖面图。
图4为图1中的剖面图。
图中,1-冻结管;2-冻结壁顶部;3-主井井筒底板;4-底板;5-冻结壁底部;6-顶板;7-无缝钢管;8-监测仪器数据传输导线;9-保温管;10-底板。
具体实施方式
以下结合实施例对本发明进一步叙述,但本发明不局限于以下实施例。
如图1-4所示,一种斜井冻结法施工长期监测巷壁应力的方法,包括如下步骤:
步骤1、巷道掘进前,利用空气将冻结管内的盐水置换干净,尽量保证冻结管内没有盐水残留;
步骤2、使用煤巷综掘机掘进工作面,将位于巷道范围内的3根冻结管露出来;
步骤3、人工用电焊将3根冻结管截断,将冻结管的上下两端做临时封闭;
步骤4、检查土压力盒及孔隙水压力计能否正常工作,如正常,则在巷道四周安装土压力盒及孔隙水压力计,确保土压力盒及孔隙水压力计与冻结壁紧密结合在一起,如不正常,需更换土压力盒或孔隙水压力计;
步骤5、将土压力盒及孔隙水压力计的监测导线绑扎好,从废弃冻结管内提升至地面;
步骤6、检查土压力盒及孔隙水压力计能否正常工作,如正常,则将监测线固定好,保护好;如不正常,更换土压力盒或孔隙水压力计,重新按照上述步骤安装。
实施例
本发明涉及的方法在陕西榆林某矿成功实施,在实施前先确定好监测仪器安放位置,在巷道掘进到该位置时,将冻结管内的盐水置换干净,确保冻结管内没有盐水残留,并将冻结管从巷道顶部切开。安装好监测仪器并做好引线保护,然后将仪器引线从切开的冻结管提升至地面,并做好固定和保护,完成之后就可以在地面对巷壁进行长期监测,避免了监测导线穿过隔水板,延伸到巷道内,进而形成一个新的漏水点,保证了巷道井壁的完整性和安全性。
Claims (1)
1.一种斜井冻结法施工长期监测巷壁应力的方法,其特征在于,包括如下步骤:
步骤1、巷道掘进前,利用空气将冻结管内的盐水置换干净,尽量保证冻结管内没有盐水残留;
步骤2、使用煤巷综掘机掘进工作面,将位于巷道范围内的3根冻结管露出来;
步骤3、人工用电焊将3根冻结管截断,将冻结管的上下两端做临时封闭;
步骤4、检查土压力盒及孔隙水压力计能否正常工作,如正常,则在巷道四周安装土压力盒及孔隙水压力计,确保土压力盒及孔隙水压力计与冻结壁紧密结合在一起,如不正常,需更换土压力盒或孔隙水压力计;
步骤5、将土压力盒及孔隙水压力计的监测导线绑扎好,从废弃冻结管内提升至地面;
步骤6、检查土压力盒及孔隙水压力计能否正常工作,如正常,则将监测线固定好,保护好;如不正常,更换土压力盒或孔隙水压力计,重新按照上述步骤安装。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810132182.6A CN108386228A (zh) | 2018-02-09 | 2018-02-09 | 一种斜井冻结法施工长期监测巷壁应力的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810132182.6A CN108386228A (zh) | 2018-02-09 | 2018-02-09 | 一种斜井冻结法施工长期监测巷壁应力的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108386228A true CN108386228A (zh) | 2018-08-10 |
Family
ID=63075512
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810132182.6A Pending CN108386228A (zh) | 2018-02-09 | 2018-02-09 | 一种斜井冻结法施工长期监测巷壁应力的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108386228A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111337533A (zh) * | 2020-02-28 | 2020-06-26 | 陕西陕煤陕北矿业有限公司 | 一种富水沙层特长冻结斜井三维数字钻孔可视化监测方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182463A (zh) * | 2011-04-12 | 2011-09-14 | 中煤邯郸特殊凿井有限公司 | 斜井冻结保温方法 |
CN102536246A (zh) * | 2012-03-09 | 2012-07-04 | 中煤第五建设有限公司 | 一种超长斜井井筒冻结管串联工艺装置 |
CN102758631A (zh) * | 2012-08-02 | 2012-10-31 | 兖矿集团有限公司 | 一种斜井冻结壁的冻结方法 |
CN102777185A (zh) * | 2012-05-15 | 2012-11-14 | 张晓岩 | 一种斜井井筒施工工艺 |
CN105828298A (zh) * | 2016-05-05 | 2016-08-03 | 中国矿业大学(北京) | 有线自供电矿井应急通信与定位系统 |
CN105848308A (zh) * | 2016-05-05 | 2016-08-10 | 中国矿业大学(北京) | 无线供电矿井应急通信与定位系统 |
CN107613580A (zh) * | 2017-10-19 | 2018-01-19 | 中国矿业大学(北京) | 抗灾变矿井应急通信系统 |
-
2018
- 2018-02-09 CN CN201810132182.6A patent/CN108386228A/zh active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102182463A (zh) * | 2011-04-12 | 2011-09-14 | 中煤邯郸特殊凿井有限公司 | 斜井冻结保温方法 |
CN102536246A (zh) * | 2012-03-09 | 2012-07-04 | 中煤第五建设有限公司 | 一种超长斜井井筒冻结管串联工艺装置 |
CN102777185A (zh) * | 2012-05-15 | 2012-11-14 | 张晓岩 | 一种斜井井筒施工工艺 |
CN102758631A (zh) * | 2012-08-02 | 2012-10-31 | 兖矿集团有限公司 | 一种斜井冻结壁的冻结方法 |
CN105828298A (zh) * | 2016-05-05 | 2016-08-03 | 中国矿业大学(北京) | 有线自供电矿井应急通信与定位系统 |
CN105848308A (zh) * | 2016-05-05 | 2016-08-10 | 中国矿业大学(北京) | 无线供电矿井应急通信与定位系统 |
CN107613580A (zh) * | 2017-10-19 | 2018-01-19 | 中国矿业大学(北京) | 抗灾变矿井应急通信系统 |
Non-Patent Citations (2)
Title |
---|
任建喜等: "富水砂层冻结斜井内外壁受力特性实测", 《西安科技大学学报》 * |
杨更社等: "白垩系地层煤矿立井冻结壁的力学特性及温度场研究", 《岩石力学与工程学报》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111337533A (zh) * | 2020-02-28 | 2020-06-26 | 陕西陕煤陕北矿业有限公司 | 一种富水沙层特长冻结斜井三维数字钻孔可视化监测方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107676097B (zh) | 一种高水压软土地层hfe组合式盾构始发方法 | |
CN102644467B (zh) | 顶管直接切削管片隧道联络通道施工方法 | |
CN204267097U (zh) | 一种用于矿井突水实时监测预报装置 | |
CN104110021B (zh) | Z型或u型截面钢板桩侧向土压力监测方法 | |
CN106195616A (zh) | 一种液体二氧化碳灌装系统 | |
CN105507938A (zh) | 钻孔内水力冲孔与预裂爆破联合增透抽采系统的施工方法 | |
CN101899978A (zh) | 砂卵石地层中盾构刀具更换方法 | |
WO2021120833A1 (zh) | 基于自然电位法的采空区滞后突水预警系统及其使用方法 | |
Broch et al. | The design of unlined hydropower tunnels and shafts: 100 years of Norwegian experience | |
CN106988754A (zh) | 狭窄空间盾构机始发方法 | |
CN104849413A (zh) | 采场膏体充填料热-水-力-化多场性能监测装置 | |
CN108386228A (zh) | 一种斜井冻结法施工长期监测巷壁应力的方法 | |
CN103115935A (zh) | 光纤温度传感监测冻结壁解冻过程的方法 | |
CN108825247A (zh) | 一种用于8导洞pba工法的外倾侧壁水平造底盆形冻结止水工法 | |
CN113217094A (zh) | 一种弱胶结强膨胀高富水软岩劣化效应控制方法 | |
CN207484536U (zh) | 测斜管保护结构 | |
CN111677514A (zh) | 顶板弱化方法 | |
CN209340000U (zh) | 一种矿房充填体脱水结构 | |
CN111577300A (zh) | 盾构穿越孤石、漂石地层中密打孔的施工方法 | |
CN208396715U (zh) | 一种区间隧道的先行导洞冻结止水结构 | |
CN103161469A (zh) | 开挖竖井地下修复顶管工具管的方法 | |
CN105134124B (zh) | 原油管道凝管蜡堵抢修工艺 | |
CN108643926A (zh) | 一种区间隧道的先行导洞冻结止水工法 | |
CN104632130A (zh) | 大修井完井工艺 | |
CN108104799A (zh) | 一种在圆管外固定压力盒的装置和加工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180810 |