CN108385885A - A kind of assembled stealth beam floor - Google Patents
A kind of assembled stealth beam floor Download PDFInfo
- Publication number
- CN108385885A CN108385885A CN201810145846.2A CN201810145846A CN108385885A CN 108385885 A CN108385885 A CN 108385885A CN 201810145846 A CN201810145846 A CN 201810145846A CN 108385885 A CN108385885 A CN 108385885A
- Authority
- CN
- China
- Prior art keywords
- floor
- concrete
- girder
- pipeline
- reinforced concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/14—Load-carrying floor structures formed substantially of prefabricated units with beams or girders laid in two directions
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/02—Load-carrying floor structures formed substantially of prefabricated units
- E04B5/023—Separate connecting devices for prefabricated floor-slabs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/48—Special adaptations of floors for incorporating ducts, e.g. for heating or ventilating
Abstract
The present invention proposes a kind of assembled stealth beam floor, belongs to building element field.Stealthy beam floor is the integral module formed by web beam with holes and reinforced concrete floor, and first using the beam being prefabricated in the factory as the frame of beam slab integral module, precast concrete is poured in beam bottom portion.Then above concrete layer can free pipeline installation, pipeline is passed through from soffit of girder plate holes between different plates, and lightweight concrete is poured after the completion of being laid with.Stealthy beam floor under the premise of not reducing bearing capacity, reduces the integral thickness of beam slab, improves building headroom, keep space layout more flexible by beam slab integration;The upper lower flange of beam is embedded in the concrete of floor, the concrete reserved around one side beam can improve the local stability of component, on the other hand alleviate fire prevention and the Anticorrosion of steel structure girder to a certain extent;The mode that web opens up hole and placement layer by layer floor is conducive to the personalized arrangement of pipeline, facilitates the repair and transformation in later stage.
Description
Technical field
The present invention designs a kind of assembled stealth beam floor, belongs to building element field.
Background technology
Annual 20 billion cubic meter of town and country newly constructed house area in China, wherein 80% or more builds for high energy consumption, China's unit
Construction area energy consumption is the 2 times or more of developed country.Meter is joined in a common effort according to Chinese steel, China's output of steel in 2011 is broken through 700,000,000 tons big
Close, it is the first to be sure to occupy within continuous 16 years countries in the world output of steel, corresponding current domestic construction industrialization degree less than 10%, and
Developed country's steel building area accounts for 50% or more overall floorage, and Japan accounts for 80%.China is as building rule in the world
Mould, the maximum country of steel yield, the development of light-duty steel construction house seriously lag.
Although existing steel building improves speed of application to a certain extent, difficulty of construction is alleviated, still
So there are problems.In the construction process, some uses composite floor with profiled steel sheet, removes a large amount of templates from, but profiled sheet increases
Add cost, and finishing processing is inconvenient below floor, additionally needs arrangement temporary support;Some is using reinforced concrete sandwich building
Plate is generally also required to arrangement temporary support, and preformed layer is thicker increases floor total height.Traditional contignation, plate are arranged in
Liang Shang increases beam slab total height, reduces structure and uses height.Girder steel is exposed to need anti-corrosion fire prevention to handle, and increases cost, and steel
The exposed flexible arrangement for being unfavorable for space of beam.Conventional floors fulgurite is embedded in structure sheaf, and building storey is poured on structure sheaf, and water warms up
Equal pipelines are embedded in building storey, keep total floor thickness larger.
Invention content
The present invention proposes a kind of assembled stealth beam floor, and the purpose is to solve in background technology to a certain extent
The problem of.Stealthy beam floor reduces the integral thickness of beam slab by beam slab integration under the premise of not reducing bearing capacity,
Building headroom is improved, beam is hidden in floor, keeps space layout more flexible;The upper lower flange of beam is embedded in
In the concrete of floor, the concrete reserved around one side beam can improve the local stability of component, avoid local buckling,
On the other hand fire prevention and the Anticorrosion of steel structure girder are alleviated to a certain extent.Web opens up hole and layering is poured
The mode of build floor is conducive to personalized arrangement and the installation of pipeline, facilitates the repair and transformation in invention later stage.
Technical solution of the present invention is as follows:
The assembled stealth beam floor is the integral module formed by the beam and reinforced concrete floor of holes in soffit.
Using the beam being prefabricated in the factory as the frame of beam slab module, arranges reinforcing bar in girder steel lower position, poured in reinforcement location high
Degree is the precast concrete of 40mm -100mm, forms reinforced concrete floor.Stealthy beam floor includes concrete (1), girder I
(2), girder II (3), girder III (4), girder IV (5), middle part secondary beam I (6) and reinforcing bar.Girder I (2), girder II (3), girder
III (4), girder IV (5) are located at reinforced concrete floor surrounding, and welding two-by-two is spliced into the frame of reinforced concrete floor, main
Beam I (2) is parallel with girder II (3), is long side;Girder III (4) is parallel with girder IV (5), is short side;Middle part secondary beam I (6) cloth
It is placed in the span centre position of reinforced concrete floor and is parallel to short side;The girder I (2), girder II (3), girder III (4), master
Beam IV (5) and middle part secondary beam I (6) open up hole at web, the laying so as to pipeline and arrangement;Then in factory's frame
Pouring for concrete is carried out, the prefabrication part of assembled stealth beam floor is eventually formed;Assembled stealth beam floor is transported
It is sent to construction site, at the construction field (site), assembled in situ is carried out using lifting, on the concrete layer of stealthy beam floor
Pipeline installation (water, warm, fulgurite etc.), pipeline is pierced by from soffit of girder plate holes, and pipeline is arranged between facilitating plate;Wait for that pipeline arranges
Finish, lightweight concrete is poured up to top surface of the beam in concrete floor.After pour lightweight concrete layer using air entrained concrete, polyphenyl
Particle concrete or haydite concrete, it is convenient to dismount and repair in the future pipeline.
Advantageous effect
The present invention proposes a kind of assembled stealth beam floor belonging to building element field, and it is pre- to overcome traditional architecture
The more complicated construction technology of floor processed.Stealthy beam floor is reduced by beam slab integration under the premise of not reducing bearing capacity
The integral thickness of beam slab, improves building headroom, and beam is hidden in floor, keeps space layout more flexible;By beam
Upper lower flange is embedded in the concrete of floor, and the part that the concrete reserved around one side beam can improve component is steady
It is fixed, local buckling is avoided, on the other hand alleviates fire prevention and the Anticorrosion of steel structure girder to a certain extent.Web is opened
The mode of apertured hole and placement layer by layer floor is conducive to personalized arrangement and the installation of pipeline, facilitates the repair in invention later stage
And transformation.
Description of the drawings
Fig. 1 is the Assembled Building slab skeleton schematic diagram of the present invention;
Fig. 2 is the prefabrication stealth beam floor schematic diagram of the present invention;
Fig. 3 be the present invention stealthy beam floor after factory pours precast concrete cross-section diagram;
Fig. 4 is that the stealthy beam floor placement layer by layer of the present invention completes cross-section diagram.
In figure, 1-concrete, 2-girders I, 3-girders II, 4-girders III, 5-girders IV, 6-middle part secondary beams I.
Specific implementation mode
The present invention is described in detail below in conjunction with the accompanying drawings, and the embodiment below with reference to attached drawing description is example
Type, it is intended to for explaining the present invention, and be not considered as limiting the invention.
Assembled stealth beam floor system proposed by the present invention, specific assembly method are as follows:It will be prefabricated in the factory first
Girder I (2), girder II (3), girder III (4) and the girder IV (5) of holes in soffit weld two-by-two is spliced into stealthy beam building slab
The frame of block, middle part secondary beam I (6) are arranged in the span centre position of stealthy beam floor modules and are parallel to short side;Then on factory side
Frame carries out pouring for concrete, eventually forms the prefabrication part of assembled stealth beam floor;By assembled stealth beam floor
It is transported to construction site, at the construction field (site), assembled in situ is carried out using lifting, on the concrete layer of stealthy beam floor
Face pipeline installation (water, warm, fulgurite etc.), pipeline is pierced by from soffit of girder plate holes, and pipeline is arranged between facilitating plate;Wait for that pipeline is arranged
It finishes, lightweight concrete is poured up to top surface of the beam in concrete floor;After pour lightweight concrete layer using air entrained concrete, poly-
Benzene particle concrete or haydite concrete, it is convenient to dismount and repair in the future pipeline.
Claims (3)
1. a kind of assembled stealth beam floor, including reinforced concrete floor, girder I, girder II, girder III, girder IV, middle part
Secondary beam I;Stealthy beam floor is the integral module formed by the beam and reinforced concrete floor of holes in soffit, first will be pre- in factory
Frame of the beam made as beam slab module arranges reinforcing bar in girder steel lower position, and it is 40mm-to pour height in reinforcement location
The precast concrete of 100mm forms reinforced concrete floor;Then arrange that pipeline, pipeline are worn on reinforced concrete floor
Cross beam web hole;It waits for that pipeline deploys, lightweight concrete is poured up to top surface of the beam in concrete floor;
Lightweight concrete density is not more than 1200kg/ cubic metres, and precast concrete uses the concrete of C30 or more intensity, close
Degree is more than 2400kg/ cubic metres.
2. a kind of assembled stealth beam floor according to claim 1, it is characterised in that:It is described stealth beam floor modules be
The integral module formed by beam and floor, the girder I, girder II, girder III and girder IV are located at reinforced concrete floor four
Week, two-by-two welding are spliced into the frame of reinforced concrete floor, and middle part secondary beam I is arranged in the span centre position of reinforced concrete floor
And it is parallel to short side;The girder I, girder III, girder IV, opens up hole at I web of middle part secondary beam at girder II, then exists
The frame for being assemblied to form beam slab module welds in factory, and pouring precast concrete in steel beam bottom constitutes reinforced concrete floor.
3. a kind of assembled stealth beam floor according to claim 1, which is characterized in that after pour lightweight concrete layer use
Air entrained concrete, granular polystyrene concrete or haydite concrete.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810145846.2A CN108385885A (en) | 2018-02-12 | 2018-02-12 | A kind of assembled stealth beam floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810145846.2A CN108385885A (en) | 2018-02-12 | 2018-02-12 | A kind of assembled stealth beam floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108385885A true CN108385885A (en) | 2018-08-10 |
Family
ID=63068839
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810145846.2A Pending CN108385885A (en) | 2018-02-12 | 2018-02-12 | A kind of assembled stealth beam floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108385885A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629733A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of assembled stealth beam floor system of bottom-up installation pipeline separation |
CN109629732A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of the cast-in-place concrete stealth beam floor and construction method of pipeline separation |
CN109629731A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of assembled stealth beam laminated floor slab of the pipeline separation of bottom-up installation |
CN109707091A (en) * | 2019-01-30 | 2019-05-03 | 北京工业大学 | A kind of assembled stealth beam laminated floor slab for the pipeline separation installed from up to down |
CN109853803A (en) * | 2019-01-31 | 2019-06-07 | 河南聚誉帆工程技术咨询有限公司 | Assembled integral floor and fabrication and installation method |
CN109930747A (en) * | 2019-04-19 | 2019-06-25 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces |
CN110042984A (en) * | 2019-04-19 | 2019-07-23 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam of splitting type holes in soffit |
CN110042985A (en) * | 2019-04-19 | 2019-07-23 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam of splitting type holes in soffit |
CN110258920A (en) * | 2019-04-19 | 2019-09-20 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam of holes in soffit |
CN110306725A (en) * | 2019-04-19 | 2019-10-08 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam of holes in soffit |
CN110306724A (en) * | 2019-04-19 | 2019-10-08 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam for the welded type holes in soffit that misplaces |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0483089A2 (en) * | 1990-10-16 | 1992-04-29 | Bengt Johansson | A beam for floor structures |
CN104278749A (en) * | 2014-10-23 | 2015-01-14 | 湖北弘毅建设有限公司 | Integral connecting system for steel-concrete composite structure component of prefabricated construction |
CN105822002A (en) * | 2016-03-29 | 2016-08-03 | 北京工业大学 | Assembled cold bending thin-wall sectional steel opening flat slab module |
CN206503303U (en) * | 2017-02-10 | 2017-09-19 | 青岛农业大学 | A kind of Honeycomb Beam and base-supporting floor combining structure suitable for floor heating house |
-
2018
- 2018-02-12 CN CN201810145846.2A patent/CN108385885A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0483089A2 (en) * | 1990-10-16 | 1992-04-29 | Bengt Johansson | A beam for floor structures |
CN104278749A (en) * | 2014-10-23 | 2015-01-14 | 湖北弘毅建设有限公司 | Integral connecting system for steel-concrete composite structure component of prefabricated construction |
CN105822002A (en) * | 2016-03-29 | 2016-08-03 | 北京工业大学 | Assembled cold bending thin-wall sectional steel opening flat slab module |
CN206503303U (en) * | 2017-02-10 | 2017-09-19 | 青岛农业大学 | A kind of Honeycomb Beam and base-supporting floor combining structure suitable for floor heating house |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109707091B (en) * | 2019-01-30 | 2020-11-03 | 北京工业大学 | Assembly type invisible beam composite floor slab with separated pipelines installed from top to bottom |
CN109629732A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of the cast-in-place concrete stealth beam floor and construction method of pipeline separation |
CN109629731A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of assembled stealth beam laminated floor slab of the pipeline separation of bottom-up installation |
CN109707091A (en) * | 2019-01-30 | 2019-05-03 | 北京工业大学 | A kind of assembled stealth beam laminated floor slab for the pipeline separation installed from up to down |
CN109629733B (en) * | 2019-01-30 | 2020-11-10 | 北京工业大学 | Assembled invisible beam floor system with separated pipelines installed from bottom to top |
CN109629733A (en) * | 2019-01-30 | 2019-04-16 | 北京工业大学 | A kind of assembled stealth beam floor system of bottom-up installation pipeline separation |
CN109629731B (en) * | 2019-01-30 | 2020-11-10 | 北京工业大学 | Assembly type invisible beam composite floor slab with separated pipelines installed from bottom to top |
CN109853803A (en) * | 2019-01-31 | 2019-06-07 | 河南聚誉帆工程技术咨询有限公司 | Assembled integral floor and fabrication and installation method |
CN110042984A (en) * | 2019-04-19 | 2019-07-23 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam of splitting type holes in soffit |
CN110306725A (en) * | 2019-04-19 | 2019-10-08 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam of holes in soffit |
CN110306724A (en) * | 2019-04-19 | 2019-10-08 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam for the welded type holes in soffit that misplaces |
CN110258920A (en) * | 2019-04-19 | 2019-09-20 | 北京工业大学 | A kind of prefabricated package Honeycomb Beam of holes in soffit |
CN110042985A (en) * | 2019-04-19 | 2019-07-23 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam of splitting type holes in soffit |
CN109930747A (en) * | 2019-04-19 | 2019-06-25 | 北京工业大学 | A kind of cast-in-place package Honeycomb Beam for the welded type holes in soffit that misplaces |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108385885A (en) | A kind of assembled stealth beam floor | |
CN108331222A (en) | A kind of Z-type connection quadrate steel pipe column-stealth beam floor assembly system | |
CN207348091U (en) | A kind of assembled pipe gallery | |
CN105019555A (en) | Novel steel reinforced concrete shearing wallboard fabricated building system | |
CN206873730U (en) | A kind of steel bar truss floor structure | |
CN108385884A (en) | A kind of bolted and welded connection steel reinforced concrete special-shape column-stealth beam floor assembly system | |
CN108360725A (en) | A kind of Z-shaped connection steel reinforced concrete special-shape column-stealth beam floor assembly system | |
CN108331225A (en) | A kind of Z-type joint steel pipe concrete profiled pile-stealth beam floor assembly system | |
CN103397700A (en) | Connection structure of building composite floor slab and steel tube shear wall | |
CN209457225U (en) | Assembled Castellated beam-truss bars concrete folding plate composite slim floor | |
CN109853873A (en) | Overlap concrete bidirectional stress insulation roof slab | |
CN107023103A (en) | A kind of part overlaps superimposed sheet with holes | |
CN105696453B (en) | A kind of steel-concrete combination beam | |
CN108331224A (en) | A kind of connection between assembled stealth beam floor | |
CN104264897B (en) | Alternate tooth must superimposed beam and plate | |
CN108331223A (en) | A kind of bolted and welded connection quadrate steel pipe column-stealth beam floor assembly system | |
CN103255834B (en) | Prefabricated heat preservation balcony suitable for industrial production and construction method of prefabricated heat preservation balcony | |
CN110409492A (en) | The combination assembled piping lane of one kind more structures containing superposed member and its construction method | |
CN108374512A (en) | A kind of bolted and welded connection concrete filled steel tube special-shape column-stealth beam floor assembly system | |
CN214785337U (en) | Prefabricated assembled concrete-filled steel tube composite column and building thereof | |
CN103541478B (en) | Lattice superposed beam and plate and construction method thereof | |
CN112922207A (en) | Concrete one-way laminated slab with exposed slab net frame at bottom | |
CN209397938U (en) | One kind reinforcing tooling for Double-side laminated co-clip heart heat-preservation shear wall wall root | |
CN207017528U (en) | A kind of prefabricated U-shaped composite beam | |
CN207499221U (en) | A kind of part overlaps superimposed sheet with holes |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180810 |