- CN108360912A CN108360912A CN201810396758.XA CN201810396758A CN108360912A CN 108360912 A CN108360912 A CN 108360912A CN 201810396758 A CN201810396758 A CN 201810396758A CN 108360912 A CN108360912 A CN 108360912A
- Authority
- CN
- China
- Prior art keywords
- slagging
- equipment
- pipeline
- environmental
- indoor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H13/00—Monuments; Tombs; Burial vaults; Columbaria
- E04H13/001—Accessories for grave sites, e.g. liners, covers, vault lowering devices
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B01—PHYSICAL OR CHEMICAL PROCESSES OR APPARATUS IN GENERAL
- B01D—SEPARATION
- B01D50/00—Combinations of methods or devices for separating particles from gases or vapours
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H13/00—Monuments; Tombs; Burial vaults; Columbaria
- E04H13/003—Funeral monuments, grave sites curbing or markers not making part of vaults
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H13/00—Monuments; Tombs; Burial vaults; Columbaria
- E04H13/005—Ventilation systems therefor
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H13/00—Monuments; Tombs; Burial vaults; Columbaria
- E04H13/006—Columbaria, mausoleum with frontal access to vaults
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Chemical Kinetics & Catalysis (AREA)
- Coin-Freed Apparatuses For Hiring Articles (AREA)
Abstract
This application involves one kind save land it is environmental and ecological bury indoor a complete set of equipment, including multiple tomb positions, further include dust pelletizing system and slag removing system;Multiple tomb positions are connect with dust pelletizing system and slag removing system respectively;Tomb position includes pedestal and storage rack;Display screen is provided on storage rack;Pedestal is internally provided with incinerator, air blower, by-pass flue and branch's slagging-off pipeline;Air blower is connect by ventilation duct with incinerator;The top of incinerator is connect by by-pass flue with dust pelletizing system;The bottom end of incinerator is connect by branch's slagging-off pipeline with slag removing system;It is also provided with burning mouth on the side wall of incinerator, burns the outside that mouth leads to pedestal.The present invention solves all drawbacks in traditional cemetery, has accomplished Economization on land, environmental protection, the purpose for meeting garden style service, the servicing of hommization, cheaply, service life length etc. advantage;It can be used for a long time, Economization on land area, price is low, environmentally protective, and can meet the feelings of cherishing the memory of souvenir of the people to the deceased.
Description
Technical field
This application involves funeral and interment product technical fields, and in particular to one kind, which saves land, environmental and ecological buries indoor a complete set of equipment.
Background technology
Social now, the whole world all suffers from the problem of soil anxiety, and especially cultivated area is fewer and fewer.Burial in the ground is China
Thousands of years folkways and customs, be desirable to relatives it is dead after being capable of " burial brings peace to the deceased ";But burial in the ground needs huge land resource, no
A large amount of land resource can be only occupied, and serious influence can be caused to the living environment of descendant.Country advocates cremation simultaneously
Cemetery is opened up to bury the bone ash of the deceased, this problem can be alleviated to a certain extent.But in recent years, with death toll
Be on the increase, the price of ceremony park graveyard constantly rises suddenly and sharply, not only expensive especially in some densely populated cities, very
To the phenomenon that there is also ceremony park envelope garden, the deceased is made nowhere to bury.
In addition, hold a memorial ceremony for visit, sacrifice rites are also one of custom important in Chinese traditional culture.Traditional ceremony park hold a memorial ceremony for visit when
It is open incineration paper money and offerings directly before cemetery, especially encountering Clear and Bright etc. holds a memorial ceremony for when paying a visit on holidays day, and ceremony park overhead flue gas is billowing,
Paper ash is boundless, not only influences atmospheric environment, but also many extra works are brought to the staff of ceremony park.In order to administer ceremony park
Environment, some ceremony parks are provided with multiple long stoves and burn mouth, and relatives hold a memorial ceremony for and need to be burned in long stove when visiing burning the nether world paper money, although controlling in this way
Ceremony park environment has been managed, but has encountered the when of offering a sacrifice to gods or ancestors red-letter day to need to be lined up, has brought inconvenience to holding a memorial ceremony for the people visitd in this way.
In the related technology, one side cemetery to the utilization ratio in soil also in lower level, due to population base Pang
Greatly, the required land area in cemetery is still a huge number, therefore cemetery cannot effectively solve the problems, such as land seizure;
On the other hand, cemetery still handles sacrificial offerings by the way of directly burning, and asking for flue dust is generated when long stove can not solve to burn
The problem of inscribing, and not allowing easy to clean there is also the lime-ash after burning.
Invention content
To overcome the problems, such as at least to a certain extent present in the relevant technologies, the application provide one kind save land it is environmental and ecological
Bury indoor a complete set of equipment.
According to an embodiment of the present application, provide one kind save land it is environmental and ecological bury indoor a complete set of equipment, including multiple tomb positions, also
Including dust pelletizing system and slag removing system;The multiple tomb position is connect with the dust pelletizing system and the slag removing system respectively;
The tomb position includes pedestal and storage rack;It is provided with display screen on the storage rack;
The pedestal is internally provided with incinerator, air blower, by-pass flue and branch's slagging-off pipeline;The air blower is logical
Ventilation duct is crossed to connect with the incinerator;The top of the incinerator is connect by the by-pass flue with the dust pelletizing system;
The bottom end of the incinerator is connect by branch slagging-off pipeline with the slag removing system;It is also opened on the side wall of the incinerator
There are burning mouth, the outside burned mouth and lead to the pedestal.
Further, the dust pelletizing system includes flue collector, primary cleaner, sack cleaner and dedusting fan;
The by-pass flue is connect with the flue collector;The flue collector leads to the primary cleaner;The primary
Cleaner, the sack cleaner and the dedusting fan are sequentially connected.
Further, the dust pelletizing system further includes multiple third motors;
The junction of each by-pass flue and the flue collector is correspondingly arranged a third motor.
Further, the dust pelletizing system further includes second except slag bath;
The bottom end of the primary cleaner and the bottom end of the sack cleaner are connected to described the by pipeline respectively
Two remove slag bath.
Further, the pedestal is internally provided with first motor, and the first motor removes the gred mounted on the branch
The junction of pipeline and the incinerator.
Further, the slag removing system includes that main slagging-off pipeline and first remove slag bath;
Branch's slagging-off pipeline is connect with the main slagging-off pipeline;The main slagging-off pipeline leads to first slagging-off
Pond.
Further, the slag removing system further includes multiple second motors;
The junction of each branch's slagging-off pipeline and the main slagging-off pipeline is correspondingly arranged second motor.
Further, the equipment includes multiple compartments, and a tomb position is correspondingly arranged in a compartment;
The compartment further includes the tomb position door that can be opened and closed, and the tomb position can be enclosed in the compartment by the tomb position door
It is internal;
It is provided with control panel on the wall of the side of the tomb position door.
Further, the equipment further includes circuit control system;
The circuit control system includes the control panel, and be electrically connected with the control panel tobacco control device,
Gating device, electric candle, light controller, slagging-off control device, ventilation controller and volume damper.
Further, the control panel includes main control circuit, display unit, card reader and key circuit, and display is single
Member, card reader and key circuit are electrically connected with main control circuit respectively.
The technical solution that embodiments herein provides can include the following benefits:
All drawbacks for solving traditional cemetery have accomplished Economization on land, environmental protection, the purpose for meeting garden style service, people
Property service, cheaply, service life length etc. advantage;It can be used for a long time, Economization on land area, price is low, green ring
It protects, and the feelings of cherishing the memory of souvenir of the people to the deceased can be met.
It should be understood that above general description and following detailed description is only exemplary and explanatory, not
The application can be limited.
Description of the drawings
The drawings herein are incorporated into the specification and forms part of this specification, and shows the implementation for meeting the application
Example, and the principle together with specification for explaining the application.
Fig. 1 is a kind of environmental and ecological internal structure for burying indoor a complete set of equipment that saves land shown according to an exemplary embodiment
Schematic diagram.
Fig. 2 is the close-up schematic view of a tomb position in Fig. 1.
Fig. 3 is the external structure schematic diagram according to a tomb position shown in an exemplary embodiment.
Fig. 4 is the external structure schematic diagram arranged side by side of multiple tomb positions shown according to an exemplary embodiment.
Fig. 5 is a kind of environmental and ecological circuit control for burying indoor a complete set of equipment that saves land shown according to an exemplary embodiment
System block diagram.
In figure:1- tombs position facade;2- tombs position door;3- tombs position label;24 filial piety figures of 4-;5- control panels;6- flue collectors;
The main slagging-off pipelines of 7-;8- burns mouth;9- display screens;10- storage racks;11- by-pass flues;12- air blowers;13- first motors;
14- branches slagging-off pipeline;15- first removes slag bath;The second motors of 16-;17- third motors;18- primary cleaners;19- is managed
Road;20- sack cleaners;21- dedusting fans;22- second removes slag bath;23- tobacco control devices;24- gating devices;25- electronic waxes
Candle;26- light controllers;27- slagging-off control devices;28- ventilation controllers;29- volume dampers.
Specific implementation mode
Example embodiments are described in detail here, and the example is illustrated in the accompanying drawings.Following description is related to
When attached drawing, unless otherwise indicated, the same numbers in different drawings indicate the same or similar elements.Following exemplary embodiment
Described in embodiment do not represent all embodiments consistent with the application.On the contrary, they be only with it is such as appended
The example of consistent device and method of some aspects be described in detail in claims, the application.
Fig. 1 is a kind of environmental and ecological internal structure for burying indoor a complete set of equipment that saves land shown according to an exemplary embodiment
Schematic diagram.As shown in Figure 1, one kind save land it is environmental and ecological bury indoor a complete set of equipment, including multiple tomb positions, further include dust pelletizing system and
Slag removing system;The multiple tomb position is connect with the dust pelletizing system and the slag removing system respectively.
As shown in Fig. 2, the tomb position includes pedestal and storage rack 10;Display screen 9 is provided on the storage rack 10.
The pedestal is internally provided with incinerator, air blower 12, by-pass flue 11 and branch's slagging-off pipeline 14;The drum
Wind turbine 12 is connect by ventilation duct with the incinerator;The top of the incinerator passes through the by-pass flue 11 and the dedusting
System connects;The bottom end of the incinerator is connect by branch slagging-off pipeline 14 with the slag removing system;The incinerator
Side wall on be also provided with and burn mouth 8, the mouth 8 that burns leads to the outside of the pedestal.
The present invention carries the device of incinerator and dust suction smoke abatement, disclosure satisfy that funeral family carries out burning the nether world paper money before old friend's tomb
Demand, burning the paper ash that the nether world paper money generates can be automatically discharged into except in slag bath, any pollution will not be caused to graveyard environment, ceremony park
Staff need to will only clean up except the ashes in slag bath in cleaning, considerably reduce workload.This hair
It is provided with LED display 9 on bright, the deadee and biography of the deceased can be shown on display screen 9.The present invention is arranged in room
Interior, burial brings peace to the deceased is changed into and enters the room as honor by traditional.
The pedestal is internally provided with first motor 13, and the first motor 13 is mounted on branch slagging-off pipeline 14
With the junction of the incinerator.First motor 13 is branch's slagging-off motor, for the Ash water that generates incinerator to dividing
Branch removes the gred in pipeline 14.
As shown in Figure 3 and Figure 4, described one kind save land it is environmental and ecological to bury indoor a complete set of equipment include multiple compartments, one
A tomb position is correspondingly arranged in the compartment.
The compartment further includes the tomb position door 2 that can be opened and closed, tomb position door 2 the tomb position can be enclosed in it is described every
Between it is internal.It is provided with control panel 5 on the wall of the side of the tomb position door 2.
The dust pelletizing system includes flue collector 6, primary cleaner 18, sack cleaner 20 and dedusting fan 21.Specifically
Ground, primary cleaner 18 use stainless steel sintered meshwork, with excellent filtering accuracy, filtering impedance, mechanical strength, wear-resisting
Property, heat resistance and processed property, are a kind of outstanding filtering materials.
The by-pass flue 11 is connect with the flue collector 6;The flue collector 6 leads to the primary cleaner 18;Institute
Primary cleaner 18, the sack cleaner 20 and the dedusting fan 21 is stated to be sequentially connected.
The dust pelletizing system further includes multiple third motors 17.The company of each by-pass flue 11 and the flue collector 6
The place of connecing is correspondingly arranged a third motor 17.Third motor 17 is that flue turnover panel controls motor, for driving in flue
The reprint of setting.Reprint is opened in smoke evacuation, smog is made to be smoothly discharged;Reprint is closed when not discharging fume, and prevents other tomb positions
Smog pour in down a chimney into this tomb position.
The dust pelletizing system further includes second except slag bath 22.The bottom end of the primary cleaner 18 and the bag-type dusting
The bottom end of device 20 is connected to described second by pipeline respectively and removes slag bath 22.
The slag removing system includes that main slagging-off pipeline 7 and first removes slag bath 15.Branch's slagging-off pipeline 14 and the master
The pipeline 7 that removes the gred connects;The main slagging-off pipeline 7 leads to described first and removes slag bath 15.
The slag removing system further includes multiple second motors 16.Each branch's slagging-off pipeline 14 is managed with the main slagging-off
The junction in road 7 is correspondingly arranged second motor 16.Second motor 16 is main slagging-off feeder motor, for removing branch
In Ash water to main slagging-off pipeline 7 in slag pipeline 14.
As shown in figure 5, the equipment of the application further includes circuit control system, to the various electronic devices in control device
It works, ensures the operation of equipment entirety.The circuit control system includes control panel 5, and electric with control panel 5
Tobacco control device 23, gating device 24, electric candle 25, light controller 26, slagging-off control device 27, the ventilation controller of connection
28 and volume damper 29.
Wherein, control panel 5 includes main control circuit, display unit, card reader and key circuit, and display unit is swiped the card
Device and key circuit are electrically connected with main control circuit respectively;Tobacco control device 23, gating device 24 etc. also respectively with main control circuit
Electrical connection.Further, display unit is used for figure and written form operation display interface.Key circuit is for being inputted
Operation, to adjust volume, image, and manipulates the work of other devices.
Card reader authentication information for identification, to start and close the work of main control circuit.The POS reads record
After having the magnetic card (or IC card etc.) of subscriber identity information, start the work of main control circuit, to which user can be in control plane
Various operations are carried out on plate;After magnetic card is removed, main control circuit closes all master control electric currents, and user can not grasp again
Make.
Tobacco control device 23 includes smoke sensor device and ventilation fan, and the two is electrically connected with main control circuit.Smoke sensor device
Smokescope for detecting indoor environment.Main control circuit receives the data of smokescope, when smokescope is more than setting
Threshold value then starts ventilation fan work with vapour discharge, to which indoor air environment is maintained normal level.
Gating device 24 includes electric machine controller and switch door motor, switch door motor, electric machine controller and main control electricity
Road is sequentially connected electrically.By the work of electric machine controller driving switch door motor, switching door motor can drive main control circuit
Tomb position door 2 is switched.To which user can manipulate the switch of tomb position door 2 by control panel 5.
Electric candle 25 can be placed on storage rack 10, and electric candle 25 is electrically connected with main control circuit.To user
The work of electric candle 25 can be manipulated by control panel 5.Electric candle 25 can substitute common candle and visit work for holding a memorial ceremony for
It is dynamic, to reduce the air pollution of candle combustion generation;And electric candle can be reused, and cost is reduced.
Light controller 26 include lighting control circuit and tomb position lamp, tomb position lamp, lighting control circuit and main control circuit according to
Secondary electrical connection.Tomb position lamp can be arranged on tomb position door 2 and/or on storage rack 10, and user can control tomb by control panel 5
The work of position lamp.
The control device 27 that removes the gred includes slagging-off control cabinet and slagging-off motor, slagging-off motor, slagging-off control cabinet and and main control
Circuit is sequentially connected electrically.Slagging-off motor includes first motor 13 and multiple second motors 16, multiple motors by slagging-off control cabinet into
Row centralized control.
Ventilation controller 28 includes air-introduced machine control cabinet, blower motor and air compressor, air-introduced machine control cabinet and master
Control circuit is electrically connected, and blower motor, air compressor are electrically connected with air-introduced machine control cabinet respectively.Ventilation controller 28 is used for
The circulation for carrying out indoor and outdoor air, ensures the pure and fresh of room air.
Volume damper 29 is electrically connected with main control circuit, the air quantity for adjusting central air-conditioning air outlet.
It should be noted that in the description of the present application, term " first ", " second " etc. are used for description purposes only, without
It can be interpreted as indicating or implying relative importance.In addition, in the description of the present application, unless otherwise indicated, the meaning of " multiple "
Refer at least two.
In the description of this specification, reference term " one embodiment ", " some embodiments ", " example ", " specifically show
The description of example " or " some examples " etc. means specific features, structure, material or spy described in conjunction with this embodiment or example
Point is contained at least one embodiment or example of the application.In the present specification, schematic expression of the above terms are not
Centainly refer to identical embodiment or example.Moreover, particular features, structures, materials, or characteristics described can be any
One or more embodiments or example in can be combined in any suitable manner.
Although embodiments herein has been shown and described above, it is to be understood that above-described embodiment is example
Property, it should not be understood as the limitation to the application, those skilled in the art within the scope of application can be to above-mentioned
Embodiment is changed, changes, replacing and modification.
Claims (10)
1. one kind saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:Including multiple tomb positions, further include dust pelletizing system and
Slag removing system;The multiple tomb position is connect with the dust pelletizing system and the slag removing system respectively;
The tomb position includes pedestal and storage rack;It is provided with display screen on the storage rack;
The pedestal is internally provided with incinerator, air blower, by-pass flue and branch's slagging-off pipeline;The air blower passes through logical
Air hose is connect with the incinerator;The top of the incinerator is connect by the by-pass flue with the dust pelletizing system;It is described
The bottom end of incinerator is connect by branch slagging-off pipeline with the slag removing system;It is also provided with and burns on the side wall of the incinerator
Burn mouth, the outside burned mouth and lead to the pedestal.
2. one kind according to claim 1 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:The dedusting system
System includes flue collector, primary cleaner, sack cleaner and dedusting fan;
The by-pass flue is connect with the flue collector;The flue collector leads to the primary cleaner;The primary dedusting
Equipment, the sack cleaner and the dedusting fan are sequentially connected.
3. one kind according to claim 2 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:The dedusting system
System further includes multiple third motors;
The junction of each by-pass flue and the flue collector is correspondingly arranged a third motor.
4. one kind according to claim 3 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:The dedusting system
System further includes second except slag bath;
The bottom end of the primary cleaner and the bottom end of the sack cleaner are connected to described second by pipeline respectively and remove
Slag bath.
5. one kind according to any one of claims 1 to 4 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:
The pedestal is internally provided with first motor, and the first motor is mounted on branch slagging-off pipeline and the incinerator
Junction.
6. one kind according to claim 5 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:It is described to remove slag system
System includes that main slagging-off pipeline and first remove slag bath;
Branch's slagging-off pipeline is connect with the main slagging-off pipeline;The main slagging-off pipeline leads to described first and removes slag bath.
7. one kind according to claim 6 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:It is described to remove slag system
System further includes multiple second motors;
The junction of each branch's slagging-off pipeline and the main slagging-off pipeline is correspondingly arranged second motor.
8. one kind according to any one of claims 1 to 4 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:
Including multiple compartments, a tomb position is correspondingly arranged in a compartment;
The compartment further includes the tomb position door that can be opened and closed, and the tomb position can be enclosed in the compartment by the tomb position door
Portion;
It is provided with control panel on the wall of the side of the tomb position door.
9. one kind according to claim 8 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:The equipment is also
Including circuit control system;
The circuit control system includes the control panel, and tobacco control device, the gate being electrically connected with the control panel
Device, electric candle, light controller, slagging-off control device, ventilation controller and volume damper.
10. one kind according to claim 9 saves land and environmental and ecological buries indoor a complete set of equipment, it is characterised in that:The control
Panel includes main control circuit, display unit, card reader and key circuit, display unit, card reader and key circuit respectively with
Main control circuit is electrically connected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810396758.XA CN108360912A (en) | 2018-04-27 | 2018-04-27 | It saves land and environmental and ecological buries indoor a complete set of equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810396758.XA CN108360912A (en) | 2018-04-27 | 2018-04-27 | It saves land and environmental and ecological buries indoor a complete set of equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108360912A true CN108360912A (en) | 2018-08-03 |
Family
ID=63009560
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810396758.XA Pending CN108360912A (en) | 2018-04-27 | 2018-04-27 | It saves land and environmental and ecological buries indoor a complete set of equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108360912A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109739165A (en) * | 2019-01-16 | 2019-05-10 | 秦皇岛海涛万福环保设备股份有限公司 | Outdoor ceremony park monitoring method and monitoring system |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104406417A (en) * | 2014-11-25 | 2015-03-11 | 江苏溧竹环境工程有限公司 | Dust removal system for high-temperature flue gas |
CN204457050U (en) * | 2015-02-04 | 2015-07-08 | 秦皇岛市海涛殡葬用品有限公司 | The indoor cemetery of familial intelligent environment protection |
CN206222292U (en) * | 2016-12-02 | 2017-06-06 | 珠海市建华锅炉机械工程有限公司 | A kind of biomass boiler energy-saving combustion system |
-
2018
- 2018-04-27 CN CN201810396758.XA patent/CN108360912A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104406417A (en) * | 2014-11-25 | 2015-03-11 | 江苏溧竹环境工程有限公司 | Dust removal system for high-temperature flue gas |
CN204457050U (en) * | 2015-02-04 | 2015-07-08 | 秦皇岛市海涛殡葬用品有限公司 | The indoor cemetery of familial intelligent environment protection |
CN206222292U (en) * | 2016-12-02 | 2017-06-06 | 珠海市建华锅炉机械工程有限公司 | A kind of biomass boiler energy-saving combustion system |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109739165A (en) * | 2019-01-16 | 2019-05-10 | 秦皇岛海涛万福环保设备股份有限公司 | Outdoor ceremony park monitoring method and monitoring system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108360912A (en) | It saves land and environmental and ecological buries indoor a complete set of equipment | |
CN107995826A (en) | A kind of server room ventilating system | |
CN204435994U (en) | The indoor cemetery of fully-automatic intelligent environmental protection | |
CN202361586U (en) | Fixed-point fresh air supply device | |
CN102705953A (en) | Heat pipe type fresh air ventilator unit special for edible mushroom factory | |
CN201734466U (en) | Multimedia intelligent environment-friendly sacrificial stage | |
CN101936563A (en) | Smoke exhaust ventilator and air curtain device | |
CN2523817Y (en) | Unit combined clean operation rooms | |
CN207067772U (en) | A kind of hospital's ultra-clean system | |
CN209047854U (en) | Intelligent environment protection offers a sacrifice to gods or ancestors garden | |
CN209028875U (en) | Sludge incinerator simulation system | |
CN106760404A (en) | A kind of fume extractor for substituting underground garage Ventilator Room | |
CN214548763U (en) | Sacrificial rites burns burning furnace with dust function of discharging fume | |
CN204457050U (en) | The indoor cemetery of familial intelligent environment protection | |
CN207599710U (en) | A kind of incinerator | |
CN205671912U (en) | Environment-friendly type offers a sacrifice to gods or ancestors thing CIU and mobile sacrifice room | |
CN111282612A (en) | Clean workbench | |
CN217004774U (en) | Intelligent ventilation system device for laboratory | |
CN209074085U (en) | A kind of burning joss furnace | |
CN209541419U (en) | A kind of resistance furnace easy to use | |
CN210197291U (en) | Ash-picking cooling system of cremation machine | |
CN208471918U (en) | A kind of straight barrel type energy conservation and environmental protection lime burner furnace | |
CN209512217U (en) | A kind of odorless air-change system applied in lavatory | |
CN108766094A (en) | sludge incinerator simulation system | |
CN207569994U (en) | A kind of air cleaning intelligent home equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180803 |
|
RJ01 | Rejection of invention patent application after publication |