CN108360458A - 整体型多向护坡石笼及施工方法 - Google Patents

整体型多向护坡石笼及施工方法 Download PDF

Info

Publication number
CN108360458A
CN108360458A CN201810498907.3A CN201810498907A CN108360458A CN 108360458 A CN108360458 A CN 108360458A CN 201810498907 A CN201810498907 A CN 201810498907A CN 108360458 A CN108360458 A CN 108360458A
Authority
CN
China
Prior art keywords
gabion
highstrenghtpiston
hexahedron
high intensity
double end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810498907.3A
Other languages
English (en)
Inventor
程玮
赵双
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road Anhui Engineering Material Co Ltd
Original Assignee
Road Anhui Engineering Material Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road Anhui Engineering Material Co Ltd filed Critical Road Anhui Engineering Material Co Ltd
Priority to CN201810498907.3A priority Critical patent/CN108360458A/zh
Publication of CN108360458A publication Critical patent/CN108360458A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/12Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
    • E02B3/122Flexible prefabricated covering elements, e.g. mats, strips
    • E02B3/123Flexible prefabricated covering elements, e.g. mats, strips mainly consisting of stone, concrete or similar stony material

Abstract

本发明涉及河流边坡维护技术领域,尤其是整体型多向护坡石笼,包括六面体石笼,所述六面体石笼由六个高强度塑料网格组合而成,每两个相邻的高强度塑料网格通过高强度双头锁扣捆扎在一起,所述高强度双头锁扣包括两个单头锁扣,两个所述单头锁扣通过连接杆固接在一起,施工方法为:折叠运输、高强度双头锁扣捆扎成型、填料、封装。本装置结构简单,运输安装起来更加方便,提高施工效率,而且本装置采用高强度塑料网格作用基材施工,使用寿命更长,使用效果更好,减少边坡防护装置维修更换次数,降低维修成本。

Description

整体型多向护坡石笼及施工方法
技术领域
本发明涉及河流边坡维护技术领域,尤其涉及整体型多向护坡石笼及施工方法。
背景技术
边坡防护主动防护系统是以钢丝绳网为主的各类柔性网覆盖包裹在所需防护斜坡或岩石上,以限制坡面岩石土体的风化剥落或破坏以及危岩崩塌(加固作用),或将落石控制于一定范围内运动(围护作用)。
双向土工格栅是用高分子聚合物通过挤压、成板、冲孔过程后再纵向、横向拉伸而成。该材料在纵向和横向上都具有很大的拉伸强度。
现在河流边坡防护时,都是采用钢丝网石笼安装在边坡上,长期使用后钢丝网石笼会锈蚀,使用寿命短,钢丝网锈蚀断裂后,将造成河流边坡泥土流失,而且钢丝网重量很大,运输起来很不方便。
发明内容
本发明的目的是为了解决现有技术中钢丝网石笼使用效果不好的缺点,而提出的整体型多向护坡石笼及施工方法。
为了实现上述目的,本发明采用了如下技术方案:
设计整体型多向护坡石笼,包括六面体石笼,所述六面体石笼由六个高强度塑料网格组合而成,每两个相邻的高强度塑料网格通过高强度双头锁扣捆扎在一起;
所述高强度双头锁扣包括两个单头锁扣,两个所述单头锁扣通过连接杆固接在一起,通过高强度双头锁扣捆扎后,有效防止相邻两个高强度塑料网格使用过程中发生错位现象,能够将六面体石笼捆扎的更加牢固。
优选的,所述高强度双头锁扣为高强度尼龙扎带。
优选的,所述高强度双头锁扣采用一体化成型。
整体型多向护坡石笼施工方法,包括以下步骤:
步骤一:六面体石笼的运输:首先将六个高强度塑料网格拼接成Z形结构,然后通过高强度双头锁扣将相邻的两个高强度塑料网格连接在一起,然后按照顺序折叠起来,将六个高强度塑料网格按照顺序折叠起来,减小空间占用率,方便运输;
步骤二:到达工地后,将折叠好的高强度塑料网格伸展开,然后通过高强度双头锁扣将其中五个高强度塑料网格连接在一起,将顶面的高强度塑料网格打开,使六面体石笼呈敞口状态,按照顺序伸展开后,通过高强度双头锁扣捆扎,安装起来简单方便,使用的时候更加方便,而且质量轻,抗拉强度高;
步骤三:从边坡由上到下安装,组装好多个六面体石笼后,排成一列,通过高强度双头锁扣将相邻的两个六面体石笼连接在一起,然后在相邻两排六面体石笼之间放置一个土工布,然后在六面体石笼中间填装泥土或者石块,相同列的六面体石笼之间通过泥土和石块连接成一个整体,提高防护性能,相邻两排六面体石笼之间通过土工布隔开,防止泥土流失到河水中;
步骤四:填装完成后,将顶部的高强度塑料网格通过高强度双头锁扣与四周的高强度塑料网格连接在一起,封装起来简单方便。
本发明提出的整体型多向护坡石笼及施工方法,有益效果在于:本装置结构简单,运输安装起来更加方便,提高施工效率,而且本装置采用高强度塑料网格作用基材施工,使用寿命更长,使用效果更好,减少边坡防护装置维修更换次数,降低维修成本。
附图说明
图1为本发明的六面体石笼结构示意图;
图2为本发明的单头锁扣结构示意图;
图3为本发明的六面体石笼安装结构示意图;
图4为本发明的高强度塑料网格折叠结构示意图;
图5为本发明的高强度塑料网格平铺结构示意图。
图中:六面体石笼1、高强度双头锁扣2、高强度塑料网格3、单头锁扣4、连接杆5、土工布6。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。
参照图1-5,整体型多向护坡石笼,包括六面体石笼1,六面体石笼1由六个高强度塑料网格3组合而成,每两个相邻的高强度塑料网格3通过高强度双头锁扣2捆扎在一起,高强度双头锁扣2为高强度尼龙扎带,高强度双头锁扣2采用一体化成型;
高强度双头锁扣2包括两个单头锁扣4,两个单头锁扣4通过连接杆5固接在一起,通过高强度双头锁扣2捆扎后,有效防止相邻两个高强度塑料网格3使用过程中发生错位现象,能够将六面体石笼捆扎的更加牢固。
整体型多向护坡石笼施工方法,包括以下步骤:
步骤一:六面体石笼的运输:首先将六个高强度塑料网格拼接成Z形结构,然后通过高强度双头锁扣将相邻的两个高强度塑料网格连接在一起,然后按照顺序折叠起来,将六个高强度塑料网格按照顺序折叠起来,减小空间占用率,方便运输;
步骤二:到达工地后,将折叠好的高强度塑料网格伸展开,然后通过高强度双头锁扣将其中五个高强度塑料网格连接在一起,将顶面的高强度塑料网格打开,使六面体石笼呈敞口状态,按照顺序伸展开后,通过高强度双头锁扣捆扎,安装起来简单方便,使用的时候更加方便,而且质量轻,抗拉强度高;
步骤三:从边坡由上到下安装,组装好多个六面体石笼后,排成一列,通过高强度双头锁扣将相邻的两个六面体石笼连接在一起,然后在相邻两排六面体石笼之间放置一个土工布,然后在六面体石笼中间填装泥土或者石块,相同列的六面体石笼之间通过泥土和石块连接成一个整体,提高防护性能,相邻两排六面体石笼之间通过土工布隔开,防止泥土流失到河水中;
步骤四:填装完成后,将顶部的高强度塑料网格通过高强度双头锁扣与四周的高强度塑料网格连接在一起,封装起来简单方便。
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。

Claims (4)

1.整体型多向护坡石笼,其特征在于,包括六面体石笼(1),所述六面体石笼(1)由六个高强度塑料网格(3)组合而成,每两个相邻的高强度塑料网格(3)通过多个高强度双头锁扣(2)捆扎在一起;
所述高强度双头锁扣(2)包括两个单头锁扣(4),两个所述单头锁扣(4)通过连接杆(5)固接在一起。
2.根据权利要求1所述的整体型多向护坡石笼,其特征在于,所述高强度双头锁扣(2)为高强度尼龙扎带。
3.根据权利要求1所述的整体型多向护坡石笼,其特征在于,所述高强度双头锁扣(2)采用一体化成型。
4.权利要求1所述的整体型多向护坡石笼施工方法,其特征在于,包括以下步骤:
步骤一:六面体石笼的运输:首先将六个高强度塑料网格拼接成Z形结构,然后通过高强度双头锁扣将相邻的两个高强度塑料网格连接在一起,然后按照顺序折叠起来;
步骤二:到达工地后,将折叠好的高强度塑料网格伸展开,然后通过高强度双头锁扣将其中五个高强度塑料网格连接在一起,将顶面的高强度塑料网格打开,使六面体石笼呈敞口状态;
步骤三:从边坡由上到下安装,组装好多个六面体石笼后,排成一列,通过高强度双头锁扣将相邻的两个六面体石笼连接在一起,然后在相邻两排六面体石笼之间放置一个土工布,然后在六面体石笼中间填装泥土或者石块;
步骤四:填装完成后,将顶部的高强度塑料网格通过高强度双头锁扣与四周的高强度塑料网格连接在一起。
CN201810498907.3A 2018-05-23 2018-05-23 整体型多向护坡石笼及施工方法 Pending CN108360458A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810498907.3A CN108360458A (zh) 2018-05-23 2018-05-23 整体型多向护坡石笼及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810498907.3A CN108360458A (zh) 2018-05-23 2018-05-23 整体型多向护坡石笼及施工方法

Publications (1)

Publication Number Publication Date
CN108360458A true CN108360458A (zh) 2018-08-03

Family

ID=63012445

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810498907.3A Pending CN108360458A (zh) 2018-05-23 2018-05-23 整体型多向护坡石笼及施工方法

Country Status (1)

Country Link
CN (1) CN108360458A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109295925A (zh) * 2018-11-13 2019-02-01 中国科学院寒区旱区环境与工程研究所 石笼边框、石笼及石笼护坡装置

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8103036A (nl) * 1981-06-23 1983-01-17 Ballast Nedam Groep Nv Maritieme constructie en werkwijze en monoliet voor het bouwen ervan.
CN2739230Y (zh) * 2004-08-07 2005-11-09 梁建国 带封边粘条的塑料水利笼箱网材
CN101522995A (zh) * 2007-01-02 2009-09-02 海斯科堡垒有限公司 石笼展开
CN104314046A (zh) * 2014-11-17 2015-01-28 宁夏防汛抗旱指挥部办公室 采用土工格栅结构体进行河道进占和护脚施工的方法
CN205369207U (zh) * 2015-12-31 2016-07-06 安徽中路工程材料有限公司 加强型抗拉伸土工格栅
CN205653750U (zh) * 2016-04-20 2016-10-19 河海大学 一种生态固土防洪石笼
CN206667176U (zh) * 2017-03-25 2017-11-24 河北福朗斯金属丝网制品有限公司 一种组合式石笼网箱

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL8103036A (nl) * 1981-06-23 1983-01-17 Ballast Nedam Groep Nv Maritieme constructie en werkwijze en monoliet voor het bouwen ervan.
CN2739230Y (zh) * 2004-08-07 2005-11-09 梁建国 带封边粘条的塑料水利笼箱网材
CN101522995A (zh) * 2007-01-02 2009-09-02 海斯科堡垒有限公司 石笼展开
CN104314046A (zh) * 2014-11-17 2015-01-28 宁夏防汛抗旱指挥部办公室 采用土工格栅结构体进行河道进占和护脚施工的方法
CN205369207U (zh) * 2015-12-31 2016-07-06 安徽中路工程材料有限公司 加强型抗拉伸土工格栅
CN205653750U (zh) * 2016-04-20 2016-10-19 河海大学 一种生态固土防洪石笼
CN206667176U (zh) * 2017-03-25 2017-11-24 河北福朗斯金属丝网制品有限公司 一种组合式石笼网箱

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109295925A (zh) * 2018-11-13 2019-02-01 中国科学院寒区旱区环境与工程研究所 石笼边框、石笼及石笼护坡装置

Similar Documents

Publication Publication Date Title
EP1680552B1 (en) A protective wire net, a protective structure constructed with the net and the use of the protective wire net for the construction of a protective structure
CN205712741U (zh) 强化柱体的围束箍筋结构及强化的柱结构
CN206667270U (zh) 斜坡防护网安装结构
CN108360458A (zh) 整体型多向护坡石笼及施工方法
CN208455570U (zh) 整体型多向护坡石笼
KR101207714B1 (ko) 충격에너지의 분배 및 흡수가 가능한 낙석방지 울타리
CN110409373A (zh) 一种抗洪抢险网装置及其应用和使用方法
US20090010718A1 (en) Method of and system for sedimentation retaining barrier packing and handling
CN217918341U (zh) 一种浮体阵列的防护装置
CN201459742U (zh) 拱形防护系统
CN108049367A (zh) 一种堤坝防护结构及其施工方法
KR101321232B1 (ko) 지반보호천이 결합된 돌망태
CN205894022U (zh) 一种水利护坡网
JP4702700B2 (ja) 越波防止装置
CN212200248U (zh) 一种安全性强的堤坝网具安装结构
JP6330454B2 (ja) 防護ネット及びその施工方法並びに既設防護ネットに対する補強構造及びその施工方法
CN211949893U (zh) 一种新型热镀锌铁路防护网
CN206220022U (zh) 环形绞索高速公路主动防护网
TW201510322A (zh) 衝擊吸收用堤體
CN210917399U (zh) 一种水土保持用土坡防塌陷装置
JP2005261904A (ja) 津波・洪水等の非常事態からの避難装置
CN207556381U (zh) 一种整体式爆破作业安全防护罩
CN111502398B (zh) 一种用于围栏养殖的编织网连接方法
CN201459617U (zh) 直立悬臂式防护系统
RU158018U1 (ru) Сетчатое ограждение от скально-обвальных явлений

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180803