CN108343081A
CN108343081A CN201710047700.XA CN201710047700A CN108343081A CN 108343081 A CN108343081 A CN 108343081A CN 201710047700 A CN201710047700 A CN 201710047700A CN 108343081 A CN108343081 A CN 108343081A
Authority
CN
China
Prior art keywords
wall
foundation pit
catch basin
pvc pipe
pit side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710047700.XA
Other languages
Chinese (zh)
Inventor
于元峰
施玉岩
王自文
李强
宗士昌
王文明
李芳�
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING AIDI GEOLOGICAL PROSPECTING FOUNDATION ENGINEERING Co Ltd
Original Assignee
BEIJING AIDI GEOLOGICAL PROSPECTING FOUNDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AIDI GEOLOGICAL PROSPECTING FOUNDATION ENGINEERING Co Ltd filed Critical BEIJING AIDI GEOLOGICAL PROSPECTING FOUNDATION ENGINEERING Co Ltd
Priority to CN201710047700.XA priority Critical patent/CN108343081A/en
Publication of CN108343081A publication Critical patent/CN108343081A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits

Abstract

A kind of foundation pit side-wall drainage arrangement and construction method are disclosed in the present invention, it is dredged applied to backwater after the concrete face wall of foundation pit, it include the catch basin after being set to concrete face wall close to concrete face wall, and the catch basin is stretched into one end, the other end extends the aqueduct outside concrete face wall, gravel material is filled in the catch basin, it forms catch basin by being excavated after the concrete face wall of foundation pit side-wall, and it is filled and is supported with seepy material, so that the backwater in the soil body after concrete face wall enters catch basin, and it is discharged by the aqueduct in catch basin, effectively to export the backwater after concrete face wall.

Description

Foundation pit side-wall drainage arrangement and construction method
Technical field
The present invention relates to foundation pit construction field, more particularly to a kind of foundation pit side-wall drainage arrangement and construction method.
Background technology
In foundation pit construction, it is often necessary to hydrophobic water guide is carried out to foundation pit side-wall and bottom wall, by the soil body in foundation pit In backwater drainage.Existing Normal practice is to do hydrophobic water guiding system, i.e.,:Aqueduct is inserted in the slope surface of side slope, by slope Backwater behind face dredges out, and drainage groove is done in bottom of foundation ditch, to collect the backwater of bottom of foundation ditch, and will be derived from aqueduct Water introduces drainage groove and uniformly drains.
In general, the way of aqueduct is analogous to the soakaway trench on ground, i.e., beaten on the tube body of PVC PE materials Hole, and in the tube body outer cladding strainer for being provided with open-work, then this part tube body is inserted into the subsequent soil body of slope surface, after slope surface The backwater of the soil body enters aqueduct by open-work, carries out white-out, strainer is then to bring silt into open-work when preventing water from entering tube body On blocked.
But in practical applications, the water inlet area of aqueduct is only the superposition of open-work area, and 33 even due to the weight of water Force effect, some open-works are flowed into without water at all, and therefore, rarely water is discharged aqueduct, and the backwater after the slope surface of foundation pit is still It is oozed out by slope surface large area, influences the stability of concrete face wall sprayed in slope surface.
Invention content
The purpose of the present invention is to provide backwater drainages after a kind of slope surface on foundation pit side-wall to be drained with foundation pit side-wall Device.
The present invention above-mentioned purpose technical scheme is that:A kind of foundation pit side-wall drainage arrangement, is answered It is dredged for backwater after the concrete face wall of foundation pit, includes the catch basin after being set to concrete face wall close to concrete face wall, And the catch basin is stretched into one end, the other end extends the aqueduct outside concrete face wall, and gravel is filled in the catch basin Material.
By using above-mentioned technical proposal, the position collected as backwater using catch basin, the water in the soil body is oozed out outward When, initially enter catch basin, after the water in catch basin saves bit by bit a certain amount of, aqueduct discharges it, prevent backwater can not from dredge Export comes and is oozed out from concrete face wall.Seepage material is filled in the side wall and roof that support catch basin is played in catch basin Effect catch basin is flooded when preventing backwater from penetrating into.
Preferably, the catch basin includes four side walls, roof and bottom wall, four sidewalls vertical settings, the bottom wall edge Horizontal direction includes at least two sections of slopes, and the inclined direction of adjacent slopes is low-lying to be formed on bottom wall on the contrary, shown water guide Pipe is inserted into shown low-lying place.
By using above-mentioned technical proposal, two, four or more slopes is arranged according to the length of catch basin in bottom wall, When adjacent slopes reversed dip, can be formed in intersection it is low-lying, backwater enter catch basin after, hitherward converged along slope, then It is inserted into aqueduct at this convergence to be drained, can preferably realize that backwater is collected, and reduce the quantity of aqueduct.
Preferably, the roof is arranged obliquely from the soil body in concrete face wall to foundation pit.
By using above-mentioned technical proposal, roof is arranged for inclined-plane, and the area that water penetrates into catch basin increases, also, catchments When the pressure of the soil body above slot acts on the inclined-plane of catch basin, the pressure of the soil body is decomposed by horizontal component, reduces longitudinal pressure, Catch basin is prevented to be collapsed.
Preferably, the aqueduct is consolidated to concrete face wall.
By using above-mentioned technical proposal, drainpipe, which is fixed to concrete face wall, can prevent aqueduct play, influence to lead Water pipe stretches into the depth of catch basin.
Preferably, the pvc pipe inserted with axis horizontal setting in the catch basin leans on the axis direction of the pvc pipe It is provided with opening on the side wall of nearly concrete face wall, several water seepage holes is offered on the tube wall on pvc pipe on the opening, it is described Gravel material is filled in pvc pipe, and shown aqueduct stretches into pvc pipe.
By using above-mentioned technical proposal, for the foundation pit of the soft bottom such as sandy soil, backfill, the soil after concrete face wall Constitution it is softer, when water is flowed to catch basin, soften due to the discharge of water in the soil body and deform, catch basin is using one Even not yet it is in time for water guide after the section time just to collapse and be submerged, " support of the water seepage hole as catch basin is opened using pvc pipe Skeleton ", backwater enter across water seepage hole in pvc pipe, and the soil body is converged by pipe walls support, water in pvc pipe, pvc pipe opening Place is for placing aqueduct.
Preferably, the gravel material is any one or a few combination in rubble, cobblestone, woven bag.
By using above-mentioned technical proposal, rubble, cobblestone etc. are the granular material of bulk, can not only play infiltration and make With the side wall soil body of catch basin can also be supported to prevent the soil body from collapsing while catchmenting;When soil body itself is more closely knit, Using woven bag simple and easy to get as filler, its intensive water hole can be utilized, realizes better earth-retaining in catch basin Effect.
Another goal of the invention of the present invention is to provide a kind of construction method for processing above-mentioned foundation pit side-wall drainage arrangement, To process above-mentioned foundation pit side-wall drainage arrangement in foundation pit side-wall, starches the backwater in foundation pit side-wall in the soil body and put together progress Dredge discharge.
The above-mentioned purpose of the present invention is achieved by the following technical solution:A kind of construction party of foundation pit side-wall drainage arrangement Method includes at least following steps:
Step 1 is excavated with Luoyang Spade on foundation pit side-wall in the horizontal direction, forms sidewalls vertical and bottom wall has along excavation side To the catch basin for including at least two sections slopes;
Soft degree of the step 2 according to the soil body after foundation pit side-wall, the gravel material of appropriate material is filled into catch basin;
Step 3 is inserted into aqueduct to the low-lying place to catchment in groove bottom wall.
It, can be in advance in foundation pit before the concrete topping construction on foundation pit side-wall by using above-mentioned technical proposal Catch basin is excavated on side wall, and fills gravel material into it, and catch basin roof and side wall after excavation are supported by gravel material, ensure collecting Catch basin keeps its cavity shape during water, before the backwater exudation concrete face wall in foundation pit side-wall, necessarily flows into and catchments Then slot is put aside at the low-lying place that two sections of slopes of the trench bottom that catchments connect, is finally exported by the aqueduct being inserted into.
Another object of the present invention is to provide it is a kind of process above-mentioned foundation pit side-wall drainage arrangement construction method, with Soft or sandy soil stratum foundation pit side-wall processes above-mentioned foundation pit side-wall drainage arrangement, starches stagnant in the soil body in foundation pit side-wall Water, which is put together, to carry out dredging discharge.
The above-mentioned purpose of the present invention is achieved by the following technical solution:
A kind of construction method of foundation pit side-wall drainage arrangement includes at least following steps:
Step 1 is excavated with Luoyang Spade on foundation pit side-wall in the horizontal direction, forms catch basin;
Step 2 takes pvc pipe, blocked to catch basin length adaptation, and cut-out tube wall in the axial direction, formation are opened Mouthful;
Several water seepage holes are beaten on the tube wall of overthe openings when step 3 opening is towards concrete face wall;
Pvc pipe is inserted into catch basin by step 4, and is open certainly into pvc pipe and is filled gravel material;
Step 5 is inserted into an appropriate number of aqueduct into pvc pipe from being open, and when being inserted into more aqueducts, whole aqueducts Along pvc pipe extending direction arranged for interval.
By using above-mentioned technical proposal, in the softer foundation pit of geology, after excavating catch basin, soil body meeting in water collecting process It flows to catch basin to be flooded, to insertion pvc pipe inside catch basin as support after excavation, and opens up infiltration on pvc pipe Hole is as collecting channel, and the lower half portion not trepanning of pvc pipe, so that water can be put aside in pipe.It is open on pvc pipe to insert Enter aqueduct.The addition of gravel material can further increase support effect of the pvc pipe for the trough wall surface that catchments.
In conclusion the invention has the advantages that:The position collected as backwater using catch basin, in the soil body When water oozes out outward, catch basin is initially entered, after the water in catch basin saves bit by bit a certain amount of, aqueduct discharges it, and prevents stagnant Water can not be oozed out from dredging out from concrete face wall.Seepage material is filled in the side that support catch basin is played in catch basin The effect of wall and roof floods catch basin when preventing backwater from penetrating into;For the foundation pit of the soft bottom such as sandy soil, backfill, mix Soil body quality after solidifying soil face wall is softer, when water is flowed to catch basin, softens due to the discharge of water in the soil body and deforms, Catch basin is in time for water guide in use for some time or even not yet and just collapses and be submerged, and opens water seepage hole with pvc pipe and makees For " support frame " of catch basin, backwater enters across water seepage hole in pvc pipe, and by pipe walls support, water carries out the soil body in pvc pipe Convergence, pvc pipe opening is for placing aqueduct.
Description of the drawings
Fig. 1 is the structural schematic diagram of embodiment 1;
Fig. 2 is the structural schematic diagram of embodiment 2;
Fig. 3 is the foundation pit slope structure view before gunite concrete;
Fig. 4 is the structural schematic diagram of embodiment 3;
Fig. 5 is the structural schematic diagram of the pvc pipe used in embodiment 3.
In figure, 1, bottom of foundation ditch;2, concrete face wall;3, aqueduct;4, catch basin;40, roof;41, side wall;42, bottom Wall;5, gravel material;6, reinforced mesh;7, pvc pipe;70, it is open;71, water seepage hole.
Specific implementation mode
Below in conjunction with attached drawing, invention is further described in detail.
Embodiment 1
A kind of foundation pit side-wall drainage arrangement is set in foundation pit mixed at 1 certain altitude of bottom of foundation ditch as shown in fig. 1 After solidifying soil face wall 2, installation position depends on the backwater extended position of prediction.It includes a catch basin 4, and is inserted into and catchments Aqueduct in slot 4,2 after concrete face wall after the soil body in the water that is detained penetrate into savings in catch basin 4, then put aside to certain It is exported by aqueduct 3 after depth.
Catch basin 4 includes four side walls 41, bottom wall 42 and roof 40, wherein:Roof 40 is then from concrete face wall 2 to mixed Soil body direction after solidifying soil face wall 2 is arranged obliquely, so that roof 40 is in the inclined-plane approximately perpendicular to concrete face wall 2.Four A side wall 41 is arranged along vertical direction, also, the upper end of the side wall 41 close to concrete face wall 2 extends on concrete face wall 2, Since the concrete topping 2 on foundation pit side-wall is inclined wall, the side wall 41 close to concrete topping 2 is extending vertically into It is engaged with concrete topping 2, the bottom of catch basin 4 can be made to form the ponding space with certain depth.
As shown in Figure 3, in order to make flow be converged to a certain position of the slot bottom of catch basin 4, to be led by one to several Water pipe 3 exports, and bottom wall 42 arranges that adjacent slopes are oblique opposite along the horizontal extension direction of concrete topping 2 in the slope of multistage With low-lying in intersection's formation one, the backwater penetrated into catch basin 4 flows to the low-lying of adjacent slopes intersection formation along slope It is interior, it is flowed out except catch basin 4 in the aqueduct 3 by stretching into the position.When the cross-directional length of catch basin 4 is longer, slope Multistage can be set, be then used cooperatively more aqueducts 3 and export the water of collection.
Slope intersection in catch basin 4 is stretched into one end of aqueduct 3, the other end extends from concrete face wall 2 and to base The direction for cheating bottom 1 extends, or the sump being arranged at access bottom of foundation ditch 1, or access gutter is discharged.In Fig. 3 Shown, aqueduct 3 is pierced by the position of concrete face wall 2, is tied up with the reinforced mesh for forming concrete face wall 2 with band or steel wire It pricks 6 to fix, then the concrete being injected on concrete face wall 2 is fixed.
Gravel material 5 is filled in catch basin 4, can according to the soil property of concrete topping 2, coarse sand, rubble, cobblestone with And one or central combination are selected between woven bag, it is excellent when the soil body after concrete topping 2 is more soft when selection First cobblestone or rubble is selected to be filled, to support catch basin 4, prevents the soil body in hydrophobic process from catchmenting with backwater entrance Slot 4 buries catch basin 4;When the soil body is more closely knit, the woven bag group that construction site can be selected discarded fills at bulk to collection In sink 4, when filling, should be noted that the nozzle that prevent the gravel material 5 of filling from blocking aqueduct 3.
Embodiment 2
A kind of foundation pit side-wall drainage arrangement, as shown in Fig. 2 to 3, with embodiment 1 difference lies in:In the present solution, catch basin 4 setting be after the construction of concrete topping 2 is completed, therefore, after the installation position of catch basin 4 is based on foundation pit molding, coagulation The position in the infiltration region on native face layer 2, when construction, dig concrete topping 2, are then opened into the soil body with Luoyang Spade etc. Digging is formed catch basin 4 and is fixed aqueduct 3 using the gravel material 5 of filling, and by it according in embodiment 1 after catch basin 4 is filled The mode of description is bound onto reinforced mesh 6.
Embodiment 3
A kind of foundation pit side-wall drainage arrangement, as shown in Figure 4, with embodiment 1 difference lies in:After concrete topping 2 After excavating catch basin 4 on the soil body, it is built into the pvc pipe 7 that an extending direction along concrete topping 2 extends to catch basin 4, and Using the inside of pvc pipe 7 as catchment area.
In conjunction with shown in Fig. 5, pvc pipe 7 is commercially available pvc pipe along tube axis direction cut-out tube wall gained, the pipe of excision Opening 70 is formed at wall, when in pvc pipe merging catch basin 4, opening 70 is arranged towards concrete topping 2.In the upper of pvc pipe 7 Several water seepage holes 71 are provided on half part tube wall, so that the water in the soil body after concrete topping 2 can pass through water seepage hole 71 It is put aside into the bottom of pvc pipe 7, not trepanning on 70 tube walls below that are open so that water can be put aside here, and passes through The aqueduct 3 being inserted into pvc pipe 7 is discharged.
Herein it should be understood that:In order to make water converge at one as possible as in 1, then led by less aqueduct 3 Go out and dredge backwater to realize, a notch can be done close to centre on the length direction of pvc pipe 7, then slightly by pvc pipe 7 An angle is bent, the tube body of notch both sides forms two slopes, and water is converged into the tube wall of incision, is inserted into water guide here Pipe 3.It is of course also possible to which multiple pvc pipes 7 are arranged, notch is done on each pvc pipe 7, forms the position of multiple water convergences, so Aqueduct 3 is inserted on each position afterwards.
Structure is suitable for the foundation pit side-wall of sandy soil stratum and some pore-formings more difficult soft geology in the present embodiment On, under these topographies, catch basin catchment after excavation beginning before can cave in, it is difficult to keep, with pvc pipe 7 as branch Support structure can prevent the soil body from moving down and bury catch basin 4 while keeping catch basin 4.In this scheme, in order to increase Add the compression capability of pvc pipe 7 and the water storage effect of inside, filtrate is filled inside pvc pipe 7, to support tube wall.In order to prevent Water seepage hole 71 is blocked, and the materials such as some strainers can also be coated and fixed in 7 outer wall of pvc pipe.
Embodiment 4
A kind of construction method of foundation pit side-wall drainage arrangement set in advance:
The slope supporting of foundation pit is carried out according to the form of existing pattern foundation pit supporting structure, and final step carries out slope surface in the supporting of slope Spray mix supporting before, increase following steps:
Step 1 is with Luoyang Spade at the position on the lower of the middle part of slope surface, or the position that empirically backwater may ooze out is opened It digs, forms that side wall 42 shown in Fig. 1 is vertical, 40 inclined catch basin 4 of roof, and bottom wall 41 is according to the level side of catch basin 4 To length two or more slopes are set, form multiple slope intersections;
Soft degree of the step 2 according to the soil property dug out fills gravel material 5 into catch basin 4, should especially when soil property is soft Catch basin 4 is filled as possible full;
Aqueduct 3 is inserted between the gravel material 5 of the slope intersection of the formation of bottom wall 41 by step 3, and according to needs in aqueduct 3 nozzle outer cladding does not coat water strainer;
Step 4 is according to structure shown in Fig. 3, the reinforced mesh 6 on slope surface upper berth, utilizes band either steel wire or other are band-like Object will be in aqueduct 3 banding fixed to reinforced mesh 6;
Step 5 gunite concrete in the slope surface of foundation pit side-wall forms concrete topping 2.
Embodiment 5
A kind of construction method for the foundation pit side-wall drainage arrangement being arranged afterwards:
According to the infiltration position on concrete topping 2, construct in accordance with the following steps:
Step 1 destroys the concrete structure on the concrete topping 2 under infiltration position;
Step 2 carries out the excavation of catch basin 4 between reinforced mesh 6, and carries out filling out for gravel material 5 in the way of embodiment 4 It fills;
Step 3 is inserted into aqueduct 3 into gravel material 5, and does not coat in the nozzle outer cladding of aqueduct 3 or drainage according to needs Net;
Step 4 is according to structure shown in Fig. 3, the reinforced mesh 6 on slope surface upper berth, utilizes band either steel wire or other are band-like Object will be in aqueduct 3 banding fixed to reinforced mesh 6.
Embodiment 6
A kind of construction method suitable for sandy soil or the foundation pit side-wall drainage arrangement of other soft bottoms:
According to the infiltration position on concrete topping 2, construct in accordance with the following steps:
Step 1 is excavated on foundation pit side-wall, forms catch basin 4;
Step 2 takes the pvc pipe being suitably inserted into catch basin 4, and cut-out tube wall is to form opening 70 in an axial direction;
Step 3 is located on pvc pipe 7 above opening 70(Herein upper and lower refers to the opening after pvc pipe 7 is inserted into catch basin 4 70 above and below)Tube wall on beat several water seepage holes 71;
Step 4 will be inserted by the pvc pipe 7 formed in step 2 and step 3 in catch basin 4;
Step 5 inserts gravel material 5 into pvc pipe 7;
An appropriate number of aqueduct 3 is inserted into step 6 pvc pipe 7, at this time it should be noted that when not doing notch on pvc pipe 7, It can much more appropriate arrangement aqueduct 3 in the horizontal direction;When doing notch on pvc pipe 7, aqueduct 3 need to correspond to incision shape At ponding point arrangement;
If the excavation node of step 7 catch basin 4 is after the construction of concrete face wall 2, then at this time directly with band or steel wire Either other ribbons are by foundation actual needs carries out or without mixed later in aqueduct 3 banding fixed to reinforced mesh 6 Coagulate the injection again of soil;If the excavation node of catch basin 4 is before the construction of concrete face wall 2, then at this time in slope surface upper berth steel Muscle mesh sheet 6, using band either steel wire or other ribbons by aqueduct 3 banding fixed to reinforced mesh 6, then according to Normal procedure carries out concrete ejection.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, people in the art Member can as needed make the present embodiment the modification of not creative contribution after reading this specification, but as long as at this It is all protected by Patent Law in the right of invention.

Claims (10)

1. a kind of foundation pit side-wall drainage arrangement is dredged applied to backwater after the concrete face wall of foundation pit, it is characterized in that:Including close to Concrete face wall(2)The catch basin being set to after concrete face wall(4)And the catch basin is stretched into one end(4), the other end prolongs Stretch out concrete face wall(2)Outer aqueduct(3), the catch basin(4)It is interior to be filled with gravel material(5).
2. foundation pit side-wall drainage arrangement according to claim 1, it is characterized in that:The catch basin(4)Including four side walls (41), roof(40)And bottom wall(42), four side walls(41)It is vertically arranged, the bottom wall(42)Include at least two in the horizontal direction Section slope, and the inclined direction of adjacent slopes is on the contrary in bottom wall(42)Low-lying, the shown aqueduct of upper formation(3)It is low shown in being inserted into Depression.
3. foundation pit side-wall drainage arrangement according to claim 2, it is characterized in that:The roof(40)From concrete face wall (2)The soil body in foundation pit is arranged obliquely.
4. foundation pit side-wall drainage arrangement according to claim 1, it is characterized in that:The aqueduct(3)Gu to concrete surface Wall(2)On.
5. foundation pit side-wall drainage arrangement according to claim 1, it is characterized in that:The catch basin(4)It is interior inserted with axis Horizontally disposed pvc pipe(7), the pvc pipe(7)Axis direction on close to concrete face wall(2)Side wall on be provided with out Mouthful(70), pvc pipe(7)On in opening(70)On tube wall on offer several water seepage holes(71), the gravel material(5)It is filled in Pvc pipe(7)It is interior, shown aqueduct(3)Stretch into pvc pipe(7)It is interior.
6. foundation pit side-wall drainage arrangement according to claim 1 or 5, it is characterized in that:The gravel material(5)For rubble, goose ovum Any one or a few combination in stone, woven bag.
7. a kind of construction method of foundation pit side-wall drainage arrangement as described in claim 1, characterized in that include at least as follows Step:
Step 1 is excavated with Luoyang Spade on foundation pit side-wall in the horizontal direction, forms sidewalls vertical and bottom wall has along excavation side To the catch basin for including at least two sections slopes;
Soft degree of the step 2 according to the soil body after foundation pit side-wall, the gravel material of appropriate material is filled into catch basin;
Step 3 is inserted into aqueduct to the low-lying place to catchment in groove bottom wall.
8. the construction method of foundation pit side-wall drainage arrangement according to claim 7, characterized in that increase after step 3 such as Lower step:It will be on the reinforced mesh of the concrete face wall of aqueduct banding fixed to foundation pit side-wall.
9. a kind of construction method of foundation pit side-wall drainage arrangement as described in claim 5, characterized in that include at least as follows Step:
Step 1 is excavated with Luoyang Spade on foundation pit side-wall in the horizontal direction, forms catch basin;
Step 2 takes pvc pipe, blocked to catch basin length adaptation, and cut-out tube wall in the axial direction, formation are opened Mouthful;
Several water seepage holes are beaten on the tube wall of overthe openings when step 3 opening is towards concrete face wall;
Pvc pipe is inserted into catch basin by step 4, and is open certainly into pvc pipe and is filled gravel material;
Step 5 is inserted into an appropriate number of aqueduct into pvc pipe from being open, and when being inserted into more aqueducts, whole aqueducts Along pvc pipe extending direction arranged for interval.
10. the construction method of foundation pit side-wall drainage arrangement according to claim 9, characterized in that place step 3 and step Increase following steps between 4:The tube wall outer cladding water strainer of water seepage hole is offered on pvc pipe.
CN201710047700.XA 2017-01-22 2017-01-22 Foundation pit side-wall drainage arrangement and construction method Pending CN108343081A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710047700.XA CN108343081A (en) 2017-01-22 2017-01-22 Foundation pit side-wall drainage arrangement and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710047700.XA CN108343081A (en) 2017-01-22 2017-01-22 Foundation pit side-wall drainage arrangement and construction method

Publications (1)

Publication Number Publication Date
CN108343081A true CN108343081A (en) 2018-07-31

Family

ID=62974522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710047700.XA Pending CN108343081A (en) 2017-01-22 2017-01-22 Foundation pit side-wall drainage arrangement and construction method

Country Status (1)

Country Link
CN (1) CN108343081A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110630270A (en) * 2019-10-25 2019-12-31 中建八局轨道交通建设有限公司 Drainage system for treating stagnant water between underground excavation shaft layers and construction method thereof
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology
CN112302029A (en) * 2020-09-18 2021-02-02 中石化宁波工程有限公司 Drainage tensile foundation pit supporting structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5836115A (en) * 1996-12-09 1998-11-17 Clay; Randy K. Foundation waterproofing and drainage system
JP2001152459A (en) * 1999-11-25 2001-06-05 Ohbayashi Corp Slope stabilizing construction method
CN202012073U (en) * 2011-04-08 2011-10-19 中国新兴保信建设总公司 Draining device of foundation pit support surface aquitard
CN202787289U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 Shut-in dewatering device for tube well
CN103669398A (en) * 2013-12-26 2014-03-26 中国水电顾问集团中南勘测设计研究院有限公司 Integrated type road cutting retaining wall
CN104314090A (en) * 2014-08-29 2015-01-28 中铁八局集团建筑工程有限公司 Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN206467677U (en) * 2017-01-22 2017-09-05 北京爱地地质勘察基础工程公司 Foundation pit side-wall drainage arrangement

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5836115A (en) * 1996-12-09 1998-11-17 Clay; Randy K. Foundation waterproofing and drainage system
JP2001152459A (en) * 1999-11-25 2001-06-05 Ohbayashi Corp Slope stabilizing construction method
CN202012073U (en) * 2011-04-08 2011-10-19 中国新兴保信建设总公司 Draining device of foundation pit support surface aquitard
CN202787289U (en) * 2012-07-29 2013-03-13 山西四建集团有限公司 Shut-in dewatering device for tube well
CN103669398A (en) * 2013-12-26 2014-03-26 中国水电顾问集团中南勘测设计研究院有限公司 Integrated type road cutting retaining wall
CN104314090A (en) * 2014-08-29 2015-01-28 中铁八局集团建筑工程有限公司 Deep foundation pit bedrock drainage culvert and drainage system and drainage construction method thereof
CN206467677U (en) * 2017-01-22 2017-09-05 北京爱地地质勘察基础工程公司 Foundation pit side-wall drainage arrangement

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
国土资源部中国地质调查局: "《中国地质调查百项技术》", 地质出版社, pages: 464 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110630270A (en) * 2019-10-25 2019-12-31 中建八局轨道交通建设有限公司 Drainage system for treating stagnant water between underground excavation shaft layers and construction method thereof
CN111042162A (en) * 2019-12-18 2020-04-21 沈阳市政集团有限公司 Construction method for solving upper layer stagnant water in deep foundation pit construction by small-conduit drainage technology
CN112302029A (en) * 2020-09-18 2021-02-02 中石化宁波工程有限公司 Drainage tensile foundation pit supporting structure

Similar Documents

Publication Publication Date Title
CN101067313B (en) Draining method and draining and irrigating tube thereof
CN109137940A (en) A kind of novel solid drainage system suitable for loose landfill side slope
CN103882880A (en) Buried type side slope drainage system and construction method thereof
KR20150065475A (en) Side gutter for mountain ridge and construction method
CN209194556U (en) Lock station drainage of foundation pit system
CN106087953B (en) A kind of drainage and construction method for preventing and treating mountain area large size spoil ground mud-rock flow
CN210066791U (en) A precipitation combined system that is used for foundation ditch pressure release precipitation and dredges precipitation
CN108343081A (en) Foundation pit side-wall drainage arrangement and construction method
CN206467677U (en) Foundation pit side-wall drainage arrangement
CN111549799A (en) Comprehensive control system applied to gravel soil slope
CN102031768B (en) Novel farmland waterlogging prevention and treatment device and applied technology thereof
CN102383408A (en) Greening method for high water level impermeable saline and alkaline lands and greening system
CN208346836U (en) A kind of hidden drainage system
KR101678127B1 (en) Block for engineering works
KR101650285B1 (en) Side gutter for mountain ridge
CN108018828A (en) A kind of protective slope structure
JP3654424B2 (en) Drain drainage structure and construction method
CN110805047A (en) Soil slope protection landscape structure and construction method
CN108824466A (en) A kind of foundation pit side-wall water burst gushes the processing method of sand
CN212316950U (en) Slope structure
CN114575921A (en) Drainage anchor rod, side slope drainage system and side slope drainage treatment method of underpass side slope tunnel
CN208934005U (en) A kind of vertical curved baffle landscape pile plate wall
CN114000497A (en) Method for reducing soil squeezing effect of precast pile
CN106149736A (en) The construction method stable based on cutting draining holding hillside fields bury excavation slope
JP2905110B2 (en) Landslide prevention method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180731