CN108337113B - Transmission line switching device and method - Google Patents
Transmission line switching device and method Download PDFInfo
- Publication number
- CN108337113B CN108337113B CN201810031778.7A CN201810031778A CN108337113B CN 108337113 B CN108337113 B CN 108337113B CN 201810031778 A CN201810031778 A CN 201810031778A CN 108337113 B CN108337113 B CN 108337113B
- Authority
- CN
- China
- Prior art keywords
- transmission line
- transmission
- current
- message
- request
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 230000005540 biological transmission Effects 0.000 title claims abstract description 354
- 238000000034 method Methods 0.000 title claims abstract description 19
- 238000004891 communication Methods 0.000 claims abstract description 79
- 238000012790 confirmation Methods 0.000 claims description 29
- 230000005856 abnormality Effects 0.000 claims description 8
- 230000002159 abnormal effect Effects 0.000 claims description 6
- 238000010586 diagram Methods 0.000 description 12
- 230000007704 transition Effects 0.000 description 3
- 230000006870 function Effects 0.000 description 2
- 102000002067 Protein Subunits Human genes 0.000 description 1
- 108010001267 Protein Subunits Proteins 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007257 malfunction Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
Images
Classifications
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/06—Management of faults, events, alarms or notifications
- H04L41/0654—Management of faults, events, alarms or notifications using network fault recovery
- H04L41/0663—Performing the actions predefined by failover planning, e.g. switching to standby network elements
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04Q—SELECTING
- H04Q1/00—Details of selecting apparatus or arrangements
- H04Q1/18—Electrical details
- H04Q1/20—Testing circuits or apparatus; Circuits or apparatus for detecting, indicating, or signalling faults or troubles
- H04Q1/22—Automatic arrangements
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04L—TRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
- H04L41/00—Arrangements for maintenance, administration or management of data switching networks, e.g. of packet switching networks
- H04L41/06—Management of faults, events, alarms or notifications
- H04L41/0654—Management of faults, events, alarms or notifications using network fault recovery
- H04L41/0668—Management of faults, events, alarms or notifications using network fault recovery by dynamic selection of recovery network elements, e.g. replacement by the most appropriate element after failure
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04Q—SELECTING
- H04Q1/00—Details of selecting apparatus or arrangements
- H04Q1/18—Electrical details
- H04Q1/30—Signalling arrangements; Manipulation of signalling currents
Landscapes
- Engineering & Computer Science (AREA)
- Computer Networks & Wireless Communication (AREA)
- Signal Processing (AREA)
- Cable Transmission Systems, Equalization Of Radio And Reduction Of Echo (AREA)
- Maintenance And Management Of Digital Transmission (AREA)
Abstract
本发明的传送线路切换装置以及方法缩短再次开始通信的时间。在通信终端装置群(2)中没有消息的发送请求、且电流未流过A系统的传送线路(主系统的传送线路)(3)的状态持续在规定时间(T)(例如,5ms)以上时,将B系统(备用系统)的传送线路(4)切换为主系统的传送线路(通过将开关(5)设为间隔状态,将开关(6)设为标记状态,从而使主系统从A系统转变成B系统)。由此,在B系统(备用系统)的传送线路(4)向主系统的传送线路的切换之后发送下一个消息时,不用等待电源装置(1)的内部的电压(VS’)调整至稳定,能够缩短再次开始通信的时间。
The transmission line switching device and method of the present invention shorten the time required to resume communication. In the communication terminal device group (2), there is no request to send a message, and the current does not flow through the transmission line of the A system (the transmission line of the main system) (3) The state continues for a predetermined time (T) (for example, 5 ms) or more When the transmission line (4) of the B system (standby system) is switched to the transmission line of the main system (by setting the switch (5) to the interval state and the switch (6) to the mark state, the main system is switched from the A system into B system). Thereby, when the next message is sent after the transmission line (4) of the B system (standby system) is switched to the transmission line of the main system, there is no need to wait for the voltage (VS') inside the power supply device (1) to be adjusted to be stable, The time to restart communication can be shortened.
Description
技术领域technical field
本发明涉及一种在通过电流环方式进行通信的通信系统中使用的传送线路切换装置以及方法。The present invention relates to a transmission line switching device and method used in a communication system that communicates by a current loop method.
背景技术Background technique
以往以来,使用通过电流环方式进行通信的通信系统。电流环方式是指根据电流值的变化而传送信号的通信方式,是根据环电流的ON(例如,30mA)和OFF(例如,2mA)而将通信信号传递给连接于传送线路中的通信终端装置的通信方式。Conventionally, a communication system that communicates by a current loop method has been used. The current loop method refers to a communication method that transmits a signal according to a change in the current value, and transmits a communication signal to a communication terminal device connected to a transmission line according to the ON (eg, 30mA) and OFF (eg, 2mA) of the loop current. method of communication.
在该通信方式中,将把环电流设为ON时的通信信号称为标记(Mark)信号,将此时的环电流称为标记电流,将把环电流设为OFF时的通信信号称为间隔(Space)信号,将此时的环电流称为间隔电流(例如,参照专利文献1)。In this communication method, a communication signal when the loop current is turned on is called a mark signal, the loop current at this time is called a mark current, and a communication signal when the loop current is turned off is called a gap (Space) signal, the loop current at this time is called a space current (for example, refer to Patent Document 1).
图8是示出采用电流环方式的使传送线路双重化的以往的通信系统的一个例子的图。在该图中,1是电源装置,2是通信终端装置群,电源装置1与通信终端装置群2之间的传送线路被双重化。即,在该通信系统100中,电源装置1与通信终端装置群2通过A系统的传送线路3和B系统的传送线路4来连接。FIG. 8 is a diagram showing an example of a conventional communication system in which transmission lines are duplexed using a current loop method. In the figure, 1 is a power supply device, 2 is a group of communication terminal devices, and the transmission line between the
此外,在图8中,为了方便说明,将通信终端装置群2分成2个而示出,但实际的通信终端装置群2是1个。通信终端装置群2由串联连接的母机、子机等构成,作为共同的负载而连接于A系统的传送线路3和B系统的传送线路4的线路中。In addition, in FIG. 8, for convenience of description, the communication
另外,在该例子中,在A系统的传送线路3上设置有开关5,在B系统的传送线路4上设置有开关6。能够使用晶体管作为开关5、6。A系统的传送线路3通过将开关5设为标记状态(电流容易流过的状态)而被设为主系统的传送线路。B系统的传送线路4通过将开关6设为间隔状态(电流不易流过的状态(2mA以下))而被设为备用系统的传送线路。In addition, in this example, the
在该通信系统100中,通信终端装置群2通过使在A系统(主系统)的传送线路3中流过的电流的值变化,即将A系统(主系统)的传送线路3的环电流设为ON(例如,30mA)或者设为OFF(例如,2mA),从而进行消息的发送。In the
〔传送线路切换装置〕[Transmission line switching device]
如图9所示,在该通信系统100中设置有传送线路切换装置7。该传送线路切换装置7监视在通信终端装置群2中有没有消息的发送请求,在有消息的发送请求的情况下,在即将发送该消息之前,确认A系统(主系统)的传送线路3以及B系统(备用系统)的传送线路4这两个系统的环路是否确立。As shown in FIG. 9 , the
在这里,在A系统(主系统)的传送线路3的环路未确立而B系统(备用系统)的传送线路4的环路已确立的情况下,判断为A系统(主系统)的传送线路3发生了断线,将B系统(备用系统)的传送线路4切换为主系统的传送线路(参照图10)。即,通过将开关5设为间隔状态,将开关6设为标记状态,从而使主系统从A系统转移成B系统。Here, when the loop of the
现有技术文献prior art literature
专利文献Patent Literature
专利文献1:日本特开平11-68856号公报Patent Document 1: Japanese Patent Application Laid-Open No. 11-68856
专利文献2:日本专利第4451718号公报Patent Document 2: Japanese Patent No. 4451718
发明内容SUMMARY OF THE INVENTION
发明要解决的技术问题The technical problem to be solved by the invention
最近,作为电源装置1,采用根据负载而调整内部的电压VS’的方式(例如,参照专利文献2)。如果采用该方式,则不再存在电压调整作业,操作性变优良,但另一方面,产生从连接通信终端装置群2至电源装置1的内部的电压VS’稳定为止(最大2秒)的无法进行通信的期间。Recently, as the
连接通信终端装置群2后立即需要进行通信的状况是罕见的,所以,它自身没有问题。但是,在上述使传送线路双重化的通信系统100中,当A系统(主系统)的传送线路3发生断线时,A系统(主系统)的阻抗负载变得极大,调整电源装置1的内部的电压VS’的功能暂时地变得不稳定。因此,在将B系统(备用系统)的传送线路4切换为主系统的传送线路的情况下,产生直至电源装置1的内部的电压VS’稳定为止需要时间、并且直至能够再次开始通信为止的时间变长这样的问题。It is rare that communication needs to be performed immediately after the connection of the communication
本发明是为了解决这样的技术问题而完成的,其目的在于,提供一种能够缩短直至能够再次开始通信为止的时间的传送线路切换装置以及方法。The present invention has been made in order to solve such a technical problem, and an object thereof is to provide a transmission line switching device and method capable of shortening the time until communication can be resumed.
解决技术问题的技术手段technical means to solve technical problems
为了达到这样的目的,本发明涉及一种传送线路切换装置(7B),其用于通信系统(200),该通信系统(200)具备:第1传送线路(3);第2传送线路(4);通信终端装置群(2),其构成为将第1传送线路以及第2传送线路分别设为主系统的传送线路以及备用系统的传送线路,通过使在主系统的传送线路中流过的电流的值变化来进行消息的发送;以及电源装置(1),其将电源电压供给到第1传送线路以及第2传送线路,并且根据负载而调整内部的电压,传送线路切换装置(7B)构成为在第1传送线路发生异常的情况下,将第2传送线路切换为主系统的传送线路,传送线路切换装置(7B)的特征在于,具备:传送线路切换部(70、70’),其构成为当在通信终端装置群中没有消息的发送请求、并且电流未流过第1传送线路的状态持续规定时间以上的情况下,判断为第1传送线路发生异常,将第2传送线路切换为主系统的传送线路。In order to achieve such an object, the present invention relates to a transmission line switching device (7B) for use in a communication system (200), the communication system (200) comprising: a first transmission line (3); a second transmission line (4) ); a group of communication terminal apparatuses (2), which are configured such that the first transmission line and the second transmission line are used as the transmission line of the main system and the transmission line of the backup system, respectively, and the current flowing in the transmission line of the main system passes the current and a power supply device (1) that supplies a power supply voltage to the first transmission line and the second transmission line, and adjusts the internal voltage according to the load, and the transmission line switching device (7B) is composed of When an abnormality occurs in the first transmission line, the second transmission line is switched to the transmission line of the main system, and the transmission line switching device (7B) is characterized by comprising: a transmission line switching unit (70, 70') having a structure In order to determine that an abnormality has occurred in the first transmission line, when there is no request to send a message in the communication terminal device group and the current does not flow through the first transmission line for a predetermined time or longer, the second transmission line is switched to be the main one transmission line of the system.
根据本发明,如果在通信终端装置群中没有消息的发送请求、并且电流未流过第1传送线路(主系统的传送线路)的状态持续在规定时间以上时,则判断为第1传送线路(主系统的传送线路)发生异常,将第2传送线路(备用系统的传送线路)切换为主系统的传送线路。According to the present invention, when there is no request to send a message in the communication terminal device group and the state where no current flows through the first transmission line (the transmission line of the main system) continues for a predetermined time or longer, it is determined that the first transmission line ( The transmission line of the main system is abnormal, and the second transmission line (the transmission line of the backup system) is switched to the transmission line of the main system.
由此,在本发明中,在通信终端装置群中没有消息的发送请求的期间内,进行第2传送线路(备用系统的传送线路)向主系统的传送线路的切换。另外,电源装置的内部的电压的调整也在通信终端装置群中没有消息的发送请求的期间内进行。因此,当在第2传送线路(备用系统的传送线路)向主系统的传送线路的切换之后发送接下来的消息时,可以不等待至电源装置的内部的电压的调整稳定为止,直至能够再次开始通信为止的时间变短。Thus, in the present invention, the second transmission line (the transmission line of the backup system) is switched to the transmission line of the main system while there is no message transmission request in the group of communication terminal apparatuses. In addition, the adjustment of the internal voltage of the power supply device is also performed during the period when there is no message transmission request in the group of communication terminal devices. Therefore, when the next message is sent after the switching of the second transmission line (the transmission line of the backup system) to the transmission line of the main system, it is not necessary to wait for the adjustment of the voltage inside the power supply device to stabilize until it can be restarted again. The time until communication becomes shorter.
此外,在本发明中,在将第2传送线路(备用系统的传送线路)切换为主系统的传送线路之后,第2传送线路成为主系统的传送线路,第1传送线路成为备用系统的传送线路。即,在将第2传送线路(备用系统的传送线路)切换为主系统的传送线路之后,第2传送线路成为本发明中所说的第1传送线路(主系统的传送线路),第1传送线路成为本发明中所说的第2传送线路(备用系统的传送线路)。Furthermore, in the present invention, after the second transmission line (the transmission line of the backup system) is switched to the transmission line of the main system, the second transmission line becomes the transmission line of the main system, and the first transmission line becomes the transmission line of the backup system . That is, after the second transmission line (the transmission line of the backup system) is switched to the transmission line of the main system, the second transmission line becomes the first transmission line (the transmission line of the main system) in the present invention, and the first transmission line becomes the first transmission line (the transmission line of the main system). The line becomes the second transmission line (transmission line of the backup system) referred to in the present invention.
此外,在上述说明中,作为一个例子,用附加有括弧的附图标记来表示与发明的结构要素对应的附图上的结构要素。In addition, in the above description, as an example, the components on the drawings corresponding to the components of the invention are represented by reference numerals in which parentheses are attached.
发明效果Invention effect
基于以上说明,根据本发明,在通信终端装置群中没有消息的发送请求、并且电流未流过第1传送线路(主系统的传送线路)的状态持续规定时间以上的情况下,判断为第1传送线路(主系统的传送线路)发生异常,将第2传送线路(备用系统的传送线路)切换为主系统的传送线路,所以当在第2传送线路(备用系统的传送线路)向主系统的传送线路的切换之后发送接下来的消息时,可以不等待至电源装置的内部的电压的调整稳定,能够缩短直至能够再次开始通信为止的时间。Based on the above description, according to the present invention, when there is no message transmission request in the communication terminal device group, and the state in which the current does not flow through the first transmission line (the transmission line of the main system) continues for a predetermined time or longer, it is determined that the first transmission line is the first transmission line. An abnormality occurs in the transmission line (transmission line of the main system), and the second transmission line (transmission line of the backup system) is switched to the transmission line of the main system. When the next message is transmitted after the switching of the transmission line, it is not necessary to wait until the voltage inside the power supply device is stabilized, and the time until the communication can be resumed can be shortened.
附图说明Description of drawings
图1是示出使用本发明的实施方式的传送线路切换装置的通信系统的主要部分的图。FIG. 1 is a diagram showing a main part of a communication system using a transmission line switching device according to an embodiment of the present invention.
图2是示出该通信系统中的传送线路切换装置的硬件构成的概略的图。FIG. 2 is a diagram showing an outline of the hardware configuration of the transmission line switching device in the communication system.
图3是示出该传送线路切换装置中的CPU执行的处理动作的第1例(实施方式1)的流程图。3 is a flowchart showing a first example (Embodiment 1) of the processing operation executed by the CPU in the transmission line switching device.
图4是示出通过该传送线路切换装置将B系统(备用系统)的传送线路切换为主系统的传送线路的状态(使主系统从A系统转变为B系统的状态)的图。4 is a diagram showing a state in which the transmission line of the B system (standby system) is switched to the transmission line of the main system by the transmission line switching device (the state of the main system being changed from the A system to the B system).
图5是执行实施方式1的处理动作的传送线路切换装置的主要部分的功能框图。5 is a functional block diagram of a main part of a transmission line switching device that executes the processing operation of the first embodiment.
图6是示出该传送线路切换装置中的CPU执行的处理动作的第2例(实施方式2)的流程图。6 is a flowchart showing a second example (Embodiment 2) of the processing operation executed by the CPU in the transmission line switching device.
图7是执行实施方式2的处理动作的第2例的传送线路切换装置的主要部分的功能框图。7 is a functional block diagram of a main part of a transmission line switching device that executes a second example of the processing operation of the second embodiment.
图8是示出采用电流环方式的使传送线路双重化的以往的通信系统的一个例子的图。FIG. 8 is a diagram showing an example of a conventional communication system in which transmission lines are duplexed using a current loop method.
图9是说明在以往的通信系统中将B系统(备用系统)的传送线路切换为主系统的传送线路的情形(切换前的状态)的图。FIG. 9 is a diagram illustrating a situation in which the transmission line of the B system (standby system) is switched to the transmission line of the main system in the conventional communication system (state before switching).
图10是说明在以往的通信系统中将B系统(备用系统)的传送线路切换为主系统的传送线路的情形(切换后的状态)的图。FIG. 10 is a diagram illustrating a situation (state after switching) of switching the transmission line of the B system (standby system) to the transmission line of the main system in the conventional communication system.
具体实施方式Detailed ways
以下,根据附图,详细说明本发明的实施方式。图1是示出使用本发明的实施方式的传送线路切换装置的通信系统200的主要部分的图。在该图中,与图9相同的符号表示与参照图9说明的结构要素相同或者等同的结构要素,说明其省略。Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. FIG. 1 is a diagram showing a main part of a
下面,为了与图9所示的以往的通信系统100中的传送线路切换装置7进行区分,用符号7A表示以往的通信系统100中的传送线路切换装置7,用符号7B表示本实施方式的通信系统200中的传送线路切换装置7。Hereinafter, in order to distinguish from the transmission
此外,在该通信系统200中,也与以往的通信系统100同样地,在A系统的传送线路3中,将开关5设为标记状态(电流容易流过的状态),在B系统的传送线路4中,将开关6设为间隔状态(电流不易流过的状态(2mA以下))。即,将A系统的传送线路3设为主系统的传送线路,将B系统的传送线路4设为备用系统的传送线路。In addition, in this
在图2中示出传送线路切换装置7B的硬件构成的概略。该传送线路切换装置7B具备中央运算处理装置(CPU)7-1、随机存取存储器(RAM)7-2、只读存储器(ROM)7-3、接口7-4、7-5以及将它们连接的母线7-6。FIG. 2 shows an outline of the hardware configuration of the transmission
在该传送线路切换装置7B中,安装有传送线路切换程序作为本实施方式特有的程序。CPU7-1通过处理经由接口7-4输入的信息,一边对RAM7-2、ROM7-3进行存取,一边依照所安装的传送线路切换程序进行动作。In the transmission
〔实施方式1〕[Embodiment 1]
下面,使用图3所示的流程图,说明CPU7-1依照传送线路切换程序执行的处理动作的第1例(实施方式1)。Next, a first example (Embodiment 1) of the processing operation executed by the CPU 7 - 1 in accordance with the transmission line switching program will be described using the flowchart shown in FIG. 3 .
在实施方式1中,CPU7-1确认在通信终端装置群2中有没有消息的发送请求(步骤S101),在没有消息的发送请求的情况下,检查在A系统(主系统)的传送线路3中流过的电流IM(IA)(步骤S102)。In
在这里,当在通信终端装置群2中没有消息的发送请求(步骤S101的“无”)、并且电流未流过A系统(主系统)的传送线路3的状态(IM=0的状态)持续规定时间T(例如,5ms)以上的情况下(步骤S102的“是”),CPU7-1判断为A系统(主系统)的传送线路3发生断线(异常)(步骤S103),将B系统(备用系统)的传送线路4切换为主系统的传送线路(步骤S104,参照图4)。即,通过将开关5设为间隔状态,将开关6设为标记状态,从而使主系统从A系统转变成B系统。Here, when there is no request to transmit a message in the communication terminal device group 2 (“None” in step S101 ) and the current does not flow through the
由此,在本实施方式中,在通信终端装置群2中没有消息的发送请求的期间内,进行B系统(备用系统)的传送线路4向主系统的传送线路的切换。另外,电源装置1的内部的电压VS’的调整也在通信终端装置群2中没有消息的发送请求的期间内进行。因此,当在B系统(备用系统)的传送线路4向主系统的传送线路的切换之后发送接下来的消息时,可以不等待至电源装置1的内部的电压VS’的调整稳定,到能够再次开始通信为止的时间变短。Thus, in the present embodiment, the
在图5中示出执行上述处理动作的第1例(实施方式1)的传送线路切换装置7B的主要部分的功能框图。在实施方式1中,在传送线路切换装置7B中,作为传送线路切换部70,具备消息发送请求有无确认部71、A系统传送线路电流确认部72以及线路切换部73。FIG. 5 shows a functional block diagram of the main part of the transmission
在传送线路切换部70中,消息发送请求有无确认部71确认在通信终端装置群2中有没有消息的发送请求。A系统传送线路电流确认部72确认电流未流过A系统(主系统)的传送线路3的状态是否持续规定时间T以上。在消息发送请求有无确认部71确认为在通信终端装置群2中没有消息的发送请求的状态下,A系统传送线路电流确认部72确认为电流未流过A系统(主系统)的传送线路3的状态持续规定时间T以上的情况下,线路切换部73判断为A系统(主系统)的传送线路3发生断线,将B系统(备用系统)的传送线路4切换为主系统的传送线路。In the transmission
此外,在该实施方式1中,在将B系统(备用系统)的传送线路4切换为主系统的传送线路之后,B系统的传送线路4成为主系统的传送线路,A系统的传送线路3成为备用系统的传送线路。即,在将B系统(备用系统)的传送线路4切换为主系统的传送线路之前,将A系统的传送线路3设为本发明中所说的第1传送线路(主系统的传送线路),将B系统的传送线路4设为本发明中所说的第2传送线路(备用系统的传送线路),在切换后,B系统的传送线路4成为本发明中所说的第1传送线路(主系统的传送线路),A系统的传送线路3成为本发明中所说的第2传送线路(备用系统的传送线路)。In addition, in
〔实施方式2〕[Embodiment 2]
接下来,使用图6所示的流程图,说明CPU7-1依照传送线路切换程序执行的处理动作的第2例(实施方式2)。Next, a second example (Embodiment 2) of the processing operation executed by the CPU 7 - 1 in accordance with the transmission line switching program will be described using the flowchart shown in FIG. 6 .
在实施方式1中,追加有逻辑构件,该逻辑构件在通信终端装置群2中没有消息的发送请求的期间内针对A系统(主系统)的传送线路3的断线进行检测并将B系统(备用系统)的传送线路4切换为主系统的传送线路。In
但是,在实施方式1中,在检测到A系统(主系统)的传送线路3的断线的情况下,立即将B系统(备用系统)的传送线路4切换为主系统的传送线路。此时,在B系统(备用系统)的传送线路4断线的情况下,将该B系统(备用系统)的传送线路4的断线检测为主系统的传送线路的断线,立即转变而返回到原来的状态。因此,重复进行从A系统向B系统、从B系统向A系统的主系统的转变,直至断线被改善为止。However, in
另外,在接入电源后,到电源装置1的内部的电压VS’的自动调整结束为止的时间为过电压保护发挥作用(最大2秒)、不流过电流的状态。因此,A系统(主系统)的传送线路3和B系统(备用系统)的传送线路4都成为检测到断线的状态。在这样的情况下,也重复进行从A系统向B系统、从B系统向A系统的主系统的转变,有可能导致误动作。In addition, after the power is turned on, the time until the automatic adjustment of the internal voltage VS' of the
因此,在实施方式2中,当在通信终端装置群2中没有消息的发送请求(步骤S201的“无”)、并且电流未流过A系统(主系统)的传送线路3的状态(IM=0的状态)持续规定时间T(例如,5ms)以上的情况下(步骤S202的“是”),在判断为A系统(主系统)的传送线路3发生断线(异常)之后(步骤S203),确认B系统(备用系统)的传送线路4的环路是否确立(步骤S204)。Therefore, in
在这里,仅在确认为B系统(备用系统)的传送线路4的环路确立的情况下(步骤S204的“是”),进行B系统(备用系统)的传送线路4的向主系统的传送线路的切换(步骤S205)。即,在未确认为B系统(备用系统)的传送线路4的环路确立的情况下(步骤S204的“否”),不进行B系统(备用系统)的传送线路4向主系统的传送线路的切换。Here, only when it is confirmed that the loop of the
由此,仅在B系统(备用系统)的传送线路4正常的情况下,将B系统(备用系统)的传送线路4切换为主系统的传送线路,不产生重复进行主系统的转变这样的问题。Thereby, only when the
在图7中示出了执行上述处理动作的第2例(实施方式2)的传送线路切换装置7B的主要部分的功能框图。在实施方式2中,在传送线路切换装置7B中,作为传送线路切换部70’,具备消息发送请求有无确认部71、A系统传送线路电流确认部72、B系统传送线路确认部74和线路切换部75。FIG. 7 shows a functional block diagram of a main part of a transmission
在传送线路切换部70’中,消息发送请求有无确认部71确认在通信终端装置群2中有没有消息的发送请求。A系统传送线路电流确认部72确认电流未流过A系统(主系统)的传送线路3的状态是否持续规定时间T以上。B系统传送线路确认部74确认B系统(备用系统)的传送线路4是否正常。在消息发送请求有无确认部71确认为在通信终端装置群2中没有消息的发送请求的状态下,A系统传送线路电流确认部72确认为电流未流过A系统(主系统)的传送线路3的状态持续规定时间T以上的情况下,线路切换部75判断为A系统(主系统)的传送线路3发生断线,并以B系统传送线路确认部74确认为B系统(备用系统)的传送线路4正常作为条件,将B系统(备用系统)的传送线路4切换为主系统的传送线路。In the transmission line switching unit 70', the message transmission request presence/
此外,在该实施方式2中,也是在将B系统(备用系统)的传送线路4切换为主系统的传送线路之后,B系统的传送线路4成为主系统的传送线路,A系统的传送线路3成为备用系统的传送线路。即,在将B系统(备用系统)的传送线路4切换为主系统的传送线路之前,将A系统的传送线路3设为本发明中所说的第1传送线路(主系统的传送线路),将B系统的传送线路4设为本发明中所说的第2传送线路(备用系统的传送线路),在切换后,B系统的传送线路4成为本发明中所说的第1传送线路(主系统的传送线路),A系统的传送线路3成为本发明中所说的第2传送线路(备用系统的传送线路)。Also in the second embodiment, after the
〔实施方式的扩展〕[Extension of Embodiment]
以上,参照实施方式说明了本发明,但本发明不限定于上述实施方式。对于本发明的结构、详细内容,能够在本发明的技术思想的范围内进行本领域技术人员能够理解的各种变更。As mentioned above, although this invention was demonstrated with reference to embodiment, this invention is not limited to the said embodiment. Various changes that can be understood by those skilled in the art can be made within the scope of the technical idea of the present invention for the configuration and details of the present invention.
符号说明Symbol Description
1…电源装置;2…通信终端装置群(负载),3…A系统的传送线路;4…B系统的传送线路;5、6…开关;7(7B)…传送线路切换装置;7-1…CPU;7-2…RAM;7-3…ROM;7-4、7-5…接口;70、70’…传送线路切换部;71…消息发送请求有无确认部;72…A系统传送线路电流确认部;73…线路切换部;73、74…B系统传送线路确认部;75…线路切换部;200…通信系统。1...power supply device; 2...communication terminal device group (load), 3...transmission line of system A; 4...transmission line of system B; 5, 6...switches; 7(7B)...transmission line switching device; 7-1 ...CPU; 7-2...RAM; 7-3...ROM; 7-4, 7-5...interface; 70, 70'...transmission line switching unit; 71...message transmission request presence/absence confirmation unit; 72...A system transmission Line current confirmation unit; 73...Line switching unit; 73, 74...B system transmission line confirmation unit; 75...Line switching unit; 200...Communication system.
Claims (6)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2017-005756 | 2017-01-17 | ||
JP2017005756A JP6760855B2 (en) | 2017-01-17 | 2017-01-17 | Transmission line switching device and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108337113A CN108337113A (en) | 2018-07-27 |
CN108337113B true CN108337113B (en) | 2020-12-01 |
Family
ID=62924893
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810031778.7A Active CN108337113B (en) | 2017-01-17 | 2018-01-12 | Transmission line switching device and method |
Country Status (3)
Country | Link |
---|---|
JP (1) | JP6760855B2 (en) |
KR (1) | KR102082849B1 (en) |
CN (1) | CN108337113B (en) |
Family Cites Families (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5646600A (en) * | 1995-01-12 | 1997-07-08 | General Electric Company | Instrument for detecting potential future failures of valves in critical control systems |
JPH1168856A (en) | 1997-08-12 | 1999-03-09 | Yamatake Honeywell Co Ltd | Communication control device |
JP3105875B2 (en) * | 1998-11-02 | 2000-11-06 | 静岡日本電気株式会社 | Remote power supply method and system |
JP3655599B2 (en) * | 2002-04-17 | 2005-06-02 | 日本電信電話株式会社 | Arbitration device, communication device using the same, and arbitration method |
JP3757417B2 (en) * | 2002-07-02 | 2006-03-22 | 横河電機株式会社 | Optical path switching device |
JP4451718B2 (en) * | 2004-06-04 | 2010-04-14 | 株式会社山武 | Power supply device and power supply method |
CA2690050C (en) * | 2007-06-15 | 2014-07-29 | Stephen G. Seberger | Bidirectional dc to dc converter for power storage control in a power scavenging application |
CN101350636B (en) * | 2008-09-04 | 2012-12-12 | 北京星网锐捷网络技术有限公司 | Method and system for link redundant backup base on photoelectric multiplexing port |
CN101807986A (en) * | 2010-04-20 | 2010-08-18 | 杭州和利时自动化有限公司 | Realization method and device of redundant serial bus |
US8774621B2 (en) * | 2010-11-25 | 2014-07-08 | Mitsubishi Electric Corporation | Communication line switching method, communication apparatus, station-side communication apparatus, communication system, and control unit |
CN104113476A (en) * | 2014-07-22 | 2014-10-22 | 深圳市邦彦信息技术有限公司 | Communication line switching method and system |
KR101752454B1 (en) * | 2015-06-03 | 2017-07-03 | 코츠테크놀로지주식회사 | Data loss prevention system when automatic switching of fiber channel duplex communication channel and method thereof |
-
2017
- 2017-01-17 JP JP2017005756A patent/JP6760855B2/en active Active
-
2018
- 2018-01-12 CN CN201810031778.7A patent/CN108337113B/en active Active
- 2018-01-16 KR KR1020180005489A patent/KR102082849B1/en active IP Right Grant
Also Published As
Publication number | Publication date |
---|---|
KR102082849B1 (en) | 2020-02-28 |
CN108337113A (en) | 2018-07-27 |
JP6760855B2 (en) | 2020-09-23 |
KR20180084666A (en) | 2018-07-25 |
JP2018117209A (en) | 2018-07-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11809291B2 (en) | Method and apparatus for redundancy in active-active cluster system | |
US8861507B2 (en) | Systems and methods for automatic public switched telephone network backup of voice over internet protocol services | |
CN101867468A (en) | Hot restart processing method of Ethernet power switch and Ethernet power switch | |
CN109301919B (en) | An uninterruptible power supply bypass takeover control method | |
CN109428728B (en) | Port adaptive method and device | |
CN104796329A (en) | Automatic link switching method and automatic link switching device | |
CN108337113B (en) | Transmission line switching device and method | |
WO2017076147A1 (en) | Remote upgrade system | |
US10289590B2 (en) | Electronic device and method of auto switching linking path giving priority to a priority port | |
US10637672B2 (en) | Apparatus and methods of power over ethernet | |
CN110417559B (en) | Ethernet power supply equipment and detection method | |
CN210608666U (en) | Control device of redundant power supply and power supply system | |
US9729004B2 (en) | Power source protection device and method | |
TWI768992B (en) | High-speed transimission system, signal redriver and control method of signal redriver | |
CN117277395A (en) | A method, device, equipment and medium for generating trigger pulses for valve control equipment | |
CN104683153A (en) | Cluster-based router host and spare MPU control method and system thereof | |
US10141778B2 (en) | Redundant power and power saving method thereof in cold redundant mode | |
JP2002062903A (en) | Control device | |
TWI523360B (en) | Power source protection device and method | |
KR101601274B1 (en) | Display device | |
US11176073B2 (en) | Data processing apparatus | |
JP2005266314A (en) | Multifunction machine and control method therefor | |
US11561594B2 (en) | Electronic device and method of power supply protection for connection port | |
JP6583321B2 (en) | Power supply control circuit and power supply control method | |
JP2018124632A (en) | Electronic control device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |