CN108331353A - Steel construction hinged-support construction - Google Patents

Steel construction hinged-support construction Download PDF

Info

Publication number
CN108331353A
CN108331353A CN201810072915.1A CN201810072915A CN108331353A CN 108331353 A CN108331353 A CN 108331353A CN 201810072915 A CN201810072915 A CN 201810072915A CN 108331353 A CN108331353 A CN 108331353A
Authority
CN
China
Prior art keywords
hinged
support
construction
steel construction
drag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810072915.1A
Other languages
Chinese (zh)
Inventor
张明明
李孟东
黄光辉
冯博龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Southern Engineering Co Ltd
Original Assignee
China Railway Construction Group Southern Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Southern Engineering Co Ltd filed Critical China Railway Construction Group Southern Engineering Co Ltd
Publication of CN108331353A publication Critical patent/CN108331353A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of steel construction hinged-support constructions, include the following steps:S1, the processing of steel construction hinged-support;S2, surveying setting-out;S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;S4, the installation of hinged-support steel construction bolt;S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, ensure that hinged-support stress meets design requirement;S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is solid and reliable.The present invention is fixed end bearing for prior art Central Plains bearing, and the in-depth of fixed end bearing is rotatable hinged-support by the characteristics of being solely subjected to axle power according to hinged-support, unlikely when being tied up to by typhoon with the power that drag-line forms to snap, to ensure structure safety.The construction of this engineering method is practical, ensured only do not sheared by axle power at node, the optimization aim of moment of flexure.

Description

Steel construction hinged-support construction
Technical field
The present invention relates to architectural engineering construction technique fields, and in particular to a kind of steel construction hinged-support construction.
Background technology
Cultural industry project in China's is largely risen in recent years, and item of recreation construction is increasingly favored.According in amusement park Engineering moulding complexity is built in the requirements such as newly, special, strange, and many common nodes are not suitable for when moulding is arranged in work progress.Steel Structure fixed end hinged-support is arranged, adaptation to local conditions, not only ensure that site operation demand, but also ensure requirement from now on.
Fixed-hinged support:It can rotate, level, vertical direction are immovable.To top power transmission only by axle power, in wind load Larger area can solve the excessive caused bottom shearing of wind-force, influence of the moment of flexure to structure.
Invention content
The purpose of the present invention is to solve drawbacks described above in the prior art, provide a kind of steel construction hinged-support construction work Method.
The purpose of the present invention can be reached by adopting the following technical scheme that:
A kind of steel construction hinged-support construction, the construction include the following steps:
S1, the processing of steel construction hinged-support;
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;
S4, the installation of hinged-support steel construction bolt;
S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, is ensured Hinged-support stress meets design requirement;
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is secured Reliably.
Further, the step S1, the processing of steel construction hinged-support include following process:
S101, drawing in-depth, the characteristics of being applied in combination according to construction site drag-line and steel construction, by steel construction fixed end bearing In-depth is hinged-support;
S102, hinged-support pivot pin hole machined ensure pin shaft hole machining accuracy, and each hole must be aligned.
Further, the step S4, the installation of hinged-support steel construction bolt include following process:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement;
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged Seat is attached;
S403, upper component is fixed temporarily, is removed after the completion of cable tension;
S404, support position is checked, and axis pin is fixed.
Further, the pin shaft hole of the pre-buried part of hinged-support is four rows, and four rounds connect top structure after being passed through by axis pin Part.
Further, the pivot pin material is 40Cr, chemical composition:C (0.37~0.44%), Si (0.17~ 0.37%), (0.80~1.10%) Mn, it is quenched to use heat treatment mode.
The present invention has the following advantages and effects with respect to the prior art:
Simple to install:Hinged bore need to be only aligned by in-site installation, pivot pin is inserted into fixed.
System easy to control the quality:In the construction process, pivot pin and bearing pin hole are the mating making of producer, and quality is secure.
Reasonable stress:Typhoon weather shears fixed end rest base, moment of flexure is larger, hinged to ensure requirement from now on Seat bottom is not subject to shearing and moment of flexure
Description of the drawings
Fig. 1 is the step flow chart of steel construction hinged-support construction disclosed by the invention;
Fig. 2 is interior joint in-depth schematic diagram of the present invention.
Specific implementation mode
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art The every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Embodiment
A kind of step flow chart of steel construction hinged-support construction as shown in Fig. 1, the attached drawing disclose specifically Steel construction hinged-support construction, detailed process includes the following steps:
S1, the processing of steel construction hinged-support;The step is specific as follows:
S101, drawing in-depth, are hinged-support by the in-depth of fixed end bearing.
The in-depth of steel construction fixed end bearing is hinged-support by the characteristics of being applied in combination according to construction site drag-line and steel construction, Ensure joints.It is specific as shown in Fig. 2.
S102, hinged-support pivot pin hole machined.
It is required that ensureing pin shaft hole machining accuracy, each hole must be aligned.
According to in-depth node diagram, the pin shaft hole of the pre-buried part of hinged-support is four rows, and four rounds connect after being passed through by axis pin Upper component.Requirement on machining accuracy is very stringent, once precision is unsatisfactory for requiring, axis pin will not pass through four rounds, to scene Construction infection is serious.
Pivot pin material is 40Cr, chemical composition:C (0.37~0.44%), Si (0.17~0.37%), Mn (0.80~ 1.10%), quenched to use heat treatment mode.
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried;
Concrete construction will be carried out after steel construction hinged-support installation of embedded parts, leveling.
S4, the installation of hinged-support steel construction bolt;The step is specific as follows:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement.
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged Seat is attached.
The lifting of all superstructures, it is necessary to, correction in place in substructure, and can be carried out after fastening supporting member.
S403, upper component is fixed temporarily, is removed after the completion of cable tension.
S404, support position is checked, and axis pin is fixed.
S5, drag-line installation;
Drag-line force value controls, and every cable tension force value must be proofreaded with design value, ensures that hinged-support stress meets Design requirement.
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is secured Reliably.
After the completion of above-mentioned construction, it is necessary to carry out antirust, preservative treatment, avoid influencing to make stress due to corrosion.
In conclusion the characteristics of being fixed end bearing, axle power is solely subjected to according to hinged-support for prior art Central Plains bearing, this It is rotatable hinged-support, the unlikely unexpected folding when being tied up to by typhoon with the power that drag-line forms to deepen fixed end bearing in invention It is disconnected, to ensure structure safety.The construction of this engineering method is practical, ensured only do not sheared by axle power at node, the optimization mesh of moment of flexure Mark.Subsequent secure use is ensured.By the force simplified of hinged-support, provided reliably for follow-up cable tension force value Modeling and Design Guarantee.When meeting with typhoon from now on, the drawbacks of bottom fixed end bearing is broken suddenly can be effectively solved, ensures the life wealth of tourist Production safety.Construction precision more preferably controls, once originally fixed end bearing precision be unsatisfactory for requiring to modify it is difficult big, spend cost Greatly, hinged-support is adjustable nodal in terms of precision controlling.
The above embodiment is a preferred embodiment of the present invention, but embodiments of the present invention are not by above-described embodiment Limitation, it is other it is any without departing from the spirit and principles of the present invention made by changes, modifications, substitutions, combinations, simplifications, Equivalent substitute mode is should be, is included within the scope of the present invention.

Claims (5)

1. a kind of steel construction hinged-support construction, which is characterized in that the construction includes the following steps:
S1, the processing of steel construction hinged-support;
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;
S4, the installation of hinged-support steel construction bolt;
S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, is ensured hinged Seat stress meets design requirement;
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support securely may be used It leans on.
2. steel construction hinged-support construction according to claim 1, which is characterized in that the step S1, steel construction Hinged-support processing includes following process:
S101, drawing in-depth, the characteristics of being applied in combination according to construction site drag-line and steel construction, steel construction fixed end bearing is deepened For hinged-support;
S102, hinged-support pivot pin hole machined ensure pin shaft hole machining accuracy, and each hole must be aligned.
3. steel construction hinged-support construction according to claim 1, which is characterized in that the step S4, hinged-support steel knot The installation of structure bolt includes following process:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement;
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged-support into Row connection;
S403, upper component is fixed temporarily, is removed after the completion of cable tension;
S404, support position is checked, and axis pin is fixed.
4. steel construction hinged-support construction according to claim 3, which is characterized in that the pin shaft hole of the pre-buried part of hinged-support is Four rows, four rounds connect upper component after being passed through by axis pin.
5. steel construction hinged-support construction according to claim 3, which is characterized in that the pivot pin material is 40Cr, is changed It studies point:C (0.37~0.44%), Si (0.17~0.37%), Mn (0.80~1.10%) are quenched to use heat treatment mode.
CN201810072915.1A 2017-11-23 2018-01-25 Steel construction hinged-support construction Pending CN108331353A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN2017111873895 2017-11-23
CN201711187389 2017-11-23

Publications (1)

Publication Number Publication Date
CN108331353A true CN108331353A (en) 2018-07-27

Family

ID=62925921

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810072915.1A Pending CN108331353A (en) 2017-11-23 2018-01-25 Steel construction hinged-support construction

Country Status (1)

Country Link
CN (1) CN108331353A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201704876U (en) * 2010-03-19 2011-01-12 中国江苏国际经济技术合作公司 Cast steel node device with self-forming included angle of stretching cables
CN202744952U (en) * 2012-08-27 2013-02-20 北京机电院高技术股份有限公司 Steel cable and cast steel support pin-connected joint for cable bridge
CN204098228U (en) * 2014-08-18 2015-01-14 中铁十八局集团建筑安装工程有限公司 A kind of steel structure universal hinged-support node

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201704876U (en) * 2010-03-19 2011-01-12 中国江苏国际经济技术合作公司 Cast steel node device with self-forming included angle of stretching cables
CN202744952U (en) * 2012-08-27 2013-02-20 北京机电院高技术股份有限公司 Steel cable and cast steel support pin-connected joint for cable bridge
CN204098228U (en) * 2014-08-18 2015-01-14 中铁十八局集团建筑安装工程有限公司 A kind of steel structure universal hinged-support node

Similar Documents

Publication Publication Date Title
CN108560719B (en) Supporting and mounting method for super-large-span double-layer bidirectional suspension cable structure
US20100031587A1 (en) Floor pier support
CN203795324U (en) Turning spherical hinge
CN103669598A (en) Layer added steel framework column base node on top of multi-layer concrete framework structure and construction method thereof
CN104631684A (en) Single-layer latticed shell steel structure roof system based on concrete building and assembling method of single-layer latticed shell steel structure roof system based on concrete building
CN101806069B (en) Integrated fixation and installation method for bolt
CN105951600A (en) Splicing and positioning method and device for prefabricated stand column and bearing platform
CN201428195Y (en) Drop ceiling node component
CN108331353A (en) Steel construction hinged-support construction
KR101621944B1 (en) setting device based towers enclosing
CN205314319U (en) Metal curtain wall articulates subassembly
CN207377146U (en) A kind of stable type prefabricated assembled concrete component
CN103741709B (en) A kind of tower crane pre-embedded bolt mould
JP4486656B2 (en) How to build a bridge
CN207017146U (en) A kind of box no axle power hinge device of clad steel
CN111794125B (en) Adjusting device and method for controlling height difference of closure section of curved bridge
CN111005323A (en) Supporting method and device for variable-slope cover beam end mold of highway bridge engineering
CN204825950U (en) Rear column single pile basis of connecting bridge
AU2011203029B2 (en) Height-Adjusting Assembly
CN105113531A (en) Single pile foundation of rear upright column of boarding bridge and construction method of single pile foundation of rear upright column of boarding bridge
CN210239172U (en) Assembled architectural design support roof beam board
CN206144246U (en) Framework that lattice formula framework post and A type framework post combined together
CN218508440U (en) Steel reinforcement cage positioning fixture
CN204510480U (en) A kind of reinforcement type pre-embedded bolt be applied in wooden construction
CN213509507U (en) Adjustable support for construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180727

RJ01 Rejection of invention patent application after publication