CN108331353A - Steel construction hinged-support construction - Google Patents
Steel construction hinged-support construction Download PDFInfo
- Publication number
- CN108331353A CN108331353A CN201810072915.1A CN201810072915A CN108331353A CN 108331353 A CN108331353 A CN 108331353A CN 201810072915 A CN201810072915 A CN 201810072915A CN 108331353 A CN108331353 A CN 108331353A
- Authority
- CN
- China
- Prior art keywords
- hinged
- support
- construction
- steel construction
- drag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a kind of steel construction hinged-support constructions, include the following steps:S1, the processing of steel construction hinged-support;S2, surveying setting-out;S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;S4, the installation of hinged-support steel construction bolt;S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, ensure that hinged-support stress meets design requirement;S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is solid and reliable.The present invention is fixed end bearing for prior art Central Plains bearing, and the in-depth of fixed end bearing is rotatable hinged-support by the characteristics of being solely subjected to axle power according to hinged-support, unlikely when being tied up to by typhoon with the power that drag-line forms to snap, to ensure structure safety.The construction of this engineering method is practical, ensured only do not sheared by axle power at node, the optimization aim of moment of flexure.
Description
Technical field
The present invention relates to architectural engineering construction technique fields, and in particular to a kind of steel construction hinged-support construction.
Background technology
Cultural industry project in China's is largely risen in recent years, and item of recreation construction is increasingly favored.According in amusement park
Engineering moulding complexity is built in the requirements such as newly, special, strange, and many common nodes are not suitable for when moulding is arranged in work progress.Steel
Structure fixed end hinged-support is arranged, adaptation to local conditions, not only ensure that site operation demand, but also ensure requirement from now on.
Fixed-hinged support:It can rotate, level, vertical direction are immovable.To top power transmission only by axle power, in wind load
Larger area can solve the excessive caused bottom shearing of wind-force, influence of the moment of flexure to structure.
Invention content
The purpose of the present invention is to solve drawbacks described above in the prior art, provide a kind of steel construction hinged-support construction work
Method.
The purpose of the present invention can be reached by adopting the following technical scheme that:
A kind of steel construction hinged-support construction, the construction include the following steps:
S1, the processing of steel construction hinged-support;
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;
S4, the installation of hinged-support steel construction bolt;
S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, is ensured
Hinged-support stress meets design requirement;
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is secured
Reliably.
Further, the step S1, the processing of steel construction hinged-support include following process:
S101, drawing in-depth, the characteristics of being applied in combination according to construction site drag-line and steel construction, by steel construction fixed end bearing
In-depth is hinged-support;
S102, hinged-support pivot pin hole machined ensure pin shaft hole machining accuracy, and each hole must be aligned.
Further, the step S4, the installation of hinged-support steel construction bolt include following process:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement;
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged
Seat is attached;
S403, upper component is fixed temporarily, is removed after the completion of cable tension;
S404, support position is checked, and axis pin is fixed.
Further, the pin shaft hole of the pre-buried part of hinged-support is four rows, and four rounds connect top structure after being passed through by axis pin
Part.
Further, the pivot pin material is 40Cr, chemical composition:C (0.37~0.44%), Si (0.17~
0.37%), (0.80~1.10%) Mn, it is quenched to use heat treatment mode.
The present invention has the following advantages and effects with respect to the prior art:
Simple to install:Hinged bore need to be only aligned by in-site installation, pivot pin is inserted into fixed.
System easy to control the quality:In the construction process, pivot pin and bearing pin hole are the mating making of producer, and quality is secure.
Reasonable stress:Typhoon weather shears fixed end rest base, moment of flexure is larger, hinged to ensure requirement from now on
Seat bottom is not subject to shearing and moment of flexure
Description of the drawings
Fig. 1 is the step flow chart of steel construction hinged-support construction disclosed by the invention;
Fig. 2 is interior joint in-depth schematic diagram of the present invention.
Specific implementation mode
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention
In attached drawing, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is
A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art
The every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
Embodiment
A kind of step flow chart of steel construction hinged-support construction as shown in Fig. 1, the attached drawing disclose specifically
Steel construction hinged-support construction, detailed process includes the following steps:
S1, the processing of steel construction hinged-support;The step is specific as follows:
S101, drawing in-depth, are hinged-support by the in-depth of fixed end bearing.
The in-depth of steel construction fixed end bearing is hinged-support by the characteristics of being applied in combination according to construction site drag-line and steel construction,
Ensure joints.It is specific as shown in Fig. 2.
S102, hinged-support pivot pin hole machined.
It is required that ensureing pin shaft hole machining accuracy, each hole must be aligned.
According to in-depth node diagram, the pin shaft hole of the pre-buried part of hinged-support is four rows, and four rounds connect after being passed through by axis pin
Upper component.Requirement on machining accuracy is very stringent, once precision is unsatisfactory for requiring, axis pin will not pass through four rounds, to scene
Construction infection is serious.
Pivot pin material is 40Cr, chemical composition:C (0.37~0.44%), Si (0.17~0.37%), Mn (0.80~
1.10%), quenched to use heat treatment mode.
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried;
Concrete construction will be carried out after steel construction hinged-support installation of embedded parts, leveling.
S4, the installation of hinged-support steel construction bolt;The step is specific as follows:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement.
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged
Seat is attached.
The lifting of all superstructures, it is necessary to, correction in place in substructure, and can be carried out after fastening supporting member.
S403, upper component is fixed temporarily, is removed after the completion of cable tension.
S404, support position is checked, and axis pin is fixed.
S5, drag-line installation;
Drag-line force value controls, and every cable tension force value must be proofreaded with design value, ensures that hinged-support stress meets
Design requirement.
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support is secured
Reliably.
After the completion of above-mentioned construction, it is necessary to carry out antirust, preservative treatment, avoid influencing to make stress due to corrosion.
In conclusion the characteristics of being fixed end bearing, axle power is solely subjected to according to hinged-support for prior art Central Plains bearing, this
It is rotatable hinged-support, the unlikely unexpected folding when being tied up to by typhoon with the power that drag-line forms to deepen fixed end bearing in invention
It is disconnected, to ensure structure safety.The construction of this engineering method is practical, ensured only do not sheared by axle power at node, the optimization mesh of moment of flexure
Mark.Subsequent secure use is ensured.By the force simplified of hinged-support, provided reliably for follow-up cable tension force value Modeling and Design
Guarantee.When meeting with typhoon from now on, the drawbacks of bottom fixed end bearing is broken suddenly can be effectively solved, ensures the life wealth of tourist
Production safety.Construction precision more preferably controls, once originally fixed end bearing precision be unsatisfactory for requiring to modify it is difficult big, spend cost
Greatly, hinged-support is adjustable nodal in terms of precision controlling.
The above embodiment is a preferred embodiment of the present invention, but embodiments of the present invention are not by above-described embodiment
Limitation, it is other it is any without departing from the spirit and principles of the present invention made by changes, modifications, substitutions, combinations, simplifications,
Equivalent substitute mode is should be, is included within the scope of the present invention.
Claims (5)
1. a kind of steel construction hinged-support construction, which is characterized in that the construction includes the following steps:
S1, the processing of steel construction hinged-support;
S2, surveying setting-out;
S3, steel construction hinged-support are pre-buried, will carry out concrete construction after steel construction hinged-support installation of embedded parts, leveling;
S4, the installation of hinged-support steel construction bolt;
S5, drag-line installation, control drag-line force value, and every cable tension force value is proofreaded with design value, is ensured hinged
Seat stress meets design requirement;
S6, force balance adjustment, adjust the force balance between drag-line and rotatable hinged-support, it is ensured that hinged-support securely may be used
It leans on.
2. steel construction hinged-support construction according to claim 1, which is characterized in that the step S1, steel construction
Hinged-support processing includes following process:
S101, drawing in-depth, the characteristics of being applied in combination according to construction site drag-line and steel construction, steel construction fixed end bearing is deepened
For hinged-support;
S102, hinged-support pivot pin hole machined ensure pin shaft hole machining accuracy, and each hole must be aligned.
3. steel construction hinged-support construction according to claim 1, which is characterized in that the step S4, hinged-support steel knot
The installation of structure bolt includes following process:
S401, hinged upper component installation is carried out after built-in fitting part concrete reaches design requirement;
S402, upper component laggard marketing axis in place are installed, by axis pin by pin shaft hole by superstructure and pre-buried hinged-support into
Row connection;
S403, upper component is fixed temporarily, is removed after the completion of cable tension;
S404, support position is checked, and axis pin is fixed.
4. steel construction hinged-support construction according to claim 3, which is characterized in that the pin shaft hole of the pre-buried part of hinged-support is
Four rows, four rounds connect upper component after being passed through by axis pin.
5. steel construction hinged-support construction according to claim 3, which is characterized in that the pivot pin material is 40Cr, is changed
It studies point:C (0.37~0.44%), Si (0.17~0.37%), Mn (0.80~1.10%) are quenched to use heat treatment mode.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2017111873895 | 2017-11-23 | ||
CN201711187389 | 2017-11-23 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108331353A true CN108331353A (en) | 2018-07-27 |
Family
ID=62925921
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810072915.1A Pending CN108331353A (en) | 2017-11-23 | 2018-01-25 | Steel construction hinged-support construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108331353A (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201704876U (en) * | 2010-03-19 | 2011-01-12 | 中国江苏国际经济技术合作公司 | Cast steel node device with self-forming included angle of stretching cables |
CN202744952U (en) * | 2012-08-27 | 2013-02-20 | 北京机电院高技术股份有限公司 | Steel cable and cast steel support pin-connected joint for cable bridge |
CN204098228U (en) * | 2014-08-18 | 2015-01-14 | 中铁十八局集团建筑安装工程有限公司 | A kind of steel structure universal hinged-support node |
-
2018
- 2018-01-25 CN CN201810072915.1A patent/CN108331353A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201704876U (en) * | 2010-03-19 | 2011-01-12 | 中国江苏国际经济技术合作公司 | Cast steel node device with self-forming included angle of stretching cables |
CN202744952U (en) * | 2012-08-27 | 2013-02-20 | 北京机电院高技术股份有限公司 | Steel cable and cast steel support pin-connected joint for cable bridge |
CN204098228U (en) * | 2014-08-18 | 2015-01-14 | 中铁十八局集团建筑安装工程有限公司 | A kind of steel structure universal hinged-support node |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108560719B (en) | Supporting and mounting method for super-large-span double-layer bidirectional suspension cable structure | |
US20100031587A1 (en) | Floor pier support | |
CN203795324U (en) | Turning spherical hinge | |
CN103669598A (en) | Layer added steel framework column base node on top of multi-layer concrete framework structure and construction method thereof | |
CN104631684A (en) | Single-layer latticed shell steel structure roof system based on concrete building and assembling method of single-layer latticed shell steel structure roof system based on concrete building | |
CN101806069B (en) | Integrated fixation and installation method for bolt | |
CN105951600A (en) | Splicing and positioning method and device for prefabricated stand column and bearing platform | |
CN201428195Y (en) | Drop ceiling node component | |
CN108331353A (en) | Steel construction hinged-support construction | |
KR101621944B1 (en) | setting device based towers enclosing | |
CN205314319U (en) | Metal curtain wall articulates subassembly | |
CN207377146U (en) | A kind of stable type prefabricated assembled concrete component | |
CN103741709B (en) | A kind of tower crane pre-embedded bolt mould | |
JP4486656B2 (en) | How to build a bridge | |
CN207017146U (en) | A kind of box no axle power hinge device of clad steel | |
CN111794125B (en) | Adjusting device and method for controlling height difference of closure section of curved bridge | |
CN111005323A (en) | Supporting method and device for variable-slope cover beam end mold of highway bridge engineering | |
CN204825950U (en) | Rear column single pile basis of connecting bridge | |
AU2011203029B2 (en) | Height-Adjusting Assembly | |
CN105113531A (en) | Single pile foundation of rear upright column of boarding bridge and construction method of single pile foundation of rear upright column of boarding bridge | |
CN210239172U (en) | Assembled architectural design support roof beam board | |
CN206144246U (en) | Framework that lattice formula framework post and A type framework post combined together | |
CN218508440U (en) | Steel reinforcement cage positioning fixture | |
CN204510480U (en) | A kind of reinforcement type pre-embedded bolt be applied in wooden construction | |
CN213509507U (en) | Adjustable support for construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180727 |
|
RJ01 | Rejection of invention patent application after publication |