CN108330958A - A kind of constructing device filled for composite pile foundation stake top cavity envelope - Google Patents
A kind of constructing device filled for composite pile foundation stake top cavity envelope Download PDFInfo
- Publication number
- CN108330958A CN108330958A CN201810330986.7A CN201810330986A CN108330958A CN 108330958 A CN108330958 A CN 108330958A CN 201810330986 A CN201810330986 A CN 201810330986A CN 108330958 A CN108330958 A CN 108330958A
- Authority
- CN
- China
- Prior art keywords
- pile
- stake top
- foundation
- cavity
- grouting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 239000002131 composite material Substances 0.000 title claims abstract description 21
- 239000002689 soil Substances 0.000 claims abstract description 19
- 230000002787 reinforcement Effects 0.000 claims abstract description 13
- 239000011440 grout Substances 0.000 claims description 14
- 239000004576 sand Substances 0.000 claims description 4
- 238000007569 slipcasting Methods 0.000 claims 7
- 238000003466 welding Methods 0.000 claims 1
- 229910000831 Steel Inorganic materials 0.000 abstract description 14
- 238000000034 method Methods 0.000 abstract description 14
- 239000010959 steel Substances 0.000 abstract description 14
- 238000007789 sealing Methods 0.000 abstract description 12
- 238000010276 construction Methods 0.000 abstract description 11
- 230000000694 effects Effects 0.000 abstract description 5
- 239000003673 groundwater Substances 0.000 description 5
- 238000009825 accumulation Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 238000005034 decoration Methods 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000004382 potting Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009440 infrastructure construction Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 230000009916 joint effect Effects 0.000 description 1
- 230000007774 longterm Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/62—Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种用于复合桩基础桩顶空腔封灌的施工装置:在桩顶进行二次浇注时,将新型注浆底管与主筋焊接牢固并浇筑在二次桩顶内部,管口插入桩顶空腔内部;基桩外的新型注浆底管埋置在地基土浅层,并由筏板侧面引出至地面。跟传统的注浆方法相比,本发明可以经济合理地实现对桩顶空腔的注浆封闭工作,可在确保注浆效果的同时,保证筏板的整体性不受破坏及钢筋绑扎工作的顺利展开,降低工程成本提高工作效率。
The invention discloses a construction device for sealing the cavity of the pile top of a composite pile foundation: when performing secondary pouring on the pile top, the new type of grouting bottom pipe and the main reinforcement are welded firmly and poured inside the secondary pile top, and the pipe The hole is inserted into the pile top cavity; the new grouting bottom pipe outside the foundation pile is embedded in the shallow layer of the foundation soil, and is led out to the ground from the side of the raft. Compared with the traditional grouting method, the present invention can economically and reasonably realize the grouting and sealing of the cavity on the top of the pile, while ensuring the grouting effect, it can ensure that the integrity of the raft is not damaged and the binding of steel bars is guaranteed. Smooth development, reduce engineering costs and improve work efficiency.
Description
技术领域technical field
本发明涉及一种用于复合桩基础桩顶空腔封灌的施工装置,尤其是用于桩顶设置弹性支座的复合桩基础的桩顶空腔封灌。The invention relates to a construction device for sealing and filling the pile top cavity of a composite pile foundation, in particular to a construction device for sealing and filling the pile top cavity of a composite pile foundation with elastic bearings arranged on the pile top.
背景技术Background technique
随着我国基础建设的大力推进,桩基础这一古老的基础形式得到前所未有的广泛应用和发展。作为桩基础的主要表现形式之一的桩筏基础,近年来同样发展迅速,桩筏基础,顾名思义是指桩与承台共同承受上部结构荷载的基础形式,具有基础整体性好、抗弯刚度大、适应性广且便于实现桩土共同作用等优点。With the vigorous promotion of infrastructure construction in our country, pile foundation, an ancient foundation form, has been widely used and developed unprecedentedly. As one of the main manifestations of pile foundations, piled raft foundations have also developed rapidly in recent years. Pile raft foundations, as the name implies, refer to the foundation form in which piles and caps bear the load of the upper structure together. It has good foundation integrity and high bending rigidity. , wide adaptability and easy to realize pile-soil interaction and other advantages.
常规桩筏基础桩-筏之间直接刚性连接,其整体刚度由筏板刚度和桩基支承刚度决定。如为某些原因需调节桩筏刚度,则筏板刚度可通过筏厚调整,但往往造价较高;桩基支承刚度则可通过改变桩长、桩径以及桩距等方法来调整,但不同桩径、不同桩长的布桩方式受上部结构形式和地质条件的影响较大,应用范围受到相当大的限制。复合桩基础新技术旨在在桩顶与筏板之间设置弹性支座来调整、优化桩筏的支承刚度,此举可以实现经济、有效地根据需要调整桩筏基础的整体刚度。The direct rigid connection between piles and rafts in conventional pile-raft foundations, the overall stiffness is determined by the stiffness of the raft slab and the support stiffness of the pile foundation. If the stiffness of the pile raft needs to be adjusted for some reasons, the stiffness of the raft slab can be adjusted through the thickness of the raft, but the cost is often high; the support stiffness of the pile foundation can be adjusted by changing the pile length, pile diameter, and pile distance, but different The pile diameter and pile layout methods of different pile lengths are greatly affected by the superstructure form and geological conditions, and the application range is considerably limited. The new technology of composite pile foundation aims to adjust and optimize the support stiffness of the pile raft by setting elastic bearings between the pile top and the raft slab, which can economically and effectively adjust the overall stiffness of the pile raft foundation as needed.
与常规桩筏基础相比,复合桩基础的特点仅在于在桩顶设置了可人为按需设定刚度的弹性支座。上述改进使人为有效、经济地干预桩筏基础的整体刚度提供了可能,同时极大地扩展了桩筏基础的应用领域。从目前的研究来看,复合桩基础可用于以下多种情形:①浅层地基土承载力较高,具有一定利用潜力,且桩基类型为端承型地区,需考虑桩、土共同作用的情况。此种情况又称为端承型桩复合桩基,与应用于软土地区的常规复合桩基合称为广义复合桩基;②以减小差异沉降和筏板(承台)内力为目标的变刚度调平设计;③考虑建筑物老桩基的承载潜力,新、旧桩基共同承担上部结构荷载的情况;④特殊地质条件下的桩筏基础,如建筑场地基岩面起伏较大或缺失以及土岩组合地基等地基土支承刚度严重不均匀的情况;⑤上述两种或多种情况的组合。Compared with the conventional pile-raft foundation, the only feature of the composite pile foundation is that an elastic support with artificial stiffness can be set on the top of the pile. The above improvements make it possible to effectively and economically intervene in the overall stiffness of the piled-raft foundation, and at the same time greatly expand the application field of the piled-raft foundation. According to the current research, the composite pile foundation can be used in the following situations: ① The shallow foundation soil has a high bearing capacity and has a certain utilization potential, and the pile foundation type is an end-bearing area, and the joint action of piles and soil needs to be considered Happening. This kind of situation is also called end-supported pile composite pile foundation, and it is called generalized composite pile foundation together with the conventional composite pile foundation applied in soft soil areas; Variable stiffness leveling design; ③Consider the bearing potential of the old pile foundation of the building, the situation that the new and old pile foundations share the load of the upper structure; Absence and soil-rock combination foundations and other situations where foundation soil support stiffness is seriously uneven; ⑤ Combination of two or more of the above situations.
采用复合桩基础形式,为了增加桩顶的耐久性,在建筑物沉降稳定后需要将桩顶空腔进行注浆封闭。目前传统的注浆封闭方法主要为“上引法”,即通过在弹性支座安装时在上盖板上开孔,注浆管与盖板焊接牢固并垂直穿过筏板引出,并进行注浆。In the form of composite pile foundation, in order to increase the durability of the pile top, the cavity of the pile top needs to be grouted and closed after the settlement of the building is stable. At present, the traditional grouting sealing method is mainly the "upward drawing method", that is, by opening a hole on the upper cover plate when the elastic support is installed, the grouting pipe and the cover plate are firmly welded and drawn out vertically through the raft, and the injection pulp.
目前传统的“上引法”为复合桩基础主要的注浆封闭方法,得到了一定范围的应用,但是工程实践的过程中存在诸多问题,主要分为以下几个方面:At present, the traditional "introduction method" is the main grouting sealing method for composite pile foundations, and it has been applied in a certain range. However, there are many problems in the process of engineering practice, which are mainly divided into the following aspects:
1、注浆管与盖板焊接联通,必须在盖板上进行开孔并焊接接头,而盖板为一到两公分的钢板,刚度大,在其上面开孔难度大,大大增加的生产成本;焊接在盖板上的接头在运输的过程中不便于保护,容易破坏变形,且不易更换,这给后期注浆管与盖板的连接带来了极大的困难。1. The grouting pipe and the cover plate are welded and connected, and the cover plate must be drilled and welded. The cover plate is a steel plate of one to two centimeters, with high rigidity, and it is difficult to open holes on it, which greatly increases the production cost. ; The joints welded on the cover plate are inconvenient to protect during transportation, are easy to be damaged and deformed, and are not easy to replace, which brings great difficulties to the connection between the grouting pipe and the cover plate in the later stage.
2、筏板内部钢筋纵横交错,数量巨大,而“上引法”是将注浆管穿过筏板引出至地面,因此带来了一个极大的难题:钢筋不易绑扎!钢筋绑扎之前,注浆管已经安装完毕,接着进行绑扎钢筋显然会与注浆管“打架”,从先前的工程案例中可以发现,诸如钢筋下放与搬运困难、注浆管被钢筋撞歪甚至撞断、为避开注浆管位置而造成钢筋布置不均匀等问题屡次出现。2. The steel bars inside the raft are criss-crossed, and the number is huge. However, the "upward drawing method" is to lead the grouting pipe through the raft to the ground, which brings a huge problem: the steel bars are not easy to bind! Before the reinforcement is bound, the grouting pipe has been installed, and then the binding of the reinforcement will obviously "fight" with the grouting pipe. From previous engineering cases, it can be found that such as difficulties in lowering and transporting the reinforcement, and the grouting pipe being bumped or even hit by the reinforcement. Problems such as breakage and uneven arrangement of reinforcement caused by avoiding the position of the grouting pipe have repeatedly occurred.
3、注浆管顶部冒出筏板20cm左右,由于地下水作用,在注浆封闭之前管内地下水会源源不断往上涌,造成地下室内部积水严重,这个后期地下室车库的装修施工带来了很大的不便。3. The top of the grouting pipe protrudes about 20cm from the raft. Due to the action of groundwater, the groundwater in the pipe will continuously flow up before the grouting is closed, resulting in serious water accumulation in the basement. The decoration construction of the basement garage in the later period has brought a lot the inconvenience.
4、筏板内分布有数量众多的注浆管,虽然后期管内有浆液充填,但充填效果得不到保证,筏板的整体性得到了破坏,而建筑物使用年限一般都大于50年,长期的荷载作用下是否存在一定的安全隐患。4. There are a large number of grouting pipes distributed in the raft. Although there is grout filling in the pipe in the later stage, the filling effect cannot be guaranteed, and the integrity of the raft is damaged. The service life of the building is generally more than 50 years. Whether there is a certain safety hazard under the load.
发明内容Contents of the invention
本发明的目的是针对上述现有技术的不足,提供一种安全可靠、技术可行、经济合理的用于复合桩基础桩顶空腔的封灌装置。The object of the present invention is to provide a safe, reliable, technically feasible, economical and reasonable sealing and filling device for the pile top cavity of the composite pile foundation, aiming at the above-mentioned deficiencies in the prior art.
一种用于复合桩基础桩顶空腔封灌的施工装置,包括一根以上的注浆底管,以及由下至上顺次排布的基桩、盖板及筏板;所述基桩包括一次浇筑桩身与二次浇筑桩顶,所述一次浇筑桩身与二次浇筑桩顶通过主筋连接固定;所述二次浇筑桩顶与盖板之间形成的空腔为桩顶空腔,桩顶空腔内置一个以上的桩顶支座,桩顶支座的顶部连接盖板,底部连接二次浇注桩顶;所述盖板顶面与筏板底部连接,盖板的侧面由地基土层与混凝土垫层包裹,混凝土垫层、地基土层由上至下叠放排布,盖板的侧面与混凝土垫层和地基土层之间的间隙处通过填砂填实;所述注浆底管包括管身、位于管身两端的进浆口和出浆口;进浆口与外部连通,管身贯穿二次浇筑桩顶后,出浆口插入桩顶空腔内,注浆底管与主筋焊接牢固。A construction device for sealing the cavity of the pile top of a composite pile foundation, comprising more than one grouting bottom pipe, and foundation piles, cover plates and rafts arranged in sequence from bottom to top; the foundation piles include The primary pouring pile body and the secondary pouring pile top, the primary pouring pile body and the secondary pouring pile top are connected and fixed through the main reinforcement; the cavity formed between the secondary pouring pile top and the cover plate is the pile top cavity, There is more than one pile top support built into the pile top cavity, the top of the pile top support is connected to the cover plate, and the bottom is connected to the secondary pouring pile top; The layer is wrapped with the concrete cushion, the concrete cushion and the foundation soil layer are stacked and arranged from top to bottom, and the gap between the side of the cover plate and the concrete cushion and the foundation soil layer is filled with sand; the grouting The bottom pipe includes a pipe body, a grout inlet and a grout outlet located at both ends of the pipe body; the grout inlet is connected to the outside, and after the pipe body passes through the pile top after the second pouring, the grout outlet is inserted into the pile top cavity, and the bottom pipe is grouted Weld firmly with the main reinforcement.
本发明通过设置下行型的注浆底管,无需在盖板上打洞,节约了成本,也保证了盖板的完整性;此外,注浆底管的位置发生变化,不会与筏板内部的钢筋结构发生安装上的冲突,不但使得工程更易推进,也解决了排布不均的问题;再次,注浆底管不再位于筏板之上,在注浆封闭之前,不再会产生管内地下水会源源不断往上涌,造成地下室内部积水严重的问题,方便后续施工;最后,填充效果也比较稳定。盖板的侧面由地基土层与混凝土垫层包裹,也是为了便于安装注浆底管,降低施工难度,保证施工的质量。本发明方案在施工时,建筑的基础形式采用复合桩基础,桩顶支座位于空腔内部,后期沉降稳定后需对空腔进行封灌。与现有的“上引法”相比,采用本发明方式填充效果的稳定性能提高了32%,而成本降低了约50%。The present invention does not need to drill holes on the cover plate by setting the downward type grouting bottom pipe, which saves the cost and ensures the integrity of the cover plate; in addition, the position of the grouting bottom pipe changes without contact with the inside of the raft. The conflicts in the installation of the reinforced steel structure not only make it easier to advance the project, but also solve the problem of uneven arrangement; again, the bottom pipe of the grouting is no longer located on the raft, and the groundwater in the pipe will no longer be generated before the grouting is closed It will continue to flow up, causing serious water accumulation in the basement, which is convenient for subsequent construction; finally, the filling effect is relatively stable. The side of the cover plate is wrapped by the foundation soil layer and the concrete cushion, which is also to facilitate the installation of the grouting bottom pipe, reduce the construction difficulty and ensure the quality of the construction. During the construction of the solution of the present invention, the foundation form of the building adopts a composite pile foundation, and the pile top support is located inside the cavity, and the cavity needs to be sealed and filled after the later settlement is stable. Compared with the existing "upward citation method", the method of the invention improves the stability of the filling effect by 32%, and reduces the cost by about 50%.
作为优选,所述一次浇筑桩身顶面位于混凝土垫层下20cm-30cm,所述二次浇筑桩顶面位于混凝土垫层下5cm-10cm;所述注浆底管管身位于二次浇筑桩顶下部5cm-15cm,所述注浆底管出浆口插入空腔内部5cm-10cm。As a preference, the top surface of the primary pouring pile body is located at 20cm-30cm below the concrete cushion, and the top surface of the secondary pouring pile is located at 5cm-10cm below the concrete cushion; The bottom part is 5cm-15cm, and the grout outlet of the grouting bottom pipe is inserted into the cavity by 5cm-10cm.
作为优选,所述注浆底管内径为2.5cm、3.2cm或4.0cm。Preferably, the inner diameter of the grouting bottom pipe is 2.5cm, 3.2cm or 4.0cm.
作为优选,所述注浆底管管身还贯穿地基土层,并由筏板侧面引出至地面与外部连通。Preferably, the body of the grouting bottom pipe also penetrates the foundation soil layer, and is led out from the side of the raft to the ground to communicate with the outside.
有益效果:本发明公开的一种用于复合桩基础桩顶空腔封灌的施工装置,经济合理地实现对桩顶空腔的注浆封闭工作,可在确保注浆效果的同时,保证筏板的整体性不受破坏及钢筋绑扎工作的顺利展开,降低工程成本提高工作效率。Beneficial effects: the invention discloses a construction device for sealing and grouting the cavity of the pile top of the composite pile foundation. The integrity of the board is not damaged and the steel bar binding work can be carried out smoothly, reducing engineering costs and improving work efficiency.
附图说明Description of drawings
图1是传统“上引法”的灌封装置的结构示意图。Fig. 1 is a schematic structural diagram of a potting device of the traditional "up-priming method".
图2是本发明一种用于桩顶空腔的封灌装置的剖面结构示意图。Fig. 2 is a schematic cross-sectional structure diagram of a sealing and filling device for a pile top cavity according to the present invention.
图3是本发明一种用于桩顶空腔的封灌装置的平面结构示意图。Fig. 3 is a schematic diagram of the planar structure of a sealing and filling device for a pile top cavity according to the present invention.
图中:1、筏板,2、桩顶空腔,3、弹性支座,4、注浆底管,5、混凝土垫层,6、地基土层,7、填砂,8、主筋,9、二次浇筑桩顶,10、基桩,11、一次浇筑桩身,12、盖板。In the figure: 1. raft, 2. pile top cavity, 3. elastic support, 4. grouting bottom pipe, 5. concrete cushion, 6. foundation soil layer, 7. sand filling, 8. main reinforcement, 9 1. Second pouring pile top, 10. Foundation pile, 11. One-time pouring pile body, 12. Cover plate.
具体实施方式Detailed ways
下面结合附图和具体实施方式对本发明做进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
如图1所示,现有“上引法”的灌封装置中,注浆底管4由上至下依次贯穿筏板1、盖板12后伸入位于盖板12和二次浇筑桩顶9之间的桩顶空间2中,其问题在于:As shown in Figure 1, in the existing potting device of the "upward lead method", the grouting bottom pipe 4 runs through the raft 1 and the cover 12 from top to bottom, and then extends into the cover 12 and the top of the secondary pouring pile. 9 in the pile top space 2, the problem is:
1、注浆底管4要贯穿盖板12,必须在盖板12上进行开孔并焊接接头,而盖板12为一到两公分的钢板,刚度大,在其上面开孔难度大,大大增加的生产成本;焊接在盖板12上的接头在运输的过程中不便于保护,容易破坏变形,且不易更换,这给后期注浆底管4与盖板12的连接带来了极大的困难。1. To penetrate the cover plate 12, the grouting bottom pipe 4 must be drilled and welded on the cover plate 12, and the cover plate 12 is a steel plate of one to two centimeters, with high rigidity, and it is difficult to open holes on it, which greatly Increased production costs; the joints welded on the cover plate 12 are not easy to protect during transportation, are easily damaged and deformed, and are not easy to replace, which brings great difficulties to the connection between the grouting bottom pipe 4 and the cover plate 12 difficulty.
2、筏板1内部钢筋纵横交错,数量巨大,而“上引法”是将注浆底管4穿过筏板1引出至地面,因此带来了一个极大的难题:钢筋不易绑扎!钢筋绑扎之前,注浆底管4已经安装完毕,接着进行绑扎钢筋显然会与注浆底管4 “打架”,从先前的工程案例中可以发现,诸如钢筋下放与搬运困难、注浆底管4被钢筋撞歪甚至撞断、为避开注浆底管4位置而造成钢筋布置不均匀等问题屡次出现。2. The steel bars inside the raft 1 are criss-crossed, and the number is huge. However, the "upward drawing method" is to lead the grouting bottom pipe 4 through the raft 1 to the ground, which brings a great problem: the steel bars are not easy to bind! Before the steel bars are bound, the grouting bottom pipe 4 has been installed, and then the steel bars will obviously "fight" with the grouting bottom pipe 4. From previous engineering cases, it can be found that such as the difficulty of lowering and transporting the steel bars, the grouting bottom pipe 4 Problems such as being knocked crookedly or even broken by steel bars, and uneven layout of steel bars caused by avoiding the position of the grouting bottom pipe 4 have repeatedly occurred.
3、注浆底管4顶部冒出筏板1约20cm,由于地下水作用,在注浆封闭之前管内地下水会源源不断往上涌,造成地下室内部积水严重,这给后期地下室车库的装修施工带来了很大的不便。3. The top of the grouting bottom pipe 4 protrudes from the raft 1 by about 20cm. Due to the action of groundwater, the groundwater in the pipe will continuously flow upwards before the grouting is closed, resulting in serious water accumulation in the basement, which will cause serious problems for the decoration construction of the basement garage in the later period. It's a big inconvenience.
4、筏板1内分布有数量众多的注浆底管4,虽然后期管内有浆液充填,但充填效果得不到保证,筏板1的整体性得到了破坏,而建筑物使用年限一般都大于50年,长期的荷载作用下是否存在一定的安全隐患。4. A large number of grouting bottom pipes 4 are distributed in the raft 1. Although the pipes are filled with grout in the later stage, the filling effect cannot be guaranteed, the integrity of the raft 1 is damaged, and the service life of the building is generally longer than 50 years, whether there are certain safety hazards under the long-term load.
如图2-3所示:为本发明封灌装置,包括一根以上的注浆底管4,以及由下至上顺次排布的基桩10、盖板12及筏板1。As shown in Figure 2-3: it is the sealing and grouting device of the present invention, which includes more than one grouting bottom pipe 4, and foundation piles 10, cover plates 12 and rafts 1 arranged in sequence from bottom to top.
所述基桩10包括一次浇筑桩身11与二次浇筑桩顶9,所述一次浇筑桩身11与二次浇筑桩顶9通过主筋8连接固定;所述二次浇筑桩顶9与盖板12之间形成的空腔为桩顶空腔2,桩顶空腔2内置一个以上的桩顶支座3,桩顶支座3的顶部连接盖板12,底部连接二次浇注桩顶9;所述盖板12顶面与筏板1底部连接,盖板12的侧面由地基土层6与混凝土垫层5包裹,混凝土垫层5、地基土层6由上至下叠放排布,盖板12的侧面与混凝土垫层5和地基土层6之间的间隙处通过填砂7填实;所述注浆底管4包括管身、位于管身两端的进浆口和出浆口;进浆口与外部连通,管身贯穿二次浇筑桩顶9后,出浆口插入桩顶空腔2内,注浆底管4与主筋8焊接牢固。The foundation pile 10 comprises a primary pouring pile body 11 and a secondary pouring pile top 9, the primary pouring pile body 11 and the secondary pouring pile top 9 are connected and fixed by the main reinforcement 8; the secondary pouring pile top 9 and the cover plate The cavity formed between 12 is the pile top cavity 2, and more than one pile top support 3 is built in the pile top cavity 2, the top of the pile top support 3 is connected to the cover plate 12, and the bottom is connected to the secondary pouring pile top 9; The top surface of the cover plate 12 is connected to the bottom of the raft 1, and the side surface of the cover plate 12 is wrapped by the foundation soil layer 6 and the concrete cushion layer 5. The concrete cushion layer 5 and the foundation soil layer 6 are stacked and arranged from top to bottom. The gap between the side of the plate 12 and the concrete cushion 5 and the foundation soil layer 6 is filled with sand 7; the grouting bottom pipe 4 includes a pipe body, a grout inlet and a grout outlet at both ends of the pipe body; The grout inlet is connected with the outside, after the pipe body penetrates the pile top 9 after secondary pouring, the grout outlet is inserted into the pile top cavity 2, and the grouting bottom pipe 4 and the main reinforcement 8 are welded firmly.
建筑的基础形式宜采用复合桩基础,桩顶支座3为弹性支座,后期沉降稳定后需对桩顶空腔2进行封灌。The foundation form of the building should be a composite pile foundation, and the pile top support 3 is an elastic support. After the later settlement is stable, the pile top cavity 2 needs to be sealed and filled.
所述一次浇筑桩身11顶面位于所述混凝土垫层5的面下20cm-30cm,所述二次浇筑桩顶9的顶面面位于所述混凝土垫层5的面下5cm-10cm。The top surface of the primary pouring pile body 11 is located 20cm-30cm below the surface of the concrete cushion 5, and the top surface of the secondary pouring pile top 9 is located 5cm-10cm below the surface of the concrete cushion 5.
所述注浆底管4管身位于二次浇筑桩顶9面下5cm-15cm,注浆底管4的出浆口插入桩顶空腔2内部5cm-10cm。。The body of the grouting bottom pipe 4 is located 5cm-15cm below the surface 9 of the secondary pouring pile, and the grouting outlet of the grouting bottom pipe 4 is inserted into the pile top cavity 2 by 5cm-10cm. .
所述注浆底管4的内径为2.5cm、3.2cm或4.0cm,所述基桩10外部的注浆底管位于地基土6浅层,并由筏板1 的侧面引出至地面。The inner diameter of the grouting bottom pipe 4 is 2.5 cm, 3.2 cm or 4.0 cm. The grouting bottom pipe outside the foundation pile 10 is located in the shallow layer of the foundation soil 6 and led out to the ground from the side of the raft 1 .
Claims (4)
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810330986.7A CN108330958A (en) | 2018-04-13 | 2018-04-13 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
CN201910136744.9A CN109577317A (en) | 2018-04-13 | 2019-02-25 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810330986.7A CN108330958A (en) | 2018-04-13 | 2018-04-13 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108330958A true CN108330958A (en) | 2018-07-27 |
Family
ID=62933149
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810330986.7A Withdrawn CN108330958A (en) | 2018-04-13 | 2018-04-13 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
CN201910136744.9A Withdrawn CN109577317A (en) | 2018-04-13 | 2019-02-25 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
Family Applications After (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910136744.9A Withdrawn CN109577317A (en) | 2018-04-13 | 2019-02-25 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN108330958A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629591A (en) * | 2018-12-05 | 2019-04-16 | 南京工业大学 | Secondary-pouring-free rigidity-controllable pile top structure and construction method thereof |
CN109798121A (en) * | 2019-03-22 | 2019-05-24 | 中建八局轨道交通建设有限公司 | The construction method of existing structure bottom plate is worn under bored tunnel is closely connected |
CN111188262A (en) * | 2019-12-25 | 2020-05-22 | 苏州大学 | A settlement control device, abutment structure, and construction method of the abutment structure |
CN115305939A (en) * | 2022-08-24 | 2022-11-08 | 中冶集团武汉勘察研究院有限公司 | Active pile-raft foundation settlement coordination structure and construction method |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3799036B2 (en) * | 2003-09-26 | 2006-07-19 | 株式会社竹中工務店 | Building basic structure and construction method |
JP2006291641A (en) * | 2005-04-14 | 2006-10-26 | Kajima Corp | Pile foundation structure and construction method |
CN205152971U (en) * | 2015-11-20 | 2016-04-13 | 中建四局第一建筑工程有限公司 | Composite pile foundation pile is offended and disobey with rude remarks and is shaken damping adjustment device |
CN107806099A (en) * | 2017-11-03 | 2018-03-16 | 五邑大学 | A kind of rigid pile composite foundation stake top filling system and its construction method |
CN209703487U (en) * | 2018-04-13 | 2019-11-29 | 常熟理工学院 | A kind of constructing device filled for composite pile foundation stake top cavity envelope |
-
2018
- 2018-04-13 CN CN201810330986.7A patent/CN108330958A/en not_active Withdrawn
-
2019
- 2019-02-25 CN CN201910136744.9A patent/CN109577317A/en not_active Withdrawn
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629591A (en) * | 2018-12-05 | 2019-04-16 | 南京工业大学 | Secondary-pouring-free rigidity-controllable pile top structure and construction method thereof |
CN109798121A (en) * | 2019-03-22 | 2019-05-24 | 中建八局轨道交通建设有限公司 | The construction method of existing structure bottom plate is worn under bored tunnel is closely connected |
CN111188262A (en) * | 2019-12-25 | 2020-05-22 | 苏州大学 | A settlement control device, abutment structure, and construction method of the abutment structure |
CN115305939A (en) * | 2022-08-24 | 2022-11-08 | 中冶集团武汉勘察研究院有限公司 | Active pile-raft foundation settlement coordination structure and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN109577317A (en) | 2019-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108330958A (en) | A kind of constructing device filled for composite pile foundation stake top cavity envelope | |
CN103485334B (en) | Bi-layer plastic-bushing inverted-arch cambered hollow special-shaped pile and construction method | |
CN102605767A (en) | Precast pile reserved with grouting pipe and piling process of precast pile | |
CN107035159A (en) | A kind of method suitable for frame structure isolated footing building underground increasing layer | |
CN116517191B (en) | Mixed reinforcement precast concrete column with spiral stirrup core column and assembly method thereof | |
CN209703487U (en) | A kind of constructing device filled for composite pile foundation stake top cavity envelope | |
CN105220720B (en) | Collapsible Loess District building strengthening of foundation stake and pressing pile construction method thereof | |
CN107700521B (en) | A building foundation reinforcement underpinning pier and its construction method | |
CN103510458B (en) | Pile type continuous rigid frame bridge and construction method thereof | |
CN207659986U (en) | A kind of building or structures foundation stabilization underpin pier | |
CN207597394U (en) | The horizontally-spliced structure of coercion underground continuous wall | |
CN203475289U (en) | Pile type continuous rigid frame bridge | |
CN105649106A (en) | Earth-retaining wall structure with steel tube reinforcing ribs and construction method for earth-retaining wall structure | |
CN204780977U (en) | Reduce steel column burried depth's type of putting more energy into and bury formula column base | |
CN107254872B (en) | Prestressed pipe pile bottom floating and fixing sealing device and control method thereof | |
CN217352519U (en) | Basement anti-floating node based on supporting structure | |
CN111764201A (en) | Subgrade structure of ballastless track resisting uplift in cutting section and its construction and design method | |
CN108425683B (en) | A prefabricated pile foundation conversion tunnel structure and construction method | |
CN217923158U (en) | Corrugated steel box culvert structure | |
CN207047839U (en) | A kind of pile for prestressed pipe stake bottom floating sealing device | |
CN212772306U (en) | Device for improving vertical compression-resistant bearing capacity of steel pipe anchor rod static pressure pile | |
CN115262531A (en) | Forming and designing method for underground continuous wall serving as vibration isolation barrier | |
CN106703023A (en) | Hydraulic hammering type four-wing prefabricated pile and construction method thereof | |
CN207661217U (en) | Underground raw water pipe protection structure | |
CN207143970U (en) | A kind of foundation pit enclosure stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20180727 |