CN108330750A - For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck - Google Patents
For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck Download PDFInfo
- Publication number
- CN108330750A CN108330750A CN201810008423.6A CN201810008423A CN108330750A CN 108330750 A CN108330750 A CN 108330750A CN 201810008423 A CN201810008423 A CN 201810008423A CN 108330750 A CN108330750 A CN 108330750A
- Authority
- CN
- China
- Prior art keywords
- sleeper
- trolley
- battery truck
- track
- shield
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 241001669679 Eleotris Species 0.000 title claims abstract description 198
- 238000010276 construction Methods 0.000 title claims abstract description 37
- 238000009434 installation Methods 0.000 title claims abstract description 19
- 238000000034 method Methods 0.000 title claims abstract description 10
- 208000020442 loss of weight Diseases 0.000 claims description 7
- 238000010586 diagram Methods 0.000 description 7
- 239000002699 waste material Substances 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000000354 decomposition reaction Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B23/00—Easily dismountable or movable tracks, e.g. temporary railways; Details specially adapted therefor
- E01B23/10—Shiftable tracks for heavy loads, e.g. carrying excavators
- E01B23/12—Sleepers
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Arrangement Or Mounting Of Propulsion Units For Vehicles (AREA)
Abstract
The present invention provides the detachable sleeper and its installation method of a kind of trolley for shield-tunneling construction and battery truck, which includes:Battery truck sleeper, is installed on shield duct piece, and battery truck track is equipped on the battery truck sleeper, and the both sides of the battery truck sleeper are respectively formed with multiple jacks;And multistage trolley sleeper, trolley sleeper described in multistage is the first connected successively along the length direction of the battery truck sleeper and is held on the shield duct piece, the both sides of the battery truck sleeper are laid with the trolley sleeper respectively, it is separately installed with trolley track on the trolley sleeper of the both sides of the battery truck sleeper, the trolley sleeper is equipped with more rooted tooth columns close to the side of the battery truck sleeper, and the tooth post is movably inserted in the jack to enable the trolley sleeper be attached to the battery truck sleeper.The present invention solve it is traditional in shield-tunneling construction trolley traveling and battery truck conveying track laying it is time-consuming and laborious, the low problem of utilization ratio.
Description
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of trolley and battery truck for shield-tunneling construction can
Dismantle sleeper and its installation method.
Background technology
Currently, being the rail for imitating railroad track to sleeper used in trolley traveling in shield-tunneling construction and battery truck conveying track
Pillow makes trolley that gauge is different and battery truck share a sleeper and is laid with, but sleeper used in this method is heavier, carries and is laid with
It is time-consuming and laborious, and the follow-up mating trolley of shield machine is one-way traffic, the not reproducible utilization of sleeper that early period is laid with causes resource
Waste.
Invention content
To overcome the defects of present in the prior art, the removable of a kind of trolley for shield-tunneling construction and battery truck is now provided
Sleeper and its installation method are unloaded, it is time-consuming to solve traditional laying to trolley traveling and battery truck conveying track in shield-tunneling construction
Arduously, the low problem of utilization ratio.
To achieve the above object, a kind of detachable sleeper of the trolley for shield-tunneling construction and battery truck is provided, including:
Battery truck sleeper, is installed on shield duct piece, and battery truck track, the storage battery are equipped on the battery truck sleeper
The both sides of track pillow are respectively formed with multiple jacks;And
Multistage trolley sleeper, trolley sleeper described in multistage along the battery truck sleeper length direction successively it is the first be connected and
It is held on the shield duct piece, the both sides of the battery truck sleeper are laid with the trolley sleeper, the storage battery track respectively
Trolley track is separately installed on the trolley sleeper of the both sides of pillow, the close battery truck sleeper of the trolley sleeper
Side is equipped with more rooted tooth columns, and the tooth post is movably inserted in the jack described to enable the trolley sleeper be attached to
Battery truck sleeper.
Further, the more tooth posts are installed on the close battery truck sleeper of the trolley sleeper by loss of weight frame
Side, the loss of weight frame includes:
Mounting plate, the more tooth posts are connected to the first side of the mounting plate;And
Connecting plate is connected to the one of the second side of the mounting plate and the close battery truck sleeper of the trolley sleeper
Between side.
Further, the trolley sleeper includes:
First cushion cap is held on the both sides on the shield duct piece and positioned at the battery truck sleeper, the trolley track
It is held on first cushion cap, the connecting plate is connected to first cushion cap;
First briquetting is installed on first cushion cap and is pressed against the inside of the trolley track;And
First spring is installed on first cushion cap and is pressed against the outside of the trolley track.
Further, the bottom of first cushion cap is arc-shaped, and the radian of first cushion cap and the shield duct piece
Radian be adapted.
Further, first briquetting includes being connected to the first connecting portion of first cushion cap and being connected to described the
First pressure section of one interconnecting piece, first pressure section are pressed down against in the outside of the trolley track.
Further, first spring is installed on by the first spring pressing plate on first cushion cap.
Further, the battery truck sleeper includes:
Second cushion cap is connected to the inside on the shield duct piece and positioned at the trolley sleeper, the battery truck track
It is held on second cushion cap, the jack is formed on the outside of second cushion cap;
Second briquetting is installed on second cushion cap and is pressed against the inside of the battery truck track;And
Second spring is installed on second cushion cap and is pressed against the outside of the battery truck track.
Further, the stage body that second cushion cap includes curved plate and shelves for the battery truck track, described
Body is set up on the curved plate.
The present invention provides the installation methods of a kind of trolley for shield-tunneling construction and the detachable sleeper of battery truck, including
Following steps:
In installation battery truck sleeper on shield duct piece;
In installation battery truck track on the battery truck sleeper;
Multistage trolley sleeper is shelved respectively in the both sides of the battery truck sleeper so that trolley sleeper described in multistage is described in
The length direction of battery truck sleeper is arranged and joins end to end;
The tooth post of trolley sleeper described in multistage is inserted in the jack of the battery truck sleeper so that trolley described in multistage
Sleeper is attached to the battery truck sleeper;
Trolley track is installed on the trolley sleeper described in multistage;
It is run to trolley sleeper described in second segment via the trolley track on trolley sleeper described in first segment in trolley
On the trolley track after, the tooth post of trolley sleeper described in first segment is extracted in the jack of the battery truck sleeper and will
Trolley sleeper described in first segment is operated to the rear of trolley sleeper described in final stage so that trolley sleeper described in first segment with most
The latter section of trolley sleeper joins end to end and is attached to the battery truck sleeper.
The beneficial effects of the present invention are the present invention passes through for the trolley of shield-tunneling construction and the detachable sleeper of battery truck
Trolley sleeper is removably disposed on battery truck sleeper, to avoid largely being laid with trolley sleeper, to cause goods and materials to waste.
The trolley sleeper of laying can be passed through in trolley and be disassembled later, continued to be laid with for trolley traveling for rear, be laid with every time
Trolley sleeper only needs a small amount of manpower that the installation of trolley sleeper can be completed.
Description of the drawings
Fig. 1 is schematic diagram of the present invention for the trolley of shield-tunneling construction and the detachable sleeper of battery truck.
Fig. 2 is decomposition diagram of the present invention for the trolley of shield-tunneling construction and the detachable sleeper of battery truck.
Fig. 3 is schematic diagram of the present invention for the trolley of shield-tunneling construction and the mounting plate of the detachable sleeper of battery truck.
Fig. 4 to Fig. 7 is the present invention showing for the installation procedure of the trolley of shield-tunneling construction and the detachable sleeper of battery truck
It is intended to.
Specific implementation mode
Illustrate that embodiments of the present invention, those skilled in the art can be by this specification below by way of specific specific example
Disclosed content understands other advantages and effect of the present invention easily.The present invention can also pass through in addition different specific realities
The mode of applying is embodied or practiced, the various details in this specification can also be based on different viewpoints with application, without departing from
Various modifications or alterations are carried out under the spirit of the present invention.
Fig. 1 is that schematic diagram, Fig. 2 of the detachable sleeper of the trolley and battery truck of the invention for shield-tunneling construction are the present invention
Decomposition diagram, Fig. 3 of the detachable sleeper of trolley and battery truck for shield-tunneling construction are the present invention for shield-tunneling construction
The schematic diagram of the mounting plate of trolley and the detachable sleeper of battery truck, Fig. 4 to Fig. 7 be the present invention for the trolley of shield-tunneling construction and
The schematic diagram of the installation procedure of the detachable sleeper of battery truck.
Shown in referring to Figure 1 to Figure 7, the present invention provides the detachable rails of a kind of trolley for shield-tunneling construction and battery truck
Pillow, including:Battery truck sleeper 1 and trolley sleeper 2.
Battery truck sleeper 1 is installed in shield duct piece (not shown).Battery truck track is installed on battery truck sleeper 1
3.The both sides of battery truck sleeper 1 are respectively formed with multiple jacks.Battery truck sleeper 1 is located at the bottom in tunnel, is located at shield duct piece
Arc bottom position.
The quantity of trolley sleeper 2 is multistage.Length direction successively the first phase of the multistage trolley sleeper 2 along battery truck sleeper 1
Even, and multistage trolley sleeper 2 is held on shield duct piece.The both sides of battery truck sleeper 1 are laid with trolley sleeper 2 respectively.Storage battery
It is separately installed with trolley track 4 on the trolley sleeper 2 of the both sides of track pillow 1.The one of the close battery truck sleeper 1 of trolley sleeper 2
Side is equipped with more rooted tooth columns 25.Tooth post 25 is movably inserted in jack to enable trolley sleeper 2 be attached to battery truck sleeper 1
On.The size of the outer diameter of tooth post 25 is adapted with the size in the aperture of jack, is inserted in jack by tooth post 25 to enable trolley
Sleeper 2 is attached on battery truck sleeper 1.
In the present embodiment, battery truck sleeper 1 is welded to connect on shield duct piece.
The present invention passes through detachable on battery truck sleeper for the trolley of shield-tunneling construction and the detachable sleeper of battery truck
Ground is arranged trolley rail and rests the head on, to avoid largely being laid with trolley sleeper, to cause goods and materials to waste.The trolley sleeper of laying can be
Trolley warp disassembles later, continues to be laid with for trolley traveling for rear, and being laid with trolley sleeper every time only needs a small amount of people
The installation of trolley sleeper can be completed in power.
Battery truck sleeper 1 includes the second cushion cap 11, the second briquetting 12 and the second spring 13.
Second cushion cap 11 is connected to the inside on shield duct piece and positioned at trolley sleeper 2.Battery truck track 3 is held on second
The top of cushion cap 11.The outside of second cushion cap 11 is formed with the jack plugged for tooth post 25.Second briquetting 12 is installed on second and holds
On platform 11 and it is pressed against the inside of battery truck track 3.Second spring 13 is installed on the second cushion cap 11 and is pressed against storage battery track
The outside in road 3.
Battery truck track 3 is limited by the second briquetting 12 and the second spring 13, prevents battery truck track 3 from laterally moving
It moves and vertically moves.
As a kind of preferable embodiment, the second spring 13 is installed on the second cushion cap 11 by the second spring pressing plate 14
On.The first end of second spring pressing plate 14 is arc section, and the second end of the second spring pressing plate 14 is straightway.Second spring pressing plate
The surface of 14 straightway fits in the top of the second cushion cap 11, the top of the arc section of the second spring pressing plate 14 and the second cushion cap 11
Portion's straight line forms the second mounting hole.Second spring 13 includes the second positioning section being inserted in the second mounting hole, is connected to second
Second linkage section of positioning section and the second cantilever segment for being connected to the second linkage section.Second cantilever segment is pressed against battery truck track 3
Outside.
Second spring 13 is railway elastic bar.Second spring 13 can be I type spring, II type spring, III type spring it is arbitrary
It is a kind of.
Second briquetting 12 includes being connected to the second connecting portion of the second cushion cap 1111 and being connected to the second connecting portion
Second pressure section, second pressure section are pressed down against in the inside of battery truck track 3.
As a kind of preferable embodiment, the second briquetting 12 is in inverted L-shaped.
As a kind of preferable embodiment, the second cushion cap 11 includes the curved plate 112 being welded to connect in shield duct piece
With the stage body 111 shelved for storage battery track road 3.Stage body 111 is set up on curved plate 112.The quantity of stage body 111 is two,
A battery truck track 3 is shelved on two stage bodies 111 respectively.The radian of curved plate 112 is adapted with the radian of shield duct piece.
Stage body 111 includes the second side plate of the inside that branch is set to curved plate 112 and the second top plate for being connected to side plate.The
Two side plates have four pieces, four piece of second rectangular arrangement of side plate.Second top plate is connected to the top of the second side plate.
Trolley sleeper 2 includes:First cushion cap 21, the first briquetting 22 and the first spring 23.First cushion cap 21 is installed on shield
Both sides on section of jurisdiction and positioned at battery truck sleeper 1.Trolley track 4 is held on the first cushion cap 21.Connecting plate 262 is connected to first
Cushion cap 21.First briquetting 22 is installed on the first cushion cap 21 and is pressed against the inside of trolley track 4.First spring 23 is installed on
On one cushion cap 21 and it is pressed against the outside of trolley track 4.
First cushion cap 21 includes the first curved plate, the first side plate and the first top plate.First side plate branch is set to the first arc
On bottom plate.First top plate is horizontally disposed.First side of the first top plate is connected to the first curved plate, and the of the first top plate
Two sides are connected to the top of the first side plate.The bottom of mounting plate 261 and interconnecting piece 262 is connected to the first curved plate.
The radian of the first curved plate of first cushion cap 21 is adapted with the radian of shield duct piece.
First briquetting 22 includes the first connecting portion for being connected to the first cushion cap 21 and be connected to the first connecting portion the
One pressure section, first pressure section are pressed down against in the inside of the trolley track 4.
As a kind of preferable embodiment, the first briquetting 22 is in inverted L-shaped.
As a kind of preferable embodiment, the first spring 23 is installed on the first cushion cap 21 by the first spring pressing plate 24
On.
The first end of first spring pressing plate 24 is arc section, and the second end of the first spring pressing plate 24 is straightway.First bullet
The surface of the straightway of pressing plate 24 fits in the top of the first cushion cap 21, the arc section and the first cushion cap of the first spring pressing plate 24
21 linear top forms the first mounting hole.
First spring 23 includes the first positioning section being inserted in the first mounting hole, is connected to the first company of the first positioning section
Connect section and the first cantilever segment for being connected to the first linkage section.First cantilever segment is pressed against the outside in trolley track road 4.
First spring 23 is railway elastic bar.First spring 23 can be I type spring, II type spring, III type spring it is arbitrary
It is a kind of.
As a kind of preferable embodiment, more rooted tooth columns 25 are installed on the close electricity of the first cushion cap 21 by loss of weight frame 26
The outside of first side plate of bottle track pillow 1.
Specifically, loss of weight frame 26 includes mounting plate 261 and connecting plate 262.More rooted tooth columns 25 are connected to the of mounting plate 261
Side.Connecting plate 262 is connected to the first side plate of the second side of mounting plate 261 and the close battery truck sleeper 1 of the first cushion cap 21
Outside.
By the way that in loss of weight frame 26 is arranged on trolley sleeper 2, the scale of construction of trolley sleeper 2 (the first cushion cap) can be as small as possible,
To facilitate construction personnel to dismantle and carry.
Fig. 4 to Fig. 7 is showing for the construction method that the present invention is used for the trolley of shield-tunneling construction and the detachable sleeper of battery truck
It is intended to.Vertical view of the present invention for the trolley of shield-tunneling construction and the Construction State of the detachable sleeper of battery truck is shown as in figure
Figure.
In conjunction with shown in Fig. 4 to Fig. 7, the above-mentioned trolley and battery truck for shield-tunneling construction is utilized the present invention provides a kind of
Detachable sleeper installation method, include the following steps:
S1:In installation battery truck sleeper 1 on shield duct piece.
It is welded to connect battery truck sleeper 1 in the arc bottom position of shield duct piece.
S2:In installation battery truck track 3 on battery truck sleeper 1.
S3:Multistage trolley sleeper 2 is respectively set in the both sides of battery truck sleeper 1 so that multistage trolley sleeper 2 is along battery truck
The length direction of sleeper 1 is arranged and joins end to end.
As shown in figure 4, in the present embodiment, the quantity of trolley sleeper 2 is six sections, and the both sides of battery truck sleeper 1 are pacified respectively
Equipped with three sections of trolley sleepers 2.Three sections of trolley sleepers 2 are installed and are joined end to end successively in every side of battery truck sleeper 1.
S4:The tooth post 25 of multistage trolley sleeper 2 is inserted in the jack of battery truck sleeper 1 so that multistage trolley sleeper 2
It is attached to battery truck sleeper 1.
S5:In installation trolley track 4 on multistage trolley sleeper 2.
S6:In trolley 5 via the operation of trolley track 4 on first segment trolley sleeper 2 to the platform on second segment trolley sleeper 2
Behind track road 4, the tooth post of first segment trolley sleeper 2 is extracted in the jack of battery truck sleeper 1 and by first segment trolley sleeper 2
It operates to the rear of final stage trolley sleeper 2 so that first segment trolley sleeper 2 joins end to end with final stage trolley sleeper 2
And it is attached to battery truck sleeper 1.
As shown in figure 5, trolley 5 travels on the trolley track 4 on first segment trolley sleeper 2.
As shown in fig. 6, trolley 5 is via the operation of trolley track 4 on first segment trolley sleeper 2 to second segment trolley sleeper 2
On trolley track 4.
As shown in fig. 7, in trolley 5 via the operation of trolley track 4 on first segment trolley sleeper 2 to second segment trolley sleeper
After trolley track 4 on 2, the tooth post of first segment trolley sleeper 2 is extracted in the jack of battery truck sleeper 1 and by first segment platform
Track pillow 2 is operated to the rear of original third section trolley sleeper 2 so that first segment trolley sleeper 2 and original third section platform
Track pillow 2 joins end to end and is attached to battery truck sleeper 1.
It so repeats, so that only needing six sections of trolley sleepers 2 and trolley track 4 in the driving process of stage body 5
Realize that trolley 5 is moved along the length direction of battery truck sleeper 1, avoiding traditional trolley sleeper and track need to largely be laid with and make
At the waste of the various resources such as goods and materials, manpower.
It should be noted that structure, ratio, size etc. depicted in this specification institute accompanying drawings, only coordinating
The bright revealed content of book is not limited to the enforceable limit of the present invention so that those skilled in the art understands and reads
Fixed condition, therefore do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size, not
It influences under the effect of present invention can be generated and the purpose that can reach, should all still fall and be obtained in disclosed technology contents
In the range of capable of covering.Meanwhile it is cited such as "upper", "lower", "left", "right", " centre " and " one " in this specification
Term is merely convenient to being illustrated for narration, rather than to limit the scope of the invention, the change of relativeness or tune
It is whole, in the case where changing technology contents without essence, when being also considered as the enforceable scope of the present invention.
The present invention has been described in detail with reference to the accompanying drawings, those skilled in the art can be according to upper
It states and bright many variations example is made to the present invention.Thus, certain details in embodiment should not constitute limitation of the invention, this
Invention will be using the range that the appended claims define as protection domain.
Claims (9)
1. a kind of for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that including:
Battery truck sleeper, is installed on shield duct piece, and battery truck track, the storage battery track are equipped on the battery truck sleeper
The both sides of pillow are respectively formed with multiple jacks;And
Multistage trolley sleeper, trolley sleeper described in multistage the first be successively connected and shelve along the length direction of the battery truck sleeper
In on the shield duct piece, the both sides of the battery truck sleeper are laid with the trolley sleeper respectively, the battery truck sleeper
Trolley track, the side of the close battery truck sleeper of the trolley sleeper are separately installed on the trolley sleeper of both sides
More rooted tooth columns are installed, the tooth post is movably inserted in the jack to enable the trolley sleeper be attached to the storage battery
Track is rested the head on.
2. according to claim 1 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that more
Tooth post described in root is installed on the side of the close battery truck sleeper of the trolley sleeper, the loss of weight frame packet by loss of weight frame
It includes:
Mounting plate, the more tooth posts are connected to the first side of the mounting plate;And
Connecting plate, be connected to the mounting plate the second side and the trolley sleeper close to the battery truck sleeper side it
Between.
3. according to claim 2 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
Stating trolley sleeper includes:
First cushion cap, is held on the both sides on the shield duct piece and positioned at the battery truck sleeper, and the trolley track is shelved
In on first cushion cap, the connecting plate is connected to first cushion cap;
First briquetting is installed on first cushion cap and is pressed against the inside of the trolley track;And
First spring is installed on first cushion cap and is pressed against the outside of the trolley track.
4. according to claim 3 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
The bottom for stating the first cushion cap is arc-shaped, and the radian of first cushion cap is adapted with the radian of the shield duct piece.
5. according to claim 3 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
It includes being connected to the first connecting portion of first cushion cap and being connected to the first of the first connecting portion to compress to state the first briquetting
Portion, first pressure section are pressed down against in the outside of the trolley track.
6. according to claim 3 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
The first spring is stated to be installed on first cushion cap by the first spring pressing plate.
7. according to claim 1 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
Stating battery truck sleeper includes:
Second cushion cap, is connected to the inside on the shield duct piece and positioned at the trolley sleeper, and the battery truck track is shelved
In on second cushion cap, the jack is formed on the outside of second cushion cap;
Second briquetting is installed on second cushion cap and is pressed against the inside of the battery truck track;And
Second spring is installed on second cushion cap and is pressed against the outside of the battery truck track.
8. according to claim 7 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck, which is characterized in that institute
It includes the stage body that curved plate and the confession battery truck track are shelved to state the second cushion cap, and the stage body is set up in the curved plate
On.
9. a kind of such as any one of claim 1~8 for the trolley of shield-tunneling construction and the detachable sleeper of battery truck
Installation method, which is characterized in that include the following steps:
In installation battery truck sleeper on shield duct piece;
In installation battery truck track on the battery truck sleeper;
Multistage trolley sleeper is shelved respectively in the both sides of the battery truck sleeper so that trolley sleeper is along the storage battery described in multistage
The length direction of track pillow is arranged and joins end to end;
The tooth post of trolley sleeper described in multistage is inserted in the jack of the battery truck sleeper so that trolley sleeper described in multistage
It is attached to the battery truck sleeper;
Trolley track is installed on the trolley sleeper described in multistage;
It is run to trolley sleeper described in second segment via the trolley track on trolley sleeper described in first segment in trolley
After the trolley track, the tooth post of trolley sleeper described in first segment is extracted in the jack of the battery truck sleeper and by first
Duan Suoshu trolley sleepers are operated to the rear of trolley sleeper described in final stage so that trolley sleeper described in first segment and last
Duan Suoshu trolley sleepers join end to end and are attached to the battery truck sleeper.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810008423.6A CN108330750A (en) | 2018-01-04 | 2018-01-04 | For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810008423.6A CN108330750A (en) | 2018-01-04 | 2018-01-04 | For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108330750A true CN108330750A (en) | 2018-07-27 |
Family
ID=62923929
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810008423.6A Pending CN108330750A (en) | 2018-01-04 | 2018-01-04 | For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108330750A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN205012169U (en) * | 2015-09-30 | 2016-02-03 | 龚金京 | Light novel shield constructs simple and easy sleeper of follow -up supporting dull and stereotyped transportation storage battery car of machine |
CN205676737U (en) * | 2016-05-27 | 2016-11-09 | 中国电建集团铁路建设有限公司 | A kind of shield-tunneling construction train sleeper |
CN106120488A (en) * | 2016-08-16 | 2016-11-16 | 中国建筑第五工程局有限公司 | Electromobile sleeper for shield-tunneling construction |
CN206015442U (en) * | 2015-07-30 | 2017-03-15 | 中国建筑第六工程局有限公司 | A kind of removable compound shield-tunneling construction sleeper |
CN207775633U (en) * | 2018-01-04 | 2018-08-28 | 中国建筑第八工程局有限公司 | Trolley and battery truck for shield-tunneling construction have enough to meet the need sleeper |
-
2018
- 2018-01-04 CN CN201810008423.6A patent/CN108330750A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN206015442U (en) * | 2015-07-30 | 2017-03-15 | 中国建筑第六工程局有限公司 | A kind of removable compound shield-tunneling construction sleeper |
CN205012169U (en) * | 2015-09-30 | 2016-02-03 | 龚金京 | Light novel shield constructs simple and easy sleeper of follow -up supporting dull and stereotyped transportation storage battery car of machine |
CN205676737U (en) * | 2016-05-27 | 2016-11-09 | 中国电建集团铁路建设有限公司 | A kind of shield-tunneling construction train sleeper |
CN106120488A (en) * | 2016-08-16 | 2016-11-16 | 中国建筑第五工程局有限公司 | Electromobile sleeper for shield-tunneling construction |
CN207775633U (en) * | 2018-01-04 | 2018-08-28 | 中国建筑第八工程局有限公司 | Trolley and battery truck for shield-tunneling construction have enough to meet the need sleeper |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202466321U (en) | Cross rail connecting device | |
CN201390546Y (en) | Slide for cage cart handling | |
CN207775633U (en) | Trolley and battery truck for shield-tunneling construction have enough to meet the need sleeper | |
WO2017020815A1 (en) | Arrangement structure of stacker device | |
CN108330750A (en) | For the trolley of shield-tunneling construction and the detachable sleeper and its installation method of battery truck | |
CN206606695U (en) | EMUs seat repair assembly line frock | |
CN205932062U (en) | Industry fortune brick machine of flexible function in area | |
CN206047418U (en) | For the welder of photovoltaic module | |
CN206568964U (en) | A kind of New Type Bin grid hood cloth holder | |
CN103216092B (en) | Construction material handling method and equipment thereof | |
CN206628808U (en) | A kind of adjustable support of screw rod transmission | |
CN106018081A (en) | Floor loading device | |
CN205663264U (en) | Mechanical type stereo garage car guide structure | |
CN205602599U (en) | Frock floor truck | |
CN206319214U (en) | A kind of self-action point pillow assembly platform | |
CN202466322U (en) | Movable cross rail connecting device | |
CN104289640B (en) | The Automatic-clamping bar reinforced bar device of conveying bar reinforcing bar equipment | |
CN207390856U (en) | A kind of road and bridge construction instrument quick-lift attachreactor | |
CN208344217U (en) | A kind of Elements of Space Grid Truss fortune beam trolley | |
CN202897514U (en) | Flask drop down machine system | |
CN206288048U (en) | It is a kind of for producing the plastic-spraying of distribution box hanger transfer car(buggy) | |
CN207844686U (en) | A kind of pay off rack that railroad track uses | |
CN202192685U (en) | Pre-binding clamping fixture for U-shaped beam reinforcement cages | |
CN201600271U (en) | Structure of sampling vehicle | |
CN208039754U (en) | A kind of system of plastering a wall can be used for outdoor work |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |