CN108316950A - Tunnel vault concrete belt mould backfills filling system and its grouting method - Google Patents

Tunnel vault concrete belt mould backfills filling system and its grouting method Download PDF

Info

Publication number
CN108316950A
CN108316950A CN201810221721.3A CN201810221721A CN108316950A CN 108316950 A CN108316950 A CN 108316950A CN 201810221721 A CN201810221721 A CN 201810221721A CN 108316950 A CN108316950 A CN 108316950A
Authority
CN
China
Prior art keywords
backfill
grouting
pipe
backfill grouting
secondary lining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810221721.3A
Other languages
Chinese (zh)
Inventor
赵立财
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201810221721.3A priority Critical patent/CN108316950A/en
Publication of CN108316950A publication Critical patent/CN108316950A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

The invention discloses a kind of tunnel vault concrete belt mould backfill filling system and its grouting method, solve that equipment investment existing for existing backfill grouting mode is more, and long in time limit and region of coming to nothing backfills the uncompacted problem of slip casting.In secondary lining trolley(6)Vault on be provided with backfill grouting port(7), backfill Grouting Pipe(1)End pass through ring flange(8)After be inserted into backfill grouting port in, the port for backfilling Grouting Pipe is waterproof layer of the topstick in once lining(5)On, in cross slip casting groove(3)Outside be wound with raw material band(2), raw material band is pasted on the nozzle of backfill Grouting Pipe;It is provided with pressure sensor in the lower end nozzle of backfill Grouting Pipe(13), branch sleeve is connected on the lower end nozzle of backfill Grouting Pipe(16), feed pipe for mortar is connected in the lower end of branch sleeve(18)And grouting pump, backfill grouting serous fluid is provided in grouting pump.Realize the defect for farthest eliminating secondary lining vault cavity.

Description

Tunnel vault concrete belt mould backfills filling system and its grouting method
Technical field
The present invention relates to a kind of Tunnel Second Lining concrete backfill filling system, more particularly to a kind of secondary lining coagulation The filling system and its grouting method that soil perfusion and backfill slip casting are disposably completed.
Background technology
In constructing tunnel, after country rock excavates, supporting steel frame is installed on section country rock interface first, then sprays coagulation Soil forms once lining, and splash guard is carried out after once lining reaches normal intensity and is applied, after splash guard applies completion, by two Secondary lining trolley is opened into place.In the vault of secondary lining trolley, it is typically provided with filling concrete mouth and backfill grouting port, is mixed Solidifying soil perfusing hole is typically provided with 2, is separately positioned on the front-end and back-end of trolley vault.After secondary lining trolley is in place, first Carry out trolley Side Template closure, secondary lining trolley and once lining, which are formed by arcuate gap, to be closed, then, in Filling concrete pipe is connected on the filling concrete mouth of low level, and the concrete of secondary lining is perfused by filling concrete pipe, In filling process, by the way of manually observing, the perfusion situation of concrete in the gap of arch is estimated, when arcuate gap perfusion is full Afterwards, the perfusion for stopping concrete removing secondary lining trolley formwork, by trolley after the secondary lining concrete final set being perfused Move to next plate Second Lining Construction position.Since filling concrete is the totally-enclosed arcuate gap on the outside of secondary lining vault Middle progress, since filling concrete applies from high to lower, the concrete ratio at secondary lining trolley abutment wall position It is more closely knit, but formation cavity is easy above secondary lining trolley vault, that is, phenomenon of coming to nothing, the prior art is to pass through geological radar To coming to nothing what region was detected, to the cavity in the secondary lining concrete that detects, disappeared by way of backfilling slip casting Except region of coming to nothing, specific way is:Rack is set up below region of coming to nothing, the secondary grouting by the rack in region of coming to nothing serves as a contrast Injected hole is set on block, grouting equipment is connected on the injected hole, region carries out backfill injecting treatment to coming to nothing, in slip casting process Middle observation grouting equipment pressure change, stops slip casting when grouting pressure reaches 0.5MPa, and observes under pressure gauge indicates whether Drop, if in 10 minutes pressure gauge instruction have no drop to 0.4MPa hereinafter, if can terminate slip casting;If drop to 0.4MPa with Under, then continue slip casting.This backfill injecting treatment method there are equipment investments more, long in time limit defect;In addition, existing backfill note It starches using single slurry or dual slurry, single slurry slip casting match ratio is:Cement is 1 with water:1, dual slurry slip casting match ratio is:Cement Than waterglass it is 1 than water:1:0.75, both match ratios are big in the presence of solidification after-contraction, and setting rate is fast, is easy to cause note The slurry contraction solidified after slurry causes secondary gap.
Invention content
The present invention provides a kind of tunnel vault concrete belt mould backfill filling system and its grouting methods, solve existing It is more to backfill equipment investment existing for grouting mode, the long in time limit and region backfill uncompacted technical problem of slip casting of coming to nothing.
The present invention is to solve the above technical problem by the following technical programs:
A kind of tunnel vault concrete belt mould backfill filling system, including once lining, are provided with waterproof layer in once lining, It is provided with secondary lining trolley immediately below once lining, two are perfused between the vault and waterproof layer of secondary lining trolley Secondary lining concrete, the secondary lining concrete above the vault of secondary lining trolley and is provided with cavity between waterproof layer, It is provided with backfill grouting port on the vault of secondary lining trolley, is provided with ring flange on backfill grouting port, backfills Grouting Pipe End by be inserted into after ring flange backfill grouting port in, the port for backfilling Grouting Pipe is waterproof layer of the topstick in once lining On, there is cross slip casting groove in the end set of backfill Grouting Pipe, raw material are wound on the outside of cross slip casting groove Band is pasted with raw material band in backfill Grouting Pipe nozzle;It is provided with pressure sensor, pressure in the lower end nozzle of backfill Grouting Pipe Sensor is linked together by transmission line and pressure display instrument table, and connector sleeve is connected on the lower end nozzle of backfill Grouting Pipe Cylinder, feed pipe for mortar is connected in branch sleeve lower end, is provided with into slurry control valve in branch sleeve, feed pipe for mortar is connected to grouting pump Together, backfill grouting serous fluid is provided in grouting pump.
The backfill grouting serous fluid that grouting serous fluid is the early strong retardation setting type of microdilatancy is backfilled, proportioning is:Cement:Water:Bentonite: Retarder=1:1:0.25:0.25.
A kind of tunnel vault concrete belt mould backfill grouting construction method, includes the following steps:
The first step makes backfill Grouting Pipe, and in the end set cross slip casting groove of backfill Grouting Pipe, is used in combination raw material band will The cross slip casting groove and backfill Grouting Pipe nozzle of setting paste;
Second step, after once lining reaches normal intensity and completes waterproof layer and applies, by secondary lining trolley navigate to this one Immediately below secondary lining cutting, ring flange is installed on the backfill grouting port being arranged on the vault of secondary lining trolley, the first step is manufactured The end of good backfill Grouting Pipe is inserted by ring flange in backfill grouting port, and makes backfill slip casting pipe port topstick primary On the waterproof layer of lining cutting, and it is fixed on ring flange by flange bolt by Grouting Pipe is backfilled;
Third step connects concrete grouting pipe on the filling concrete mouth of the vault low side of secondary lining trolley, carries out secondary Lining concrete is perfused;
4th step, the early strong retardation setting type of configuration microdilatancy backfill grouting serous fluid, and the early strong retardation setting type grouting serous fluid match ratio of microdilatancy is: Cement:Water:Bentonite:Retarder=1:1:0.25:0.25;
5th step, after secondary lining concrete final set, by backfilling the Grouting Pipe backfill grouting serous fluid that has configured the 4th step It is injected into the cavity between waterproof layer and secondary lining trolley exterior sheathing;
6th step, in backfilling grouting serous fluid injection process, compartment of terrain is collected overflows in the end die slot gap of secondary lining trolley Grouting serous fluid is backfilled, the concentration for the backfill grouting serous fluid that the concentration of the backfill grouting serous fluid of spilling and the 4th step have configured is carried out Comparison, when the concentration of the backfill grouting serous fluid of spilling is identical as the backfill concentration of grouting serous fluid that the 4th step has configured, eventually Non-return fills out the slip casting of grouting serous fluid.
By in the lower end nozzle of pressure sensor setting to backfill Grouting Pipe, and by the transmission line and pressure of pressure sensor Display instrument links together, and branch sleeve is connected on the lower end nozzle of backfill Grouting Pipe, is connected in branch sleeve lower end There is feed pipe for mortar, is provided with into slurry control valve in branch sleeve, pressure display instrument table is observed during injection backfills injection slurry Upper shown grouting pressure value makes the grouting pressure value of the nozzle of backfill Grouting Pipe 1 be less than 1.0MPa, if grouting pressure is more than When 1.0MPa, slip casting pump pressure is adjusted, the nozzle pressure of backfill Grouting Pipe 1 is made to be maintained at 1.0MPa hereinafter, being filled in prevent non-return There is feed pipe for mortar explosion during slurry.
The present invention synchronously completes secondary lining filling concrete and backfill grouting with plunger, by secondary lining trolley top Portion opens up backfill grouting port, the grouting serous fluid with the early strong retardation setting type of mould high pressure injection microdilatancy, the early strong retardation setting type slip casting of microdilatancy Slurries have good mobility and aid pumpability, and bleeding is not shunk, and intensity is high after condensation, when having longer construct Between, excellent self-leveling energy;It is good with concrete bonding performance, while the reaction of high-performance injecting paste material hydration heat is uniform, it is non- Often be conducive to lining concrete and administer vault cavity, ensures the thickness of Tunnel Second Lining.The present invention is by optimizing backfill note The device of slurry, grouting construction process, the early strong retardation setting type grouting serous fluid of microdilatancy, realize and farthest eliminate secondary lining arch The defect in head space hole;Microdilatancy early-strength retardation setting type is implemented using higher grouting pressure using the support of secondary lining trolley Grouting serous fluid, backfill slip casting are closely knit, reliable.
Description of the drawings
Fig. 1 is the structural schematic diagram for implementing the present invention;
Fig. 2 is the attachment structure schematic diagram of the backfill Grouting Pipe of the present invention.
Specific implementation mode
The present invention is described in detail below in conjunction with the accompanying drawings:
A kind of tunnel vault concrete belt mould backfill filling system, including once lining 4, waterproof is provided in once lining 4 Layer 5, is provided with secondary lining trolley 6, between the vault and waterproof layer 5 of secondary lining trolley 6 in the underface of once lining 4 It is perfused with secondary lining concrete 9, between the secondary lining concrete 9 above the vault of secondary lining trolley 6 and waterproof layer 5 It is provided with cavity 11, backfill grouting port 7 is provided on the vault of secondary lining trolley 6, method is provided on backfill grouting port 7 Blue disk 8, the end for backfilling Grouting Pipe 1 are inserted by ring flange 8 in backfill grouting port 7, and the port of backfill Grouting Pipe 1 is topstick On the waterproof layer 5 of once lining, there is cross slip casting groove 3 in the end set of backfill Grouting Pipe 1, in cross slip casting The outside of groove 3 is wound with raw material band 2, it is pasted with raw material band 2 in backfill 1 nozzle of Grouting Pipe;In the lower end of backfill Grouting Pipe 1 Pressure sensor 13 is provided in nozzle, pressure sensor 13 is linked together by transmission line 14 and pressure display instrument table 15, It is connected with branch sleeve 16 on the lower end nozzle of backfill Grouting Pipe 1, feed pipe for mortar 18 is connected in 16 lower end of branch sleeve, even Female connector cylinder 16 is provided with into slurry control valve 17, and feed pipe for mortar 18 links together with grouting pump, and backfill note is provided in grouting pump Starch slurries.
The backfill grouting serous fluid that grouting serous fluid is the early strong retardation setting type of microdilatancy is backfilled, proportioning is:Cement:Water:Bentonite: Retarder=1:1:0.25:0.25.
A kind of tunnel vault concrete belt mould backfill grouting construction method, includes the following steps:
The first step makes backfill Grouting Pipe 1, and in the end set cross slip casting groove 3 of backfill Grouting Pipe 1, raw material is used in combination The cross slip casting groove 3 of setting and backfill 1 nozzle of Grouting Pipe are pasted with 2;
Second step, after once lining 4 reaches normal intensity and completes waterproof layer 5 and applies, secondary lining trolley 6 is navigated to this Immediately below once lining 4, ring flange 8 is installed on the backfill grouting port 7 being arranged on the vault of lining trolley 4, by first step system The end for the backfill Grouting Pipe 1 made is inserted by ring flange 8 in backfill grouting port 7, and makes 1 port topstick of backfill Grouting Pipe It is fixed on ring flange 8 on the waterproof layer 5 of once lining, and by flange bolt by Grouting Pipe 1 is backfilled;
Third step connects concrete grouting pipe on the filling concrete mouth of the vault low side of secondary lining trolley 6, carries out secondary Lining concrete is perfused;
4th step, the match ratio of the early strong retardation setting type backfill grouting serous fluid of microdilatancy are:Cement:Water:Bentonite:Retarder=1:1: 0.25:0.25;
5th step, after secondary lining 9 final set of concrete, backfill microdilatancy morning for having been configured the 4th step by backfilling Grouting Pipe Strong type slow setting slurries are injected into the cavity 11 between waterproof layer 5 and secondary lining trolley exterior sheathing 10;
6th step, in backfilling grouting serous fluid injection process, compartment of terrain is collected overflows in the end die slot gap 12 of secondary lining trolley 6 Backfill grouting serous fluid, the concentration for backfilling grouting serous fluid that the concentration of the backfill grouting serous fluid of spilling and the 4th step have been configured into Row comparison, when the concentration of the backfill grouting serous fluid of spilling is identical as the backfill concentration of grouting serous fluid that the 4th step has configured, Terminate the slip casting of backfill grouting serous fluid.
By in the lower end nozzle of the setting of pressure sensor 13 to backfill Grouting Pipe 1, and by the transmission line of pressure sensor 14 It links together with pressure display instrument table 15, branch sleeve 16 is connected on the lower end nozzle of backfill Grouting Pipe 1, in connector sleeve 16 lower ends of cylinder are connected with feed pipe for mortar 18, are provided with into slurry control valve 17 in branch sleeve 16, in the process of injection backfill injection slurry Shown grouting pressure value, makes the grouting pressure value of the nozzle of backfill Grouting Pipe 1 be less than on middle observation pressure display instrument table 15 1.0MPa adjusts slip casting pump pressure, the nozzle pressure of backfill Grouting Pipe 1 is made to be maintained at if grouting pressure is more than 1.0MPa There is the explosion of feed pipe for mortar 18 in the process hereinafter, filling in slurry to prevent non-return in 1.0MPa.
The present invention waits for lining cutting by the way that backfill Grouting Pipe, optimization backfill slip casting pipe connecting structure are arranged at the top of lining trolley After rushing to summit, using backfill injection slurry of the slip casting all-in-one machine with the early strong retardation setting type of mould high pressure injection microdilatancy, slip casting is improved Tooling and technique, substantially overcome the resistance of the resistance of ducting and slurries vertical transport of low ratio of water to material slurry, and it is anti-to permeate blocking Water plate is damaged, has the function of to repair secondary lining vault cavity and water blockoff;Backfill slip casting is supported to connect using secondary lining trolley Structure implements low ratio of water to material grout material slip casting using higher grouting pressure, and the timely backfill in cavity 11 is made to reach fully closely knit With safe and reliable effect.

Claims (3)

1. a kind of tunnel vault concrete belt mould backfills filling system, including once lining(4), in once lining(4)Upper setting There is waterproof layer(5), in once lining(4)Underface be provided with secondary lining trolley(6), in secondary lining trolley(6)Arch Top and waterproof layer(5)Between be perfused with secondary lining concrete(9), in secondary lining trolley(6)Vault above secondary lining Building concrete(9)With waterproof layer(5)Between be provided with cavity(11), which is characterized in that in secondary lining trolley(6)Vault on It is provided with backfill grouting port(7), in backfill grouting port(7)On be provided with ring flange(8), backfill Grouting Pipe(1)End pass through Ring flange(8)After be inserted into backfill grouting port(7)In, backfill Grouting Pipe(1)Port be waterproof layer of the topstick in once lining (5)On, in backfill Grouting Pipe(1)End set have cross slip casting groove(3), in cross slip casting groove(3)It is outer Side is wound with raw material band(2), in backfill Grouting Pipe(1)Nozzle on be pasted with raw material band(2);In backfill Grouting Pipe(1)Under It is provided with pressure sensor in end pipe mouth(13), pressure sensor(13)Pass through transmission line(14)With pressure display instrument table(15)Even It is connected together, in backfill Grouting Pipe(1)Lower end nozzle on be connected with branch sleeve(16), in branch sleeve(16)Lower end connect It is connected to feed pipe for mortar(18), in branch sleeve(16)On be provided with into slurry control valve(17), feed pipe for mortar(18)It is connected to grouting pump Together, backfill grouting serous fluid is provided in grouting pump.
2. a kind of tunnel vault concrete belt mould according to claim 1 backfills filling system, which is characterized in that backfill note The backfill grouting serous fluid that slurries are the early strong retardation setting type of microdilatancy is starched, proportioning is:Cement:Water:Bentonite:Retarder=1:1: 0.25:0.25.
3. a kind of tunnel vault concrete belt mould backfills grouting construction method, include the following steps:
The first step makes backfill Grouting Pipe(1), and in backfill Grouting Pipe(1)End set cross slip casting groove(3), and Use raw material band(2)By the cross slip casting groove of setting(3)And backfill Grouting Pipe(1)Nozzle paste;
Second step works as once lining(4)Reach normal intensity, and completes waterproof layer(5)After applying, by secondary lining trolley(6) Navigate to the once lining(4)Underface, in secondary lining trolley(6)Vault on the backfill grouting port that is arranged(7)Upper peace Fill ring flange(8), backfill Grouting Pipe that the first step has been manufactured(1)End pass through ring flange(8)It is inserted into backfill grouting port (7)In, and make backfill Grouting Pipe(1)Port topstick once lining waterproof layer(5)On, backfill is noted by flange bolt Slurry pipe(1)It is fixed on ring flange(8)On;
Third walks, in secondary lining trolley(6)Vault low side filling concrete mouth on connect concrete grouting pipe, carry out two Secondary lining concrete perfusion;
The backfill grouting serous fluid of 4th step, the early strong retardation setting type of configuration microdilatancy, the grouting serous fluid cooperation of the early strong retardation setting type of microdilatancy Than for:Cement:Water:Bentonite:Retarder=1:1:0.25:0.25;
5th step, when secondary lining concrete(9)After final set, starched by backfilling the backfill slip casting that Grouting Pipe has configured the 4th step Liquid is injected into waterproof layer(5)With secondary lining trolley exterior sheathing(10)Between cavity(11)In;
6th step, in backfilling grouting serous fluid injection process, compartment of terrain collect secondary lining trolley(6)End die slot gap(12)In The concentration of the backfill grouting serous fluid of spilling is backfilled the dense of grouting serous fluid by the backfill grouting serous fluid of spilling with what the 4th step had configured Degree is compared, until the concentration of the backfill grouting serous fluid of spilling is identical as the backfill concentration of grouting serous fluid that the 4th step has configured When, terminate the slip casting of backfill grouting serous fluid.
CN201810221721.3A 2018-03-18 2018-03-18 Tunnel vault concrete belt mould backfills filling system and its grouting method Pending CN108316950A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810221721.3A CN108316950A (en) 2018-03-18 2018-03-18 Tunnel vault concrete belt mould backfills filling system and its grouting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810221721.3A CN108316950A (en) 2018-03-18 2018-03-18 Tunnel vault concrete belt mould backfills filling system and its grouting method

Publications (1)

Publication Number Publication Date
CN108316950A true CN108316950A (en) 2018-07-24

Family

ID=62899340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810221721.3A Pending CN108316950A (en) 2018-03-18 2018-03-18 Tunnel vault concrete belt mould backfills filling system and its grouting method

Country Status (1)

Country Link
CN (1) CN108316950A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109404015A (en) * 2018-12-10 2019-03-01 中交公局桥隧工程有限公司 A kind of vault band mould grouting construction process
CN109505633A (en) * 2019-01-15 2019-03-22 北京市市政工程研究院 Lining cutting behind guide pipe grouting for water blocking device and construction method for shaly formation
CN109707411A (en) * 2019-03-04 2019-05-03 中铁十六局集团有限公司 A kind of technique of tunnel grouting construction
CN110469346A (en) * 2019-08-23 2019-11-19 中铁十一局集团第五工程有限公司 The anti-visualized forward direction of coming to nothing of tunnel vault concrete is rushed to summit construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1405651A (en) * 1964-08-10 1965-07-09 Typenprojektierung Bei Der Deu Method and device for placing reinforced concrete sheet piles by hydraulic backfilling
CN103147450A (en) * 2013-03-19 2013-06-12 成军 Construction method for plugging partial steel pipe dewatering well by using flange plates for excavation of deep foundation pit
CN103510964A (en) * 2013-07-31 2014-01-15 中铁隧道集团有限公司 Method for performing backfill grouting on pea gravel by adoption of shield type TBM in construction process
CN203546725U (en) * 2013-07-09 2014-04-16 中铁十四局集团有限公司 Backfilling grouting device capable of being recycled
CN105715296A (en) * 2016-01-25 2016-06-29 赵立财 Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN105937221A (en) * 2016-05-31 2016-09-14 深圳市宏业基基础工程有限公司 Manufacturing method for drilled grouting piles
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN206928955U (en) * 2017-05-10 2018-01-26 中国水利水电第五工程局有限公司 A kind of device for being used to backfill slip casting
CN107762532A (en) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 Tunnel vault band mould grouting construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1405651A (en) * 1964-08-10 1965-07-09 Typenprojektierung Bei Der Deu Method and device for placing reinforced concrete sheet piles by hydraulic backfilling
CN103147450A (en) * 2013-03-19 2013-06-12 成军 Construction method for plugging partial steel pipe dewatering well by using flange plates for excavation of deep foundation pit
CN203546725U (en) * 2013-07-09 2014-04-16 中铁十四局集团有限公司 Backfilling grouting device capable of being recycled
CN103510964A (en) * 2013-07-31 2014-01-15 中铁隧道集团有限公司 Method for performing backfill grouting on pea gravel by adoption of shield type TBM in construction process
CN105715296A (en) * 2016-01-25 2016-06-29 赵立财 Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN105937221A (en) * 2016-05-31 2016-09-14 深圳市宏业基基础工程有限公司 Manufacturing method for drilled grouting piles
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN107762532A (en) * 2016-08-23 2018-03-06 中铁十局集团第工程有限公司 Tunnel vault band mould grouting construction method
CN206928955U (en) * 2017-05-10 2018-01-26 中国水利水电第五工程局有限公司 A kind of device for being used to backfill slip casting

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109404015A (en) * 2018-12-10 2019-03-01 中交公局桥隧工程有限公司 A kind of vault band mould grouting construction process
CN109505633A (en) * 2019-01-15 2019-03-22 北京市市政工程研究院 Lining cutting behind guide pipe grouting for water blocking device and construction method for shaly formation
CN109505633B (en) * 2019-01-15 2024-03-29 北京市市政工程研究院 Lining back guide pipe grouting water plugging device for muddy stratum and construction method
CN109707411A (en) * 2019-03-04 2019-05-03 中铁十六局集团有限公司 A kind of technique of tunnel grouting construction
CN110469346A (en) * 2019-08-23 2019-11-19 中铁十一局集团第五工程有限公司 The anti-visualized forward direction of coming to nothing of tunnel vault concrete is rushed to summit construction method

Similar Documents

Publication Publication Date Title
CN108316950A (en) Tunnel vault concrete belt mould backfills filling system and its grouting method
CN103790592B (en) A kind of end soil body hardened system and method
CN104500082B (en) In Tunneling by mining method, shield receives construction method
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN103526766B (en) Method for plugging relief well of deep foundation pit
CN101666234B (en) Fracture rock no-slurry-blocking wall compound grouting construction method
CN105386435B (en) It is a kind of to be used for the double-liquid grouting system and its construction technology of cement and water glass solution
CN106761835B (en) A kind of Karst Tunnel leak segmenting slip casting construction method
CN106761837B (en) Slip casting structure and matched grouting method in tunnel excavating process
CN103277120A (en) Post-unfreezing water burst prevention method of non-full-depth freezing vertical shaft
CN101525881B (en) Structure of karst strata pile holes protecting wall and method for constructing pile holes
CN101864960A (en) Carst region double-arch road tunnel construction method
CN104711987B (en) A kind of deep covering layer sleeving valve tube method controllable grouting method
CN109139048A (en) A kind of per-fore pouring liquid with small pipe structure and its construction method
CN101793154A (en) Method for grouting for stopping up water by using geological parameters of tunnel surrounding rocks and setting relief holes
CN103334446A (en) Soil texture deep excavation side wall water burst plugging device and method
CN109763837A (en) A kind of TBM tunnel film bag cement stops paste structure and construction method
CN110206071A (en) A kind of diaphram wall seam reinforcement means and device
CN103437779B (en) The construction method of regulation tunnel lining pore gas flow
CN105155544A (en) Grouting construction method for radius-controllable deep holes
CN210768836U (en) Underground excavation tunnel and supporting construction thereof
CN107905815A (en) Rock pillar construction method in a kind of two fluid grouting Strengthening Tunnel soil property
CN208252125U (en) Tunnel vault concrete belt mould backfills grouting system
CN209557025U (en) Suitable for the locking angle ductule on steel bracket
CN110469338A (en) A kind of artesian water stratum shield method of reseptance

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination