CN108316076A - A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure - Google Patents

A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure Download PDF

Info

Publication number
CN108316076A
CN108316076A CN201810081503.4A CN201810081503A CN108316076A CN 108316076 A CN108316076 A CN 108316076A CN 201810081503 A CN201810081503 A CN 201810081503A CN 108316076 A CN108316076 A CN 108316076A
Authority
CN
China
Prior art keywords
earth shoulder
making
bed course
base
shoulder
Prior art date
Application number
CN201810081503.4A
Other languages
Chinese (zh)
Inventor
刘全
Original Assignee
刘全
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 刘全 filed Critical 刘全
Priority to CN201810081503.4A priority Critical patent/CN108316076A/en
Publication of CN108316076A publication Critical patent/CN108316076A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C19/00Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving
    • E01C19/48Machines, tools or auxiliary devices for preparing or distributing paving materials, for working the placed materials, or for forming, consolidating, or finishing the paving for laying-down the materials and consolidating them, or finishing the surface, e.g. slip forms therefor, forming kerbs or gutters in a continuous operation in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ

Abstract

A kind of highway earth shoulder sliding formwork forces closely knit making construction method to be related to a kind of earth shoulder construction method of highway, and this method comprises the following steps:Embankment section roadbed fills;The sideline setting-out of bed course and bed course earth shoulder;According to sideline setting-out as a result, carrying out bed course earth shoulder with synovial membrane machine forces closely knit making, repaves and build bed course;The sideline setting-out of underlayment and underlayment earth shoulder;According to sideline setting-out as a result, carrying out underlayment earth shoulder with synovial membrane machine forces closely knit making, repaves and build underlayment;The sideline setting-out of base and base's earth shoulder;According to sideline setting-out as a result, being carried out forcing closely knit making to base's earth shoulder with synovial membrane machine, repaves and build base;Prevent road surface structare layer to pave the pollution in place;Realize it is disposable complete being molded of earth shoulder, closely knit construction, save many cumbersome process in conventional construction method, seamless;Solves low production efficiency existing for conventional method, the problems such as labor intensity is big, and production cost is high, and flatness error is big.

Description

A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure

Technical field

The present invention relates to a kind of earth shoulder construction method of highway, specifically highway earth shoulder sliding formwork forces closely knit paving Build construction method.

Background technology

Roadbed is the basic structure of highway, is the basis for supporting pavement structure, pavement structure is making in highway subgrade The structure sheaf being in direct contact with wheel, pavement structure are generally made of face layer, base, underlayment and bed course.

Curb is to be located at runway outer rim to shoulder, has the band-like portions of one fixed width.Curb is generally by hard road Shoulder (containing side trip), earth shoulder composition.

Earth shoulder refers to the road component part close to hardened verge or close to the track of not hardened verge.Earth shoulder plays The effect on road surface and roadbed is protected, and lateral clearance is provided.The main function of earth shoulder is:The position of temporary parking is provided;For Temporary parking provides strong stabilization and keeps the surface of certain safe distance with runway;Conserve and stop in emergency use;Laterally Support road surface;Carry road equipment, including guard boom;Improve horizontal sight distance.

Currently, in the paving process of road surface structure layer, although also there is the dirt road of advanced row road surface structare layer both sides The construction method of the making of shoulder, but the process that paves in the paving process of above method earth shoulder:Extremely with transport vehicle haul Scene unloads according to live mark position, is first paved with excavator and loading machine, gentle using hand fit's excavator essence The levelling construction of land leveller.There is the construction site of pollution road surface structare layer in the process that paves, low production efficiency, labor intensity is big, Flatness error is big, increases transverse joint processing links, the problems such as integer effect difference;Roller compaction processes:Rubble is measured after essence is flat Native moisture content is mended mode using more solarizations, is ground after moisture content reaches optimum moisture content ± 2%, then with small-size vibratory roller less Pressure rolls and follows quiet one and shake a quiet principle, and one goes one to return to be one time, backtracking, Bu Nengluan are wanted after proceeding to terminal when closely knit Beat direction.Road roller static pressure first pass is first used, then with the weak first pass that shakes of vibrated roller, then with vibrated roller shakes second by force Time, it is not achieved until detection need to reach 95% or more compactness until surface without apparent wheelmark, carries out compactness inspection immediately The paragraph of compactness will carry out ftercompction.There are when gravelly soil moisture content ± 2%, the compactness after rolling is difficult the roller compaction processes It is up to standard, the earth shoulder transversely deforming to have paved is easily caused in roller compaction process, and side slope is needed to carry out the problems such as integer.

Invention content

It is an object of the invention to overcome shortcoming in the prior art, it is close to provide a kind of highway earth shoulder sliding formwork pressure Real making construction method.

In order to achieve the object of the present invention, we will adopt the following technical scheme that and be implemented.

A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure, highway includes road structure and pavement structure, road For face structure setting on road structure top surface, road structure includes half cut subgrade of filled-up ground, cut subgrade and half embankment, This method is suitable for half cut subgrade of filled-up ground and half embankment;Pavement structure from top to bottom include face layer, base, underlayment with And bed course, this method is suitable for base, the making of underlayment and bed course earth shoulder;It is characterized in that:The method includes Following steps:

(1), filled-up ground and half embankment, half cut subgrade carry out filling for roadbed by drawing and design requirement, and to its side Slope and top surface carry out smooth compacting, and compactness should be greater than design requirement, and flatness deviation is less than design requirement;

(2), native to bed course and bed course according to the highway center line after review on the top surface of the roadbed described in step (1) The sideline of curb carries out setting-out;

(3), the sideline setting-out according to bed course and bed course earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (1) bed course earth shoulder is carried out on the top surface of the roadbed described in and forces closely knit making, then according to drawing and design requirement making pad Layer;

(4), according to the highway center line after review on the top surface of step (3) making good bed course and bed course earth shoulder Setting-out is carried out to the sideline of underlayment and underlayment earth shoulder;

(5), the sideline setting-out according to underlayment and underlayment earth shoulder is as a result, first use earth shoulder molding synovial membrane machine to exist Underlayment earth shoulder is carried out on the top surface of step (3) making good bed course and bed course earth shoulder and forces closely knit making, then root According to drawing and design requirement making underlayment;

(6), according in the highway after review on the top surface of step (5) making good underlayment and underlayment earth shoulder Heart line carries out setting-out to the sideline of base and base's earth shoulder;

(7), the sideline setting-out according to base and base's earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine to base Earth shoulder carries out forcing closely knit making, then according to drawing and design requirement making base.

Highway includes road structure and pavement structure, and pavement structure is set on road structure top surface, and road structure includes Half cut subgrade of filled-up ground, cut subgrade and half embankment, this method are suitable for half cut subgrade of filled-up ground and half embankment; The pavement structure includes that face layer, base and bed course, this method are also applied for base and bed course earth shoulder from top to bottom Making;This method comprises the following steps:

(1), filled-up ground and half embankment, half cut subgrade carry out filling for roadbed by drawing and design requirement, and to its side Slope and top surface carry out smooth compacting, and compactness should be greater than design requirement, and flatness deviation is less than design requirement;

(2), native to bed course and bed course according to the highway center line after review on the top surface of the roadbed described in step (1) The sideline of curb carries out setting-out;

(3), the sideline setting-out according to bed course and bed course earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (1) bed course earth shoulder is carried out on the top surface of the roadbed described in and forces closely knit making, then according to drawing and design requirement making pad Layer;

(4), according to the highway center line after review on the top surface of step (3) making good bed course and bed course earth shoulder Setting-out is carried out to the sideline of base and base's earth shoulder;

(5), the sideline setting-out according to base and base's earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (3) base's earth shoulder is carried out on the top surface of the good bed course of making and bed course earth shoulder and force closely knit making, then according to drawing With design requirement making base.

Further, the closely knit making of pressure is the earth shoulder making material feeding earth shoulder molding synovial membrane that will have been mixed and stirred Machine, earth shoulder are molded the step described in step (3), step (5) and step (7) or claim 2 of the synovial membrane machine in claim 1 Suddenly the sideline setting-out result set in (3), step (5) is advanced, and is molded the synovial membrane and synovial membrane of synovial membrane machine in earth shoulder Under the upper concrete vibrating mechanism synergistic effect with compacting effect, vibrate pressure according to sideline trend and the automatic sliding formwork of size of earth shoulder Closely knit making formation meets predetermined compactness and requires and can keep stable shaped earth shoulder.

Further, the earth shoulder making material include chisley soil, coarse-grained soil, fine grained soil, in choose any one kind of them or appoint The combination or full choosing for selecting two kinds are mixed and stirred with suitable quantity of water, and soil ratio controls between 0.04-0.05.

Further, the gait of march of earth shoulder molding synovial membrane machine is according to the scheduled compactness of design, synovial membrane Vibrate frequency and earth shoulder making material rate of feeding setting.

Further, before the closely knit making of the pressure, in half cut subgrade of filled-up ground or half embankment, bed course and bed course Earth shoulder, underlayment (or base) and underlayment (or base) earth shoulder or the surface of base and base's earth shoulder top surface are spilt Water moistens.

Further, the offset and torsion that earth shoulder is strictly controlled in the described closely knit paving process of pressure, to earth shoulder at The traveling of type synovial membrane machine is rectified a deviation, entangles torsion operation, is slowly carried out by the scheduled method of Design of Construction Organization.

Further, the described earth shoulder making material feeding should ensure that the continuity for forcing closely knit making, and with frequency of vibrating It is consistent.

Further, earth shoulder molding synovial membrane machine gait of march one is selected, to keep stable, reduce to the greatest extent and stop The machine number of starts, to ensure to force closely knit making quality.

Further, when the described earth shoulder molding synovial membrane machine is in place, according to bed course earth shoulder, underlayment earth shoulder (or base Layer earth shoulder) or base's earth shoulder sideline setting-out result setting earth shoulder be molded synovial membrane machine position, detection sensor opposite side The accuracy of the linear induction of line construction layout.

Advantageous effect

1, prevented when carrying out earth shoulder making, road pavement structure sheaf paves the pollution in place;

2, the earth shoulder that closely knit paving structure layer is forced using earth shoulder molding synovial membrane machine, realizes disposable completion Being molded of earth shoulder, closely knit construction, save flat survey in traditional earth shoulder construction method, smooth, levelling, integer, joint treatment, Roll, etc. cumbersome process, simplify earth shoulder making, linear more smooth, beautiful, the seamless of earth shoulder;

3, the soil ratio of earth shoulder making material controls between 0.04-0.05, increases the compactness of earth shoulder;

4, low production efficiency existing for traditional earth shoulder construction method is solved, labor intensity is big, and production cost is high, smooth Spend the problems such as error is big.

Description of the drawings

Fig. 1 is the structural schematic diagram that pavement structure of the present invention is base, underlayment and bed course;

Fig. 2 is the structural schematic diagram that pavement structure of the present invention is base and bed course;

Fig. 3 is that earth shoulder of the present invention is molded synovial membrane machine in construction cross-sectional view;

Fig. 4 is that earth shoulder of the present invention is molded synovial membrane machine in construction floor map.

Specific implementation mode

In conjunction with the accompanying drawings and embodiments, the present invention is described further.

As shown in Fig. 1, Fig. 3 or Fig. 4, a kind of closely knit making construction method of highway earth shoulder sliding formwork pressure, highway includes road Based structures 1 and pavement structure 2, pavement structure 2 are set on 1 top surface of road structure, and road structure 1 includes filled-up ground, excavation Half cut subgrade of roadbed and half embankment, this method are suitable for half cut subgrade of filled-up ground and half embankment;Pavement structure 2 is from upper To lower including face layer, base 2-1, underlayment 2-2 and bed course 2-3, this method is suitable for base 2-1, underlayment 2-2 and pad The making of layer 2-3 earth shoulders;It is characterized in that:The method includes the following steps:

(1), filled-up ground and half embankment, half cut subgrade carry out filling for roadbed by drawing and design requirement, and to its side Slope and top surface carry out smooth compacting, and compactness should be greater than design requirement, and flatness deviation is less than design requirement;

(2), the highway center line on the top surface of the roadbed described in step (1) after foundation review is to bed course 2-3 and pad The sideline of layer earth shoulder 2-3-1 carries out setting-out;

(3), according to the sideline setting-out of bed course 2-3 and bed course earth shoulder 2-3-1 as a result, first earth shoulder is used to be molded synovial membrane Carry out bed course earth shoulder 2-3-1 on the top surface of roadbed of the machine 3 described in step (1) and force closely knit making, then according to drawing and Design requirement making bed course 2-3;

(4), according to the public affairs after review on the top surface of step (3) making good bed course 2-3 and bed course earth shoulder 2-3-1 Lu Zhizheng line carries out setting-out to the sideline of underlayment 2-2 and underlayment earth shoulder 2-2-1;

(5), according to the sideline setting-out of underlayment 2-2 and underlayment earth shoulder 2-2-1 as a result, first earth shoulder is used to be molded Synovial membrane machine 3 carries out underlayment earth shoulder 2- on the top surface of step (3) making good bed course 2-3 and bed course earth shoulder 2-3-1 2-1 forces closely knit making, then according to drawing and design requirement making underlayment 2-2;

(6), after on the top surface of step (5) making good underlayment 2-2 and underlayment earth shoulder 2-2-1 according to review Highway center line setting-out is carried out to the sideline of base 2-1 and base earth shoulder 2-1-1;

(7), according to the sideline setting-out of base 2-1 and base earth shoulder 2-1-1 as a result, first earth shoulder is used to be molded synovial membrane Machine 3 carries out forcing closely knit making to base earth shoulder 2-1-1, then according to drawing and design requirement making base 2-1.

The implementation of the above method has prevented when carrying out earth shoulder making, and road pavement structure sheaf paves the pollution in place;It adopts Force the earth shoulder of closely knit paving structure layer with earth shoulder molding synovial membrane machine, realize it is disposable complete earth shoulder at Type, closely knit construction, save the flat survey in traditional earth shoulder construction method, smooth, levelling, integer, joint treatment, roll, etc. it is numerous Trivial process simplifies earth shoulder making, linear more smooth, beautiful, the seamless of earth shoulder;It solves traditional earth shoulder to apply The problems such as low production efficiency existing for work method, labor intensity is big, and production cost is high, and flatness error is big.

As shown in Fig. 2, Fig. 3 or Fig. 4, a kind of closely knit making construction method of highway earth shoulder sliding formwork pressure, the road surface Structure 2 includes that face layer, base 4-1 and bed course 4-2, this method are also applied for base 4-1 and bed course 4-1 dirt roads from top to bottom The making of shoulder;This method comprises the following steps:

(1), filled-up ground 1-1 and half embankment, half cut subgrade 1-2 carries out filling for roadbed by drawing and design requirement, and Smooth compacting is carried out to its side slope and top surface, compactness should be greater than design requirement, and flatness deviation is less than design requirement;

(2), the highway center line on the top surface of the roadbed described in step (1) after foundation review is to bed course 4-2 and pad The sideline of layer earth shoulder 4-2-1 carries out setting-out;

(3), according to the sideline setting-out of bed course 4-2 and bed course earth shoulder 4-2-1 as a result, first earth shoulder is used to be molded synovial membrane Carry out bed course earth shoulder 4-2-1 on the top surface of roadbed of the machine 3 described in step (1) and force closely knit making, then according to drawing and Design requirement making bed course 4-2;

(4), according to the public affairs after review on the top surface of step (3) making good bed course 4-2 and bed course earth shoulder 4-2-1 Lu Zhizheng line carries out setting-out to the sideline of base 4-1 and base earth shoulder 4-1-1;

(5), according to the sideline setting-out of base 4-1 and base earth shoulder 4-1-1 as a result, first earth shoulder is used to be molded synovial membrane Machine 3 carries out base earth shoulder 4-1-1 pressures on the top surface of step (3) making good bed course 4-2 and bed course earth shoulder 4-2-1 Closely knit making, then according to drawing and design requirement making base 4-1.

The implementation of the above method has prevented when carrying out earth shoulder making, and road pavement structure sheaf paves the pollution in place;It adopts Force the earth shoulder of closely knit paving structure layer with earth shoulder molding synovial membrane machine, realize it is disposable complete earth shoulder at Type, closely knit construction, save the flat survey in traditional earth shoulder construction method, smooth, levelling, integer, joint treatment, roll, etc. it is numerous Trivial process simplifies earth shoulder making, linear more smooth, beautiful, the seamless of earth shoulder;It solves traditional earth shoulder to apply The problems such as low production efficiency existing for work method, labor intensity is big, and production cost is high, and flatness error is big.

Embodiment 1

As shown in Figure 3 or Figure 4, the described closely knit making of pressure be the earth shoulder making material feeding earth shoulder that will mix at The feeding hopper 3-1 of type synovial membrane machine 3, earth shoulder are molded synovial membrane machine 3 along step described in claim 1 (3), step (5) or right It is required that the sideline setting-out result set in step (3), step (5) and step (7) in 2 is advanced, and it is molded in earth shoulder On the synovial membrane 3-2 and synovial membrane 3-2 of synovial membrane machine 3 under the concrete vibrating mechanism 3-3 synergistic effects with compacting effect, according to earth shoulder Linear automatic sliding formwork, which vibrates, to be forced closely knit making formation to meet predetermined compactness requirement and can keep stable shaped earth shoulder.It adopts Force the earth shoulder of closely knit paving structure layer with earth shoulder molding synovial membrane machine, realize it is disposable complete earth shoulder at Type meets compactness and requires construction, save flat survey in traditional earth shoulder construction method, smooth, levelling, integer, joint treatment, Roll, etc. cumbersome process, simplify earth shoulder making, linear more smooth, beautiful, the seamless of earth shoulder;Solves biography Low production efficiency existing for earth shoulder construction method of uniting, labor intensity is big, and production cost is high, and flatness error is big etc. many asks Topic.

Embodiment 2

The earth shoulder making material include chisley soil, coarse-grained soil, fine grained soil, in choose any one kind of them or optional two kinds of group It closes or full choosing is mixed and stirred with suitable quantity of water, soil ratio controls between 0.04-0.05.Using above-mentioned making material, enable to The compactness that synovial membrane machine making structure sheaf earth shoulder is molded using earth shoulder meets the requirement of structure design.

Embodiment 3

As shown in Figure 3 or Figure 4, the gait of march of earth shoulder molding synovial membrane machine 3 is scheduled closely knit according to designing Vibrate frequency and earth shoulder making material rate of feeding and the conveying mechanism 3- of the bottoms feeding hopper 3-1 setting of degree, synovial membrane 3-2 4 conveying speed setting.

Embodiment 4

As shown in Fig. 1 or Fig. 2 or Fig. 3 or Fig. 4, before the closely knit making of the pressure, in filled-up ground 1-1 or half embankment half The top surface of cut subgrade 1-2, bed course 2-3 and bed course earth shoulder 2-3-1, underlayment 2-2 (or base 4-1) and underlayment The surface of (or base) earth shoulder 2-2-1 or 4-1-1 or base 2-1 and the top surfaces base earth shoulder 2-1-1 watering moistening.To increase By force viscous between earth shoulder and each top surface and.

Embodiment 5

As shown in Figure 3 or Figure 4, the offset and torsion of earth shoulder are strictly controlled in the closely knit paving process of pressure, it is right Earth shoulder molding synovial membrane machine 3, which is advanced, is rectified a deviation, entangles torsion operation, is slowly carried out by the scheduled method of Design of Construction Organization.Ensure Construction quality.

Embodiment 6

The earth shoulder making material feeding should ensure that the continuity for forcing closely knit making, and be consistent with frequency of vibrating.

Embodiment 7

As shown in Figure 3 or Figure 4, earth shoulder molding synovial membrane 3 gait of march one of machine are selected, to keep stable, to the greatest extent Amount, which is reduced, shuts down the number of starts, to ensure to force closely knit making quality.

Embodiment 8

As shown in Figure 3 or Figure 4, when earth shoulder molding synovial membrane machine 3 is in place, according to bed course earth shoulder 2-1-1, base The sideline setting-out result setting earth shoulder of layer earth shoulder 2-2-1 (or base earth shoulder 4-1-1) or base earth shoulder 2-3-1 is molded The position of synovial membrane machine 3, accuracy of the detection sensor to the linear induction of sideline construction layout.

Claims (10)

1. a kind of highway earth shoulder sliding formwork forces closely knit making construction method, highway includes road structure and pavement structure, road surface For structure setting on road structure top surface, road structure includes half cut subgrade of filled-up ground, cut subgrade and half embankment, should Method is suitable for half cut subgrade of filled-up ground and half embankment;Pavement structure from top to bottom include face layer, base, underlayment and Bed course, this method is suitable for base, the making of underlayment and bed course earth shoulder;It is characterized in that:The method includes such as Lower step:
(1), filled-up ground and half embankment, half cut subgrade carry out filling for roadbed by drawing and design requirement, and to its side slope and Top surface carries out smooth compacting, and compactness should be greater than design requirement, and flatness deviation is less than design requirement;
(2), the highway center line on the top surface of the roadbed described in step (1) after foundation review is to bed course and bed course earth shoulder Sideline carry out setting-out;
(3), the sideline setting-out according to bed course and bed course earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (1) Bed course earth shoulder is carried out on the top surface of the roadbed and forces closely knit making, then according to drawing and design requirement making bed course;
(4), the highway center line on the top surface of step (3) making good bed course and bed course earth shoulder after foundation review is the bottom of to The sideline of base and underlayment earth shoulder carries out setting-out;
(5), the sideline setting-out according to underlayment and underlayment earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (3) underlayment earth shoulder is carried out on the top surface of the good bed course of making and bed course earth shoulder and force closely knit making, then according to figure Paper and design requirement making underlayment;
(6), according to the highway center line after review on the top surface of step (5) making good underlayment and underlayment earth shoulder Setting-out is carried out to the sideline of base and base's earth shoulder;
(7), the sideline setting-out according to base and base's earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine to base's dirt road Shoulder carries out forcing closely knit making, then according to drawing and design requirement making base.
2. a kind of highway earth shoulder sliding formwork according to claim 1 forces closely knit making construction method, it is characterised in that:Institute The pavement structure stated includes face layer, base and bed course from top to bottom, and this method is also applied for base and bed course earth shoulder Making;This method comprises the following steps:
(1), filled-up ground and half embankment, half cut subgrade carry out filling for roadbed by drawing and design requirement, and to its side slope and Top surface carries out smooth compacting, and compactness should be greater than design requirement, and flatness deviation is less than design requirement;
(2), the highway center line on the top surface of the roadbed described in step (1) after foundation review is to bed course and bed course earth shoulder Sideline carry out setting-out;
(3), the sideline setting-out according to bed course and bed course earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (1) Bed course earth shoulder is carried out on the top surface of the roadbed and forces closely knit making, then according to drawing and design requirement making bed course;
(4), the highway center line on the top surface of step (3) making good bed course and bed course earth shoulder after foundation review is to base The sideline of layer and base's earth shoulder carries out setting-out;
(5), the sideline setting-out according to base and base's earth shoulder is as a result, first use earth shoulder to be molded synovial membrane machine in step (3) Base earth shoulder is carried out on the top surface of the good bed course of making and bed course earth shoulder and forces closely knit making, then according to drawing and is set Meter requires making base.
3. a kind of highway earth shoulder sliding formwork according to claim 1 or 2 forces closely knit making construction method, feature to exist In:The closely knit making of pressure is the feeding hopper for the earth shoulder making material feeding earth shoulder molding synovial membrane machine that will have been mixed and stirred, soil Curb is molded step (3), step (5) of the synovial membrane machine in step described in claim 1 (3), step (5) or claim 2 It advances with the sideline setting-out result set in step (7), and has on the synovial membrane and synovial membrane that earth shoulder is molded synovial membrane machine Have under the concrete vibrating mechanism synergistic effect that compacting acts on, vibrating according to the sideline trend and the automatic sliding formwork of size of earth shoulder, it is closely knit to force Making formation meets predetermined compactness and requires and can keep stable shaped earth shoulder.
4. a kind of highway earth shoulder sliding formwork according to claim 3 forces closely knit making construction method, it is characterised in that:Institute The earth shoulder making material stated include chisley soil, coarse-grained soil, fine grained soil, in choose any one kind of them or optional two kinds of combination or full choosing and Suitable quantity of water is mixed and stirred, and soil ratio controls between 0.04-0.05.
5. a kind of highway earth shoulder sliding formwork according to claim 3 forces closely knit making construction method, it is characterised in that:Institute The gait of march for the earth shoulder molding synovial membrane machine stated is according to vibrate frequency and the earth shoulder for designing scheduled compactness, synovial membrane The conveying speed setting of making material rate of feeding and the conveying mechanism of feeding hopper bottom setting.
6. a kind of highway earth shoulder sliding formwork according to claim 1 or 2 or 3 forces closely knit making construction method, feature It is:Before the closely knit making of the pressure, at half cut subgrade of filled-up ground or half embankment, bed course and bed course earth shoulder, bottom Base (or base) and underlayment (or base) earth shoulder or the surface of base and base's earth shoulder top surface watering moistening.
7. a kind of highway earth shoulder sliding formwork according to claim 1 or 2 or 3 forces closely knit making construction method, feature It is:The offset and torsion that earth shoulder is strictly controlled in the closely knit paving process of pressure, synovial membrane machine row is molded to earth shoulder Into being rectified a deviation, entangling torsion operation, slowly carried out by the scheduled method of Design of Construction Organization.
8. a kind of highway earth shoulder sliding formwork according to claim 1 or 2 or 3 forces closely knit making construction method, feature It is:The earth shoulder making material feeding should ensure that the continuity for forcing closely knit making, and be consistent with frequency of vibrating.
9. a kind of highway earth shoulder sliding formwork according to claim 5 forces closely knit making construction method, it is characterised in that:Institute The earth shoulder molding synovial membrane machine gait of march one stated is selected, to keep stable, reduce the shutdown number of starts to the greatest extent, strong to ensure Make closely knit making quality.
10. a kind of highway earth shoulder sliding formwork according to claim 1 or 2 or 3 forces closely knit making construction method, feature It is:When described earth shoulder molding synovial membrane machine is in place, according to bed course earth shoulder, underlayment earth shoulder (or base's earth shoulder) or The sideline setting-out result setting earth shoulder of base's earth shoulder is molded the position of synovial membrane machine, and detection sensor is to sideline construction layout line The accuracy of shape induction.
CN201810081503.4A 2018-01-23 2018-01-23 A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure CN108316076A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810081503.4A CN108316076A (en) 2018-01-23 2018-01-23 A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810081503.4A CN108316076A (en) 2018-01-23 2018-01-23 A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure

Publications (1)

Publication Number Publication Date
CN108316076A true CN108316076A (en) 2018-07-24

Family

ID=62888654

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810081503.4A CN108316076A (en) 2018-01-23 2018-01-23 A kind of closely knit making construction method of highway earth shoulder sliding formwork pressure

Country Status (1)

Country Link
CN (1) CN108316076A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004051748A1 (en) * 2004-10-23 2006-04-27 Baulabor Fienstedt Gmbh Procedure for laying multilevel asphaltic surfacing by layers of different mixing combinations such that lower layer is of bitumen and upper layer is of asphalt laid while in hot state
JP2012036718A (en) * 2010-07-16 2012-02-23 Touou Co Ltd Court construction method and court
CN102701658A (en) * 2012-06-27 2012-10-03 匡许衡 High-strength pore concrete pavement and preparation method thereof
KR101256341B1 (en) * 2012-12-26 2013-04-18 김진아 Method of paving latex modified concrete and paver adapting thereof
CN203049397U (en) * 2012-12-18 2013-07-10 中建三局第一建设工程有限责任公司 Comprehensive processing system of soft foundation of soft soil road of coal ash storeroom
CN103835205A (en) * 2012-11-26 2014-06-04 五冶集团上海有限公司 Construction method for road edge stone sliding mode
CN103966939A (en) * 2014-05-15 2014-08-06 核工业西南建设集团有限公司 Earth shoulder paver
CN203834324U (en) * 2014-05-15 2014-09-17 核工业西南建设集团有限公司 Soil shoulder paver
CN105220602A (en) * 2014-08-10 2016-01-06 刘全 A kind of curb forming machine
CN106638213A (en) * 2016-11-09 2017-05-10 中铁局集团天津建设工程有限公司 Cement road construction method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102004051748A1 (en) * 2004-10-23 2006-04-27 Baulabor Fienstedt Gmbh Procedure for laying multilevel asphaltic surfacing by layers of different mixing combinations such that lower layer is of bitumen and upper layer is of asphalt laid while in hot state
JP2012036718A (en) * 2010-07-16 2012-02-23 Touou Co Ltd Court construction method and court
CN102701658A (en) * 2012-06-27 2012-10-03 匡许衡 High-strength pore concrete pavement and preparation method thereof
CN103835205A (en) * 2012-11-26 2014-06-04 五冶集团上海有限公司 Construction method for road edge stone sliding mode
CN203049397U (en) * 2012-12-18 2013-07-10 中建三局第一建设工程有限责任公司 Comprehensive processing system of soft foundation of soft soil road of coal ash storeroom
KR101256341B1 (en) * 2012-12-26 2013-04-18 김진아 Method of paving latex modified concrete and paver adapting thereof
CN103966939A (en) * 2014-05-15 2014-08-06 核工业西南建设集团有限公司 Earth shoulder paver
CN203834324U (en) * 2014-05-15 2014-09-17 核工业西南建设集团有限公司 Soil shoulder paver
CN105220602A (en) * 2014-08-10 2016-01-06 刘全 A kind of curb forming machine
CN106638213A (en) * 2016-11-09 2017-05-10 中铁局集团天津建设工程有限公司 Cement road construction method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
N1这个坏蛋: "土路肩施工组织设计", 《HTTPS:WENKU.BAIDU.COM/VIEW/36486DF8CF2F0066F5335A8102D276A20029603B.HTML》 *
中交第一公路工程局有限公司: "《公路路基施工技术规范》", 31 December 2016 *

Similar Documents

Publication Publication Date Title
US6623207B2 (en) Method of upgrading gravel and/or dirt roads and a composite road resulting therefrom
CN103628363B (en) Construction method for filling and building subgrade by using silty-fine sand as filling materials
CN101368383B (en) Method for treating soft soil roadbed by artificial composite crust layer
ES2689538T3 (en) Pavement system with geocells and geogrids and procedure to install a pavement system
US7591608B2 (en) Checking density while compacting
CN1259484C (en) Road finisher and method of applying surface layers
CN101962928B (en) Construction method for processing aeolian sand roadbed base through impacting and grinding
BE1012425A3 (en) Machine forms for slippery roads of concrete structures.
CN104358188B (en) Filling construction method for collapsible loess subgrade
EP1496161B1 (en) Method for stabilising ground for a traffic route
CN104278608B (en) The constructional method of a kind of highway embankment widened structure
CN103669145B (en) A kind of paving method of permeable pavement structure
CN103790166B (en) Method for treating foundation of loess area saturated zone slope filling and digging joint part
BE1014060A3 (en) Road paving.
EP0324491A1 (en) Method and machine for renewing a road surface of bituminous mix, with cold application of the recycled covering material
CN1034602A (en) The mould that is used for constructing pavement boards
CN104762858B (en) Asphalt concrete construction method for soft soil matrix pavement
CN105862710B (en) A kind of drain bar and construction method for Tidal Flat Inning Area processing
CN106245488B (en) A kind of construction method for stirring formula voluntarily sliding formwork continuous placing roadbed gutter using vibration
KR20050115234A (en) Asphalt delivery and compaction system
CN203383119U (en) Novel widening structure of highway embankment
CN205152761U (en) A curb former for paver
CN105780618B (en) A kind of prefabricated board is to stretching vertical no slope embankment and construction method
CN101974898B (en) Roller compacted concrete cushion changing and filling method
CN103866668B (en) A kind of cement permeable concrete ground structure of surface pervious asphalt and preparation method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination