CN108301586A - A kind of outer laying and hanging ornamental prefabricated component mounting structure of building - Google Patents
A kind of outer laying and hanging ornamental prefabricated component mounting structure of building Download PDFInfo
- Publication number
- CN108301586A CN108301586A CN201810103595.1A CN201810103595A CN108301586A CN 108301586 A CN108301586 A CN 108301586A CN 201810103595 A CN201810103595 A CN 201810103595A CN 108301586 A CN108301586 A CN 108301586A
- Authority
- CN
- China
- Prior art keywords
- plug
- wall
- decoration materials
- plate
- component mounting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/07—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor
- E04F13/08—Coverings or linings, e.g. for walls or ceilings composed of covering or lining elements; Sub-structures therefor; Fastening means therefor composed of a plurality of similar covering or lining elements
- E04F13/0801—Separate fastening elements
- E04F13/0803—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements
- E04F13/0805—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall
- E04F13/0808—Separate fastening elements with load-supporting elongated furring elements between wall and covering elements with additional fastening elements between furring elements and the wall adjustable in several directions one of which is perpendicular to the wall
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Finishing Walls (AREA)
Abstract
The invention discloses laying and hanging ornamental prefabricated component mounting structures outside a kind of building,Belong to decorating outer wall of building technical field,The cooperation solved between existing metal hanger and decoration materials is all more close,So that when typhoon,The wind pressure that plug-in decoration materials are subject to all acts on metal hanger,The problem of service life of metal hanger is impacted,Its key points of the technical solution are that a kind of outer laying and hanging ornamental prefabricated component mounting structure of building,It is characterized in that,Include perpendicular to wall and several installation parts for being arranged in array,The installation part includes the first fixation steel plate for supplying the bearing plate of plug-in decoration materials setting and being embedded in advance simultaneously in bearing plate and wall,The distance between adjacent two described bearing plate is identical as the height of the vertical direction of plug-in decoration materials on vertical direction,There are buffer gaps with surface of wall towards the one side of surface of wall for the plug-in decoration materials,The stress for capableing of external ornament material plays buffering effect,Preferably protecting effect is played to metal hanger.
Description
Technical field
The invention belongs to decorating outer wall of building technical field, more particularly to the outer laying and hanging ornamental prefabricated component installation knot of a kind of building
Structure.
Background technology
To increase the dicoration of surface of wall, many buildings all can be arranged some decoration materials in surface of wall and form decoration at present
For curtain wall to increase the aesthetics of wall, decoration materials can be according to materials such as decoration demand selection slabstone, glass plate, steel plate, planks.
Existing decoration materials trailing is broadly divided into two kinds, and one is directly adhered to facing decoration materials using grouting bonding method
In wall outer side, another kind is hung facing decoration materials in wall outer side by metal hanger using decoration materials dry-hanging method.
Since decoration materials dry-hanging method compared with than grouting bonding method there is stronger load-bearing capacity to be therefore used in more and more widely
In various construction.In order to ensure the stability of decoration materials, the cooperation between existing metal hanger and decoration materials is all more close,
So that when typhoon, the wind pressure that plug-in decoration materials are subject to all acts on metal hanger, increases the load of metal hanger, right
The service life of metal hanger impacts.
Invention content
The object of the present invention is to provide laying and hanging ornamental prefabricated component mounting structures outside a kind of building, are capable of the stress of external ornament material
Buffering effect is played, preferably protecting effect is played to metal hanger.
The present invention above-mentioned technical purpose technical scheme is that:
A kind of outer laying and hanging ornamental prefabricated component mounting structure of building, which is characterized in that if including perpendicular to wall and being arranged in array
Dry installation part, the installation part include the bearing plate for the setting of plug-in decoration materials and be embedded in advance simultaneously in bearing plate and wall the
One fixation steel plate, height phase of the distance between the adjacent two described bearing plate with the vertical direction of plug-in decoration materials on vertical direction
Together, there are buffer gaps with surface of wall towards the one side of surface of wall for the plug-in decoration materials.
By using above-mentioned technical proposal, the space being embedded in for plug-in decoration materials is formed on vertical direction between two bearing plates,
There are buffer gaps with surface of wall after wall outer side for plug-in decoration materials setting, when typhoon, blow plug-in decoration materials, plug-in
The buffer gap of decoration materials and surface of wall can play the effect of buffering, plug-in decoration materials can occur to gap slight deformation with
The load for reducing installation part, increases the service life of installation part;In addition, installation part and the first fixation steel plate one moulding by casting,
First fixation steel plate is embedded in advance again on the inside of wall, and the structural strength of installation part is enabled to get a promotion, and further promotes installation
The service life of part.
Preferably, the plug-in decoration materials are towards having the inner groovy being recessed inwardly on the surface of wall side.
By using above-mentioned technical proposal, by making plug-in decoration materials be set towards inner groovy on the surface of wall side
Meter, when the wind pressure that plug-in decoration materials are subject to is stronger, preferably inside groove a degree of deformation can occur for plug-in decoration materials,
And then play preferably buffering effect.
Preferably, be provided with the first ladder platform between the bearing plate and wall, the plug-in decoration materials are towards wall one
The surface of side is abutted with the first ladder platform.
By using above-mentioned technical proposal, by being provided with the first ladder platform, after plug-in decoration materials are embedded between two bearing plates
It is abutted with the first ladder platform, plug-in decoration materials is enabled to not contacted with wall towards the surface of wall side, can played more preferable
Ground buffering effect.
Preferably, the four edges setting of the plug-in decoration materials is both provided with fixing piece, the fixing piece includes vertical
Cross positioning plate in surface of wall and pre- the second fixation steel plate being embedded in cross positioning plate and wall, the cross positioning
The second ladder platform is provided between plate and wall, the surface of the plug-in decoration materials towards wall side is abutted with the second ladder platform.
By using above-mentioned technical proposal, by the design of fixing piece, cross positioning plate is formed to be determined there are four perpendicular type
Position slot is respectively used to fix the corner of four plug-in decoration materials, by the design of the second ladder platform, plug-in decoration materials and the second ladder platform
It abuts, can preferably form buffer gap;In addition, fixing piece and the second fixation steel plate one moulding by casting, second fixes steel
Plate is embedded in advance again on the inside of wall, and the structural strength of fixing piece is enabled to get a promotion, and further promote fixing piece uses the longevity
Life.
Preferably, being provided with the locating framework for limiting four edge of plug-in decoration materials, institute on the outside of the plug-in decoration materials
It is several located lateral plates and vertical positioning plate that spacing transverse and longitudinal is interlocked to state ornament material length and width other than locating framework includes, described
The medium position of cross positioning plate offers first positioning hole, and the intersection of the located lateral plate and vertical positioning plate offers
Second location hole corresponding with first positioning hole, the first positioning hole wear positioning spiral shell after being connected to second location hole correspondence
Locating framework is fixed on outside plug-in decoration materials by bolt.
By using above-mentioned technical proposal, by the design of locating framework, locating framework can be by the outside of plug-in decoration materials
Four edge of face is fixed, and deviates from outward to limit plug-in decoration materials.
Preferably, the locating framework further includes being located at parallel with located lateral plate and being located at the top located lateral plate
The weather shield of top, the front end of the weather shield extend to the outside of plug-in decoration materials.
By using above-mentioned technical proposal, when typhoon, would generally mix the ash in air along with heavy rain, rainwater
Dirt is flow to along surface of wall at plug-in decoration materials, is easy to form dirtier washmarking after becoming a fine day, to influence U.S. of plug-in decoration materials
The property seen, by the design of weather shield, the rainwater to flow downward from exterior surface of wall, from the front end of weather shield after dropping down onto on weather shield
It flows away, the aesthetics that a large amount of rainwater flow to the external ornament material in surface of plug-in decoration materials can be avoided to impact.
Preferably, the weather shield includes being bonded and tilting down the first guide face of setting with wall and with first
Guide face turns to the second guide face for being connected and being equally arranged diagonally downward.
By using above-mentioned technical proposal, by the design of the first guide face and the second guide face, rainwater drops down onto weather shield
It can flow away along the first guide face and the second guide face after upper, the first guide face and the second guide face can be to the sides of falling on
Rainwater play guiding role, to avoid rainwater from being accumulated on weather shield.
Preferably, the angle of inclination and the second guide face of first guide face and horizontal plane and the first guide face it
Between inclined angle be unanimously 150 °.
By using above-mentioned technical proposal, by the way that the angle of inclination of the first guide face and the second guide face is disposed as
150 °, rainwater is dropped down onto along the outer surface of wall on the first guide face, and by tilting 150 ° of the first guide face, rainwater drops down onto
Too many spray will not be splash on first guide face, set by the second guide face for being 150 ° with the first guide face angle of inclination
The angle of meter, the second guide face and vertical surface of wall is 60 °, and rainwater is flowed downward out along the second guide face of this angle, energy
Rainwater is enough enable preferably to flow away from water fender.
Preferably, the side shield that restricted rainwater is flowed out to both sides is arranged in the both sides of the weather shield.
By using above-mentioned technical proposal, by the design of the side shield of weather shield both sides, the rainwater on weather shield is dropped down onto
Limited by side shield, rainwater can be avoided to be flowed outwardly from the both sides of weather shield so that drop down onto rainwater on weather shield all along
The outflow of the second guide face.
In conclusion the invention has the advantages that:
1. the space for the insertion of plug-in decoration materials is formed on vertical direction between two bearing plates, by being provided with the first ladder platform, outside
It is abutted with the first ladder platform and between connecting plate there are certain gap after between ornament material two bearing plates of insertion, works as typhoon
Come interim, blow plug-in decoration materials, the gap between plug-in decoration materials and connecting plate can play the effect of buffering, and plug-in decoration materials can be with
Slight deformation occurs to reduce the load of installation part and fixing piece to gap, enhances the shock resistance of plug-in decoration materials;
2. by the way that locating framework is arranged on the outside of outer ornament material, locating framework can further enhance steady after plug-in decoration materials are hung
It is qualitative, at the same in locating framework top setting weather shield can to avoiding rainwater from being flowed at plug-in decoration materials along surface of wall,
So that plug-in decoration materials surface is formed washmarking, influences the aesthetics of plug-in decoration materials.
Description of the drawings
Fig. 1 is that plug-in decoration materials are hung to the front view of wall outer side;
Fig. 2 is the connection diagram of plug-in decoration materials and bearing plate and cross positioning plate;
Fig. 3 is the schematic diagram of installation part;
Fig. 4 is the schematic diagram of fixing piece;
Fig. 5 is the section view connection diagram of plug-in decoration materials and bearing plate and cross positioning plate;
Fig. 6 is the connection diagram of locating framework and plug-in decoration materials;
Fig. 7 is the schematic cross-sectional view of mounting structure;
Fig. 8 is the enlarged drawing at A in Fig. 7.
In figure, 1, wall;11, plug-in decoration materials;111, inner groovy;112, mounting groove;2, installation part;21, first steel is fixed
Plate;22, bearing plate;23, the first ladder platform;24, buffer gap;3, fixing piece;31, the second fixation steel plate;32, cross positions
Plate;321, first positioning hole;33, the second ladder platform;4, locating framework;41, located lateral plate;42, vertical positioning plate;43,
Two location holes;44, protective plate;5, weather shield;51, the first guide face;52, the second guide face;53, reinforce plate muscle;54, side block
Plate.
Specific implementation mode
Below in conjunction with attached drawing, invention is further described in detail.
Referring to Figures 1 and 2, the present invention proposes a kind of outer laying and hanging ornamental prefabricated component mounting structure of building, including perpendicular to wall
Body 1 and several installation parts 2 and several fixing pieces 3 being arranged in array.
With reference to Fig. 2, Fig. 3 and Fig. 4, installation part 2 includes the bearing plate 22 being arranged for the plug-in decoration materials 11 of rectangular configuration and same
When be embedded in the first fixation steel plate 21 in bearing plate 22 and wall 1 in advance, fixing piece 3 includes that four corners hung down for plug-in decoration materials 11 are fixed
The cross positioning plate 32 of position and pre- the second fixation steel plate 31 being embedded in cross positioning plate 32 and wall 1.Phase on vertical direction
The distance between adjacent two bearing plates 22 are identical as the height of the vertical direction of plug-in decoration materials 11.
With reference to Fig. 3, Fig. 4 and Fig. 5, be provided with the first ladder platform 23 between bearing plate 22 and wall 1, cross positioning plate 32 with
The second ladder platform 33 is provided between wall 1, the surface of plug-in decoration materials 11 towards 1 side of wall has the inner groovy being recessed inwardly
111, inner groovy 111 can be rectangular channel or arc groove.It is preferably arc groove, plug-in decoration materials 11 and the first ladder in the present embodiment
After platform 23 and the second ladder platform 33 abut, buffer gap 24 is formed between 1 surface of plug-in decoration materials 11 and wall(Such as institute in Fig. 8
Show).
With reference to Fig. 4 and Fig. 6,11 outside of plug-in decoration materials is provided with the locating framework for limiting 11 4 edge of plug-in decoration materials
4, locating framework 4 includes several located lateral plates 41 and vertical positioning plate that 11 length and width of ornament material are spacing transverse and longitudinal is interlocked in addition
42 and the protective plate 44 that extends to 1 inside of wall in outermost located lateral plate 41 and vertical positioning plate 42.Cross positions
The medium position of plate 32 offers first positioning hole 321, the intersection of located lateral plate 41 and vertical positioning plate 42 offer with
321 corresponding second location hole 43 of first positioning hole, the first positioning hole 321 are worn after being connected to the correspondence of second location hole 43
If locating framework 4 is fixed on outside plug-in decoration materials 11 by positioning bolt.Four edges of plug-in decoration materials 11 are offered for located lateral
The mounting groove 112 that plate 41 and vertical positioning plate 42 are embedded in, located lateral plate 41 and vertical positioning plate 42 are embedded in plug-in decoration materials 11
It is concordant with the end face outside of plug-in decoration materials 11 behind four edges.
With reference to Fig. 6, Fig. 7 and Fig. 8, locating framework 4 further includes parallel with located lateral plate 41 and laterally fixed positioned at topmost
The outside of plug-in decoration materials 11 is stretched out in the weather shield 5 of the position top of plate 41, the front end of weather shield 5, and includes the abutted with wall 1
One guide face 51 and turn to the second guide face 52 for being connected with the first guide face 51, wherein the first guide face 51 and wall 1 it
Between filled with the calking agent of filling up gap, the angle of inclination of the first guide face 51 and horizontal plane is 150 °, the second guide face 52
Angle of inclination between the first guide face 51 is similarly 150 °.Weather shield 5 is hollow structure, and setting and the in weather shield 5
The vertical reinforcement plate muscle 53 of one guide face 51,5 both sides of weather shield, which are provided with, closes 5 both sides of weather shield and limits rainwater to both sides
The side shield 54 of outflow, side shield 54 are identical as the spacing of the first guide face 51 and the second guide face 52.
When typhoon is along with very heavy rains, Action of Wind pressure is on plug-in decoration materials 11, and plug-in decoration materials 11 are to buffer gap 24
Place is deformed upon plays buffering effect to installation part 2 and fixing piece 3;Rainwater flows downward along 1 surface of wall to be hindered by weather shield 5
Gear, and flowed downward out along the first guide face 51 and the second guide face 52 of weather shield 5, drop down onto plug-in wall 1 to reduce
The amount of rainfall on surface mitigates the washmarking on 1 surface of plug-in wall.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, people in the art
Member can as needed make the present embodiment the modification of not creative contribution after reading this specification, but as long as at this
It is all protected by Patent Law in the right of invention.
Claims (10)
1. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building, which is characterized in that including perpendicular to wall(1)And it is arranged in array
Several installation parts(2), the installation part(2)Including supplying plug-in decoration materials(11)The bearing plate of setting(22)And it is embedded in advance simultaneously
Bearing plate(22)And wall(1)The first interior fixation steel plate(21), adjacent two bearing plate on vertical direction(22)Between
Distance and plug-in decoration materials(11)Vertical direction height it is identical, the plug-in decoration materials(11)Towards wall(1)The side on surface
Face and wall(1)Surface is formed with buffer gap(24).
2. according to laying and hanging ornamental prefabricated component mounting structure outside a kind of building described in claim 1, which is characterized in that described plug-in
Decoration materials(11)Towards wall(1)There is the inner groovy being recessed inwardly on the surface of side(111).
3. according to laying and hanging ornamental prefabricated component mounting structure outside a kind of building described in claim 1, which is characterized in that the load-bearing
Plate(22)With wall(1)Between be provided with the first ladder platform(23), the plug-in decoration materials(11)Towards wall(1)The surface of side
With the first ladder platform(23)It abuts.
4. according to laying and hanging ornamental prefabricated component mounting structure outside a kind of building described in claim 3, the plug-in decoration materials(11)'s
The setting of four edges is both provided with fixing piece(3), the fixing piece(3)Including perpendicular to wall(1)The cross positioning plate on surface
(32)And it is embedded in cross positioning plate in advance(32)And wall(1)The second interior fixation steel plate(31), the cross positioning plate(32)
With wall(1)Between be provided with the second ladder platform(33), the plug-in decoration materials(11)Towards wall(1)The surface of side and second
Ladder platform(33)It abuts.
5. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 4, which is characterized in that the outer ornament
Material(11)Outside is provided with plug-in decoration materials(11)The locating framework that four edges are limited(4), other than the positioning plate includes
Ornament material(11)Length and width are several located lateral plates that spacing transverse and longitudinal is interlocked(41)With vertical positioning plate(42), the cross is fixed
Position plate(32)Medium position offer first positioning hole(321), the located lateral plate(41)With vertical positioning plate(42)'s
Intersection offers and first positioning hole(321)Corresponding second location hole(43), the first positioning hole(321)With second
Location hole(43)Positioning bolt is worn by locating framework after corresponding connection(4)It is fixed on plug-in decoration materials(11)Outside.
6. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 5, which is characterized in that the positioning bone
Frame(4)Further include being located at and located lateral plate(41)It is parallel and be located at the top located lateral plate(41)The weather shield of top(5),
The weather shield(5)Front end extend to plug-in decoration materials(11)Outside.
7. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 6, which is characterized in that the weather shield
(5)Including with wall(1)First guide face of fitting(51)And with the first guide face(51)Turn to the second connected guide face
(52).
8. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 7, which is characterized in that the weather shield
(5)Including with wall(1)It is bonded and tilts down the first guide face of setting(51)And with the first guide face(51)Turn to phase
The second guide face being arranged diagonally downward together with sample(52).
9. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 8, which is characterized in that described first leads
Stream interface(51)Angle of inclination with horizontal plane and the second guide face(52)With the first guide face(51)Between inclined angle
Consistent is 150 °.
10. a kind of outer laying and hanging ornamental prefabricated component mounting structure of building according to claim 6, which is characterized in that described to keep off the rain
Plate(5)Both sides the side shield that restricted rainwater is flowed out to both sides is set(54).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810103595.1A CN108301586A (en) | 2018-02-01 | 2018-02-01 | A kind of outer laying and hanging ornamental prefabricated component mounting structure of building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810103595.1A CN108301586A (en) | 2018-02-01 | 2018-02-01 | A kind of outer laying and hanging ornamental prefabricated component mounting structure of building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108301586A true CN108301586A (en) | 2018-07-20 |
Family
ID=62850683
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810103595.1A Pending CN108301586A (en) | 2018-02-01 | 2018-02-01 | A kind of outer laying and hanging ornamental prefabricated component mounting structure of building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108301586A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109113239A (en) * | 2018-09-28 | 2019-01-01 | 浙江广安建设有限公司 | A kind of back-bolt type stone curtain wall and its construction method |
CN110173083A (en) * | 2019-06-04 | 2019-08-27 | 上海建工一建集团有限公司 | A kind of stone facing unit and faced wall containing troffer |
CN110173082A (en) * | 2019-06-04 | 2019-08-27 | 上海建工一建集团有限公司 | A kind of modularization stone facing wall and its construction method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000110286A (en) * | 1998-10-05 | 2000-04-18 | Daido Steel Sheet Corp | Connection structure of wall panel, and wall panel execution method |
CN201193371Y (en) * | 2008-03-27 | 2009-02-11 | 珠海兴业幕墙工程有限公司 | Single-cable porefree point supporting glass curtain wall system |
JP2009209597A (en) * | 2008-03-05 | 2009-09-17 | Nittai-Kogyo Co Ltd | Wall material and mounting bracket therefor |
CN102051923A (en) * | 2010-12-07 | 2011-05-11 | 北京城建建设工程有限公司 | Fireproofing retardant cement calcium silicate board insulating wall body and construction method thereof |
CN202081538U (en) * | 2010-12-11 | 2011-12-21 | 上海美特幕墙有限公司 | Glass combined clamp in point connection type glass curtain wall |
CN102733570A (en) * | 2011-03-30 | 2012-10-17 | 金刚T&A有限公司 | Ceramic panel assembly |
KR101211481B1 (en) * | 2012-03-21 | 2012-12-12 | 백승기 | A fixing apparatus of a stone panel which is to be quake-proof |
CN103711280A (en) * | 2014-01-15 | 2014-04-09 | 江苏德一新型建筑材料科技有限公司 | Assembling structure of heat-preservation and decoration integrated board |
CN102900212B (en) * | 2012-10-30 | 2014-07-02 | 广东省第四建筑工程公司 | Construction method for light external-wall heat-insulating decorative plate |
CN205954947U (en) * | 2016-08-24 | 2017-02-15 | 深圳市麦诺幕墙技术有限公司 | Hide drag -line glass clamp |
-
2018
- 2018-02-01 CN CN201810103595.1A patent/CN108301586A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000110286A (en) * | 1998-10-05 | 2000-04-18 | Daido Steel Sheet Corp | Connection structure of wall panel, and wall panel execution method |
JP2009209597A (en) * | 2008-03-05 | 2009-09-17 | Nittai-Kogyo Co Ltd | Wall material and mounting bracket therefor |
CN201193371Y (en) * | 2008-03-27 | 2009-02-11 | 珠海兴业幕墙工程有限公司 | Single-cable porefree point supporting glass curtain wall system |
CN102051923A (en) * | 2010-12-07 | 2011-05-11 | 北京城建建设工程有限公司 | Fireproofing retardant cement calcium silicate board insulating wall body and construction method thereof |
CN202081538U (en) * | 2010-12-11 | 2011-12-21 | 上海美特幕墙有限公司 | Glass combined clamp in point connection type glass curtain wall |
CN102733570A (en) * | 2011-03-30 | 2012-10-17 | 金刚T&A有限公司 | Ceramic panel assembly |
KR101211481B1 (en) * | 2012-03-21 | 2012-12-12 | 백승기 | A fixing apparatus of a stone panel which is to be quake-proof |
CN102900212B (en) * | 2012-10-30 | 2014-07-02 | 广东省第四建筑工程公司 | Construction method for light external-wall heat-insulating decorative plate |
CN103711280A (en) * | 2014-01-15 | 2014-04-09 | 江苏德一新型建筑材料科技有限公司 | Assembling structure of heat-preservation and decoration integrated board |
CN205954947U (en) * | 2016-08-24 | 2017-02-15 | 深圳市麦诺幕墙技术有限公司 | Hide drag -line glass clamp |
Non-Patent Citations (1)
Title |
---|
董博等: "《土木工程施工》", 31 January 2017 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109113239A (en) * | 2018-09-28 | 2019-01-01 | 浙江广安建设有限公司 | A kind of back-bolt type stone curtain wall and its construction method |
CN110173083A (en) * | 2019-06-04 | 2019-08-27 | 上海建工一建集团有限公司 | A kind of stone facing unit and faced wall containing troffer |
CN110173082A (en) * | 2019-06-04 | 2019-08-27 | 上海建工一建集团有限公司 | A kind of modularization stone facing wall and its construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108301586A (en) | A kind of outer laying and hanging ornamental prefabricated component mounting structure of building | |
CN204875847U (en) | Prefabricated assembled retaining wall | |
CN211396175U (en) | Stone curtain wall mounting structure | |
CN208441370U (en) | One kind being used for parapet of roofing flashing GRC decorative panel and its mounting structure | |
CN201137253Y (en) | Roof flat tile | |
CN210857648U (en) | Stone curtain wall moulding | |
CN107859274A (en) | A kind of waterproof skirting | |
CN209568441U (en) | Foundation pit edge protection can be had enough to meet the need | |
CN208396176U (en) | The rain cover structure of steel building | |
CN216586107U (en) | Non-column type bridge | |
CN211572313U (en) | Stair structure with water dripping line | |
CN110173056B (en) | Super-thick reinforced concrete inclined wall structure and construction method | |
CN100357546C (en) | Hollow building block for construction | |
CN206220301U (en) | The partition wall of pre- crack resistence | |
CN205604067U (en) | Bridge plate formula rubber support structure | |
CN205475947U (en) | A abat -vent that is used for formula eaves mouth structure that shields of inorganization drainage to reach including eaves mouth structure | |
CN203113564U (en) | Stone curtain wall | |
CN219218667U (en) | Post-adding type bridge water drop edge structure | |
CN215888565U (en) | Remote cantilever diagonal bracing balcony structure | |
CN213358207U (en) | Multipurpose plate-shaped prefabricated part | |
CN213115243U (en) | Spherical glass curtain wall daylighting roof structure | |
CN214090809U (en) | Anti-sagging drip line with grid cloth | |
CN212295233U (en) | Hanging plate type curtain wall | |
CN109868960A (en) | A kind of plate brick paving structure | |
CN209907778U (en) | Archaize floor railing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180720 |
|
RJ01 | Rejection of invention patent application after publication |