CN108286335A - A kind of construction through-flooring sleeve fixing device and its fixing means - Google Patents
A kind of construction through-flooring sleeve fixing device and its fixing means Download PDFInfo
- Publication number
- CN108286335A CN108286335A CN201810347511.9A CN201810347511A CN108286335A CN 108286335 A CN108286335 A CN 108286335A CN 201810347511 A CN201810347511 A CN 201810347511A CN 108286335 A CN108286335 A CN 108286335A
- Authority
- CN
- China
- Prior art keywords
- flooring
- cylindrical die
- casing
- upper layer
- center
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G15/00—Forms or shutterings for making openings, cavities, slits, or channels
- E04G15/06—Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
Abstract
The invention discloses a kind of construction through-flooring sleeve fixing devices and its fixing means, device to include:One cylindrical die, center positioning hole is equipped at the center of the cylindrical die, the outer diameter of cylindrical die be less than through-flooring casing inner diameter, cylindrical die integrally embed be set to through-flooring inside pipe casing after, the axis co-axial of the axis and through-flooring casing of the center positioning hole;One aciculiform inserted link, the aciculiform inserted link are plugged in center positioning hole;The center positioning hole of the cylindrical die and upper layer through-flooring cannula center point is corresponding;Through-flooring casing is set in fixed between cylindrical die outside cylindrical die.A kind of construction through-flooring sleeve fixing device of the present invention, utilize the central point of determining through-flooring casing, use a kind of through-flooring casing fixing mould with center positioning hole, ensure that the centralized positioning of through-flooring casing is accurate, ensure that through-flooring casing fixation, through-flooring sleeve fixing device may be reused simultaneously.
Description
Technical field
The present invention relates to a kind of construction through-flooring sleeve fixing devices, belong to the realm of building construction.
Background technology
In building construction process, the fixation of through-flooring casing is typically now fixed using steel wire lashing or using wearing mould
Slab muscle nut is fixed.Steel wire lashing fixation is insecure, can generate displacement as reinforcing bar shakes;Wearing template reinforcing bar fixing means needs
The trepanning in template destroys template, and need to go to tighten nut to template lower section, and working efficiency is not high.
Invention content
In view of the above technical problems, the present invention proposes a kind of construction through-flooring sleeve fixing device, can securely consolidate
Determine through-flooring casing, and position it is convenient accurate, it is simple and efficient to handle, destruction will not be generated to template, carry through-flooring casing
Head protector prevents concrete from entering in through-flooring casing, while mold can reuse.
In order to achieve the above technical purposes, the present invention adopts the following technical scheme that:
A kind of construction through-flooring sleeve fixing device, including:
One cylindrical die is equipped with center positioning hole at the axle center of the cylindrical die, and the outer diameter of cylindrical die, which is less than, to be worn
Floor sleeve internal diameter, cylindrical die integrally embed be set to through-flooring inside pipe casing after, the axis of the center positioning hole and
The axis co-axial of through-flooring casing;
One aciculiform inserted link, the aciculiform inserted link is plugged in center positioning hole, and can above and below be moved in center positioning hole
Dynamic, center positioning hole is surrounded by engraved structure;
The fixing device determines upper layer through-flooring set when in use, based on the through-flooring casing for having poured lower-layer concrete floor
The position of pipe;
The bottom of the cylindrical die has anti-displacement glue-line;
Through-flooring casing is set in outside cylindrical die, and by detachable fixing piece by through-flooring casing and cylindrical mould
It is relatively fixed between tool.
The detachable fixing piece is filled in for , at least provided with arranged symmetrically on the outer wall of the cylindrical die upper end
Liang Ge plug angle.
The top of the upper layer through-flooring casing is equipped with a capping, described to cover upper layer through-flooring bobbin seal.
Setting is through the through-hole of cylindrical die at the center of the cylindrical die, be equipped at the center of through-hole it is described in
Heart location hole, center positioning hole are supported by the inner wall of centre bore floor and through-hole and are connected.
The present invention further discloses a kind of fixation side of the construction through-flooring sleeve fixing device described in application
Method, this method comprises the following steps:
Step 1 determines the upper layer fixed position of through-flooring casing based on the through-flooring casing for having poured lower-layer concrete floor, packet
It includes:
The template bottom that through-flooring cannula center point is projected to by laser zenith meter upper layer floor has been installed by lower layer first, then
According to the center position projected below the template of upper layer floor, corresponding center point above the template of upper layer floor is determined
It sets, and line mark of crossing at the template upper surface center position of upper layer floor;
Then cylindrical die integrated hanging is moved to the top of upper layer floor, slowly move the position of cylindrical die, is led to
Whether the engraved structure observation aciculiform inserted link and the cross hairs mark for crossing center positioning hole surrounding are aligned;
After step 2, alignment, anti-displacement glue-line is pasted in the bottom of cylindrical die, then slowly by cylindrical die along vertical
Direction declines, until template contacts and fixation that the bottom of cylindrical die passes through anti-displacement glue-line and upper layer floor;
Upper layer through-flooring casing is set in outside cylindrical die by step 3, by detachable fixing piece by through-flooring casing
It is relatively fixed between cylindrical die;
Step 4 fills glass cement at the template contacts of through-flooring casing and upper layer floor, prevents cement mortar from injecting through-flooring set
In pipe.
In step 1, when the template that through-flooring cannula center point is projected to upper layer floor has been installed by laser zenith meter by lower layer
Behind bottom, saturating, line of crossing at nail hole is followed closely into incident point with wire nail.
In step 2, the anti-displacement glue-line is the shape double-sided adhesive offset plate consistent with cylindrical die base profile.
Advantageous effect:
Using a kind of construction through-flooring sleeve fixing device of the present invention, template reinforcing bar spiral shell is fixed and worn relative to steel wire lashing
Female fixed method, has following advantageous effect:
The first, speed of application is fast, efficient.
The second, accurate positioning, firm position.
Third can reuse, and not damage template, material-saving environmental.
4th, easy construction does not need other tools.
Description of the drawings
Fig. 1 is a kind of structural schematic diagram of construction through-flooring sleeve fixing device of the present invention;
Fig. 2 is the vertical view of Fig. 1;
Fig. 3 is aciculiform hinge pedestal structure schematic diagram;
Fig. 4 is closure construction schematic diagram;
Fig. 5 is Fig. 4 side views;
6 Wei of figure plug structure schematic diagram;
Wherein, 1 is through-flooring casing;2 be cylindrical die;Peep hole centered on 3;Hole floor centered on 4;5 Wei plug angle;
6 be double-glue bat;7 be concrete blinding;8 be aciculiform inserted link;9 be capping;10 Wei plug.
Specific implementation mode
With reference to the accompanying drawings of the specification and specific embodiment is described in further detail technical scheme of the present invention.
As shown in Fig. 1 ~ Fig. 6, a kind of construction through-flooring sleeve fixing device of the present invention, including:
One cylindrical die is equipped with center positioning hole at the center of the cylindrical die, and the outer diameter of cylindrical die, which is less than, to be worn
Floor sleeve internal diameter, cylindrical die integrally embed be set to through-flooring inside pipe casing after, the axis of the center positioning hole and
The axis co-axial of through-flooring casing;
One aciculiform inserted link, the aciculiform inserted link are plugged in center positioning hole;
The fixing device determines upper layer through-flooring set when in use, based on the through-flooring casing for having poured lower-layer concrete floor
Fixed position is managed, by the aciculiform inserted link by the center positioning hole of the cylindrical die and casting concrete floor
Through-flooring cannula center is corresponding;
The bottom of the cylindrical die has anti-skidding bed course;
Through-flooring casing is set in outside cylindrical die, by detachable fixing piece by through-flooring casing and cylindrical die
Between it is fixed.
In the present embodiment, cylindrical die, outer diameter is less than through-flooring casing inner diameter 2mm, passes through double faced adhesive tape mode and building
Layer concrete template bond, the through-flooring casing of engineering is then coated at mold, cylindrical die ontology is fixed, pass through by
Jian cylindrical die and through-flooring casing stopper close, ensure that outer through-flooring casing is fixed from face.
As the further preferred scheme of technical solution of the present invention, cylindrical die center sets center positioning hole, uses one
Root is directed at determining through-flooring cannula center point with the aciculiform inserted link that the aperture of center positioning hole is adapted, it is ensured that upper layer through-flooring
Casing accurate positioning.
As the further preferred scheme of technical solution of the present invention, center positioning hole surrounding does hollow design, convenient for observation
Whether aciculiform inserted link is directed at through-flooring cannula center point.
As the further preferred scheme of technical solution of the present invention, the height of cylindrical die is debugged less than through-flooring casing
10mm, through-flooring sleeve kit capping, prevents concrete from entering in through-flooring casing and mold.
As the further preferred scheme of technical solution of the present invention, the detachable fixing piece Wei plug, cylindrical mould
Have and fill in angle at least provided with symmetrically arranged two on the outer wall of upper end, is just filled in .
As the further preferred scheme of technical solution of the present invention, the anti-skidding bed course is to be arranged at the bottom of cylindrical die
The viscose glue bed course in portion.In the present embodiment, the viscose glue bed course is double-glue bat.
A kind of fixing means using heretofore described construction through-flooring sleeve fixing device, this method include
Following steps:
Step 1 determines the upper layer fixed position of through-flooring casing based on the through-flooring casing for having poured lower-layer concrete floor, packet
It includes:
The template bottom that through-flooring cannula center point is projected to by laser zenith meter upper layer floor has been installed by lower layer first, then
According to the center position projected below the template of upper layer floor, corresponding center point above the template of upper layer floor is determined
It sets, and line mark of crossing at the center position described in the template upper surface of upper layer floor;
Then cylindrical die integrated hanging is moved to the top of upper layer floor, slowly move the position of cylindrical die, is led to
Whether the engraved structure observation aciculiform inserted link and the cross hairs mark for crossing center positioning hole surrounding are aligned;
After step 2, alignment, anti-displacement glue-line is pasted in the bottom of cylindrical die, then slowly by cylindrical die along vertical
Direction declines, until the bottom of cylindrical die and template contacts and the fixation of upper layer floor, determine cylindrical die bottom and
It is contacted between the template upper surface of upper layer floor secured;
Through-flooring casing is set in outside cylindrical die by step 3, by detachable fixing piece by through-flooring casing and circle
It is fixed between cylindrical mold;
Step 4 is filled at template contacts of the through-flooring casing with upper layer floor with glass cement, prevents cement mortar from injecting through-flooring
In casing.
As the further preferred of the method for the present invention technical solution, in step 1, lower layer installed when laser zenith meter and has been worn
After floor sleeve central point is projected to the template bottom of upper layer floor, incident point wire nail is followed closely thoroughly, and then determine upper layer floor
Template above corresponding center position.
As the further preferred of the method for the present invention technical solution, in step 2, the anti-displacement glue-line is shape and cylinder
The consistent double-sided adhesive offset plate of shape mold bottom shape.
Claims (7)
1. a kind of construction through-flooring sleeve fixing device, which is characterized in that including:
One cylindrical die is equipped with center positioning hole at the axle center of the cylindrical die, and the outer diameter of cylindrical die, which is less than, to be worn
Floor sleeve internal diameter, cylindrical die integrally embed be set to through-flooring inside pipe casing after, the axis of the center positioning hole and
The axis co-axial of through-flooring casing;
One aciculiform inserted link, the aciculiform inserted link is plugged in center positioning hole, and can above and below be moved in center positioning hole
Dynamic, center positioning hole is surrounded by engraved structure;
The fixing device determines upper layer through-flooring set when in use, based on the through-flooring casing for having poured lower-layer concrete floor
The position of pipe;
The bottom of the cylindrical die has anti-displacement glue-line;
Through-flooring casing is set in outside cylindrical die, and by detachable fixing piece by through-flooring casing and cylindrical mould
It is relatively fixed between tool.
2. construction through-flooring sleeve fixing device according to claim 1, which is characterized in that described detachable solid
Determine part to fill in for , fills in angle at least provided with symmetrically arranged two on the outer wall of the cylindrical die upper end.
3. construction through-flooring sleeve fixing device according to claim 1, which is characterized in that the upper layer through-flooring
The top of casing is equipped with a capping, described to cover upper layer through-flooring bobbin seal.
4. construction through-flooring sleeve fixing device according to claim 1, which is characterized in that the cylindrical die
Center at setting through the through-hole of cylindrical die, the center positioning hole is equipped at the center of through-hole, center positioning hole is logical
The inner wall support for crossing centre bore floor and through-hole connects.
5. a kind of fixing means using construction through-flooring sleeve fixing device described in claim 1, which is characterized in that
This method comprises the following steps:
Step 1 determines the upper layer fixed position of through-flooring casing based on the through-flooring casing for having poured lower-layer concrete floor, packet
It includes:
The template bottom that through-flooring cannula center point is projected to by laser zenith meter upper layer floor has been installed by lower layer first, then
According to the center position projected below the template of upper layer floor, corresponding center point above the template of upper layer floor is determined
It sets, and line mark of crossing at the template upper surface center position of upper layer floor;
Then cylindrical die integrated hanging is moved to the top of upper layer floor, slowly move the position of cylindrical die, is led to
Whether the engraved structure observation aciculiform inserted link and the cross hairs mark for crossing center positioning hole surrounding are aligned;
After step 2, alignment, anti-displacement glue-line is pasted in the bottom of cylindrical die, then slowly by cylindrical die along vertical
Direction declines, until template contacts and fixation that the bottom of cylindrical die passes through anti-displacement glue-line and upper layer floor;
Upper layer through-flooring casing is set in outside cylindrical die by step 3, by detachable fixing piece by through-flooring casing
It is relatively fixed between cylindrical die;
Step 4 fills glass cement at the template contacts of through-flooring casing and upper layer floor, prevents cement mortar from injecting through-flooring set
In pipe.
6. the fixing means of construction through-flooring sleeve fixing device according to claim 5, which is characterized in that step
In 1, after through-flooring cannula center point has been installed by laser zenith meter by lower layer is projected to the template bottom of upper layer floor, it will project
Point follows closely saturating, line of crossing at nail hole with wire nail.
7. the fixing means of construction through-flooring sleeve fixing device according to claim 6, which is characterized in that step
In 2, the anti-displacement glue-line is the shape double-sided adhesive offset plate consistent with cylindrical die base profile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810347511.9A CN108286335B (en) | 2018-04-18 | 2018-04-18 | Building construction floor penetrating sleeve fixing device and fixing method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810347511.9A CN108286335B (en) | 2018-04-18 | 2018-04-18 | Building construction floor penetrating sleeve fixing device and fixing method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108286335A true CN108286335A (en) | 2018-07-17 |
CN108286335B CN108286335B (en) | 2023-09-01 |
Family
ID=62834647
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810347511.9A Active CN108286335B (en) | 2018-04-18 | 2018-04-18 | Building construction floor penetrating sleeve fixing device and fixing method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108286335B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309369A (en) * | 2021-06-29 | 2021-08-27 | 方泽华 | Accurate positioning and mounting method for building structure embedded sleeve and sleeve assembly component |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202055529U (en) * | 2011-04-07 | 2011-11-30 | 刘开阳 | Pipe standing device capable of completing pouring sleeves of water supply pipe and sewer pipe in one step in building construction |
CN204691282U (en) * | 2015-05-20 | 2015-10-07 | 河南六建建筑集团有限公司 | A kind of locating wedge |
CN204983657U (en) * | 2015-09-17 | 2016-01-20 | 湖南六建机电安装有限责任公司 | Floor buried sleeve positioner |
CN205917944U (en) * | 2016-06-28 | 2017-02-01 | 苏州东宇建设发展有限公司 | Floor buried sleeve positioner |
CN206189855U (en) * | 2016-11-21 | 2017-05-24 | 青岛东捷建设工程有限公司 | Reserve continuous auxiliary positioning device in entrance to a cave between concrete floor |
CN208310215U (en) * | 2018-04-18 | 2019-01-01 | 中建八局第三建设有限公司 | A kind of construction through-flooring sleeve fixing device |
-
2018
- 2018-04-18 CN CN201810347511.9A patent/CN108286335B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202055529U (en) * | 2011-04-07 | 2011-11-30 | 刘开阳 | Pipe standing device capable of completing pouring sleeves of water supply pipe and sewer pipe in one step in building construction |
CN204691282U (en) * | 2015-05-20 | 2015-10-07 | 河南六建建筑集团有限公司 | A kind of locating wedge |
CN204983657U (en) * | 2015-09-17 | 2016-01-20 | 湖南六建机电安装有限责任公司 | Floor buried sleeve positioner |
CN205917944U (en) * | 2016-06-28 | 2017-02-01 | 苏州东宇建设发展有限公司 | Floor buried sleeve positioner |
CN206189855U (en) * | 2016-11-21 | 2017-05-24 | 青岛东捷建设工程有限公司 | Reserve continuous auxiliary positioning device in entrance to a cave between concrete floor |
CN208310215U (en) * | 2018-04-18 | 2019-01-01 | 中建八局第三建设有限公司 | A kind of construction through-flooring sleeve fixing device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309369A (en) * | 2021-06-29 | 2021-08-27 | 方泽华 | Accurate positioning and mounting method for building structure embedded sleeve and sleeve assembly component |
Also Published As
Publication number | Publication date |
---|---|
CN108286335B (en) | 2023-09-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104018422A (en) | Wet joint structure for prefabrication and splicing of joint part between bridge pier column and cover beam | |
CN203878461U (en) | Wet joint structure for prefabricating and splicing connecting portion between pier stand column and cover beam | |
CN110185199A (en) | A kind of half grouting connection sleeve of the automatic deviation correction for prefabricated post wall | |
CN108286335A (en) | A kind of construction through-flooring sleeve fixing device and its fixing means | |
CN203569487U (en) | Embedded part for installation of bridge pier hanging basket | |
CN208310215U (en) | A kind of construction through-flooring sleeve fixing device | |
CN208966022U (en) | A kind of template poured for large-scale beam column | |
CN205857238U (en) | A kind of underground engineering steel pipe column pilework | |
CN205662838U (en) | Prestressing force joint construction of pier is assembled to prefabricated segment | |
CN204098489U (en) | A kind of mould making concrete floorslab preformed hole | |
CN207549035U (en) | A kind of precast beam molding die | |
CN106522545B (en) | A kind of self-unloading is adjustable Screw arbor with nut at both-ends device and its assembly and disassembly methods | |
CN206397154U (en) | The dismounting device of the outer eaves mould of complicated concrete | |
CN104314179A (en) | Anti-shear stud for GFRP concrete combined member and construction method thereof | |
CN107806243A (en) | A kind of fixed structure of the pre-buried line box of aluminum alloy mould plate | |
CN211114435U (en) | A half grout connecting sleeve of automatic rectifying for prefabricated post wall | |
CN206221170U (en) | Concrete towers cartridge module | |
CN206607753U (en) | After pour beam steel anchor | |
CN207568181U (en) | A kind of fixed structure of the pre-buried wire box of aluminum alloy mould plate | |
CN207453121U (en) | A kind of hydraulic structure flow-passing surface pre-embedded anchoring bolts | |
CN207003245U (en) | A kind of bridge fence-slab fixing device | |
CN206233111U (en) | A kind of two-way horn mouth anchorage | |
CN205840329U (en) | A kind of novel pipeline reserves sleeve pipe | |
CN206308907U (en) | A kind of anchor reserved for reinforcing bar | |
CN206110537U (en) | Cement mortar stair angle steel external corner angle bead device of marking time |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |