CN108284210A - The method for improving continuous casting production quick change success rate - Google Patents

The method for improving continuous casting production quick change success rate Download PDF

Info

Publication number
CN108284210A
CN108284210A CN201710860081.6A CN201710860081A CN108284210A CN 108284210 A CN108284210 A CN 108284210A CN 201710860081 A CN201710860081 A CN 201710860081A CN 108284210 A CN108284210 A CN 108284210A
Authority
CN
China
Prior art keywords
tundish
spare
continuous casting
molten steel
quick change
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710860081.6A
Other languages
Chinese (zh)
Inventor
卜志胜
徐栋
郭庆华
陈刚
汤新彦
郭鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xinjiang Bayi Iron and Steel Co Ltd
Original Assignee
Xinjiang Bayi Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xinjiang Bayi Iron and Steel Co Ltd filed Critical Xinjiang Bayi Iron and Steel Co Ltd
Priority to CN201710860081.6A priority Critical patent/CN108284210A/en
Publication of CN108284210A publication Critical patent/CN108284210A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/16Controlling or regulating processes or operations
    • B22D11/18Controlling or regulating processes or operations for pouring
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D11/00Continuous casting of metals, i.e. casting in indefinite lengths
    • B22D11/10Supplying or treating molten metal
    • B22D11/11Treating the molten metal
    • B22D11/111Treating the molten metal by using protecting powders

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Continuous Casting (AREA)

Abstract

The invention discloses a kind of methods improving continuous casting production quick change success rate, have the following steps:(1) the ladle stand-by period for filling with molten steel is 5 10min, and it is 1,590 1600 °C that ladle, which reaches continuous casting platform temperature,;(2) work Metal in Tundish pulling rate dropped one grade every 20 seconds, and 8min is interior to be down to 0.3m/min by conticaster pulling rate;(3) work tundish liquid level is measured to start spare tundish car simultaneously to the other side with the work tundish car poured into a mould when work tundish stops pouring;(4) after spare tundish car reaches cast position, Fast Installation red heat submersed nozzle;(5) after spare tundish car is ready, after pouring into a mould 10 tons of molten steel, 150 200kg covertures are added to spare tundish;(6) when ladle is to 20 tons of molten steel of spare basket pouring, molten steel is injected into crystallizer;(7) spare centre is unwrapped pour after, carry out conticaster pulling rate driveaway operation.The present invention shortens the continuous casting production quick change time, improves continuous casting production quick change success rate, improves conticaster operating rate, reduces production cost, reduces the labor intensity of worker.

Description

The method for improving continuous casting production quick change success rate
Technical field
The invention belongs to steel-making continuous casting technical field, especially a kind of method improving continuous casting production quick change success rate.
Background technology
Conticaster is in order to reduce cost and improve operating rate, when tundish reaches service life, needs to carry out intermediate Packet quick change operates, and in tundish quick change, Casting speed is off, and strand remains in spray and constantly continues the state of cooling, If middle packet quick change overlong time, most probably since slab cooling is excessive, so that strand is hardened and cause stagnant base, make production disruption, very It may extremely cause to freeze base accident.At present there is tundish quick change and operate in steel plant continuous casting machine in process of production, but for The control range of each operation does not do specific description.
Invention content
The purpose of the present invention is to provide a kind of method improving continuous casting production quick change success rate, the present invention can shorten The continuous casting production quick change time improves continuous casting production quick change success rate, improves conticaster operating rate, reduces production cost, drop The labor intensity of low worker.
The object of the present invention is achieved like this:A method of improving continuous casting production quick change success rate, characterized in that It has the following steps:
(1) during quick change continuous casting production, the ladle stand-by period for filling with molten steel is 5-10min, and ladle reaches continuous casting Platform temperature is 1590-1600 °C;
(2) work Metal in Tundish pulling rate dropped one grade every 20 seconds, and conticaster pulling rate is down to 0.3m/min in 8min;
(3) work tundish liquid level is measured to start equipped with the standby of spare tundish when liquid level is in 300-500mm in packet Prepare region with tundish car to heat exchange, at work between packet when stopping pouring, by spare tundish car and the work poured into a mould Tundish car starts simultaneously to the other side;
(4) after spare tundish car reaches cast position, when Fast Installation red heat submersed nozzle, wherein submersed nozzle roasting Between >=2h;Spare tundish car position is adjusted, submersed nozzle is made to be in crystallizer centre position, after being packed into blind plate, adjustment is standby With tundish car height, make submersed nozzle bottom away from crystallizer 150-180mm suitable for reading;
(5) after spare tundish car is ready, ladle is opened, and after pouring into a mould 10 tons of molten steel, 150- is added to spare tundish 200kg covertures, measurement, which is opened, pours 1550 °C of tundish temperature >;
(6) when ladle is to 20 tons of molten steel of spare basket pouring, spare tundish start will to wrap in molten steel injection crystallizer;
(7) spare centre is unwrapped pour after, seedling-growing time control is in 80-120S, when molten steel is reached away from submersed nozzle in crystallizer Bottom 115-125mm carries out conticaster pulling rate driveaway operation, and pulling rate is 0.3m/min after starting, and 0.3m/min pulling rates are kept 1min, then pulling rate increase to normal value 0.9m/min, stop being poured onto spare centre from work tundish and unwrap and pour, draw to crystallizer Speed starting, time control is in 4-5min.
Blind plate is on the slideway of spare tundish car quick-changing mechanism.
Coverture is carbon-free covering agent, and ingredient is with SiO2Based on.
The present invention is directed to steel mill sheet billet continuous casting, pulling rate when tundish quick change, make strand receive spray constantly continue it is cold But, it causes slab cooling to be excessively hardened, causes the production problem of stagnant base, the tundish quick change method provided is improved and changed into soon The operating rate of power and conticaster, reduces hand labor intensity, and positive exemplary role is played for the energy-saving of enterprise. Shorten the tundish quick change time as far as possible, strand is avoided to cause sub-cooled that stagnant base phenomenon occurs since cooling time is long, it is evident Aobvious technological progress.
The principle of the present invention is that control molten steel is standby to be wrapped the time and reach continuous casting platform temperature by coordinating molten steel rhythm, Control prompt drop time and control tundish liquid level;Spare middle packet is started to cast position, before tundish stops pouring, in spare Between wrap and started simultaneously in opposite directions with the work tundish just poured into a mould, spare tundish reaches Fast Installation submersed nozzle behind cast position And centering, notify big unwrap to pour after being packed into blind plate;The spare centre for stopping being poured onto replacement from work tundish unwraps and pours pulling rate, when total Between control within 5-6min.
The present invention is suitable for same type conticaster, and the method that can improve conticaster heat exchange success rate keeps tundish hot Swap time controlled within 5-6 minutes, reduced cost, improved operating rate.
Present invention reduces the continuous casting production quick change times, improve continuous casting production quick change success rate, improve continuous casting Machine operation rate, reduces production cost, reduces the labor intensity of worker.
Specific implementation mode
The technical solution further illustrated the present invention below by specific implementation mode
Embodiment 1:
It is a kind of improve continuous casting production quick change success rate method include the following steps:
Step 1:During quick change continuous casting production, molten steel ladle stand-by period 5-10min is filled with, it is flat that ladle reaches continuous casting 1590-1600 DEG C of platform temperature;
Step 2:The Metal in Tundish pulling rate that works dropped one grade every 20 seconds, and conticaster pulling rate is down to 0.3m/min in 8min;
Step 3:Work tundish liquid level is measured, when the tundish liquid level that works is in 400mm, spare tundish car is started and arrives Heat exchange prepares region, at work between packet when stopping pouring, by spare tundish car and the work tundish car poured into a mould to another It starts simultaneously side;
Step 4:After spare tundish car reaches cast position, Fast Installation red heat submersed nozzle, wherein submersed nozzle dry Roasting time >=2h;Spare tundish car position is adjusted, submersed nozzle is made to be in crystallizer centre position, after being packed into blind plate, is adjusted It reorganizes and outfit with tundish car height, ensures submersed nozzle bottom away from crystallizer 170mm suitable for reading;
Step 5:After spare tundish car is ready, ladle is opened, and after pouring into a mould 10 tons of molten steel, 150- is added to tundish 200kg covertures, it is 1560 DEG C that measurement, which opens and pours tundish temperature,;
Step 6:When 20 ton hour of steel ladle pouring, spare tundish proceeds by cast, and spare Metal in Tundish is injected crystallizer;
Step 7:Centre is unwrapped pour after, seedling-growing time control is in 90-100s, when molten steel is reached away from submersed nozzle in crystallizer Bottom 115-125mm, i.e. molten steel did not had submersed nozzle, carried out pulling rate driveaway operation, and pulling rate is 0.3m/min after starting, 0.3m/min pulling rates keep 1min, and then pulling rate adds to normal value 0.9m/min;Stop being poured onto spare tundish from work tundish Starting, time control is in 4-5min.

Claims (3)

1. a kind of method improving continuous casting production quick change success rate, characterized in that have the following steps:
(1) during quick change continuous casting production, the ladle stand-by period for filling with molten steel is 5-10min, and ladle reaches continuous casting Platform temperature is 1590-1600 °C;
(2) work Metal in Tundish pulling rate dropped one grade every 20 seconds, and conticaster pulling rate is down to 0.3m/min in 8min;
(3) work tundish liquid level is measured to start equipped with the standby of spare tundish when liquid level is in 300-500mm in packet Prepare region with tundish car to heat exchange, at work between packet when stopping pouring, by spare tundish car and the work poured into a mould Tundish car starts simultaneously to the other side;
(4) after spare tundish car reaches cast position, when Fast Installation red heat submersed nozzle, wherein submersed nozzle roasting Between >=2h;Spare tundish car position is adjusted, submersed nozzle is made to be in crystallizer centre position, after being packed into blind plate, adjustment is standby With tundish car height, make submersed nozzle bottom away from crystallizer 150-180mm suitable for reading;
(5) after spare tundish car is ready, ladle is opened, and after pouring into a mould 10 tons of molten steel, 150- is added to spare tundish 200kg covertures, measurement, which is opened, pours 1550 °C of tundish temperature >;
(6) when ladle is to 20 tons of molten steel of spare basket pouring, spare tundish start will to wrap in molten steel injection crystallizer;
(7) spare centre is unwrapped pour after, seedling-growing time control is in 80-120S, when molten steel is reached away from submersed nozzle in crystallizer Bottom 115-125mm carries out conticaster pulling rate driveaway operation, and pulling rate is 0.3m/min after starting, and 0.3m/min pulling rates are kept 1min, then pulling rate increase to normal value 0.9m/min, stop being poured onto spare centre from work tundish and unwrap and pour, draw to crystallizer Speed starting, time control is in 4-5min.
2. the method according to claim 1 for improving continuous casting production quick change success rate, it is characterized in that:Blind plate is mounted in spare On the slideway of tundish car quick-changing mechanism.
3. the method according to claim 1 for improving continuous casting production quick change success rate, it is characterized in that:Coverture is carbon-free Coverture, ingredient is with SiO2Based on.
CN201710860081.6A 2017-09-21 2017-09-21 The method for improving continuous casting production quick change success rate Pending CN108284210A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710860081.6A CN108284210A (en) 2017-09-21 2017-09-21 The method for improving continuous casting production quick change success rate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710860081.6A CN108284210A (en) 2017-09-21 2017-09-21 The method for improving continuous casting production quick change success rate

Publications (1)

Publication Number Publication Date
CN108284210A true CN108284210A (en) 2018-07-17

Family

ID=62831684

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710860081.6A Pending CN108284210A (en) 2017-09-21 2017-09-21 The method for improving continuous casting production quick change success rate

Country Status (1)

Country Link
CN (1) CN108284210A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108817341A (en) * 2018-07-18 2018-11-16 中天钢铁集团有限公司 Conticaster reduces the method that pulling rate improves quick change success rate
CN109894587A (en) * 2019-04-03 2019-06-18 南京钢铁股份有限公司 A kind of generous specification slab CC tundish docking production technology
CN110640107A (en) * 2019-10-17 2020-01-03 山东钢铁集团日照有限公司 Method for preventing blank shell from shrinking during quick changing of tundish of continuous casting machine
CN110653349A (en) * 2019-07-31 2020-01-07 广东韶钢松山股份有限公司 One-key type quick ladle connecting device for tundish of continuous casting machine and using method
CN111112565A (en) * 2020-01-15 2020-05-08 首钢京唐钢铁联合有限责任公司 Method for quickly replacing peritectic steel tundish
CN112191837A (en) * 2020-10-12 2021-01-08 马鞍山钢铁股份有限公司 Control method for slab continuous casting silicon steel quick-change tundish process
CN112823966A (en) * 2019-11-20 2021-05-21 上海梅山钢铁股份有限公司 Method for quickly and automatically replacing continuous casting tundish
CN113579184A (en) * 2021-07-28 2021-11-02 北京首钢股份有限公司 Slab tundish casting method and device
CN114406223A (en) * 2022-01-29 2022-04-29 新疆八一钢铁股份有限公司 Method for replacing tundish of iron and steel enterprise without shutdown in continuous casting
CN114472835A (en) * 2022-01-28 2022-05-13 新疆八一钢铁股份有限公司 Heat exchange operation method for wide and thick plate blank continuous casting tundish

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006150428A (en) * 2004-11-30 2006-06-15 Kobe Steel Ltd Consecutive continuous casting method for steels different in kind
CN103464699A (en) * 2013-08-13 2013-12-25 新疆八一钢铁股份有限公司 Method for increasing success rate of heat exchange of continuous casting machine tundish
CN105987598A (en) * 2015-01-29 2016-10-05 边仁杰 Regenerative furnace pump

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006150428A (en) * 2004-11-30 2006-06-15 Kobe Steel Ltd Consecutive continuous casting method for steels different in kind
CN103464699A (en) * 2013-08-13 2013-12-25 新疆八一钢铁股份有限公司 Method for increasing success rate of heat exchange of continuous casting machine tundish
CN105987598A (en) * 2015-01-29 2016-10-05 边仁杰 Regenerative furnace pump

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108817341A (en) * 2018-07-18 2018-11-16 中天钢铁集团有限公司 Conticaster reduces the method that pulling rate improves quick change success rate
CN109894587A (en) * 2019-04-03 2019-06-18 南京钢铁股份有限公司 A kind of generous specification slab CC tundish docking production technology
CN110653349A (en) * 2019-07-31 2020-01-07 广东韶钢松山股份有限公司 One-key type quick ladle connecting device for tundish of continuous casting machine and using method
CN110640107A (en) * 2019-10-17 2020-01-03 山东钢铁集团日照有限公司 Method for preventing blank shell from shrinking during quick changing of tundish of continuous casting machine
CN110640107B (en) * 2019-10-17 2021-06-01 山东钢铁集团日照有限公司 Method for preventing blank shell from shrinking during quick changing of tundish of continuous casting machine
CN112823966A (en) * 2019-11-20 2021-05-21 上海梅山钢铁股份有限公司 Method for quickly and automatically replacing continuous casting tundish
CN111112565A (en) * 2020-01-15 2020-05-08 首钢京唐钢铁联合有限责任公司 Method for quickly replacing peritectic steel tundish
CN111112565B (en) * 2020-01-15 2021-11-05 首钢京唐钢铁联合有限责任公司 Method for quickly replacing peritectic steel tundish
CN112191837A (en) * 2020-10-12 2021-01-08 马鞍山钢铁股份有限公司 Control method for slab continuous casting silicon steel quick-change tundish process
CN113579184A (en) * 2021-07-28 2021-11-02 北京首钢股份有限公司 Slab tundish casting method and device
CN114472835A (en) * 2022-01-28 2022-05-13 新疆八一钢铁股份有限公司 Heat exchange operation method for wide and thick plate blank continuous casting tundish
CN114406223A (en) * 2022-01-29 2022-04-29 新疆八一钢铁股份有限公司 Method for replacing tundish of iron and steel enterprise without shutdown in continuous casting

Similar Documents

Publication Publication Date Title
CN108284210A (en) The method for improving continuous casting production quick change success rate
CA2742889C (en) Method and device for casting a cast part from a metal melt
CN103464699B (en) A kind of method improving continuous casting tundish heat exchange success rate
WO2007048250A8 (en) Homogenization and heat-treatment of cast metals
CN107649657A (en) A kind of small billet tundish stops the method poured
EP3821998A1 (en) Cored wire for reducing degree of superheat of molten steel and use method thereof
CN104259413A (en) Continuous casting system and process producing large-specification elliptical billets
CN102166632B (en) Casting method of large-scale steel ingot
CN109420747B (en) High-yield automatic capping process for slab caster
CN110064741A (en) Continuous cast crystallizer number lift technique in steel-making continuous casting
CN106363149B (en) Steel-making continuous casting molten steel process temperature kinetic-control system and control method
CN114619008A (en) Method for continuously casting and quickly changing tundish of continuous casting machine
CN102161080A (en) Manufacturing tool of high-compact wide and thick plate blank for wide and thick plate rolling mill and method
CN202762983U (en) Efficient production tool of wide and thick slabs for wide and thick plate rolling mill
CN103160635B (en) Process for producing die steel by utilizing converter continuous casting mode
CN104439147A (en) Method for treating casting contraction cavities
CN204209084U (en) A kind of continuous casting system producing the oval base of large gauge
CN106493313A (en) One Albatra metal floating pouring procedure
KR100241404B1 (en) Method and device for control of tundish nozzle
CN201940550U (en) Manufacturing tooling of high density, wide and thick plate blank for wide and heavy plate mill
KR100406380B1 (en) Method For Manufacturing Strip Using Strip Caster
CN107326258B (en) A kind of following minor diameter Ductile iron bar of diameter 25mm and preparation method thereof
CN110947923A (en) Quick change process for special-shaped blank continuous casting tundish below 600kg/m
CN215966207U (en) Metal ingot surface accelerated solidification device
CN117696853A (en) Method for realizing rapid casting by replacing tundish

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180717