CN108277909A - A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique - Google Patents

A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique Download PDF

Info

Publication number
CN108277909A
CN108277909A CN201710006680.1A CN201710006680A CN108277909A CN 108277909 A CN108277909 A CN 108277909A CN 201710006680 A CN201710006680 A CN 201710006680A CN 108277909 A CN108277909 A CN 108277909A
Authority
CN
China
Prior art keywords
concrete
self
formwork
pours
compacting concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710006680.1A
Other languages
Chinese (zh)
Inventor
王涛
隋群
邵云波
彭军
刘日伍
解华
李凤龙
吕海亮
王锡强
郑学高
韩晓娜
赵功江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Original Assignee
Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs filed Critical Energy-Saving Building Material Device Fabrication Co Ltd Is Led In Yantai Political Affairs
Priority to CN201710006680.1A priority Critical patent/CN108277909A/en
Publication of CN108277909A publication Critical patent/CN108277909A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/246Safety or protective measures preventing damage to building parts or finishing work during construction specially adapted for curing concrete in situ, e.g. by covering it with protective sheets
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/84Walls made by casting, pouring, or tamping in situ
    • E04B2/86Walls made by casting, pouring, or tamping in situ made in permanent forms
    • E04B2002/8682Mixed technique using permanent and reusable forms

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a kind of modified cement polyphenyl mould case lattice type concrete walls to pour self-compacting concrete technique, and feature includes the following steps:Pour self-compacting concrete preparatory process, pour self-compacting concrete pour process, pour self-compacting concrete cleaning sampling process, pour self-compacting concrete maintenance process, it is mounted on the inside of concrete blinding when plate formwork concrete structure construction, it is poured together with structural concrete, the present invention realizes that construction cost is low, speed of application is fast, the good feature of overall performance.

Description

A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete Technique
Technical field
The present invention relates to formwork construction process fields, are exactly a kind of modified cement polyphenyl formwork lattice concrete Wall pours self-compacting concrete technique.
Background technology
Modified cement polyphenyl mould case lattice type concrete wall is a kind of light set, moisturizing, fire prevention, sound insulation, load-bearing, resists The multi-functional completely new energy conservation and environmental protection composite building wall construction material in one such as shake, can be used for multilayer residential houses, can use In load-bearing, non-bearing heat-preserving wall.In the prior art, in a kind of module walls of CN201410001972 self-compacting concrete company The technical issues of continuous casting method, solution is to complete structure to one-time continuous after the installation for completing construction module wall is in place The self-compacting concrete of module wall is poured into a mould, the construction method of CN 103993696A wall blocks and wall and wall, is solved The technical issues of be construction procedure complexity, installing and dismounting inside and outside wall template operation trouble pours complex procedures, inefficiency, In the prior art, there is no the wall body structure fire safety problems solved truly, that is to say, that these are poured, and wall is practical to be reached Less than the requirement of fireproof fire endurance, excessive height is generally poured, one-time-concreting is porous, and two-step pouring time interval is long, In casting process, formwork is easy to loosen, and influences construction efficiency.
Invention content
Pour that wall is practical to be not achieved wanting for fireproof fire endurance the technical problem to be solved by the present invention is to the prior art It asks, pours self-compacting concrete and pour in process, generally pour excessive height, one-time-concreting is porous, two-step pouring time interval It is long, lack additional reinforcement part.
In order to solve the above technical problems, the present invention uses following technological means:
A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique, and feature includes following step Suddenly:
1)Pour self-compacting concrete preparatory process:Formwork core bore is clear and coherent, is cleaned out in hole, is installed with that electrical, hot-water heating is pre-buried Pipeline and built-in fitting, hole, collar tie beam, constructional column, the non-standard formwork installed at door-window opening, need to fix and filling-foam glue is close Envelope;
2)It pours self-compacting concrete and pours process:First pour cement bonded sand identical with core bore self-compacting concrete strength grade Slurry;Core bore concreting height should not exceed 0.9m, and two holes of the appropriate to the occasion primary movement of casting concrete every time, and should be along wall Long connection pours, and intermittent time of two-step pouring must not exceed the concrete initial set time, when concreting should take drill rod into Pedestrian's work plugs and pounds, and each vertical core bore will plug and pound one by one, until core bore inner concrete holds one's breath bubble, connected core bore inner concrete Until surface does not decline;
3)Pour self-compacting concrete cleaning sampling process:After concreting, the extra concrete of wall is removed immediately With the concrete for being attached to surface of wall, when casting concrete, should randomly select concrete sample in its pouring location, as required Cured under same condition test specimen is made, core bore self-compacting concrete intensity is detected;
4)Pour self-compacting concrete maintenance process:It should be carried out immediately after self-compacting concrete pours in form wall core bore Maintenance, the visual concrete covering on reply wall top when summer climate is dried carry out water conservation moisture-keeping maintaining, and when winter cold needs To visual concrete plus heat-preserving anti-freezing layer.
Preferably, the further technical solution of the present invention is:
Described to pour self-compacting concrete preparatory process, when plate formwork concrete structure construction, is mounted on concrete blinding Inside, poured with structural concrete needs the plate formwork of first well cutting size to be temporarily fixed at cast-in-place concrete mould together On the inside of plate, the position of formwork is adjusted, the gap of formwork adjacent thereto is made to inject polyurethane foam glue in 5mm or so, gap, Gu Determine support shuttering after-pouring concrete, form removal after the completion of concrete is raised has completed that formwork is assembled, formwork plate stitch is close Envelope, temporary support working procedure, steel-bar arrangement protective layer.
Described pours self-compacting concrete preparatory process, and in formwork assembly, formwork is equipped with connecting hole, connection in high spot Lateral connection bar, lateral connection bar both ends is assigned to be equipped with buckle in hole, opposite install is equipped with vertical reinforcing prop, erects on the outside of formwork It is equipped with card slot to the side of reinforcing prop, card slot and snaps connection fixation.
The self-compacting concrete that pours pours process, and the cement mortar first poured is 50mm thick.
Described pours self-compacting concrete cleaning sampling process, and the rainy day does not answer casting concrete, just poured the mixed of completion Solidifying soil will prevent rain drop erosion.
It is described pour self-compacting concrete maintenance process can after self-compacting concrete intensity reaches 5 to 10MPa Remove temporary support.
Present invention reduces building cost, wall is to reach carrying, energy saving, three body of facing conjunction by disposably constructing One function, and meet finishing carry requirement with certain intensity.Modified cement polyphenyl mould case lattice type concrete wall is built Since heat-preserving wall is thin from heavy and light wall, load is substantially cut down in the house made, and foundation's bottom area reduces very much.It constructs in this way Middle saving lot of materials takes, labour cost, effectively reduces building cost.Modified cement cement polyphenyl formwork although block is larger, But density is small, and a people can move, and since heat preserving formwork is without building by laying bricks or stones, need to only position and put foamed glue jointing, in construction Bricklayer masonry mortar is not needed;The labor intensity of worker is reduced, and speed of application can be greatly improved.The globality of structure Energy is good, construction wall is made all to be connected to become an entirety by netted concrete.This structural system belongs to prefabricated and cast-in-place Half fabricated construction being combined has prefabricated components and two big advantage of site concrete concurrently, is equipped under plate at building absolute altitude and wall With the poly- formwork of spill of pitch-row, reinforcing bar passes through body with concrete continuous at floor absolute altitude when job-poured concrete, avoids pre- Difficult template and the support for not needing Bars In Poured Concrete Slab again of component connection processed, substantially eliminates the weakness of the two, and node connection more has It ensures, structure is made to have more globality.
Description of the drawings
Fig. 1 is the form wall construction process figure of the present invention.
Fig. 2 is the concrete construction flow chart of the present invention.
Fig. 3 is the structural schematic diagram of the formwork auxiliary support member of the present invention.
Reference sign:The vertical reinforcing props of 1-;2- is modified cement polyphenyl formwork;3- lateral connection bars;4- connections Hole.
Specific implementation mode
With reference to embodiment, further illustrate the present invention.
Specific embodiment 1:
According to Fig. 1 and Fig. 2 it is found that a kind of 2 lattice type concrete wall of modified cement polyphenyl formwork of the invention pours self-compaction and mixes Solidifying earth process, includes the following steps:
1)Pour self-compacting concrete preparatory process:Formwork core bore is clear and coherent, is cleaned out in hole, is installed with that electrical, hot-water heating is pre-buried Pipeline and built-in fitting, hole, collar tie beam, constructional column, the non-standard formwork installed at door-window opening, need to fix and filling-foam glue is close Envelope;Formwork assembled, the sealing of formwork plate stitch, temporary support working procedure are completed, steel-bar arrangement protective layer;
2)It pours self-compacting concrete and pours process:First pour cement bonded sand identical with core bore self-compacting concrete strength grade Slurry;Core bore concreting height should not exceed 0.9m, and two holes of the appropriate to the occasion primary movement of casting concrete every time, and should be along wall Long connection pours, and intermittent time of two-step pouring must not exceed the concrete initial set time, when concreting should take drill rod into Pedestrian's work plugs and pounds, and each vertical core bore will plug and pound one by one, until core bore inner concrete holds one's breath bubble, connected core bore inner concrete Until surface does not decline;The cement mortar first poured is 50mm thick;
3)Pour self-compacting concrete cleaning sampling process:After concreting, the extra concrete of wall is removed immediately With the concrete for being attached to surface of wall, when casting concrete, should randomly select concrete sample in its pouring location, as required Cured under same condition test specimen is made, core bore self-compacting concrete intensity is detected;Rainy day does not answer casting concrete, has just poured the mixed of completion Solidifying soil will prevent rain drop erosion;
4)Pour self-compacting concrete maintenance process:It should be carried out immediately after self-compacting concrete pours in form wall core bore Maintenance, the visual concrete covering on reply wall top when summer climate is dried carry out water conservation moisture-keeping maintaining, and when winter cold needs To visual concrete plus heat-preserving anti-freezing layer, after self-compacting concrete intensity reaches 5 to 10MPa, temporary support can be removed.
Specific embodiment 2:
As can be seen from FIG. 3, a kind of 2 lattice type concrete wall of modified cement polyphenyl formwork of the present invention pours self-compacting concrete work Skill is mounted on the inside of concrete blinding when plate formwork concrete structure construction, is poured together with structural concrete, need elder generation The plate formwork of well cutting size is temporarily fixed on the inside of cast in place concrete form, is adjusted the position of formwork, is made adjacent thereto Polyurethane foam glue, fixed support shuttering after-pouring concrete, concrete packet are injected in the gap of formwork in 5mm or so, gap Form removal after the completion of supporting, completed formwork assembled, the sealing of formwork plate stitch, temporary support working procedure, and steel-bar arrangement is protected Sheath, completed formwork assembled, the sealing of formwork plate stitch, temporary support working procedure, steel-bar arrangement protective layer.It pours from close Real concrete preparatory process, in formwork assembly, formwork is equipped with connecting hole 4 in high spot, and lateral connection bar 3 is assigned in connecting hole 4, 3 both ends of lateral connection bar are equipped with buckle, and opposite install is equipped with vertical reinforcing prop 1 on the outside of formwork, the side of vertical reinforcing prop 1 is set There is a card slot, card slot and snaps connection fixation.
Specific embodiment 3:
A kind of 2 lattice type concrete wall of modified cement polyphenyl formwork of the present invention pours self-compacting concrete technique, formwork core bore It is interior to be equipped with flow-guiding structure, it is equipped with diversion trench in formwork core bore, coagulation is promoted when diversion trench helps casting concrete in formwork core bore The flow velocity of soil, promotion pour effect, and raising pours efficiency.
Since the foregoing is merely the specific implementation modes of the present invention, but the protection of the present invention is without being limited thereto, any skill The technical staff in art field it is contemplated that the equivalent variation or replacement of the technical program technical characteristic, all cover the present invention's Within protection domain.

Claims (6)

1. a kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique, feature includes following Step:
1)Pour self-compacting concrete preparatory process:Formwork core bore is clear and coherent, is cleaned out in hole, is installed with that electrical, hot-water heating is pre-buried Pipeline and built-in fitting, hole, collar tie beam, constructional column, the non-standard formwork installed at door-window opening, need to fix and filling-foam glue is close Envelope;
2)It pours self-compacting concrete and pours process:First pour cement bonded sand identical with core bore self-compacting concrete strength grade Slurry;Core bore concreting height should not exceed 0.9m, and two holes of the appropriate to the occasion primary movement of casting concrete every time, and should be along wall Long connection pours, and intermittent time of two-step pouring must not exceed the concrete initial set time, when concreting should take drill rod into Pedestrian's work plugs and pounds, and each vertical core bore will plug and pound one by one, until core bore inner concrete holds one's breath bubble, connected core bore inner concrete Until surface does not decline;
3)Pour self-compacting concrete cleaning sampling process:After concreting, the extra concrete of wall is removed immediately With the concrete for being attached to surface of wall, when casting concrete, should randomly select concrete sample in its pouring location, as required Cured under same condition test specimen is made, core bore self-compacting concrete intensity is detected;
4)Pour self-compacting concrete maintenance process:It should be carried out immediately after self-compacting concrete pours in form wall core bore Maintenance, the visual concrete covering on reply wall top when summer climate is dried carry out water conservation moisture-keeping maintaining, and when winter cold needs To visual concrete plus heat-preserving anti-freezing layer.
2. a kind of modified cement polyphenyl mould case lattice type concrete wall according to claim 1 pours self-compacting concrete Technique, which is characterized in that described to pour self-compacting concrete preparatory process, when plate formwork concrete structure construction installs On the inside of concrete blinding, poured with structural concrete needs the plate formwork of first well cutting size to be temporarily fixed at together On the inside of cast in place concrete form, the position of formwork is adjusted, so that the gap of formwork adjacent thereto is injected in 5mm or so, gap poly- Urethane foamed glue, fixed support shuttering after-pouring concrete, form removal after the completion of concrete is raised have completed formwork spelling Dress, the sealing of formwork plate stitch, temporary support working procedure, steel-bar arrangement protective layer have completed that formwork is assembled, formwork plate stitch is close Envelope, temporary support working procedure, steel-bar arrangement protective layer.
3. it is mixed that a kind of modified cement polyphenyl mould case lattice type concrete wall according to claim 1 or 2 pours self-compaction Solidifying earth process, which is characterized in that described pours self-compacting concrete preparatory process, and in formwork assembly, formwork is set in high spot There is connecting hole, lateral connection bar, lateral connection bar both ends is assigned to be equipped with buckle, be equipped on the outside of opposite installation formwork perpendicular in connecting hole To reinforcing prop, the side of vertical reinforcing prop is equipped with card slot, card slot and snaps connection fixation.
4. a kind of modified cement polyphenyl mould case lattice type concrete wall according to claim 1 pours self-compacting concrete Technique, which is characterized in that the self-compacting concrete that pours pours process, and the cement mortar first poured is 50mm thick.
5. a kind of modified cement polyphenyl mould case lattice type concrete wall according to claim 1 pours self-compacting concrete Technique, which is characterized in that described pours self-compacting concrete cleaning sampling process, and the rainy day does not answer casting concrete, just pours The concrete of completion will prevent rain drop erosion.
6. a kind of modified cement polyphenyl mould case lattice type concrete wall according to claim 1 pours self-compacting concrete Technique, which is characterized in that described pours self-compacting concrete maintenance process, when self-compacting concrete intensity reaches 5 to 10MPa Afterwards, temporary support can be removed.
CN201710006680.1A 2017-01-05 2017-01-05 A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique Pending CN108277909A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710006680.1A CN108277909A (en) 2017-01-05 2017-01-05 A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710006680.1A CN108277909A (en) 2017-01-05 2017-01-05 A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique

Publications (1)

Publication Number Publication Date
CN108277909A true CN108277909A (en) 2018-07-13

Family

ID=62800436

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710006680.1A Pending CN108277909A (en) 2017-01-05 2017-01-05 A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique

Country Status (1)

Country Link
CN (1) CN108277909A (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2780873Y (en) * 2005-02-16 2006-05-17 张良纯 Cement polyppenyl module casing structure type concrete energy-saving bearing wall
CN102731031A (en) * 2012-06-25 2012-10-17 葛兆明 Cement polyphenyl granule concrete lattice composite wall shuttering, its manufacturing method, lattice composite wall and its manufacturing method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2780873Y (en) * 2005-02-16 2006-05-17 张良纯 Cement polyppenyl module casing structure type concrete energy-saving bearing wall
CN102731031A (en) * 2012-06-25 2012-10-17 葛兆明 Cement polyphenyl granule concrete lattice composite wall shuttering, its manufacturing method, lattice composite wall and its manufacturing method

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
山东省建筑科学研究院等: "《DB37/T 5005-2013水泥聚苯模壳格构式混凝土墙体保温结构一体化应用技术规程》", 20 December 2013, 山东省住房和城乡建设厅 *
董士文等: "改性水泥聚苯模壳格构式混凝土墙体建筑体系", 《新型建筑材料》 *

Similar Documents

Publication Publication Date Title
CN106013811B (en) A kind of installation method of assembled architecture
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN110439137A (en) Prefabricated panel, wall and prefabricated panel production method, precast wall body construction method
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN102644382B (en) Mounting technology of large-module wall
CN105804292A (en) Environment-friendly and energy-saving integrated cast-in-situ lightweight concrete wall and construction method thereof
US9605423B2 (en) Method of basement construction
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CA2842249A1 (en) Prefabricated reinforced concrete wall panel and installation method
CN104120883A (en) Construction method for non-removal fire-prevention heat-preservation building component formwork
CN108301531A (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame-floor connecting node
CN110409860A (en) A kind of reconstruction structure and its remodeling method in old house
CN207110214U (en) A kind of prefabricated interior fill concrete wallboard
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
CN211548083U (en) Connecting joint of external wall panel
JP2011069151A (en) Concrete panel form
CN108277909A (en) A kind of modified cement polyphenyl mould case lattice type concrete wall pours self-compacting concrete technique
CN205502377U (en) Hanging wallboard is partly inlayed to unit -installment light
CN108277907A (en) A kind of lattice type concrete wall building block is modified the mounting process of cement polyphenyl formwork
CN108149827A (en) The compound girt strip floor of assembled with prefabricated reinforced concrete bearing
CN106638941A (en) Building method of box body type integral cast-in-situ house
CN113356405A (en) Prefabricated composite wall structure based on embedded profile steel and construction method thereof
CN102644349A (en) Cast-in-place concrete floor and construction process thereof
CN111305590A (en) Assembly type low-energy-consumption transformation structure and rapid transformation method for existing building balcony

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180713