CN102644349A CN2012101374188A CN201210137418A CN102644349A CN 102644349 A CN102644349 A CN 102644349A CN 2012101374188 A CN2012101374188 A CN 2012101374188A CN 201210137418 A CN201210137418 A CN 201210137418A CN 102644349 A CN102644349 A CN 102644349A
Authority
CN
China
Prior art keywords
floor
post
cast
wall
place concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101374188A
Other languages
Chinese (zh)
Inventor
孔德志
洪芳鹏
陈燚华
朱小军
姜涛
李鑫奎
孙杰
俞荣仁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction Group Co Ltd
Original Assignee
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction Group Co Ltd filed Critical Shanghai Construction Group Co Ltd
Priority to CN2012101374188A priority Critical patent/CN102644349A/en
Publication of CN102644349A publication Critical patent/CN102644349A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a cast-in-place concrete floor and a construction process thereof. A core-embedding core-forming process is adopted in the structure of the cast-in-place concrete floor, round high definition composite thin wall pipes are arranged on a floor bottom rib of the floor at intervals, and concrete is cast after the thin wall pipes are fixed. The floor cast in the mode can form a cast-in-place multipore hollow plate provided with countless small I beams for stress, and the small I beams can bear large shock, so that the floor has better shockproof effects. Further, self weight and construction materials of the floor are reduced due to the fact that using amount of the concrete is reduced, cost for constructing the floor is saved, and simultaneously safety factor of the floor is increased.

Description

Cast-in-place concrete floor and construction technology thereof
Technical field
The present invention relates to the building site construction technology, relate in particular to a kind of cast-in-place concrete floor and construction technology thereof.
Background technology
In the present most building structure, floor adopts pre-stress hollow precast plate and two-way concrete slab to arrange cast-in-place solid floor more, wherein; Pre-stress hollow precast floor slab floor must add cement mortar screeding on the floor upper berth when construction is combined into floor; Increased the deadweight of floor, its water proofing property also can be very poor, often between prestressed slab and plate, the seepage phenomenon can occur; And its overall structure power-assisted is little; Do not reach good shockproof effect, precast floor slab generally is used in the brick mix structure system in addition, in frame structure system, seldom can adopt; And two-way concrete slab is arranged cast-in-place solid floor because its concrete amount is many, so its cost is high, and the floor deadweight is heavier, and also lower to the utilization rate of material, economy is relatively poor.
Summary of the invention
The purpose of this invention is to provide a kind of cast-in-place concrete floor and construction technology thereof,, on the basis of economical with materials, make floor have good seismic resistance simultaneously with alleviating the floor deadweight.
For solving the problems of the technologies described above; The present invention provides a kind of cast-in-place concrete floor, and it is provided with Vierendeel girder between wall and post or post and post, and said Vierendeel girder is positioned at said floor bed die top; Said Vierendeel girder comprises muscle at the bottom of the plate; Said cast-in-place concrete floor also comprises some high-strength compound light-wall pipes, and muscle is latticed colligation and fixes and be arranged between wall and post or post and the post at the bottom of the said plate, and said some high-strength compound light-wall pipes uniformly-spaced are fixedly set at the bottom of the said plate on the muscle.
Further, said cast-in-place concrete floor also comprises iron wire, and muscle is fixedly connected with steel pipe in the said floor bed die through iron wire at the bottom of the said plate.
Further, said cast-in-place concrete floor also comprises the anti-floating reinforcing bar, and said some high-strength compound light-wall pipes are fixedly connected with steel pipe in the said floor bed die through said anti-floating reinforcing bar.
Further, said Vierendeel girder also comprises some intercostal reinforcing bars, and said some intercostal reinforcing bars uniformly-spaced are fixedly set at the bottom of the said plate on the muscle, and said every high-strength compound light-wall pipe is arranged between corresponding adjacent two roots between the reinforcing bar respectively.
Further, said Vierendeel girder also comprises top reinforcement, and said top reinforcement is fixedly set on said some intercostal reinforcing bars, and said top reinforcement and some intercostal reinforcing bar bindings are fixed and are arranged between wall and post or post and the post.
Further, said high-strength compound light-wall pipe is a GBF high-strength compound light-wall pipe.
The present invention also provides a kind of construction technology of above-mentioned cast-in-place concrete floor, and described construction technology comprises:
Step 1: the floor bed die is installed;
Step 2: dark beam is installed within wall, post, and installing frame is set a roof beam in place between wall and post, post and post, and in wall, post parts such as pre-buried water power box;
Step 3: the muscle equal intervals fixedly installs some high-strength compound light-wall pipes at the bottom of the plate of Vierendeel girder;
Step 4: build and curing concrete, reach form removal after the design strength.
Compared with prior art, the present invention has following beneficial effect:
Cast-in-place concrete floor provided by the invention and construction technology thereof; In the cast-in-place concrete floor structure, adopt and bury the core pore-forming technique; Every at a distance from compound light-wall pipe of circular high definition of segment distance placement on the muscle at the bottom of the plate in floor, at fixing light-wall pipe after-pouring concrete, the floor that this mode builds out can form the in-situ deposited porous hollowcore slab that has countless unskilled labourer's word beam stress; These little i beams can bear bigger vibrations; Thereby make floor that shockproof effect preferably arranged, and, make this floor deadweight and construction material thereof all reduce to some extent because concrete consumption reduces; Save the cost of making this floor, also increased the safety factor of this floor simultaneously.
Description of drawings
Below in conjunction with accompanying drawing the present invention is described further:
The structural representation of the cast-in-place concrete floor that Fig. 1 provides for the embodiment of the invention;
The flow chart of the cast-in-place concrete floor construction technology that Fig. 2 provides for the embodiment of the invention.
In Fig. 1,
1: the floor bed die; 11: steel pipe; 2: Vierendeel girder; 21: muscle at the bottom of the plate; 22: the intercostal reinforcing bar; 23: top reinforcement; 3: the high-strength compound light-wall pipe; 4: iron wire; 5: the anti-floating reinforcing bar.
The specific embodiment
Below in conjunction with accompanying drawing and specific embodiment cast-in-place concrete floor and construction technology thereof that the present invention proposes are done further explain.According to following explanation and claims, advantage of the present invention and characteristic will be clearer.What need explanation is, accompanying drawing all adopts the form of simplifying very much and all uses non-ratio accurately, only in order to convenient, the purpose of the aid illustration embodiment of the invention lucidly.
Core concept of the present invention is, a kind of cast-in-place concrete floor and construction technology thereof are provided, and it is provided with Vierendeel girder between wall and post or post and post; Said Vierendeel girder is positioned at said floor bed die top, and said Vierendeel girder comprises muscle at the bottom of the plate, and said cast-in-place concrete floor also comprises some high-strength compound light-wall pipes; Muscle is latticed colligation and fixes and be arranged between wall and post or post and the post at the bottom of the said plate, and said some high-strength compound light-wall pipes uniformly-spaced are fixedly set at the bottom of the said plate on the muscle, cast-in-place concrete floor provided by the invention and construction technology thereof; In the cast-in-place concrete floor structure, adopt and bury the core pore-forming technique; Every at a distance from compound light-wall pipe of circular high definition of segment distance placement on the muscle at the bottom of the plate in floor, at fixing light-wall pipe after-pouring concrete, the floor that this mode builds out can form the in-situ deposited porous hollowcore slab that has countless unskilled labourer's word beam stress; These little i beams can bear bigger vibrations; Thereby make floor that shockproof effect preferably arranged, and, make this floor deadweight and construction material thereof all reduce to some extent because concrete consumption reduces; Save the cost of making this floor, also increased the safety factor of this floor simultaneously.
Please refer to Fig. 1 and Fig. 2, the structural representation of the cast-in-place concrete floor that Fig. 1 provides for the embodiment of the invention; The flow chart of the cast-in-place concrete floor construction technology that Fig. 2 provides for the embodiment of the invention.
Please emphasis with reference to figure 1; As shown in Figure 1; The embodiment of the invention provides a kind of cast-in-place concrete floor, and it is provided with Vierendeel girder 2 between wall and post or post and post, and said Vierendeel girder 2 is positioned at said floor bed die 1 top; Said Vierendeel girder 2 comprises muscle 21 at the bottom of the plate; Said cast-in-place concrete floor also comprises some high-strength compound light-wall pipes 3, and muscle 21 is latticed colligation and fixes and be arranged between wall and post or post and the post at the bottom of the said plate, and said some high-strength compound light-wall pipes 3 uniformly-spaced are fixedly set at the bottom of the said plate on the muscle 21.
Further, said high-strength compound light-wall pipe 3 is a GBF high-strength compound light-wall pipe, and GBF foamed heat insulating building material is a kind of with the inorganic integrated pouredly building thermal insulation material of materials such as special cement, flyash, slag powders, blowing agent, waterproof agent employing foam-in-place; Be used for the insulation of roofing and floor; Belong to state key and promote the energy-conserving, environment protection building material product, into a single integrated structure with the GBF high-strength compound light-wall pipe that the GBF foaming thermal-insulating is made, seamless surface; Prevented the situation of leaking that produces owing to floor building material surface slit; This light-wall pipe can also play insulation effect, can stablize the temperature of floor, and its manufacturing materials is simple; With low cost, can reduce the cost that adopts the floor that this light-wall pipe makes.
Further; Said cast-in-place concrete floor also comprises iron wire 4 and anti-floating reinforcing bar 5; Muscle 21 is fixedly connected with steel pipe 11 in the said floor bed die 1 through iron wire 4 at the bottom of the said plate; Said some high-strength compound light-wall pipes 3 are fixedly connected with steel pipe 11 in the said floor bed die 1 through said anti-floating reinforcing bar 5; The present invention has played the anti-floating fixation of high-strength compound light-wall pipe 3 through the iron wire 4 and this design of anti-floating reinforcing bar 5, iron wire 4 and anti-floating reinforcing bar 5 can hold respectively muscle 21 at the bottom of the plate and high-strength compound light-wall pipe 3 on it make they can be the time because of concreting concrete to the vibrations of its buoyancy or floor, loosening and come-up causes the loosening of building structure.
Further; Said Vierendeel girder 2 also comprises some intercostal reinforcing bars 22 and top reinforcement 23; Said some intercostal reinforcing bars 22 uniformly-spaced are fixedly set at the bottom of the said plate on the muscle 21; Said every high-strength compound light-wall pipe 3 is arranged between corresponding adjacent two roots between the reinforcing bar 22 respectively, and said intercostal reinforcing bar 22 can either play the supporting role of whole Vierendeel girder 2, can also play the effect of fixing high-strength compound light-wall pipe 3 in it; Said top reinforcement 23 is fixedly set on said some intercostal reinforcing bars 22; Said top reinforcement 23 and some intercostal reinforcing bar 22 colligations are fixed and are arranged between wall and post or post and the post, and said top reinforcement 23 can either play the effect of fixing whole Vierendeel girder 2, can also play limiting and the fixedly effect of high-strength compound light-wall pipe 3.
Please emphasis with reference to figure 2, as shown in Figure 2, the embodiment of the invention also provides a kind of construction technology of above-mentioned cast-in-place concrete floor, described construction technology comprises:
Step 1: floor bed die 1 is installed;
Step 2: unwrapping wire on floor bed die 1, carry out the location work of high-strength compound light-wall pipe 3, then dark beam is installed within wall, post according to the size of having good positioning, installing frame sets a roof beam in place 2 between wall and post, post and post, and in wall, post parts such as pre-buried water power box;
Step 3: muscle 21 equal intervals fixedly install some high-strength compound light-wall pipes 3 at the bottom of the plate of Vierendeel girder 2, and light-wall pipe is carried out the anti-floating grappling;
Step 4: build and curing concrete, reach form removal after the design strength.
Cast-in-place concrete floor that the embodiment of the invention provides and construction technology thereof; In the cast-in-place concrete floor structure, adopt and bury the core pore-forming technique; Every at a distance from compound light-wall pipe 3 of circular high definition of segment distance placement on the muscle 21 at the bottom of the plate in floor, at fixing light-wall pipe after-pouring concrete, the floor that this mode builds out can form the in-situ deposited porous hollowcore slab that has countless unskilled labourer's word beam stress; These little i beams can bear bigger vibrations; Thereby make floor that shockproof effect preferably arranged, and, make this floor deadweight and construction material thereof all reduce to some extent because concrete consumption reduces; Save the cost of making this floor, also increased the safety factor of this floor simultaneously.
Obviously, those skilled in the art can carry out various changes and distortion to the present invention and not break away from the spirit and scope of the present invention.Like this, belong within the scope of claim of the present invention and equivalent technologies thereof if of the present invention these are revised with modification, then the present invention also is intended to comprise these changes and modification interior.

Claims (7)

1. cast-in-place concrete floor; It is provided with Vierendeel girder between wall and post or post and post, said Vierendeel girder is positioned at said floor bed die top, it is characterized in that; Said Vierendeel girder comprises muscle at the bottom of the plate; Said cast-in-place concrete floor also comprises some high-strength compound light-wall pipes, and muscle is latticed colligation and fixes and be arranged between wall and post or post and the post at the bottom of the said plate, and said some high-strength compound light-wall pipes uniformly-spaced are fixedly set at the bottom of the said plate on the muscle.
2. according to the said cast-in-place concrete floor of claim 1, it is characterized in that, also comprise iron wire, muscle is fixedly connected with steel pipe in the said floor bed die through iron wire at the bottom of the said plate.
3. according to the said cast-in-place concrete floor of claim 1, it is characterized in that, also comprise the anti-floating reinforcing bar, said some high-strength compound light-wall pipes are fixedly connected with steel pipe in the said floor bed die through said anti-floating reinforcing bar.
4. according to claim 2 or 3 said cast-in-place concrete floors; It is characterized in that; Said Vierendeel girder also comprises some intercostal reinforcing bars; Said some intercostal reinforcing bars uniformly-spaced are fixedly set at the bottom of the said plate on the muscle, and said every high-strength compound light-wall pipe is arranged between corresponding adjacent two roots between the reinforcing bar respectively.
5. according to the said cast-in-place concrete floor of claim 4; It is characterized in that; Said Vierendeel girder also comprises top reinforcement, and said top reinforcement is fixedly set on said some intercostal reinforcing bars, and said top reinforcement and some intercostal reinforcing bar bindings are fixed and are arranged between wall and post or post and the post.
6. according to the said cast-in-place concrete floor of claim 1, it is characterized in that said high-strength compound light-wall pipe is a GBF high-strength compound light-wall pipe.
7. construction technology of cast-in-place concrete floor according to claim 1 is characterized in that described construction technology comprises:
Step 1: the floor bed die is installed;
Step 2: dark beam is installed within wall, post, and installing frame is set a roof beam in place between wall and post, post and post, and in wall, post parts such as pre-buried water power box;
Step 3: the muscle equal intervals fixedly installs some high-strength compound light-wall pipes at the bottom of the plate of Vierendeel girder;
Step 4: build and curing concrete, reach form removal after the design strength.
CN2012101374188A 2012-05-03 2012-05-03 Cast-in-place concrete floor and construction process thereof Pending CN102644349A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101374188A CN102644349A (en) 2012-05-03 2012-05-03 Cast-in-place concrete floor and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101374188A CN102644349A (en) 2012-05-03 2012-05-03 Cast-in-place concrete floor and construction process thereof

Publications (1)

Publication Number Publication Date
CN102644349A true CN102644349A (en) 2012-08-22

Family

ID=46657407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101374188A Pending CN102644349A (en) 2012-05-03 2012-05-03 Cast-in-place concrete floor and construction process thereof

Country Status (1)

Country Link
CN (1) CN102644349A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485465A (en) * 2013-10-12 2014-01-01 广东电白建设集团有限公司 CBM inner mould and construction process for CBM high-strength thin-walled tube cast-in-place hollow floorslab
CN103790271A (en) * 2014-01-26 2014-05-14 宁波大学 Steel and bamboo composite floor and reinforced concrete beam connecting structure and processing method
CN111926974A (en) * 2020-08-20 2020-11-13 福建宏盛建设集团有限公司 Precast slab construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201424728Y (en) * 2009-05-26 2010-03-17 内蒙古兴泰建筑有限责任公司 Cast-in-situ concrete hollow floorslab of thin-wall box body
CN102182313A (en) * 2011-03-30 2011-09-14 中联世纪建设集团有限公司 Anti-floating construction method of cast-in-situ concrete girderless hollow floor slab
CN202090482U (en) * 2011-05-18 2011-12-28 济南四建(集团)有限责任公司 Anti-floating structure for cast-in-place concrete GBF hollow floorslab
CN202595983U (en) * 2012-05-03 2012-12-12 上海建工集团股份有限公司 Cast-in-place concrete floor slab

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201424728Y (en) * 2009-05-26 2010-03-17 内蒙古兴泰建筑有限责任公司 Cast-in-situ concrete hollow floorslab of thin-wall box body
CN102182313A (en) * 2011-03-30 2011-09-14 中联世纪建设集团有限公司 Anti-floating construction method of cast-in-situ concrete girderless hollow floor slab
CN202090482U (en) * 2011-05-18 2011-12-28 济南四建(集团)有限责任公司 Anti-floating structure for cast-in-place concrete GBF hollow floorslab
CN202595983U (en) * 2012-05-03 2012-12-12 上海建工集团股份有限公司 Cast-in-place concrete floor slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
闫赫赫,吴启星,荣彤: "GBF高强薄壁管现浇混凝土空心楼盖施工技术", 《建筑施工》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485465A (en) * 2013-10-12 2014-01-01 广东电白建设集团有限公司 CBM inner mould and construction process for CBM high-strength thin-walled tube cast-in-place hollow floorslab
CN103485465B (en) * 2013-10-12 2016-07-06 广东电白建设集团有限公司 CBM internal mold and CBM high-strength thin-wall pipe cast-in-situ hollow floor plate construction technology
CN103790271A (en) * 2014-01-26 2014-05-14 宁波大学 Steel and bamboo composite floor and reinforced concrete beam connecting structure and processing method
CN103790271B (en) * 2014-01-26 2016-02-24 宁波大学 The syndeton of steel bamboo composite floor and reinforced concrete beam and processing method
CN111926974A (en) * 2020-08-20 2020-11-13 福建宏盛建设集团有限公司 Precast slab construction method

Similar Documents

Publication Publication Date Title
CN103821276A (en) Novel assembly-type modular building system
CN104405062A (en) Integrated column-equipped heat preservation wallboard, production and building techniques and matched equipment
CN103469825A (en) Prefabricated water-resistant post-pouring belt formwork and installation method
CN108643396B (en) Assembled built-in heat insulation layer foamed concrete composite wall-light steel frame connecting node
CN109083308B (en) Anti-seismic prefabricated assembly type wall and construction method thereof
CN105113706A (en) Reinforced truss gypsum plate with insulation layer, novel dismantling-free formwork and their construction method
CN105155763A (en) Prefabricated core pulling hole-forming slab
CN208105502U (en) Assembled built-in heat insulation layer concrete composite wall-light steel frame connecting node
CN102644349A (en) Cast-in-place concrete floor and construction process thereof
CN202595983U (en) Cast-in-place concrete floor slab
CN205035970U (en) Prefabricated orifice plate of loosing core into
CN210421568U (en) Assembled beam and plate structure
CN107313551A (en) A kind of concrete prefabricated wallboard of steel bar girder and structural system and its construction method
CN204959963U (en) Compound lightweight wall housing construction of assembled steel frame
CN103469889A (en) Steel structure concrete construction house
CN107237448A (en) A kind of prefabricated interior fill concrete wallboard and its manufacture method
CN203462576U (en) Steel structure concrete building house
CN207469430U (en) A kind of assembled arthitecutral structure
CN210685110U (en) Assembled novel bidirectional ribbed profiled steel sheet composite floor
CN207538511U (en) A kind of Applying Steel Structures To A Villa
CN104234432B (en) Shed deckhead construction method
CN207538199U (en) A kind of support construction of Applying Steel Structures To A Villa
CN208309951U (en) Cavity board member for stress island superstructure
CN201771081U (en) Built-in core mould of cast-in-situ reinforced concrete anti-floating & positioning combination
CN106869403B (en) Multilayer prefabricated square steel pipe concrete connecting beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120822