Prior art keywords
platform
operation platform
montant
beams
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711444345.6A
Other languages
Chinese (zh)
Inventor
孙晓伟
任雷
张大军
夏婵婷
童卫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201711444345.6A priority Critical patent/CN108277745A/en
Publication of CN108277745A publication Critical patent/CN108277745A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Ladders (AREA)

Abstract

The present invention relates to bridge construction technical field of structures, in particular to a kind of T beams suspension operation platform structure and T beam interval board construction methods.Including operation platform and more montants being fixed on operation platform;Operation platform is the platform structure that width is less than adjacent T beams gap, and operation platform both lateral sides are provided with rotating platform;Montant lower end is fixed on operation platform, and the upper end is provided with and the fixed fixed structure in T beam wing plates edge;Rotating platform one end is rotatably articulated and connected in operation platform side, and the other end can be fixedly connected when being flipped up vertical state with montant, and rotating platform maintains an equal level when being turned to horizontality with operation platform.It is the configuration of the present invention is simple, easy to operate, job platform takes full advantage of the gap between T beam webs, operation platform, guardrail, skirting board are hinged, once mounting is in place, assembling and disassembling cycle operation is realized by rotation, and articulated manner keeps preferable suspension operation platform globality, sound construction, safety higher.

Description

A kind of T beams suspension operation platform structure and T beam interval board construction methods
Technical field
The present invention relates to bridge construction technical field of structures, in particular in a kind of T beams suspension operation platform structure and T beams Diaphragm construction method.
Background technology
After the completion of Precast T-Beam is set up, need to carry out T beam mid-board cast-in-place constructions and T negative moment of girder tensioning mud jacking, due to It is in courage jacking mouth form that gap width, which only has space between 70cm or so, beam, between T beam beams, and construction space is smaller, not easy to operate.At present Most engineerings weld cage mode using reinforcing bar or shaped steel, but its there are following inconvenience:1, in operation process, flexible cage There are larger shakings;2, construction space is only the wet gaping of joints width of T beams, narrow space, construction inconvenience;3, only both sides when operation There are protection, for interval metope without guardrail, construction safety risk is high;4, cage includes cat ladder, step plate, protection etc., and primary structural component is more, Construction turnover is inconvenient.
Invention content
Present invention aim to solve the deficiency of above-mentioned background technology, a kind of T beams suspension operation platform structure is provided And T beam interval board construction methods.
The technical scheme is that:A kind of T beams suspension operation platform structure, it is characterised in that:Including operation platform and More montants being fixed on operation platform;The operation platform is the platform structure that width is less than adjacent T beams gap, construction Platform both lateral sides are provided with rotating platform;The montant lower end is fixed on operation platform, and the upper end is provided with and the T beam wings The fixed fixed structure of edges of boards edge;Described rotating platform one end is rotatably articulated and connected in operation platform side, the other end It can be fixedly connected with montant when being flipped up vertical state, rotating platform is held when being turned to horizontality with operation platform It is flat.
The further rotating platform side is provided with guardrail;The guardrail includes more upright bars and cross bar;Institute The upright bar lower end stated rotatably is articulated and connected in the one end of rotating platform far from its coercive mechanism;It the cross bar both ends respectively can It is rotatably articulated and connected on montant and upright bar.
One end far from its coercive mechanism is provided with two upright bars on the further rotating platform, between two upright bars More vertically spaced apart stulls are installed, stull both ends are separately fixed in two upright bars.
The further fixed structure is the hook for being fixed on montant upper end;The hook is to be fixed on montant Hold the rod-like structure extended along horizontal cross.
It is further to be provided with cat ladder between two montants of operation platform both lateral sides;The cat ladder is vertically Arrangement, upper end extend to montant upper end, and lower end extends on operation platform.
There are two cat ladder settings, can one on the other, facilitate safety and the convenience of construction personnel.
Longitudinal both sides of the further operation platform are provided with skirting board;The skirting board lower end is rotatably It is articulated and connected on operation platform.
The further operation platform transverse ends are respectively rotatably articulated and connected on two montants;Positioned at applying In work platform crossbeam is provided between two montants of longitudinal both sides;The crossbeam arranges that both ends can revolve along horizontal cross Turn ground articulated connection on two montants.
The articulated connection of operation platform both ends makes the montant of both sides be superimposed on montant, can rotating operation platform, Reduce the occupancy volume of device, is convenient for fast removal and assembling.Guard bar structure of the crossbeam as operation platform ensures construction personnel Construction safety.Crossbeam both ends are rotatably articulated and connected on montant, both sides montant can be convenient for collapse together.
A kind of T beams interval board construction method, it is characterised in that:Job platform is hoisted between adjacent T beams in the vertical direction In gap, the hook on job platform is hooked on T beam wing plates edge, so that the operation platform of lower section is hung between adjacent T beams, applies Cat ladder of the worker person on montant expands operation platform on operation platform, along operation platform horizontal direction, relies on after expanding Operation platform construct mid-board, complete construction operation after, lifting job platform to next construction point.
Further include the following steps:
1), lifting job platform and slowly decentralization is between adjacent T beams gap by it, until the hook of job platform hooks At T beam wing plates edge;
2), cat ladder of the construction personnel on montant is transferred to operation platform, the rotating platform exhibition that will be fixed on montant Opening makes it maintain an equal level with operation platform;
3) skirting board on operation platform and rotating platform, is overturn to vertical state;
4), construction personnel relies on operation platform and rotating platform to carry out the construction operation of mid-board;
5), after the completion of construction operation, skirting board is overturn to horizontality, rotation rotating platform is fixed in montant On, construction personnel withdraws operation platform, then entire job platform is hoisted to next construction point.
In the further step 5, the method that rotation rotating platform is fixed on montant is:It will using iron wire Guardrail on rotating platform is fixed on montant cat ladder, to which rotating platform to be fixed on montant.
The configuration of the present invention is simple, easy to operate, job platform takes full advantage of the gap between T beam webs, construction space Abundant, operation platform, guardrail, skirting board are hinged, and once mounting realizes assembling and disassembling cycle operation in place, by rotation, And articulated manner keeps preferable suspension operation platform globality, sound construction, safety higher.
Description of the drawings
Fig. 1:The front view of the present invention;
Fig. 2:The operation platform of the present invention and cat ladder structural schematic diagram;
Wherein:1-operation platform;2-montants;3-hooks;4-rotating platforms;5-upright bars;6-cross bars;7-stulls; 8-cat ladders;9-skirting boards;10-crossbeams.
Specific implementation mode
The following further describes the present invention in detail with reference to the accompanying drawings and specific embodiments.
Such as Fig. 1~2, a kind of T beams suspension operation platform structure, including operation platform 1 and be set to it is more on operation platform 1 Root montant 2, hook 3 is disposed on montant 2, and hook 3 be the rod-like structure for being fixed on 2 upper end edge horizontal cross of montant and extending.This The montant 2 of embodiment has four, the quadrangle for the operation platform 1 that is placed in, and hook 3 is hooked on T flange of beam edge.Wherein, it applies The both lateral sides of work platform 1 are rotatably articulated and connected in the montant gathering on the montant 2 of both sides, being convenient for when carrying by both sides To together, reduces and occupy volume.
Operation platform 1 is the platform structure that width is less than adjacent T beams gap, can be from top to bottom convenient for lifting job platform Operation platform 1 is hung to gap.1 both lateral sides of operation platform are provided with rotating platform 4, for expanding operation platform 1 Transverse width is convenient for the construction of construction personnel.
As shown in Figure 1,4 one end of rotating platform is rotatably articulated and connected in 1 side of operation platform, the other end is to turning over It can be fixedly connected with montant 2 when going to vertical state, rotating platform 4 maintains an equal level when being turned to horizontality with operation platform 1.It turns over When going to vertical state, the handling of job platform, overturning to the width that operation platform 1 can be expanded when horizontality are not influenced.
4 side of rotating platform is provided with guardrail, and guardrail includes more upright bars 5 and cross bar 6, and 5 lower end of upright bar is rotatably cut with scissors It is connected to the one end of rotating platform 4 far from its coercive mechanism in succession, 6 both ends of cross bar are respectively rotatably articulated and connected in montant 2 and stand On bar 5.One end far from its coercive mechanism is provided with two upright bars 5 on rotating platform 4, and more edges are equipped between two upright bars 5 The spaced apart stull 7 (as shown in Figure 2) of vertical direction, 7 both ends of stull are separately fixed in two upright bars 5.
For the ease of the traveling of construction personnel, it is provided with and climbs between two montants 2 of the both lateral sides of operation platform 1 Ladder 8, cat ladder 8 is vertically arranged, and upper end extends to 2 upper end of montant, and lower end extends on operation platform 1.The transverse direction of operation platform 1 Two groups of cat ladders 8 are arranged in both sides, can be convenient for the action of construction personnel one on the other.Wherein, in order to enhance entire platform structure Stability, the present embodiment are provided with crossbeam 10 between two montants 2 of the longitudinal both sides of operation platform 1, and crossbeam 10 is along horizontal horizontal To arrangement, both ends are rotatably articulated and connected on the montant 2 of both sides, guard bar structure of the crossbeam 10 as operation platform 1.It is whole When a platform structure needs to collapse, the montant of both sides can be collapsed to and is superimposed together by swing bolster 10.
In addition, longitudinal both sides of operation platform 1 are provided with skirting board 9,9 lower end of skirting board is rotatably articulated and connected in applying On work platform 1.In fact, be also equipped with skirting board 9 on rotating platform 4, when use, overturns to vertical state, overturns when not in use To level.
The construction of central division wall method of the present embodiment includes the following steps:
1, lifting job platform and slowly decentralization is between adjacent T beams gap by it, until the hook 3 of job platform hooks At T beam wing plates edge,
2, in the decentralization to operation platform 1 of cat ladder 8 of the construction personnel on montant 2, the rotating platform on montant 2 will be fixed on 4 expansion make it maintain an equal level with operation platform 1,
3, skirting board 9 on operation platform 1 and rotating platform 4 is overturn to vertical state,
4, construction personnel relies on operation platform 1 and rotating platform 4 to carry out the construction operation of mid-board,
5, after the completion of construction operation, by the overturning of skirting board 9 to horizontality, rotating platform 4 is overturn, will be rotated using iron wire Guardrail on platform 4 is fixed on montant 2, and construction personnel withdraws operation platform 1, then entire job platform is hoisted to next apply Work point.
After the completion of entire construction, operation platform 1 can be rotated after collapsing rotating platform 4 and collapse the cat ladder 8 of both sides To being superimposed together, reduce the volume of whole device, is convenient for quick handling and installation.
The transverse direction of the present embodiment refers to the left and right directions in Fig. 1, longitudinally refers to the front-rear direction of vertical paper in Fig. 1.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry Personnel are it should be appreciated that the present invention is not limited to the above embodiments, and the above embodiments and description only describe this The principle of invention, various changes and improvements may be made to the invention without departing from the spirit and scope of the present invention, these changes Change and improvement all fall within the protetion scope of the claimed invention.The claimed scope of the invention by appended claims and its Equivalent defines.

Claims (10)

1. a kind of T beams suspension operation platform structure, it is characterised in that:Including operation platform (1) and it is set on operation platform (1) More montants (2);The operation platform (1) is the platform structure that width is less than adjacent T beams gap, and operation platform (1) is horizontal Both sides are provided with rotating platform (4);Described montant (2) lower end is fixed on operation platform (1), and the upper end is provided with and T The fixed fixed structure in beam wing plate edge;Described rotating platform (4) one end is rotatably articulated and connected in operation platform (1) side Portion, the other end can be fixedly connected when being flipped up vertical state with montant (2), rotating platform (4) be turned to it is horizontal Maintain an equal level with operation platform (1) when state.
2. a kind of T beams suspension operation platform structure as described in claim 1, it is characterised in that:Described rotating platform (4) side Portion is provided with guardrail;The guardrail includes more upright bars (5) and cross bar (6);Described upright bar (5) lower end is rotatably hinged It is connected to the one end of rotating platform (4) far from its coercive mechanism;Described cross bar (6) both ends are respectively rotatably articulated and connected in perpendicular On bar (2) and upright bar (5).
3. a kind of T beams suspension operation platform structure as claimed in claim 2, it is characterised in that:On the rotating platform (4) One end far from its coercive mechanism is provided with two upright bars (5), and being equipped with more between two upright bars (5) is vertically spaced cloth The stull (7) set, stull (7) both ends are separately fixed on two upright bars (5).
4. a kind of T beams suspension operation platform structure as described in claim 1, it is characterised in that:The fixed structure is solid The hook (3) being scheduled on montant (2);The hook (3) is the rod-shaped knot for being fixed on the extension of montant (2) upper end edge horizontal cross Structure.
5. a kind of T beams suspension operation platform structure as described in claim 1, it is characterised in that:Laterally positioned at operation platform (1) It is provided with cat ladder (8) on two montants (2) of both sides;The cat ladder (8) is vertically arranged, and upper end extends on montant (2) End, lower end extends on operation platform (1).
6. a kind of T beams suspension operation platform structure as described in claim 1, it is characterised in that:The operation platform (1) Longitudinal both sides are provided with skirting board (9);Described skirting board (9) lower end is rotatably articulated and connected on operation platform (1).
7. a kind of T beams suspension operation platform structure as described in claim 1, it is characterised in that:The operation platform (1) is horizontal It is respectively rotatably articulated and connected to both ends on two montants (2);Two montants positioned at the longitudinal both sides of operation platform (1) (2) crossbeam (10) is provided between;The crossbeam (10) arranges that both ends are rotatably articulated and connected in two along horizontal cross On root montant (2).
8. a kind of T beams interval board construction method, it is characterised in that:Job platform is hoisted to adjacent T beams gap in the vertical direction It is interior, the hook (3) on job platform is hooked on T beam wing plates edge, make lower section operation platform (1) hang on adjacent T beams it Between, it is flat that cat ladder (8) of the construction personnel on montant (2) expands construction on operation platform, along operation platform (1) horizontal direction Platform (1) relies on operation platform (1) the construction mid-board after expanding, after completing construction operation, lifting job platform to next construction Point.
9. a kind of T beams interval board construction method as described in right 8, it is characterised in that:Include the following steps:
1), lifting job platform and slowly decentralization is between adjacent T beams gap by it, until the hook (3) of job platform hooks At T beam wing plates edge;
2), in cat ladder (8) decentralization to operation platform (1) of the construction personnel on montant (2), the rotation on montant (2) will be fixed on Turning platform (4) expansion makes it maintain an equal level with operation platform (1);
3), the skirting board (9) on overturning operation platform (1) and rotating platform (4) is to vertical state;
4), construction personnel relies on operation platform (1) and rotating platform (4) to carry out the construction operation of mid-board;
5), after the completion of construction operation, by skirting board (9) overturning to horizontality, overturning rotating platform (4) is fixed in montant (2) on, construction personnel withdraws operation platform (1), then entire job platform is hoisted to next construction point.
10. a kind of T beams interval board construction method as described in right 9, it is characterised in that:In the step 5, rotary flat is overturn The method that platform (1) is fixed on montant (2) is:The guardrail on rotating platform (4) is fixed on montant (2) using iron wire On, to which rotating platform (4) is fixed on montant (2).
CN201711444345.6A 2017-12-27 2017-12-27 A kind of T beams suspension operation platform structure and T beam interval board construction methods Pending CN108277745A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711444345.6A CN108277745A (en) 2017-12-27 2017-12-27 A kind of T beams suspension operation platform structure and T beam interval board construction methods

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711444345.6A CN108277745A (en) 2017-12-27 2017-12-27 A kind of T beams suspension operation platform structure and T beam interval board construction methods

Publications (1)

Publication Number Publication Date
CN108277745A true CN108277745A (en) 2018-07-13

Family

ID=62802430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711444345.6A Pending CN108277745A (en) 2017-12-27 2017-12-27 A kind of T beams suspension operation platform structure and T beam interval board construction methods

Country Status (1)

Country Link
CN (1) CN108277745A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554079A (en) * 2021-01-27 2021-03-26 中铁二十四局集团有限公司 Novel fabricated ladder well for construction of upper-crossing railway bridge cross beam and application method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107523A (en) * 1997-10-06 1999-04-20 Koyo Kikai Sangyo Kk Hanging scaffold, method for constructing the same, and mounting bracket for standard pipe, etc.
CN201785704U (en) * 2010-09-19 2011-04-06 中铁十二局集团有限公司 Cradle device of continuous box beam folding-segment construction
CN203947422U (en) * 2014-07-02 2014-11-19 中铁四局集团第一工程有限公司 A kind of collapsible aerial work platform
CN206109986U (en) * 2016-08-17 2017-04-19 中国建筑第六工程局有限公司 A simply hang basket for construction of bridge cross slab
CN206219988U (en) * 2016-09-29 2017-06-06 中国一冶集团有限公司 Foldable hanging basket
CN107297816A (en) * 2017-08-21 2017-10-27 五冶集团上海有限公司 The diaphragm plate Cast-in-Situ Segment template system and construction method connected for Precast T-Beam
CN207793892U (en) * 2017-12-27 2018-08-31 中交第二航务工程局有限公司 A kind of T beams suspension operation platform structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11107523A (en) * 1997-10-06 1999-04-20 Koyo Kikai Sangyo Kk Hanging scaffold, method for constructing the same, and mounting bracket for standard pipe, etc.
CN201785704U (en) * 2010-09-19 2011-04-06 中铁十二局集团有限公司 Cradle device of continuous box beam folding-segment construction
CN203947422U (en) * 2014-07-02 2014-11-19 中铁四局集团第一工程有限公司 A kind of collapsible aerial work platform
CN206109986U (en) * 2016-08-17 2017-04-19 中国建筑第六工程局有限公司 A simply hang basket for construction of bridge cross slab
CN206219988U (en) * 2016-09-29 2017-06-06 中国一冶集团有限公司 Foldable hanging basket
CN107297816A (en) * 2017-08-21 2017-10-27 五冶集团上海有限公司 The diaphragm plate Cast-in-Situ Segment template system and construction method connected for Precast T-Beam
CN207793892U (en) * 2017-12-27 2018-08-31 中交第二航务工程局有限公司 A kind of T beams suspension operation platform structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112554079A (en) * 2021-01-27 2021-03-26 中铁二十四局集团有限公司 Novel fabricated ladder well for construction of upper-crossing railway bridge cross beam and application method thereof

Similar Documents

Publication Publication Date Title
CN207048306U (en) Sliding formwork flexibility platform
CN207793892U (en) A kind of T beams suspension operation platform structure
CN107201719B (en) Viaduct anti-collision wall template hoisting transfer machine and anti-collision wall construction method
CN110306774A (en) A kind of installation method and device of spigot-and-socket builder's jack
CN107524284A (en) A kind of regularization pylon protection system and installation method
JP5484983B2 (en) Method for assembling and dismantling bridge moving work device
CN209307862U (en) Pier top Cast-in-Situ Segment fabricated construction platform structure
CN108277745A (en) A kind of T beams suspension operation platform structure and T beam interval board construction methods
CN103758045A (en) Box girder wet joint formwork construction method under space limitation condition
CN206784172U (en) Overpass anti-collision wall formwork hoisting conveyance
JP6339986B2 (en) How to assemble a suspended scaffold using a slide frame
CN205917598U (en) Welded platform travelling car
CN210061545U (en) Prefabricated T roof beam concrete placement platform truck
CN107587711A (en) A kind of regularization assembled overhanging protection canopy and its assembly method
CN108589552B (en) Folding suspension device
CN205369866U (en) Assembled steel ladder
CN215858986U (en) Crane beam operation cage
CN213572930U (en) Self-locking hinged elevator shaft construction platform device
CN204728688U (en) A kind of combined template for architecture
CN205242982U (en) Platform is used in construction of building outer wall
CN212316686U (en) Net piece folding type combined safety hanging basket
CN211037760U (en) Novel instrument formula elevartor shaft construction operation platform
CN209907226U (en) Aerial work construction platform
CN207794582U (en) A kind of hanging large span combination support for shuttering
CN206971699U (en) Combination hanging basket for the construction of wet seam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180713