CN108275542B - A kind of telescopic based on motor control hides high building hanging basket - Google Patents
A kind of telescopic based on motor control hides high building hanging basket Download PDFInfo
- Publication number
- CN108275542B CN108275542B CN201810076168.9A CN201810076168A CN108275542B CN 108275542 B CN108275542 B CN 108275542B CN 201810076168 A CN201810076168 A CN 201810076168A CN 108275542 B CN108275542 B CN 108275542B
- Authority
- CN
- China
- Prior art keywords
- maneuvering board
- gear
- face
- motor
- hanging basket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B9/00—Kinds or types of lifts in, or associated with, buildings or other structures
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66B—ELEVATORS; ESCALATORS OR MOVING WALKWAYS
- B66B11/00—Main component parts of lifts in, or associated with, buildings or other structures
- B66B11/04—Driving gear ; Details thereof, e.g. seals
- B66B11/043—Driving gear ; Details thereof, e.g. seals actuated by rotating motor; Details, e.g. ventilation
Abstract
The invention belongs to high building hanging basket technical fields, especially a kind of telescopic based on motor control hides high building hanging basket, it includes the first wirerope, the first fixed plate, set casing, the first motor, loading shell, L shape fixed link, C-shaped fixed link, the first maneuvering board, the second maneuvering board, third gear, third maneuvering board, the 4th maneuvering board, first motor axis, cavity, movement slots etc., wherein the first fixed plate is mounted on the side of building upper end window side;First wirerope one end is mounted at the first fixed plate lower end surface center;Internal screw thread is provided on axle sleeve inner headed face;Screw rod is mounted on axle sleeve by being threadedly engaged with the internal screw thread on axle sleeve;High building hanging basket in the present invention has when piling up on the ground found near building has barrier; it can achieve the purpose for hiding sundries on ground; the case where sundries collides on hanging basket mechanism and ground is prevented, to play the effect of personnel and article safety in protection hanging basket mechanism.
Description
Technical field
The invention belongs to high building hanging basket technical field, especially a kind of telescopic based on motor control hides high building hanging basket.
Background technique
Current existing high building hanging basket is that one kind can substitute traditional scaffold, can reduce labor intensity, improves work effect
Rate, and the novel high-rise working equipment that can be reused.The use of building hanging basket has been increasingly becoming a kind of trend, in high level
External wall construction, curtain wall installation, thermal insulation construction and maintenance cleaning exterior wall of multilayer high building etc., which are higher by operation, to be widely recognized,
It can be used for the operation of the engineerings such as large tank, bridge and dam simultaneously.Using high building hanging basket, scaffolding can be exempted from.Make to be constructed into
This reduction, operating expenses is the 28% of traditional scaffold, and working efficiency greatly improves.Hanging basket flexible operation, displacement are easy,
It is convenient and practical, but the security risk of high building hanging basket is also exposed simultaneously, due to often being piled up on the ground of building
Many sundries, so that high building hanging basket is soon landing the phenomenon that heap building materials for laying on the ground Shi Huiyu collides, thus right
Personnel and article in high building hanging basket cause unnecessary damage.In order to avoid the generation of such phenomenon, design a kind of based on electricity
Machine control it is telescopic hide high building hanging basket be very it is necessary to.
The present invention design a kind of telescopic based on motor control hide high building hanging basket solve the problems, such as it is as above.
Summary of the invention
(1) the technical problem to be solved in the present invention
The problem to be solved in the present invention is to provide a kind of based on motor control it is telescopic hide high building hanging basket, it is existing to overcome
The problem of having in technology high building hanging basket in landing, often colliding with the sundries for piling up near the building on ground.
(2) technical solution of the present invention
To solve drawbacks described above in the prior art, the present invention discloses a kind of telescopic based on motor control and hides high building
Hanging basket, it adopts the following technical solutions to realize.
A kind of telescopic based on motor control hides high building hanging basket, it is characterised in that: there are many windows for setting on building
Family;Hanging basket mechanism is mounted on building.
Above-mentioned hanging basket mechanism is solid including the first wirerope, the first fixed plate, set casing, the first motor, loading shell, L shape
Fixed pole, C-shaped fixed link, the first maneuvering board, the second maneuvering board, third gear, third maneuvering board, the 4th maneuvering board, first motor
Axis, cavity, movement slots, the 6th gear, fixed block, pouring weight, square groove, motor axis hole, the 7th gear, the first fixed strip, second are consolidated
Determine article, the first T shape guide groove, first sliding groove, second sliding slot, the 2nd T shape guide groove, the first draw runner, the second draw runner, the first T shape guide block,
2nd T shape guide block, first rotating shaft hole, the second shaft hole, the second motor, screw rod, axle sleeve, first gear, the first fixing axle,
Two fixing axles, second gear, third fixing axle, the 4th fixing axle, the second motor shaft, the first support, the second support, wherein first
Fixed plate is mounted on the side of building upper end window side;First wirerope one end is mounted in the first fixed plate lower end surface
At the heart;Internal screw thread is provided on axle sleeve inner headed face;Sleeve outer circle face is mounted on first wirerope one end;Screw rod by on axle sleeve
Internal screw thread be threadedly engaged and be mounted on axle sleeve;Second motor shaft one end on second motor is mounted on screw rod end face;The
Acceleration sensing is installed on two motor;The square groove of perforation is provided on set casing side;At the end face center of set casing
On be provided with motor axis hole, and motor axis hole is communicated with square groove;First rotating shaft hole is symmetrically provided on square groove end face about motor axis hole
With the second shaft hole;Set casing upper surface is mounted on the second motor lower end surface;First motor is mounted on set casing end face
On, and first motor axis passes through motor axis hole;Third gear is mounted on first motor axis by key;In second movement plate end face
It is provided with the first T shape guide groove being not penetrated;The first sliding groove of perforation is provided in second movement plate end face;First shape guide block one end T peace
On square groove end face, and the first T shape guide block is distributed along square groove side;Second maneuvering board passes through the first T shape guide groove and the first T shape
Guide block is slidably installed in set casing, and the external tooth opened on the second maneuvering board lower end surface is engaged with third gear;The
The 2nd T shape guide groove being not penetrated is provided in three movement plate end faces;The second sliding slot of perforation is provided in third movement plate end face;Second
T shape guide block one end is mounted on square groove end face, and the 2nd T shape guide block is distributed far from the first shape guide block side T;Third maneuvering board is logical
Being slidably installed in set casing of the 2nd T shape guide groove and the 2nd T shape guide block is crossed, and opened on third maneuvering board upper surface
External tooth is engaged with third gear;First fixing axle one end is mounted in first rotating shaft hole by bearing;First gear is pacified by key
In the first fixing axle, and first gear is engaged with third gear;First support lower end surface is mounted on the second maneuvering board upper end
Face side;Third fixing axle is mounted on the first support;7th gear is mounted in third fixing axle;First draw runner is mounted on
In one sliding slot;First fixed strip lower end side is mounted on the first draw runner end face;It is fixed that first maneuvering board side is mounted on first
On side, and the external tooth opened on the first maneuvering board lower end surface is engaged with the 7th gear;Two C-shaped fixed links are sliding about first
Item is symmetrical, and two C-shaped fixed link upper ends are installed on the side of the first maneuvering board;Second fixing axle one end passes through axis
It holds and is mounted in the second shaft hole;Second gear is mounted in the second fixing axle by key, and second gear is nibbled with third gear
It closes;Second support lower end surface is mounted on side of the third maneuvering board lower end surface far from the first support;4th fixing axle is mounted on
On two supports;6th gear is mounted in the 4th fixing axle;Second draw runner is mounted in second sliding slot;Second fixed strip upper end one
Side is mounted on the second draw runner end face;Fixed block one end is mounted in the 4th movement plate end face, and upper end of fixing block face is mounted on the
On two fixed strip lower end surfaces, and the external tooth opened on the 4th maneuvering board upper surface is engaged with the 6th gear;The shape fixed link upper end L peace
On lower end of fixing block face;There is cavity on loading shell;The movement slots of perforation are provided in cavity side;Pouring weight side is mounted on
L shape fixed link one end, and pouring weight and movement slots cooperate;Third gear, the 6th gear, the periphery diameter of the 7th gear are homogeneous
Together;The periphery diameter of first gear and second gear is all the same;The periphery diameter dimension of first gear and third gear
The ratio of periphery diameter dimension is 3/7;First maneuvering board, the second maneuvering board, third maneuvering board, the length of the 4th maneuvering board are equal
It is identical;The length dimension of first T shape guide block is the half of the length dimension of the second maneuvering board;First fixing axle and third fixing axle
Between pass through flexible axle connect;It is connected between second fixing axle and the 4th fixing axle by flexible axle.
It is advanced optimized as this technology, solid lubrication oil is coated between the first sliding groove and the first draw runner, second is sliding
Solid lubrication oil is coated between slot and the second draw runner.
It is advanced optimized as this technology, the diameter of first wirerope is 5mm-10mm.
It is advanced optimized as this technology, the diameter of first wirerope is 8mm.
It is advanced optimized as this technology, the first T shape guide block is identical as the length dimension of the 2nd T shape guide block.
It is advanced optimized as this technology, first maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board
Thickness it is all the same.
It is advanced optimized as this technology, first maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board
Length dimension be equal to set casing length dimension.
Be arranged on building in the present invention be easy for there are many effect of window by the personnel of floor each in building or
Person's article is transported on ground;Hanging basket mechanism is mounted on the personnel or cargo that the effect on building is easy in transport high building.
The effect of hanging basket mechanism in the present invention is easy for personnel or cargo in transport high building;The installation of first fixed plate
Effect on the side of building upper end window side is easy for the first wirerope of installation;Set casing is provided with perforation on side
The effect of square groove is easy for the first maneuvering board of installation, the second maneuvering board, third maneuvering board, the 4th maneuvering board etc.;Axle sleeve inner headed face
On open internal thread effect be easy for installation screw rod, thus with screw rod formation be threadedly engaged;Sleeve outer circle face is mounted on first
Effect on wirerope one end is easy for installation screw rod;Screw rod is mounted on axle sleeve by being threadedly engaged with the internal screw thread on axle sleeve
Effect be easy for installation the second motor shaft;Second motor shaft one end on second motor is mounted on the effect on screw rod end face
It is easy for driving the second motor shaft movement, to achieve the purpose that drive screw motion;Acceleration is installed on second motor
The effect of sensing device is whether induction hanging basket mechanism is in equilibrium state, to reach the second motor movement of control, reaches
Stablize the purpose of hanging basket mechanism;The effect in first rotating shaft hole Yu the second shaft hole is symmetrically provided on square groove end face about motor axis hole
It is easy for the first fixing axle of installation and the second fixing axle;The effect that set casing upper surface is mounted on the second motor lower end surface is
It is easily installed and protects the first maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board etc.;The end face center of set casing
Be provided with motor axis hole in place, and the effect that is communicated with square groove of motor axis hole be easy for first motor axis pass through set casing;First
Motor is mounted on set casing end face, and first motor axis is easy for driving third gear fortune across the effect of motor axis hole
It is dynamic;Third gear is easy for the second maneuvering board of driving by the effect that key is mounted on first motor axis and third maneuvering board is transported
It is dynamic;Be provided in second movement plate end face the first T shape guide groove being not penetrated effect be easy for and be mounted on square groove end face the
One T shape guide block cooperation, to achieve the purpose that install the second maneuvering board;The first sliding groove of perforation is provided in second movement plate end face
Effect be easy for installation the first draw runner;The effect that first T shape guide block one end is mounted on square groove end face is easy for the first movement
Plate is moved along square groove direction;Second maneuvering board is slidably installed by the first T shape guide groove and the first T shape guide block in set casing
It is interior, and the effect that the external tooth opened on the second maneuvering board lower end surface is engaged with third gear is easy for the first maneuvering board of installation;The
Being provided with the effect for the 2nd T shape guide groove being not penetrated in three movement plate end faces is formed with the 2nd T shape guide block being mounted on square groove
It is slidably matched;The effect for the second sliding slot for being provided with perforation in third movement plate end face is easy for the second draw runner of installation;2nd T shape is led
Block one end is mounted on square groove end face, and the 2nd T shape guide block far from the effect that the first shape guide block side T is distributed be easy for guidance and
The movement for limiting third maneuvering board, so that third maneuvering board can be moved with left direction;Third maneuvering board passes through the 2nd T shape
Guide groove and the 2nd T shape guide block are slidably installed in set casing, and the external tooth opened on third maneuvering board upper surface and
The effect of three gears engagement is easy for the 4th maneuvering board of installation;First fixing axle one end is mounted in first rotating shaft hole by bearing
Effect be easy for installation first gear;The effect that first support lower end surface is mounted on the second maneuvering board upper surface side is easy for
Third fixing axle is installed;The effect that third fixing axle is mounted on the first support is easy for the 7th gear of installation;7th gear peace
Effect in third fixing axle is easy for driving the first maneuvering board movement;First draw runner is mounted on the effect in first sliding groove
It is easy for the first fixed strip of installation;First fixed strip lower end side is mounted on the first draw runner end face, and the first fixed strip is close
The effect of first T shape guide block distribution is easy for that the first maneuvering board is fixedly mounted;First maneuvering board side is mounted on the first fixed strip
On side, and the effect that the external tooth opened on the first maneuvering board lower end surface is engaged with the 7th gear is easy for the first wirerope of installation
With C-shaped fixed link;Two C-shaped fixed links are symmetrical about the first draw runner, and two C-shaped fixed link upper ends are installed in first
Effect on the side of maneuvering board is easy for that loading shell is fixedly mounted;Second fixing axle one end is mounted on the second shaft by bearing
Effect in hole is easy for installation second gear;Second support lower end surface is mounted on third maneuvering board lower end surface far from the first support
Side effect be easy for installation the 4th fixing axle;The effect that 4th fixing axle is mounted on the second support is easy for installation
Six gears;The effect that 6th gear is mounted in the 4th fixing axle is easy for driving the 4th maneuvering board movement;The installation of second draw runner
Effect in second sliding slot is easy for the second fixed strip of installation;Second fixed strip upper end side is mounted on the end of the second draw runner
Effect on face is easy for installation fixed block;Fixed block one end is mounted on end face of the 4th maneuvering board far from the first T shape guide block
Effect be easy for installation the 4th fixed plate;4th maneuvering board is mounted on upper end of fixing block face, and the 4th maneuvering board upper surface
On the effect engaged with the 6th gear of the external tooth opened be easy for installation L shape fixed link;L shape fixed link upper end is mounted on fixed block
Effect on lower end surface is easy for installation pouring weight;Have the function of that cavity is easy for carrying individuals and cargo on loading shell;Cavity
The effect that the movement slots of perforation are provided on side is easy for the movement of pouring weight;Pouring weight side is mounted on L shape fixed link one end, and again
The effect of block and movement slots cooperation is to balance the weight of personnel and cargo in loading shell;The outer circle of first gear and second gear
Face diameter is all the same;The ratio of the periphery diameter dimension of the periphery diameter dimension and third gear of first gear is 3/7
Effect is the half for allowing the second maneuvering board and third maneuvering board to move its length, and the first maneuvering board and the 4th maneuvering board
The distance of 7/6 times of its length can be moved;First maneuvering board, the second maneuvering board, third maneuvering board, the length of the 4th maneuvering board are equal
Identical effect is easy for saving the space of hanging basket mechanism, so that hanging basket mechanism is using upper more flexible;First sliding groove and first
Solid lubrication oil is coated between draw runner, the effect that solid lubrication oil is coated between second sliding slot and the second draw runner is reduction they it
Between frictional force;The diameter of first wirerope is that the effect of 5mm-10mm is can to guarantee that hanging basket agency security can in this way
Meanwhile saving the use cost of wirerope;First maneuvering board, the second maneuvering board, third maneuvering board, the thickness of the 4th maneuvering board are equal
Identical effect be so that the bulk of hanging basket mechanism is smaller so that hanging basket mechanism using more flexible;First maneuvering board,
Effect of the length dimension equal to the length dimension of set casing of second maneuvering board, third maneuvering board, the 4th maneuvering board is so that solid
The first maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board can smoothly be protected by determining shell;The diameter of first wirerope
Effect for 8mm is so that the security performance and production cost of hanging basket mechanism reach optimum value;The first T shape guide block and
The identical effect of the length dimension of two T shape guide blocks be the second maneuvering board of better limitation and third maneuvering board movement maximum away from
From.
Three) the advantages of the present invention
Relative to traditional high building hanging basket technology, the high building hanging basket in the present invention has the ground near discovery building
On pile up when having barrier, can achieve the purpose for hiding sundries on ground, prevent sundries collision on hanging basket mechanism and ground
It happens, to play the effect of personnel and article safety in protection hanging basket mechanism.
Detailed description of the invention
Fig. 1 is global facility distribution schematic diagram.
Fig. 2 is fabric structure schematic diagram.
Fig. 3 is screw rod mounting structure schematic diagram.
Fig. 4 is the first wirerope mounting structure schematic diagram.
Fig. 5 is the first electric motor mounting structure schematic diagram.
Fig. 6 is third gear installation structure schematic diagram.
Fig. 7 is loading shell structure schematic diagram.
Fig. 8 is the first fixing axle mounting structure schematic diagram.
Fig. 9 is set casing structural schematic diagram.
Figure 10 is axle sleeve mounting structure schematic diagram.
Figure 11 is second gear mounting structure schematic diagram.
Figure 12 is first gear mounting structure schematic diagram.
Figure 13 is the second motor shaft mounting structure schematic diagram.
Figure 14 is the 6th gear installation structure schematic diagram.
Figure 15 is the 7th gear installation structure schematic diagram.
Figure 16 is the second Sportsboard structures schematic diagram.
Figure 17 is third Sportsboard structures schematic diagram.
Figure 18 is third fixing axle mounting structure schematic diagram.
Figure 19 is the first maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board motion principle schematic diagram.
Figure label title: 1, building;2, hanging basket mechanism;3, window;4, the first wirerope;5, the first fixed plate;10,
Set casing;11, the first motor;12, loading shell;13, L shape fixed link;14, C-shaped fixed link;15, the first maneuvering board;17,
Two maneuvering boards;19, third gear;20, third maneuvering board;22, the 4th maneuvering board;25, first motor axis;26, cavity;27, it transports
Dynamic slot;32, the 6th gear;33, fixed block;34, pouring weight;39, square groove;42, motor axis hole;43, the 7th gear;47, first is solid
Determine item;51, the second fixed strip;52, the first T shape guide groove;53, first sliding groove;54, second sliding slot;55, the 2nd T shape guide groove;56,
First draw runner;57, the second draw runner;58, the first T shape guide block;59, the 2nd T shape guide block;60, first rotating shaft hole;61, the second shaft
Hole;62, the second motor;63, screw rod;64, axle sleeve;65, first gear;66, the first fixing axle;67, the second fixing axle;68,
Second gear;69, third fixing axle;70, the 4th fixing axle;71, the second motor shaft;72, the first support;73, the second support.
Specific embodiment
With reference to the accompanying drawings and examples, specific embodiments of the present invention will be described in further detail.Implement below
Example is not intended to limit the scope of the invention for illustrating the present invention.
As shown in Fig. 2, there are many windows 3 for setting on building 1;As shown in Figure 1, hanging basket mechanism 2 is mounted on building 1
On.
As shown in figure 3, above-mentioned hanging basket mechanism 2 is electronic including the first wirerope 4, the first fixed plate 5, set casing 10, first
Machine 11, loading shell 12, L shape fixed link 13, C-shaped fixed link 14, the first maneuvering board 15, the second maneuvering board 17, third gear 19,
Three maneuvering boards 20, the 4th maneuvering board 22, first motor axis 25, cavity 26, movement slots 27, the 6th gear 32, fixed block 33, pouring weight
34, square groove 39, motor axis hole 42, the 7th gear 43, the first fixed strip 47, the second fixed strip 51, the first T shape guide groove 52, first
Sliding slot 53, second sliding slot 54, the 2nd T shape guide groove 55, the first draw runner 56, the second draw runner 57, the first T shape guide block 58, the 2nd T shape are led
Block 59, first rotating shaft hole 60, the second shaft hole 61, the second motor 62, screw rod 63, axle sleeve 64, first gear 65, first are fixed
Axis 66, the second fixing axle 67, second gear 68, third fixing axle 69, the 4th fixing axle 70, the second motor shaft 71, the first support
72, the second support 73, as shown in Figure 1, wherein the first fixed plate 6 is mounted on the side of 1 upper end window of building, 3 side;Such as
Shown in Fig. 4,4 one end of the first wirerope is mounted at 6 lower end surface center of the first fixed plate;As shown in Fig. 5,13,64 inner circle of axle sleeve
Internal screw thread is provided on face;As shown in Fig. 6,13,64 periphery of axle sleeve is mounted on 4 one end of the first wirerope;As shown in fig. 6, spiral shell
Bar 63 is mounted on axle sleeve 64 by being threadedly engaged with the internal screw thread on axle sleeve 64;As shown in figure 13, on the second motor 62
Second motor shaft, 71 one end is mounted on 63 end face of screw rod;Acceleration sensing is installed on second motor 62;Such as Fig. 9 institute
Show, the square groove 39 of perforation is provided on 10 side of set casing;As shown in figure 9, being provided with motor shaft at the end face center of set casing 10
Hole 42, and motor axis hole 42 is communicated with square groove 39;As shown in figure 9, is symmetrically provided on 39 end face of square groove about motor axis hole 42
One shaft hole 60 and the second shaft hole 61;As shown in figure 8,10 upper surface of set casing is mounted on 62 lower end surface of the second motor;
As shown in fig. 6, the first motor 11 is mounted on 10 end face of set casing, and first motor axis 25 passes through motor axis hole 42;Such as Fig. 8
Shown, third gear 19 is mounted on first motor axis 25 by key;As shown in figure 16, it is provided with not on 17 end face of the second maneuvering board
First T shape guide groove 52 of perforation;As shown in figure 16, the first sliding groove 53 of perforation is provided on 17 end face of the second maneuvering board;Such as Fig. 8 institute
Show, 58 one end of the first T shape guide block is mounted on 39 end face of square groove, and the first T shape guide block 58 is distributed along 39 side of square groove;Such as Fig. 6
Shown, the second maneuvering board 17 is slidably installed in set casing 10 by the first T shape guide groove 52 and the first T shape guide block 58,
And the external tooth opened on 17 lower end surface of the second maneuvering board is engaged with third gear 19;As shown in figure 17,20 end face of third maneuvering board
On be provided with the 2nd T shape guide groove 55 being not penetrated;As shown in figure 17, the second sliding slot of perforation is provided on 20 end face of third maneuvering board
54;As shown in fig. 6,59 one end of the 2nd T shape guide block is mounted on 39 end face of square groove, and the 2nd T shape guide block 59 is led far from the first T shape
The distribution of 58 side of block;As shown in figure 8, being slidably matched by the 2nd T shape guide groove 55 and the 2nd T shape guide block 59 of third maneuvering board 20
It is mounted in set casing 10, and the external tooth opened on 20 upper surface of third maneuvering board is engaged with third gear 19;As shown in figure 8,
First fixing axle, 66 one end is mounted in first rotating shaft hole 60 by bearing;As shown in figure 11, first gear 65 is installed by key
In the first fixing axle 66, and first gear 65 is engaged with third gear 19;As shown in figure 18,72 lower end surface of the first support is installed
In 17 upper surface side of the second maneuvering board;As shown in figure 18, third fixing axle 69 is mounted on the first support 72;Such as Figure 12 institute
Show, the 7th gear 43 is mounted in third fixing axle 69;First draw runner 56 is mounted in first sliding groove 53;As shown in figure 14,
One fixed strip, 47 lower end side is mounted on 56 end face of the first draw runner;As shown in figure 14,15 side of the first maneuvering board is mounted on
On one fixed strip, 47 side, and the external tooth opened on 15 lower end surface of the first maneuvering board is engaged with the 7th gear 43;As shown in Figure 10,
Two C-shaped fixed links 14 are symmetrical about the first draw runner 56, and two 14 upper ends of C-shaped fixed link are installed in the first maneuvering board
On 15 side;As shown in figure 8,67 one end of the second fixing axle is mounted in the second shaft hole 61 by bearing;As shown in figure 15,
Second gear 68 is mounted in the second fixing axle 67 by key, and second gear 68 is engaged with third gear 19;As shown in figure 18,
Second support, 73 lower end surface is mounted on side of 20 lower end surface of third maneuvering board far from the first support 72;As shown in figure 15, the 4th
Fixing axle 70 is mounted on the second support 73;6th gear 32 is mounted in the 4th fixing axle 70;As shown in figure 13, the second draw runner
57 are mounted in second sliding slot 54;Second fixed strip, 51 upper end side is mounted on 57 end face of the second draw runner;As shown in figure 8, solid
Determine 33 one end of block and be mounted on 22 end face upper mounted plate upper surface of the 4th maneuvering board to be mounted on 51 lower end surface of the second fixed strip, and
The external tooth opened on four maneuvering boards, 22 upper surface is engaged with the 6th gear 32;As shown in figure 8,13 upper end of L shape fixed link is mounted on
On 33 lower end surface of fixed block;As shown in fig. 7, having cavity 26 on loading shell 12;The movement slots of perforation are provided on 26 side of cavity
27;34 side of pouring weight is mounted on 13 one end of L shape fixed link, and pouring weight 34 and movement slots 27 cooperate;Third gear 19, the 6th gear
32, the periphery diameter of the 7th gear 43 is all the same;First gear 65 and the periphery diameter of second gear 68 are all the same;First
The ratio of the periphery diameter dimension of the periphery diameter dimension and third gear 19 of gear 65 is 3/7;First maneuvering board 15,
Two maneuvering boards 17, third maneuvering board 20, the length of the 4th maneuvering board 22 are all the same;The length dimension of first T shape guide block 58 is
The half of the length dimension of two maneuvering boards 17;It is connected between first fixing axle 66 and third fixing axle 69 by flexible axle;Second is solid
It is connected between dead axle 67 and the 4th fixing axle 70 by flexible axle.
Be coated with solid lubrication oil between the first sliding groove 53 and the first draw runner 56, second sliding slot 54 and the second draw runner 57 it
Between be coated with solid lubrication oil.
The diameter of first wirerope 4 is 5mm-10mm.
The diameter of first wirerope 4 is 8mm.
The first T shape guide block 58 is identical as the length dimension of the 2nd T shape guide block 59.
First maneuvering board 15, the second maneuvering board 17, third maneuvering board 20, the thickness of the 4th maneuvering board are all the same.
First maneuvering board 15, the second maneuvering board 17, third maneuvering board 20, the 4th maneuvering board 22 length dimension be equal to
The length dimension of set casing 10.
Specific embodiment are as follows: as shown in a of Figure 19, when hanging basket mechanism 2 delivers upper personnel or cargo moves downward,
The first maneuvering board 15, the second maneuvering board 17, third maneuvering board 20, the 4th maneuvering board 22 at this time is in set casing 10;When
Need the personnel at the window 3 of 1 two sides of carry construction object perhaps cargo when or realize when having sundries on 1 ground of building, this
When the first motor 11 will will drive first motor axis 25 and rotate, first motor axis 25 will will drive third gear 19 and rotate,
Third gear 19 will will drive first gear 65 and rotate, and first gear 65 will will drive the first fixing axle 66 and move, and first is fixed
Axis 66 will will drive flexible axle movement, and flexible axle will will drive third fixing axle 69 and move;Third fixing axle 69 will will drive the 7th tooth
43 movement of wheel;7th gear 43 will will drive the first maneuvering board 15 and move, and the first maneuvering board 15 at this time will will drive C-shaped and fix
Bar 14 moves, and C-shaped fixed link 14 will will drive loading shell 12 and move, and drives first gear 65 to move in third gear 19 same
When, the third gear 19 of movement will will drive second gear 68 and move, and the second gear 68 of movement will will drive the second fixing axle
67 movements, the second fixing axle 67 will will drive flexible axle movement, and flexible axle will will drive the 6th gear 32 and move, and the 6th gear 32 will
The 4th maneuvering board 22 is driven to move, the 4th maneuvering board 22 of movement at this time will will drive fixed block 33 and move, and fixed block 33 will
It will drive the movement of L shape fixed link 13, L shape fixed link 13 will will drive pouring weight 34 and move, pouring weight 34 and loading shell 12 1 at this time
Movement is played, while the third gear 19 moved will drive the second maneuvering board 17 to move with third maneuvering board 20, the second maneuvering board
17, which will will drive the first support 72, moves, and the first support 72 will will drive third fixing axle 69 and move, and third fixing axle 69 will
The 7th gear 43 is driven to move;Third maneuvering board 20 will will drive the second support 73 and move, and the second support 73 will will drive the 4th
Fixing axle 70 moves, and the 4th fixing axle 70 will will drive the 6th gear 32 and move;As shown in the b of Figure 19, so that the first fortune
Movable plate 15, the second maneuvering board 17, third maneuvering board 20, the 4th maneuvering board 22 move out set casing 10, loading shell 12 at this time
Will smoothly hide out the sundries of the downside of building 1, pouring weight 34 will balance loading shell 12 and its personnel in loading shell 12 or
The weight of person's cargo, to achieve the purpose that the barrier under building 1 on ground is hidden by hanging basket mechanism 2;When the second motor
The acceleration sensing installed on 62, which senses, will drive the second motor 62 to move when hanging basket mechanism 2 is uneven, and second
Motor 62 will will drive the second motor shaft 71 and move, and the second motor shaft 71 will will drive screw rod 63 and move, and screw rod 63 will be
It is moved under the action of axle sleeve 64 along own axes direction, screw rod 63 at this time will successively drive second the 71, second electricity of motor shaft
Motivation 62, set casing 10, the first maneuvering board 15, the second maneuvering board 17, third maneuvering board 20, the 4th maneuvering board 22 are equal to luck
It is dynamic, to achieve the purpose that stable hanging basket mechanism 2.
In conclusion it is restricted embodiment of the invention, all those skilled in the art that above embodiment, which is not,
On the basis of substantive content of the invention, several improvements and modifications can also be made, these improvements and modifications also should be regarded as this
The protection scope of invention.
Claims (7)
1. a kind of telescopic based on motor control hides high building hanging basket, it is characterised in that: there are many windows for setting on building;
Hanging basket mechanism is mounted on building;
The hanging basket mechanism include the first wirerope, the first fixed plate, set casing, the first motor, loading shell, L shape fixed link,
C-shaped fixed link, the first maneuvering board, the second maneuvering board, third gear, third maneuvering board, the 4th maneuvering board, first motor axis, sky
Chamber, movement slots, the 6th gear, fixed block, pouring weight, square groove, motor axis hole, the 7th gear, the first fixed strip, the second fixed strip,
First T shape guide groove, first sliding groove, second sliding slot, the 2nd T shape guide groove, the first draw runner, the second draw runner, the first T shape guide block, the 2nd T
Shape guide block, first rotating shaft hole, the second shaft hole, the second motor, screw rod, axle sleeve, first gear, the first fixing axle, second are consolidated
Dead axle, second gear, third fixing axle, the 4th fixing axle, the second motor shaft, the first support, the second support, wherein first is fixed
Plate is mounted on the side of building upper end window side;First wirerope one end is mounted on the first fixed plate lower end surface center
Place;Internal screw thread is provided on axle sleeve inner headed face;Sleeve outer circle face is mounted on first wirerope one end;Screw rod by on axle sleeve
Internal screw thread, which is threadedly engaged, to be mounted on axle sleeve;Second motor shaft one end on second motor is mounted on screw rod end face;Second
Acceleration sensing is installed on motor;The square groove of perforation is provided on set casing side;
Motor axis hole is provided at the end face center of set casing, and motor axis hole is communicated with square groove;About motor on square groove end face
Axis hole is symmetrically provided with first rotating shaft hole and the second shaft hole;Set casing upper surface is mounted on the second motor lower end surface;First
Motor is mounted on set casing end face, and first motor axis passes through motor axis hole;Third gear is mounted on the first electricity by key
On arbor;The first T shape guide groove being not penetrated is provided in second movement plate end face;The first of perforation is provided in second movement plate end face
Sliding slot;First T shape guide block one end is mounted on square groove end face, and the first T shape guide block is located at the distribution of square groove side;Second maneuvering board
By being slidably installed in set casing for the first T shape guide groove and the first T shape guide block, and opened on the second maneuvering board lower end surface
External tooth engaged with third gear;The 2nd T shape guide groove being not penetrated is provided in third movement plate end face;Third moves in plate end face
It is provided with the second sliding slot of perforation;2nd T shape guide block one end is mounted on square groove end face, and the 2nd T shape guide block is led far from the first T shape
The distribution of block side;Third maneuvering board is slidably installed in set casing by the 2nd T shape guide groove and the 2nd T shape guide block, and
The external tooth opened on third maneuvering board upper surface is engaged with third gear;First fixing axle one end is mounted on first turn by bearing
In axis hole;First gear is mounted in the first fixing axle by key, and first gear is engaged with third gear;First support lower end
Face is mounted on the second maneuvering board upper surface side;Third fixing axle is mounted on the first support;It is solid that 7th gear is mounted on third
On dead axle;First draw runner is mounted in first sliding groove;First fixed strip lower end side is mounted on the first draw runner end face;First fortune
Movable plate side is mounted on the first fixed strip side, and the external tooth opened on the first maneuvering board lower end surface is engaged with the 7th gear;
Two C-shaped fixed links are symmetrical about the first draw runner, and two C-shaped fixed link upper ends are installed in the side of the first maneuvering board
On;Second fixing axle one end is mounted in the second shaft hole by bearing;Second gear is mounted in the second fixing axle by key,
And second gear is engaged with third gear;Second support lower end surface is mounted on one of third maneuvering board lower end surface far from the first support
Side;4th fixing axle is mounted on the second support;6th gear is mounted in the 4th fixing axle;
Second draw runner is mounted in second sliding slot;Second fixed strip upper end side is mounted on the second draw runner end face;Fixed block one
End is mounted in the 4th movement plate end face, and upper end of fixing block face is mounted on the second fixed strip lower end surface, and on the 4th maneuvering board
The external tooth opened on end face is engaged with the 6th gear;L shape fixed link upper end is mounted on lower end of fixing block face;Have on loading shell
Cavity;The movement slots of perforation are provided in cavity side;Pouring weight side is mounted on L shape fixed link one end, and pouring weight is matched with movement slots
It closes;Third gear, the 6th gear, the periphery diameter of the 7th gear are all the same;The periphery of first gear and second gear is straight
Diameter is all the same;The ratio of the periphery diameter dimension of the periphery diameter dimension and third gear of first gear is 3/7;First fortune
Movable plate, the second maneuvering board, third maneuvering board, the length of the 4th maneuvering board are all the same;The length dimension of first T shape guide block is second
The half of the length dimension of maneuvering board;It is connected between first fixing axle and third fixing axle by flexible axle;Second fixing axle and the
It is connected between four fixing axles by flexible axle.
2. a kind of telescopic based on motor control according to claim 1 hides high building hanging basket, it is characterised in that: described
It is coated with solid lubrication oil between first sliding groove and the first draw runner, solid lubrication oil is coated between second sliding slot and the second draw runner.
3. a kind of telescopic based on motor control according to claim 1 hides high building hanging basket, it is characterised in that: described
The diameter of first wirerope is 5mm-10mm.
4. a kind of telescopic based on motor control according to claim 3 hides high building hanging basket, it is characterised in that: described
The diameter of first wirerope is 8mm.
5. a kind of telescopic based on motor control according to claim 1 hides high building hanging basket, it is characterised in that: described
First T shape guide block is identical as the length dimension of the 2nd T shape guide block.
6. a kind of telescopic based on motor control according to claim 1 hides high building hanging basket, it is characterised in that: described
First maneuvering board, the second maneuvering board, third maneuvering board, the thickness of the 4th maneuvering board are all the same.
7. a kind of telescopic based on motor control according to claim 1 hides high building hanging basket, it is characterised in that: described
First maneuvering board, the second maneuvering board, third maneuvering board, the 4th maneuvering board length dimension be equal to set casing length dimension.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810076168.9A CN108275542B (en) | 2018-01-26 | 2018-01-26 | A kind of telescopic based on motor control hides high building hanging basket |
CN201910224663.4A CN109775517A (en) | 2018-01-26 | 2018-01-26 | A kind of the telescopic of motor control hides high building hanging basket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810076168.9A CN108275542B (en) | 2018-01-26 | 2018-01-26 | A kind of telescopic based on motor control hides high building hanging basket |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910224663.4A Division CN109775517A (en) | 2018-01-26 | 2018-01-26 | A kind of the telescopic of motor control hides high building hanging basket |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108275542A CN108275542A (en) | 2018-07-13 |
CN108275542B true CN108275542B (en) | 2019-05-10 |
Family
ID=62805284
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910224663.4A Withdrawn CN109775517A (en) | 2018-01-26 | 2018-01-26 | A kind of the telescopic of motor control hides high building hanging basket |
CN201810076168.9A Expired - Fee Related CN108275542B (en) | 2018-01-26 | 2018-01-26 | A kind of telescopic based on motor control hides high building hanging basket |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910224663.4A Withdrawn CN109775517A (en) | 2018-01-26 | 2018-01-26 | A kind of the telescopic of motor control hides high building hanging basket |
Country Status (1)
Country | Link |
---|---|
CN (2) | CN109775517A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108179869B (en) * | 2018-01-26 | 2019-11-22 | 南京三协电机制造有限公司 | A kind of building construction safety hanging cradle |
CN113833248B (en) * | 2021-10-20 | 2022-10-04 | 浙江恒宸建设集团有限公司 | Assembly type building structure and construction method thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204957056U (en) * | 2015-09-16 | 2016-01-13 | 湖南富马科食品工程技术有限公司 | Packagine machine pulls bagging apparatus |
CN205325110U (en) * | 2016-01-05 | 2016-06-22 | 江苏格律斯科技有限公司 | Fuel tank cap dismounting device with adjustable |
CN206690253U (en) * | 2017-02-23 | 2017-12-01 | 象山仲堇生物科技有限公司 | A kind of waste wood material processing device for building |
CN107495730A (en) * | 2017-09-18 | 2017-12-22 | 安徽工程大学 | A kind of mosquito net |
CN206912037U (en) * | 2017-07-10 | 2018-01-23 | 魏喜荣 | A kind of easy-to-dismount mould punching machine |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100778245B1 (en) * | 2007-08-29 | 2007-11-22 | 한건정공 주식회사 | Inclination control lift apparatus |
-
2018
- 2018-01-26 CN CN201910224663.4A patent/CN109775517A/en not_active Withdrawn
- 2018-01-26 CN CN201810076168.9A patent/CN108275542B/en not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204957056U (en) * | 2015-09-16 | 2016-01-13 | 湖南富马科食品工程技术有限公司 | Packagine machine pulls bagging apparatus |
CN205325110U (en) * | 2016-01-05 | 2016-06-22 | 江苏格律斯科技有限公司 | Fuel tank cap dismounting device with adjustable |
CN206690253U (en) * | 2017-02-23 | 2017-12-01 | 象山仲堇生物科技有限公司 | A kind of waste wood material processing device for building |
CN206912037U (en) * | 2017-07-10 | 2018-01-23 | 魏喜荣 | A kind of easy-to-dismount mould punching machine |
CN107495730A (en) * | 2017-09-18 | 2017-12-22 | 安徽工程大学 | A kind of mosquito net |
Also Published As
Publication number | Publication date |
---|---|
CN109775517A (en) | 2019-05-21 |
CN108275542A (en) | 2018-07-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206088903U (en) | C type steel guide rail formula lift | |
WO2016015450A1 (en) | 2d suspended platform | |
CN108275542B (en) | A kind of telescopic based on motor control hides high building hanging basket | |
CN106064801A (en) | A kind of multilamellar construction lifting platform | |
CN108275543B (en) | A kind of high building hanging basket | |
CN206502489U (en) | A kind of lift | |
CN107352350A (en) | A kind of spiral straight top type safe elevator | |
CN202643238U (en) | Variable cross-section roadway stacker | |
CN208531967U (en) | A kind of elevator guide rail | |
CN205892678U (en) | Multilayer construction lift platform | |
CN108179869B (en) | A kind of building construction safety hanging cradle | |
CN113443535B (en) | Down extending type lifting equipment for well construction and mounting method thereof | |
CN108560897B (en) | A kind of telescopic based on motor control can avoiding barrier high building hanging basket | |
CN114314263A (en) | Sprocket traction type villa elevator | |
CN206336873U (en) | A kind of elevator down mechanical holdout device | |
CN106836899A (en) | Hanging ladder multi-storied garage | |
CN209548716U (en) | A kind of vertical sunpender unit | |
CN207524773U (en) | A kind of spiral straight top type safe elevator | |
CN208585903U (en) | A kind of elevator of intelligent display weight | |
CN205187563U (en) | Computer lab elevator is not had in big load | |
CN207017622U (en) | A kind of elevator safe construction operating platform | |
CN106429749B (en) | A kind of parallel intelligent and safe elevator of double carriages of gear drive | |
CN206915547U (en) | A kind of coal mine well tower | |
CN106348132B (en) | A kind of motor-driven continuous circulation elevator system | |
CN217732371U (en) | Sprocket traction type villa elevator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20190412 Address after: 443200 Xiannu Economic and Trade Zone, Zhijiang City, Yichang City, Hubei Province Applicant after: Zhongyuan Hongyu Construction Group Co.,Ltd. Address before: 215562 No. 26 Shatong Road, Xinzhuang Town, Changshu City, Jiangsu Province Applicant before: CHANGSHU YUTONG PHOTOELECTRIC TECHNOLOGY Co.,Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190510 Termination date: 20220126 |