CN108266190A - A kind of hard rock tunnel construction method - Google Patents

A kind of hard rock tunnel construction method Download PDF

Info

Publication number
CN108266190A
CN108266190A CN201711484246.0A CN201711484246A CN108266190A CN 108266190 A CN108266190 A CN 108266190A CN 201711484246 A CN201711484246 A CN 201711484246A CN 108266190 A CN108266190 A CN 108266190A
Authority
CN
China
Prior art keywords
borehole
group
construction method
tunnel construction
hard rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711484246.0A
Other languages
Chinese (zh)
Inventor
曹苏亚
郑文昌
张星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ranken Railway Construction Group Co Ltd
Original Assignee
Ranken Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ranken Railway Construction Group Co Ltd filed Critical Ranken Railway Construction Group Co Ltd
Priority to CN201711484246.0A priority Critical patent/CN108266190A/en
Publication of CN108266190A publication Critical patent/CN108266190A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/006Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by making use of blasting methods
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines

Abstract

The invention discloses a kind of hard rock tunnel construction methods, include the following steps:(1), it lays borehole and clears up blasthole:First borehole group and the second borehole group are evenly distributed along the circumferential direction of excavation line, second borehole group and the setting of the first borehole group concentric circles, third borehole group is triangle, and a wherein affiliated borehole is using the center of circle of excavation face as vertex, 4th borehole group arranges the bottom for being located at excavation face, is set in a horizontal linear;(2), simultaneously ignition charge obtains rock fracture for installation;(3), along rock fracture tunneling.A rate of advance of the present invention is fast, and the rock after explosion generates a large amount of cracks, and integral strength is less than cantilever excavator and excavates ability, greatly accelerates driving speed.

Description

A kind of hard rock tunnel construction method
Technical field
The present invention relates to constructing tunnel fields, and in particular to a kind of hard rock tunnel construction method.
Background technology
Common technical measures have drilling and blasting method and shield method in existing subway tunnel, and drilling and blasting method is controlled in urban sector vibration velocity Difficulty is big, has destruction to periphery pipeline and structures, security risk is big, while easily causes dispute;Furthermore explosive transport and Keeping controls stringent, it is impossible to ensure to supply continuity, the duration does not ensure;Shield method is of high cost, suitable for long distance tunnel;Together When be confined to its construction, shield machine can play the advantages of it is efficiently quick in uniform geology, in unevenness such as karsts Without clear superiority in even geology.
It is 90MPa that EBZ260 cantilever excavators maximum, which excavates rock strength, when rock strength is more than 90MPa, to equipment Loss increase, and construction speed is slow, leads to claim for eot, and cost increases.
Patent application CN201710709431.9 discloses a kind of hard rock tunnel excavation construction method, and this method essence is quick-fried It breaks digging to be added with cantilever excavator two kinds of the simple of construction method of excavation, narrow-bore tunnel is only applicable to, without fundamentally Control of the blast working in the process to Explosive Vibrating Velocity is solved, the construction effect being added two-by-two more than 2 is not achieved, if the construction method Apply in municipal works, especially wear down in the constructing tunnel of building without clear superiority, it is also possible to can cause house crack, The accidents such as face sedimentation.
Invention content
Present invention aims at a kind of hard rock tunnel construction method is provided, hard rock tunnel difficulty of construction in municipal works is solved Greatly, the problem of construction risk is high, long in time limit, of high cost.
The present invention is achieved through the following technical solutions:
A kind of hard rock tunnel construction method, includes the following steps:
(1), it lays borehole and clears up blasthole:First borehole group and the second borehole group are uniformly arranged along the circumferential of excavation line Row, the second borehole group and the setting of the first borehole group concentric circles, third borehole group is triangle, and wherein affiliated borehole Using the center of circle of excavation face as vertex, the 4th borehole group arranges the bottom for being located at excavation face, is set in a horizontal linear;
(2), simultaneously ignition charge obtains rock fracture for installation;
(3), along rock fracture tunneling.
Air line distance between the borehole two-by-two of first borehole group is 1000mm.
Air line distance between the borehole two-by-two of second borehole group is 1000mm.
The air line distance using the center of circle as the borehole side end point on earth on vertex of third borehole group is 1000mm.
Air line distance between the borehole two-by-two of 4th borehole group is 1330mm.
The radial distance of first borehole group and the second borehole group is 1000mm.
The radial distance of first borehole group and excavation line is 500mm.
Step (3) tunneling carries out the excavation of S-shaped using cantilever excavator from top to bottom along excavation face.
Construction method disclosed in prior art CN201710709431.9 patents is the effect of 1+1=2, of the invention then be 1+ The effect of 1 > 2, in essence, their method, which is that two kinds of construction methods are front and rear, constructs, and can be mutually disengaged reality to each other It is existing, and the present invention is that two kinds of processes combine together, complementary relationship, the present invention strictly controls explosive by this method Dosage, by the control on explosive charge, to reduce Explosive Vibrating Velocity, (Explosive Vibrating Velocity, which crosses conference, influences the structure peace of surrounding building Entirely, cause the consequence of house crack, land subsidence);And CN201710709431.9 makes rock in the case where identical borehole is set Stone generates throwing, and explosive consumption is more, and Explosive Vibrating Velocity cannot be controlled effectively, does not have safely to surrounding building structure It ensures.
The present invention be directed to the rocks that rock strength is more than cantilever excavator excavation ability, take and first loosen rock Blast working increases rock fracture, can reach rapid construction so as to reduce country rock integral strength, reduce cost, reduction duration Purpose, while can effective controlled blasting vibration velocity, can more preferably protect the structure safety of surrounding building.
The distance between adjacent borehole in the present invention in borehole group can reduce 0-500mm, that is, increase the number of borehole, Further reduce Explosive Vibrating Velocity, but explosive charge will not be increased in the present invention.The setting of the distance between the number of borehole and borehole The effect of standing is influenced, is directly related to the generation in crack and distribution situation in country rock, and then influences cantilever excavator and opens The complexity of digging process.
Compared with prior art, the present invention it has the following advantages and advantages:
1st, construction safety, by effective control to Explosive Vibrating Velocity, surrounding building and pipeline will not be caused damage and It destroys;
2nd, a rate of advance is fast, and the rock after explosion generates a large amount of cracks, and integral strength is less than cantilever excavator and excavates ability, Greatly accelerate driving speed;
3rd, construction cost is reduced, the increase of rock fracture reduces integral strength, reduces the attrition of equipment, simultaneously Increase construction speed, thereby reduce cost.
Description of the drawings
Attached drawing described herein is used for providing further understanding the embodiment of the present invention, forms one of the application Point, do not form the restriction to the embodiment of the present invention.In the accompanying drawings:
Fig. 1 is schematic structural view of the invention.
Fig. 2 is the present invention installation explosive location drawing.
Fig. 3 excavates line map for cantilever excavator.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiment and attached drawing, to this Invention is described in further detail, and exemplary embodiment of the invention and its explanation are only used for explaining the present invention, do not make For limitation of the invention.
Embodiment 1
The construction method for excavating hard rock tunnel includes the following steps:
Step 1: borehole is laid and drilling
According to design requirement, with reference to on-site actual situations Reasonable Arrangement borehole, borehole spacing, borehole depth, borehole are included Angle of inclination etc.;Later, borehole is set using YT-28 air drills according to surveying and locating and clears up blasthole, it is ensured that demolition effect.
Step 2: explosive installation and ignition
Emulsion is carried out to each blasthole according to design parameter and millisecond delay electric detonator is installed, according to quick-fried in installation process Principle control dynamite quantity per hole, single hop dose and detonator section of the broken vibration velocity no more than 1cm/s, are checked, really after installation is complete It is ignited under the premise of ensuring safety.
Step 3: cantilever excavator is constructed
Digging excavation is carried out to the rock that crack is developed strongly using cantilever excavator after Danger removal by blasting, is applied with this to improve Work efficiency rate.
Specific reference to Fig. 1 and Fig. 2, laying and drilling to blasthole.The first borehole group and the second borehole in excavation face Group is evenly distributed along the circumferential direction of excavation line, and the second borehole group and the setting of the first borehole group concentric circles, third borehole group form three It is angular, and wherein affiliated borehole, using the center of circle of excavation face as vertex, the 4th borehole group arranges the bottom for being located at excavation face, is in One horizontal linear setting;
Air line distance between the borehole two-by-two of first borehole group is 1000mm.
Air line distance between the borehole two-by-two of second borehole group is 1000mm.
The air line distance using the center of circle as the borehole side end point on earth on vertex of third borehole group is 1000mm.Third borehole group For 3 boreholes, one of borehole is vertex of other two borehole as base using the center of circle of excavation face as vertex.
Air line distance between the borehole two-by-two of 4th borehole group is 1330mm.
The radial distance of first borehole group and the second borehole group is 1000mm.
The radial distance of first borehole group and excavation line is 500mm.
Detonator section may be provided at the first borehole group and the second borehole group is located between the last position borehole below excavation face, with And it is arranged between third borehole group and the last position borehole of the 4th borehole group.
Shown in Fig. 3, explosion can be carried out after explosive installation, after explosion, hard rock generates crack, and crack is distributed in excavation face On, cantilever excavator can be by the excavation for making S types from top to bottom along excavation face.In the process, by the setting to blasthole to quick-fried Broken vibration velocity has carried out effective control, and surrounding building and pipeline will not be caused to damage and destroyed.After explosion, a rate of advance is fast, Rock after explosion generates a large amount of cracks, and integral strength is less than cantilever excavator and excavates ability, accelerates driving speed.
Above-described specific embodiment has carried out the purpose of the present invention, technical solution and advantageous effect further It is described in detail, it should be understood that the foregoing is merely the specific embodiment of the present invention, is not intended to limit the present invention Protection domain, all within the spirits and principles of the present invention, any modification, equivalent substitution, improvement and etc. done should all include Within protection scope of the present invention.

Claims (8)

1. a kind of hard rock tunnel construction method, which is characterized in that include the following steps:
(1), it lays borehole and clears up blasthole:First borehole group and the second borehole group are evenly distributed along the circumferential direction of excavation line, the Two borehole groups and the setting of the first borehole group concentric circles, multiple boreholes of third borehole group are triangle, and wherein affiliated one For a borehole using the center of circle of excavation face as vertex, the 4th borehole group arranges the bottom for being located at excavation face, is set in a horizontal linear;
(2), simultaneously ignition charge obtains rock fracture for installation;
(3), along rock fracture tunneling.
2. hard rock tunnel construction method according to claim 1, which is characterized in that between the borehole two-by-two of the first borehole group Air line distance be 1000mm.
3. hard rock tunnel construction method according to claim 1, which is characterized in that between the borehole two-by-two of the second borehole group Air line distance be 1000mm.
4. hard rock tunnel construction method according to claim 1, which is characterized in that third borehole group using the center of circle as vertex Borehole on earth side end point air line distance be 1000mm.
5. hard rock tunnel construction method according to claim 1, which is characterized in that between the borehole two-by-two of the 4th borehole group Air line distance be 1330mm.
6. hard rock tunnel construction method according to claim 1, which is characterized in that the first borehole group and the second borehole group Radial distance is 1000mm.
7. hard rock tunnel construction method according to claim 1, which is characterized in that the first borehole group and the radial direction of excavation line Distance is 500mm.
8. hard rock tunnel construction method according to claim 1, which is characterized in that step (3) tunneling uses cantilever Development machine carries out the excavation of S-shaped along excavation face from top to bottom.
CN201711484246.0A 2017-12-29 2017-12-29 A kind of hard rock tunnel construction method Pending CN108266190A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711484246.0A CN108266190A (en) 2017-12-29 2017-12-29 A kind of hard rock tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711484246.0A CN108266190A (en) 2017-12-29 2017-12-29 A kind of hard rock tunnel construction method

Publications (1)

Publication Number Publication Date
CN108266190A true CN108266190A (en) 2018-07-10

Family

ID=62772867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711484246.0A Pending CN108266190A (en) 2017-12-29 2017-12-29 A kind of hard rock tunnel construction method

Country Status (1)

Country Link
CN (1) CN108266190A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100676914B1 (en) * 2006-06-13 2007-02-01 주식회사 무진네오테크 Excavating method of tunnel with slight vibration
CN101191416A (en) * 2006-11-27 2008-06-04 杨仁树 Rock lane digging method
CN104482815A (en) * 2014-11-28 2015-04-01 中铁二十三局集团有限公司 Tunnel smooth blasting method
CN104596375A (en) * 2015-02-09 2015-05-06 安徽理工大学 Fully mechanized excavation construction method for rock roadway
CN105937395A (en) * 2015-09-14 2016-09-14 安徽建筑大学 Fast and highly-efficient tunneling method for large section of hard-rock tunnel in coal mine by combination of fully-mechanized tunneling and blasting driving
CN107269284A (en) * 2017-08-18 2017-10-20 徐工集团工程机械有限公司 Hard rock tunnel excavation construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100676914B1 (en) * 2006-06-13 2007-02-01 주식회사 무진네오테크 Excavating method of tunnel with slight vibration
CN101191416A (en) * 2006-11-27 2008-06-04 杨仁树 Rock lane digging method
CN104482815A (en) * 2014-11-28 2015-04-01 中铁二十三局集团有限公司 Tunnel smooth blasting method
CN104596375A (en) * 2015-02-09 2015-05-06 安徽理工大学 Fully mechanized excavation construction method for rock roadway
CN105937395A (en) * 2015-09-14 2016-09-14 安徽建筑大学 Fast and highly-efficient tunneling method for large section of hard-rock tunnel in coal mine by combination of fully-mechanized tunneling and blasting driving
CN107269284A (en) * 2017-08-18 2017-10-20 徐工集团工程机械有限公司 Hard rock tunnel excavation construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
付路军 等: "硬岩松动爆破加综掘机下山联合掘进", 《江西煤炭科技》 *

Similar Documents

Publication Publication Date Title
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
Singh et al. Controlled blasting for long term stability of pit-walls
CN104533467B (en) A kind of high artesian, the method for protecting support in fault disruption zone tunnel
CN107643028A (en) House owed by a citizen weakness section blasting construction method is worn under shallow embedding railway tunnel
CN102518470B (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN103016027B (en) Tunnel or roadway excavating method under weak and broken complicated geological conditions
KR102131823B1 (en) Method of excavation
KR101889961B1 (en) Excavation method for rock blasting having no-vibration
WO2024027030A1 (en) Method for preventing and controlling rock burst at source by means of coal mine roof area fracturing
WO2019109602A1 (en) Short-face coal-pillar-free mining method having zero gangue discharge
CN105443133A (en) Underground rock cumulative charge explosion device and method for non-excavation construction
CN105569693A (en) Underground stable rock stratum large-scale chamber construction method applied to medium-length hole blasting
CN105065004B (en) A kind of Shallow Large Span rock tunnel Portal Section weak blast excavation construction method
CN105135960A (en) Static blasting method of stonework
CN107165641B (en) High inclination-angle ladder way opposite direction excavating construction method in thin layer breaking up hard rock stratum
CN103967001A (en) Hole-forming construction method for punching pile
CN108050902A (en) A kind of tunnel blasting excavation method
CN108266190A (en) A kind of hard rock tunnel construction method
CN114165268B (en) Grading coordination strengthening method for coal roadway tunneling broken surrounding rock
CN110030001A (en) A kind of construction method that mountain tunnel is appeared
RU2490461C1 (en) Method to mine thick steep deposits of unstable ores
JP2014167202A (en) Disassembling method
CN105587321A (en) Collapse column bypassing extraction process
CN112901175A (en) Method for constructing underground laboratory spiral downward slope by applying TBM
RU2010953C1 (en) Method of determination of cracks spreading height in basic zone of working

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180710

RJ01 Rejection of invention patent application after publication