CN108252651B - Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof - Google Patents
Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof Download PDFInfo
- Publication number
- CN108252651B CN108252651B CN201810029026.7A CN201810029026A CN108252651B CN 108252651 B CN108252651 B CN 108252651B CN 201810029026 A CN201810029026 A CN 201810029026A CN 108252651 B CN108252651 B CN 108252651B
- Authority
- CN
- China
- Prior art keywords
- holes
- working face
- roof
- blasting
- blastholes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000005065 mining Methods 0.000 title claims abstract description 43
- 238000000034 method Methods 0.000 title claims abstract description 22
- 239000006185 dispersion Substances 0.000 title abstract 3
- 238000005520 cutting process Methods 0.000 claims abstract description 23
- 238000005553 drilling Methods 0.000 claims abstract description 16
- 239000003245 coal Substances 0.000 claims description 36
- 238000005422 blasting Methods 0.000 claims description 35
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 13
- 239000004927 clay Substances 0.000 claims description 7
- 238000010276 construction Methods 0.000 claims description 7
- 238000009826 distribution Methods 0.000 claims description 6
- 238000005728 strengthening Methods 0.000 claims description 6
- 238000004519 manufacturing process Methods 0.000 claims description 5
- 230000008569 process Effects 0.000 claims description 5
- 238000009434 installation Methods 0.000 claims description 4
- 239000002360 explosive Substances 0.000 claims description 3
- 238000007789 sealing Methods 0.000 claims description 3
- 230000009286 beneficial effect Effects 0.000 abstract description 2
- 239000002689 soil Substances 0.000 description 11
- 230000003014 reinforcing effect Effects 0.000 description 4
- 239000011435 rock Substances 0.000 description 3
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 230000006978 adaptation Effects 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000001680 brushing effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000007789 gas Substances 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000035939 shock Effects 0.000 description 1
- 125000006850 spacer group Chemical group 0.000 description 1
- 231100000331 toxic Toxicity 0.000 description 1
- 230000002588 toxic effect Effects 0.000 description 1
- 230000007704 transition Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/007—Drilling by use of explosives
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B10/00—Drill bits
- E21B10/42—Rotary drag type drill bits with teeth, blades or like cutting elements, e.g. fork-type bits, fish tail bits
- E21B10/43—Rotary drag type drill bits with teeth, blades or like cutting elements, e.g. fork-type bits, fish tail bits characterised by the arrangement of teeth or other cutting elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B10/00—Drill bits
- E21B10/46—Drill bits characterised by wear resisting parts, e.g. diamond inserts
- E21B10/54—Drill bits characterised by wear resisting parts, e.g. diamond inserts the bit being of the rotary drag type, e.g. fork-type bits
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Mechanical Engineering (AREA)
- Earth Drilling (AREA)
- Drilling And Exploitation, And Mining Machines And Methods (AREA)
Abstract
Description
技术领域technical field
本发明属于煤矿开采领域,特别涉及综采工作面多点分散平行式炮眼预裂顶板的方法。The invention belongs to the field of coal mining, and particularly relates to a method for pre-splitting roofs of multi-point dispersed parallel blastholes in fully mechanized mining faces.
背景技术Background technique
综放工作面在安装完毕后,进行初采初放,按照以往经验与方式,为确保工作面顺利初次放顶,需分别在上、下顺槽向工作面侧方向布置多组深孔炮眼,伴随工作面推进过程中以达到超前预裂顶板,使顶板顺利垮落的目的,但该方法打眼时间长,耗费人力、物力、工时较多,且综合预裂效果不佳,往往在工作面推进30-40m左右时,顶板才会出现垮落,悬顶面积大、垮落时伴随的冲击波对工作面作业人员以及机械设备危害较大,顶板大面积垮落时扬起的粉尘、有毒有害气体易造成事故的发生。After the installation of the fully mechanized caving face, the initial mining and initial caving shall be carried out. According to the past experience and methods, in order to ensure the smooth initial caving of the working face, it is necessary to arrange multiple groups of deep hole blastholes in the upper and lower grooves to the side of the working face, respectively. Along with the advancing process of the working face, it can achieve the purpose of pre-splitting the roof in advance and make the roof collapse smoothly. However, this method takes a long time to drill holes, consumes a lot of manpower, material resources, and man-hours, and the comprehensive pre-splitting effect is not good, so it is often advanced on the working face. The roof will collapse when it is about 30-40m. The overhang area is large, and the shock wave accompanying the collapse is more harmful to the working face operators and mechanical equipment. The dust and toxic and harmful gases raised when the roof collapses in a large area prone to accidents.
发明内容SUMMARY OF THE INVENTION
发明目的:为了克服现有技术中存在的不足,本发明提供一种综采工作面多点分散平行式炮眼预裂顶板的方法,有利于顶板的完全垮落,在最大程度内降低了悬顶垮落冲击范围、提高了顶板垮落效率。Purpose of the invention: In order to overcome the deficiencies in the prior art, the present invention provides a method for pre-splitting the roof of the fully mechanized mining face with multi-point dispersed parallel blastholes, which is conducive to the complete collapse of the roof and reduces the suspended roof to the greatest extent. The caving impact range improves the roof caving efficiency.
技术方案:为实现上述目的,本发明的技术方案如下:Technical scheme: in order to achieve the above object, the technical scheme of the present invention is as follows:
综采工作面多点分散平行式炮眼预裂顶板的方法,包括以下步骤:The method for pre-splitting roof of multi-point scattered parallel blasthole in fully mechanized mining face includes the following steps:
步骤一:根据切眼内安装的支架最大及最小采高确定钻机支设角度,并根据顶板岩性确定炮眼终孔深度、角度以及炮眼间距、炮眼个数;Step 1: Determine the drilling rig support angle according to the maximum and minimum mining heights of the brackets installed in the cutting hole, and determine the depth and angle of the final hole of the blasthole, the distance between the blastholes, and the number of blastholes according to the lithology of the roof;
步骤二:在采煤工作面切眼内打设炮眼,所述炮眼间距回采侧煤墙和工作面煤墙打设,且所述炮眼倾斜于工作面顶板、平行于工作面倾向打设,若干炮眼以相等间距沿工作面切眼倾向均匀打设;Step 2: Drill holes in the cutting holes of the coal mining face, the holes are set at the distance between the mining side coal wall and the coal wall of the working face, and the holes are inclined to the top plate of the working face and parallel to the working face. The blastholes are evenly set along the incision tendency of the working face at equal intervals;
步骤三:在上顺槽中打设第一组炮眼,所述第一组炮眼包含上顺槽炮眼S1和上顺槽炮眼S2,上顺槽炮眼S1间距上顺槽回采侧煤墙和工作面煤墙打设,且所述上顺槽炮眼S1倾斜于工作面顶板、平行于顺槽走向打设;所述上顺槽炮眼S2间距上顺槽炮眼S1一米的距离打设;然后在上顺槽长度方向依次间距打设辅助炮眼;Step 3: Set the first group of blastholes in the upper trough, the first group of blastholes includes upper trough holes S1 and upper trough holes S2, and the upper trough holes S1 are spaced from the upper trough mining side coal wall and working face The coal wall is set, and the upper slotted blasthole S1 is inclined to the top plate of the working face and parallel to the slotted direction; the upper slotted blasthole S2 is set at a distance of one meter from the upper slotted blasthole S1; Auxiliary blastholes are set at intervals along the length of the groove;
步骤四:在下顺槽中重复步骤三的施工操作步骤,下顺槽炮眼分布与上顺槽炮眼分布一致;Step 4: Repeat the construction operation steps of Step 3 in the lower slot, and the distribution of blast holes in the lower slot is consistent with the distribution of blast holes in the upper slot;
步骤五:在切眼内、上顺槽和下顺槽的炮眼内均安置爆破药包,封泥时先使用若干个水炮泥轻轻捣入爆破药包底部,再使用黏土炮泥封口,黏土炮泥封泥至孔口;Step 5: Place blasting charge packs in the cut holes, upper and lower blastholes. When sealing the mud, first use a number of water cannon mud to gently smash into the bottom of the blasting charge bag, and then use clay mud to seal it. Clay mud is sealed to the orifice;
步骤六:按工作面切眼至下顺槽至上顺槽的顺序进行爆破,工作面切眼内布置的炮眼由机头向机尾依次进行分组爆破,上、下顺槽内布置的炮眼由里向外依次进行分组爆破;Step 6: The blasting is carried out in the order from the cutting hole of the working face to the lower groove to the upper groove. The blastholes arranged in the cutting hole of the working face are blasted in groups from the nose to the tail of the machine. The blastholes arranged in the upper and lower grooves are blasted from the inside. Carry out group blasting outwards in turn;
步骤七:在工作面推进过程中观察采空区顶板垮落情况,若顶板垮落充分,超前预裂爆破工作结束,若顶板垮落不充分,工作面及上、下顺槽均按照以上方案继续打设炮眼直至顶板垮落。Step 7: Observe the roof collapse in the goaf during the advancing process of the working face. If the roof collapses sufficiently, the advance pre-split blasting work is completed. Continue to punch holes until the top plate collapses.
进一步的,切眼内炮眼在工作面液压支架安装完毕至试生产前进行爆破,上、下顺槽距离工作面煤墙35m范围内的炮眼,在工作面安装完毕至试生产前进行爆破,距离工作面煤墙35m范围外的炮眼,随着工作面回采超前至工作面煤墙35m时进行爆破。Further, the blastholes in the cut hole shall be blasted from the completion of the installation of the hydraulic support on the working face to the trial production. The blastholes outside the 35m range of the coal wall of the working face shall be blasted with the mining advance of the working face to 35m of the coal wall of the working face.
进一步的,爆破采用分组装药分组爆破,每次爆破一组,每次爆破不超过3个炮眼;上顺槽每次爆破2个、下顺槽每次爆破1个、切眼内每次爆破3个,装药采用正向装药,组内炸药采用串联方式连接。Further, the blasting is carried out in groups of sub-groups, one group at a time, and no more than 3 blastholes per blasting; 2 blasting in the upper slot, 1 blasting in the lower slot, and each blasting in the incision hole. 3, the charge is forward charge, and the explosives in the group are connected in series.
进一步的,包括钻杆,所述钻杆的一端安装有可拆卸式的钻头,所述钻头包括基体和一体设置在所述基体上的刀具,所述基体为锥形体结构,且所述基体与钻杆同轴设置,所述基体的小端朝外,且所述基体的小端上设置有刀片组件,所述刀片组件包括若干圆形阵列排列设置的破碎刀片,三组所述刀具等距间隔设置在基体的外侧,且所述刀具高出基体的顶端。Further, it includes a drill rod, one end of the drill rod is mounted with a detachable drill bit, the drill bit includes a base body and a cutter integrally provided on the base body, the base body is a cone structure, and the base body and the The drill rod is coaxially arranged, the small end of the base body faces outward, and the small end of the base body is provided with a blade assembly, the blade assembly includes a number of crushing blades arranged in a circular array, and three sets of the cutters are equidistant. The spacers are provided on the outside of the base body, and the cutter is above the top end of the base body.
进一步的,所述刀具为斜楔式块状结构,且所述刀具的斜楔面朝向钻杆的轴线,且所述斜楔面倾斜向远离基体端部的一侧设置,所述斜楔面上镶嵌设置有至少一个刀口镶件,所述刀口镶件与刀片组件相对设置,所述刀具的外侧镶嵌设置有至少一个强化镶件,所述强化镶件为条状硬质合金,且所述强化镶件平行钻杆的轴线方向设置,所述强化镶件的外侧边缘凸出刀具的外侧面。Further, the cutter is an inclined wedge block structure, and the inclined wedge surface of the cutter faces the axis of the drill rod, and the inclined wedge surface is inclined to the side away from the end of the base body. At least one knife-edge insert is inlaid on the upper part, the knife-edge insert is arranged opposite to the blade assembly, and at least one reinforcement insert is inlaid on the outer side of the tool, and the reinforcement insert is a strip-shaped cemented carbide, and the The reinforcing inserts are arranged parallel to the axial direction of the drill rod, and the outer edges of the reinforcing inserts protrude from the outer side surface of the tool.
进一步的,所述基体上贯通开设有出水孔,若干所述出水孔分别靠近刀具设置,且所述出水孔倾斜朝向相邻刀具的斜楔面设置。Further, water outlet holes are formed through the base body, a plurality of the water outlet holes are respectively arranged close to the cutter, and the water outlet holes are arranged inclined toward the inclined wedge surface of the adjacent cutter.
有益效果:本发明改变以往顺槽集中式预裂的思维模式,采取在切眼及上、下顺槽布置多点分散平行式炮眼超前预裂工作面顶板的方法,有利于顶板的完全垮落,在最大程度内缩小了悬顶面积、降低了悬顶垮落冲击范围、提高了顶板垮落效率,确保了综采工作面安全,可高效、顺利地完成初采初放;还包括了一种用于炮眼打设的钻杆,有效地适应不同的地质条件的炮眼打设,减少卡钻现象。Beneficial effects: The present invention changes the previous thinking mode of centralized pre-splitting along the groove, and adopts the method of arranging multi-point scattered parallel blastholes in the cutting hole and the upper and lower grooves in advance to pre-split the working face roof, which is conducive to the complete collapse of the roof. , to minimize the area of the overhanging roof, reduce the impact range of the overhanging roof collapse, improve the roof collapse efficiency, ensure the safety of the fully mechanized mining face, and complete the initial mining and initial release efficiently and smoothly; it also includes a This kind of drill pipe is used for blast hole drilling, which can effectively adapt to different geological conditions for blast hole drilling and reduce the phenomenon of sticking.
附图说明Description of drawings
附图1为本发明的步骤框图;Accompanying drawing 1 is the step block diagram of the present invention;
附图2为本发明的炮眼布置俯视图;Accompanying drawing 2 is the top view of blasthole arrangement of the present invention;
附图3为本发明的炮眼布置主视图;Accompanying drawing 3 is the front view of blasthole arrangement of the present invention;
附图4为本发明的钻杆结构示意图。Figure 4 is a schematic view of the drill pipe structure of the present invention.
具体实施方式Detailed ways
下面结合附图对本发明作更进一步的说明。The present invention will be further described below in conjunction with the accompanying drawings.
如附图1至附图3所示,综采工作面多点分散平行式炮眼预裂顶板的方法,包括以下步骤:As shown in the accompanying drawings 1 to 3, the method for the multi-point scattered parallel blasthole pre-split roof in the fully mechanized mining face includes the following steps:
步骤一:根据切眼内安装的支架最大及最小采高确定钻机支设角度,并根据顶板岩性确定炮眼终孔深度、角度以及炮眼间距、炮眼个数;Step 1: Determine the drilling rig support angle according to the maximum and minimum mining heights of the brackets installed in the cutting hole, and determine the depth and angle of the final hole of the blasthole, the distance between the blastholes, and the number of blastholes according to the lithology of the roof;
步骤二:在采煤工作面切眼内打设炮眼,所述炮眼间距回采侧煤墙和工作面煤墙打设,且所述炮眼倾斜于工作面顶板、平行于工作面倾向打设,若干炮眼以相等间距沿工作面切眼倾向均匀打设;Step 2: Drill holes in the cutting holes of the coal mining face, the holes are set at the distance between the mining side coal wall and the coal wall of the working face, and the holes are inclined to the top plate of the working face and parallel to the working face. The blastholes are evenly set along the incision tendency of the working face at equal intervals;
步骤三:在上顺槽中打设第一组炮眼,所述第一组炮眼包含上顺槽炮眼S1和上顺槽炮眼S2,上顺槽炮眼S1间距上顺槽回采侧煤墙和工作面煤墙打设,且所述上顺槽炮眼S1倾斜于工作面顶板、平行于顺槽走向打设;所述上顺槽炮眼S2间距上顺槽炮眼S1一米的距离打设;然后在上顺槽长度方向依次间距打设辅助炮眼;Step 3: Set the first group of blastholes in the upper trough, the first group of blastholes includes upper trough holes S1 and upper trough holes S2, and the upper trough holes S1 are spaced from the upper trough mining side coal wall and working face The coal wall is set, and the upper slotted blasthole S1 is inclined to the top plate of the working face and parallel to the slotted direction; the upper slotted blasthole S2 is set at a distance of one meter from the upper slotted blasthole S1; Auxiliary blastholes are set at intervals along the length of the groove;
步骤四:在下顺槽中重复步骤三的施工操作步骤,下顺槽炮眼分布与上顺槽炮眼分布一致;Step 4: Repeat the construction operation steps of Step 3 in the lower slot, and the distribution of blast holes in the lower slot is consistent with the distribution of blast holes in the upper slot;
步骤五:在切眼内、上顺槽和下顺槽的炮眼内均安置爆破药包,封泥时先使用若干个水炮泥轻轻捣入爆破药包底部,再使用黏土炮泥封口,黏土炮泥封泥至孔口;Step 5: Place blasting charge packs in the cut holes, upper and lower blastholes. When sealing the mud, first use a number of water cannon mud to gently smash into the bottom of the blasting charge bag, and then use clay mud to seal it. Clay mud is sealed to the orifice;
步骤六:按工作面切眼至下顺槽至上顺槽的顺序进行爆破,工作面切眼内布置的炮眼由机头向机尾依次进行分组爆破,上、下顺槽内布置的炮眼由里向外依次进行分组爆破;Step 6: The blasting is carried out in the order from the cutting hole of the working face to the lower groove to the upper groove. The blastholes arranged in the cutting hole of the working face are blasted in groups from the nose to the tail of the machine. The blastholes arranged in the upper and lower grooves are blasted from the inside. Carry out group blasting outwards in turn;
步骤七:在工作面推进过程中观察采空区顶板垮落情况,若顶板垮落充分,超前预裂爆破工作结束,若顶板垮落不充分,工作面及上、下顺槽均按照以上方案继续打设炮眼直至顶板垮落。Step 7: Observe the roof collapse in the goaf during the advancing process of the working face. If the roof collapses sufficiently, the advance pre-split blasting work is completed. Continue to punch holes until the top plate collapses.
切眼内炮眼在工作面液压支架安装完毕至试生产前进行爆破,上、下顺槽距离工作面煤墙35m范围内的炮眼,在工作面安装完毕至试生产前进行爆破,距离工作面煤墙35m范围外的炮眼,随着工作面回采超前至工作面煤墙35m时进行爆破。The blasthole in the cut hole shall be blasted from the completion of the installation of the hydraulic support on the working face to before the trial production. The blastholes outside the 35m range of the wall shall be blasted with the mining advance of the working face to 35m of the coal wall of the working face.
爆破采用分组装药分组爆破,每次爆破一组,每次爆破不超过3个炮眼;上顺槽每次爆破2个、下顺槽每次爆破1个、切眼内每次爆破3个,装药采用正向装药,组内炸药采用串联方式连接。The blasting is carried out by sub-group blasting, one group at a time, and no more than 3 blastholes per blasting; 2 blasting in the upper slot, 1 blasting in the lower slot, and 3 blasting in the incision hole each time. The charge adopts forward charge, and the explosives in the group are connected in series.
本发明改变以往顺槽集中式预裂的思维模式,采取在切眼及上、下顺槽布置多点分散平行式炮眼超前预裂工作面顶板的方法,有利于顶板的完全垮落,在最大程度内缩小了悬顶面积、降低了悬顶垮落冲击范围、提高了顶板垮落效率,确保了综采工作面安全,可高效、顺利地完成初采初放。在实际生产应用中,支架完全推进切眼5-10m范围内,顶板完全垮落,比以往方法30-40m范围内方可垮落,缩短了25-30m的顶板垮落步距,在该25-30m范围内工作面可放顶煤回采,可增加采煤产量,提高经济效益。The invention changes the previous thinking mode of centralized pre-splitting along the groove, and adopts the method of arranging multi-point scattered parallel blastholes in the cutting hole and the upper and lower grooves in advance to pre-split the working face roof, which is conducive to the complete collapse of the roof, and the maximum It reduces the area of the overhanging roof, reduces the impact range of the overhanging roof collapse, improves the roof collapse efficiency, ensures the safety of the fully mechanized mining face, and can efficiently and smoothly complete the initial mining and initial caving. In the actual production application, the support is fully advanced within the range of 5-10m of the cut hole, and the roof completely collapses. Compared with the previous method, the collapse can only be achieved within the range of 30-40m, which shortens the roof collapse step distance of 25-30m. The working face within the range of -30m can be caving top coal for mining, which can increase the coal mining output and improve the economic benefits.
下面以在阿克苏地区一采煤作业生产中实际应用为例说明,在综放工作面呈规则的长方形布置,切眼长60m,上顺槽长706.2m,下顺槽长703.5m,工作面平均走向长度为704.9m,煤层厚度5.2~5.8m,平均5.5m,煤层倾角22°~30°,工作面坡度平均约27°,工作面切眼长度为58.6m,上、下顺槽和切眼掘进过程中均未揭露断裂构造,工作面地质条件简单。工作面采用ZF4800/17/30液压支架和ZFG4800/19/32型过渡液压支架支护顶板,在现场根据切眼内安装的支架最大及最小采高确定钻机支设角度,并根据顶板岩性确定炮眼终孔深度、角度以及炮眼间距、炮眼个数,最终确定炮眼打设方案。The following is an example of the actual application in a coal mining operation in Aksu area. The fully mechanized caving face is arranged in a regular rectangle. The length of the cut hole is 60m, the length of the upper groove is 706.2m, and the length of the lower groove is 703.5m. The average working face is The strike length is 704.9m, the coal seam thickness is 5.2~5.8m, the average is 5.5m, the coal seam dip angle is 22°~30°, the working face slope is about 27° on average, and the cutting hole length of the working face is 58.6m. No fault structure was exposed during the excavation process, and the geological conditions of the working face were simple. The working face adopts ZF4800/17/30 hydraulic support and ZFG4800/19/32 type transition hydraulic support to support the roof. The drilling rig support angle is determined according to the maximum and minimum mining height of the support installed in the cut hole on site, and is determined according to the lithology of the roof. The depth and angle of the end hole of the blasthole, as well as the distance between the blastholes and the number of blastholes, finally determine the blasthole setting plan.
工作面切眼扩刷完毕后,切眼内分别在距离上顺槽回采侧煤墙3m位置和90m位置,各布置一台KHYD155型岩石钻机。使用KHYD155岩石钻机,按照设计要求在切眼内施工预裂顶板眼,切眼内钻眼施工完毕后,钻机分别运输至上下顺槽施工顺槽内的预裂顶板眼。根据顶板岩性、之前类似工作面预裂顶板经验、所选岩石钻机适应条件、顺槽内装备的设备影响等因素综合考虑,预裂顶板眼设计如下:After the cutting hole and brushing of the working face are completed, a KHYD155 rock drilling rig is arranged in the cutting hole at a distance of 3m and 90m from the coal wall on the mining side of the upper trough respectively. The KHYD155 rock drilling rig is used to construct pre-split roof holes in the cut holes according to the design requirements. After the drilling in the cut holes is completed, the drilling rigs are transported to the pre-split roof holes in the upper and lower grooves for construction. According to the comprehensive consideration of the roof lithology, previous experience of pre-splitting the roof of similar working face, the adaptation conditions of the selected rock drilling rig, and the influence of the equipment in the trough, the pre-split roof hole is designed as follows:
切眼内预裂顶板眼设计:第一组炮眼:距离上顺槽回采侧煤墙3m、距离工作面煤墙0.5m、与工作面顶板夹角为75°、平行于工作面倾向(朝向上端头方向)、终孔深度8m。其余炮眼:每个炮眼与上一个炮眼间距3m、距离工作面煤墙0.5m、与工作面顶板夹角75°、平行于工作面倾向(朝向上端头方向)、终孔深度8m。工作面切眼倾向长度186.5m,合计布置炮眼60个。Roof hole design for pre-splitting in the cut hole: The first group of blastholes: 3m away from the coal wall on the mining side of the upper trough, 0.5m away from the coal wall of the working face, the angle with the roof of the working face is 75°, and the inclination parallel to the working face (toward the upper end) head direction), the final hole depth is 8m. Other blastholes: the distance between each blasthole and the previous blasthole is 3m, the distance from the coal wall of the working face is 0.5m, the angle with the roof of the working face is 75°, the inclination parallel to the working face (towards the upper end), and the depth of the final hole is 8m. The length of the incision inclination of the working face is 186.5m, and a total of 60 blastholes are arranged.
上顺槽预裂顶板眼设计:S1#炮眼:距离切眼老塘侧煤墙5m、距离上顺槽回采侧煤墙1.5m、与顺槽顶板夹角为75°、平行于顺槽走向(朝向采空区方向)、终孔深度8m。Design of pre-split roof hole in the upper trough: S1# blasthole: 5m away from the coal wall on the old pond side of the cutting hole, 1.5m from the coal wall on the mining side of the upper trough, and the angle with the roof of the trough is 75°, parallel to the trend of the trough ( toward the gob direction), the final hole depth is 8m.
S2#炮眼:距离切眼老塘侧煤墙5m、距离上顺槽回采侧煤墙2.5m、与顺槽顶板夹角为75°、平行于顺槽走向(朝向采空区方向)、终孔深度8m。S2# blasthole: 5m away from the coal wall on the old pond side of the cutting hole, 2.5m from the coal wall on the side of the upper trough, and the angle with the roof of the trough is 75°, parallel to the trend of the trough (towards the goaf), and the end hole Depth 8m.
其余炮眼:每组炮眼距离上一组炮眼间距3m,每组炮眼其余参数参照S1#、S2#炮眼施工。Other blastholes: The distance between each group of blastholes is 3m from the previous group of blastholes, and the other parameters of each group of blastholes refer to the construction of S1# and S2# blastholes.
下顺槽预裂顶板眼设计:X1#炮眼:距离切眼老塘侧煤墙5m、距离下顺槽回采侧煤墙1.5m、与顺槽顶板夹角75°、平行于顺槽走向(朝向采空区方向)、终孔深度8m。其余炮眼:每个炮眼距离上一个炮眼间距3m,每组炮眼其余参数参照X1#炮眼施工。Design of pre-split roof hole in the lower trough: X1# blasthole: 5m away from the coal wall on the side of the cutting hole, 1.5m from the coal wall on the mining side of the lower trough, with an angle of 75° with the roof of the trough, parallel to the trend of the trough (towards the side of the trough) gob direction), and the final hole depth is 8m. Other blastholes: The distance between each blasthole is 3m from the previous blasthole, and the rest parameters of each group of blastholes refer to X1# blasthole construction.
炮眼施工完毕后进行分组依次爆破,保证工作面的推进和煤层回采。After the blasthole construction is completed, the blasting is carried out in groups and sequentially to ensure the advancement of the working face and the recovery of the coal seam.
如附图4所示,一种用于综采工作面多点分散平行式炮眼预裂顶板的钻杆1,所述钻杆1的一端安装有可拆卸式的钻头,方便维修与更换,所述钻头包括基体8和一体设置在所述基体8上的刀具2,所述基体8为锥形体结构,且所述基体8与钻杆同轴设置,所述基体8的小端朝外,且所述基体8的小端上设置有刀片组件5,所述刀片组件5包括若干圆形阵列排列设置的破碎刀片,三组所述刀具2等距间隔设置在基体8的外侧,且所述刀具2高出基体8的顶端。由于在实际的开采工作中,不同地域、不同区域、不同深度的地质,其土壤性质不同,有坚硬、粘性大或土质疏松等多种环境,一般的钻杆在遇到土质较松的土壤和粘性较大的土质时,极易发生粘钻或者卡钻的情况,导致钻杆磨损,十分影响进度,通过本发明中的钻杆,可有效地解决土壤粘钻和卡钻的问题,通过突出的刀具进行先行破碎并对碎土进行导流,使碎土有较多的空间向钻孔外部移动,避免了土壤堆积集聚在刀具与待钻土壤之间,减少了黏土粘钻及卡钻的情况,并同时通过刀片组件5进行进一步的碎土,防止大块的土块的形成。As shown in Figure 4, a drill pipe 1 used for multi-point dispersed parallel blasthole pre-split roof in fully mechanized mining face, one end of the drill pipe 1 is equipped with a detachable drill bit, which is convenient for maintenance and replacement. The drill bit includes a
所述刀具2为斜楔式块状结构,且所述刀具的斜楔面7朝向钻杆的轴线,且所述斜楔面7倾斜向远离基体8端部的一侧设置,所述斜楔面7上镶嵌设置有至少一个刀口镶件6,所述刀口镶件6与刀片组件5相对设置,钻取的土壤通过斜楔面向刀具围合的中间区域移动,并在钻杆转动时通过破碎刀片破碎,同时刀口镶件6起到增加刀具强度的作用,减少刀具的磨损,所述刀具2的外侧镶嵌设置有至少一个强化镶件3,所述强化镶件3为条状硬质合金,且所述强化镶件3平行钻杆的轴线方向设置,所述强化镶件3的外侧边缘凸出刀具2的外侧面。在钻孔时,通过强化镶件3及刀口镶件6对土壤中的碎石或坚硬物进行破碎,提高刀具的寿命。The tool 2 is a wedge block structure, and the wedge surface 7 of the tool faces the axis of the drill rod, and the wedge surface 7 is inclined to the side away from the end of the
所述基体8上贯通开设有出水孔4,若干所述出水孔4分别靠近刀具2设置,且所述出水孔4倾斜朝向相邻刀具2的斜楔面设置。减少钻孔时的钻头发热量,增加刀具的耐用性,同时也可对斜楔面上的刀口镶件6进行降热及冲洗,防止卡钻。The
以上所述仅是本发明的优选实施方式,应当指出:对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。The above is only the preferred embodiment of the present invention, it should be pointed out that: for those skilled in the art, without departing from the principle of the present invention, several improvements and modifications can also be made, and these improvements and modifications are also It should be regarded as the protection scope of the present invention.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810029026.7A CN108252651B (en) | 2018-01-12 | 2018-01-12 | Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810029026.7A CN108252651B (en) | 2018-01-12 | 2018-01-12 | Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108252651A CN108252651A (en) | 2018-07-06 |
CN108252651B true CN108252651B (en) | 2020-01-10 |
Family
ID=62726660
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810029026.7A Expired - Fee Related CN108252651B (en) | 2018-01-12 | 2018-01-12 | Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108252651B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110645854B (en) * | 2019-09-29 | 2022-03-04 | 太原理工大学 | Arrangement of pre-split blasting holes and on-line detonation method for hard roof in the initial mining of fully mechanized mining face |
CN110685691B (en) * | 2019-11-16 | 2020-12-01 | 山东科技大学 | A kind of hard roof forced roofing method |
CN113107486B (en) * | 2021-03-02 | 2023-09-19 | 库车县科兴煤炭实业有限责任公司 | Initial mining and initial setting drilling construction method for coal face |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102322262A (en) * | 2011-09-12 | 2012-01-18 | 山东科技大学 | Colliery isolated island coal column crossheading bump control method |
CN102797492A (en) * | 2012-08-31 | 2012-11-28 | 中国矿业大学 | Arrangement method for precracking roof for roof-cutting roadway |
CN104481537A (en) * | 2014-11-18 | 2015-04-01 | 山西潞安环保能源开发股份有限公司 | Gas phase fracturing roof weakening treatment and safety caving method |
CN105865279A (en) * | 2016-04-15 | 2016-08-17 | 中国矿业大学(北京) | Block cutting type cut hole forced caving detonation method |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9458670B2 (en) * | 2014-05-13 | 2016-10-04 | Hypersciences, Inc. | Ram accelerator system with endcap |
-
2018
- 2018-01-12 CN CN201810029026.7A patent/CN108252651B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102322262A (en) * | 2011-09-12 | 2012-01-18 | 山东科技大学 | Colliery isolated island coal column crossheading bump control method |
CN102797492A (en) * | 2012-08-31 | 2012-11-28 | 中国矿业大学 | Arrangement method for precracking roof for roof-cutting roadway |
CN104481537A (en) * | 2014-11-18 | 2015-04-01 | 山西潞安环保能源开发股份有限公司 | Gas phase fracturing roof weakening treatment and safety caving method |
CN105865279A (en) * | 2016-04-15 | 2016-08-17 | 中国矿业大学(北京) | Block cutting type cut hole forced caving detonation method |
Also Published As
Publication number | Publication date |
---|---|
CN108252651A (en) | 2018-07-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105569659B (en) | A kind of tunnel hydraulic slotted liner technique directional blasting cuts top pressure relief method | |
CN105178961B (en) | A kind of roomy stope borehole drilling stage open stope afterwards filling mining method | |
US20200040727A1 (en) | Method for mining ultra-thick coal seam by utilizing goaf solid backfilling technique | |
CN108252651B (en) | Method for fully mechanized mining face multipoint dispersion parallel type blast hole presplitting roof | |
CN104790949B (en) | Huge thick tight roof high methane high seam Roof Control and method and the drilling machine improving gas drainage under suction efficiency | |
CN113465461B (en) | Large-section tunnel blasting hole-reducing layout method | |
CN110778324B (en) | A hard rock roadway excavation method integrating drilling, water exploration and milling | |
CN113153292B (en) | Method of hydraulic fracturing to quickly pass through hard rock faults in underground coal mining working faces of coal mines | |
CN112983418A (en) | Method for hydraulic fracturing pressure relief of coal mine underground coal face withdrawal channel | |
CN113959283A (en) | Blasting construction method for large-section tunnel | |
CN107975373A (en) | A kind of lower continuous digging hard-rock mine method of mechanization of liquid-gas phase transition induction | |
CN109026028A (en) | A kind of rock roadway in coal mine mechanical rock breaking method | |
CN111577309A (en) | Multi-hob sectional type wedge cracking hard rock mass method | |
CN106703808A (en) | Method for increasing end top coal recovery rate by means of thick coal seam fully-mechanized caving face mining roadway drilling presplitting | |
CN110879027A (en) | Efficient energy-gathered blasting rapid tunneling method for half coal rock roadway | |
CN110359910B (en) | Fully mechanized caving high-level filling mining method for thick coal seam strips under coal mine railway | |
CN114810075B (en) | Steeply inclined horizontal sectional top coal caving pressure relief method | |
CN110906822A (en) | A kind of deep hole blasting charge and detonation method based on digital detonator lowering foundation | |
CN111022053B (en) | Blasting ore removal method for reducing caving of filling body of stoping two-step mining room | |
CN118548059A (en) | Mining method for protecting surrounding rock of steep-dip thick ore body | |
CN104612690A (en) | Strip-shaped drilling type coal mining method for steep inclined thin coal seam | |
CN204920811U (en) | Mud drum PDC drill bit is prevented to step wing | |
CN105064994B (en) | A kind of airborne continuous grooving release coal mining equipment and method | |
CN109882189B (en) | Horseshoe-shaped half-section shield machine suitable for fault fracture zone and construction method | |
CN109322668B (en) | Slotting method in steeply inclined and extremely unstable ore bodies |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20200110 |