CN108252517A - Prefabricated concrete structure laminated floor slab girder muscle covers construction method - Google Patents

Prefabricated concrete structure laminated floor slab girder muscle covers construction method Download PDF

Info

Publication number
CN108252517A
CN108252517A CN201711038952.2A CN201711038952A CN108252517A CN 108252517 A CN108252517 A CN 108252517A CN 201711038952 A CN201711038952 A CN 201711038952A CN 108252517 A CN108252517 A CN 108252517A
Authority
CN
China
Prior art keywords
catching groove
shape
construction
concrete structure
floor slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711038952.2A
Other languages
Chinese (zh)
Other versions
CN108252517B (en
Inventor
索屹楠
高杰文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201711038952.2A priority Critical patent/CN108252517B/en
Publication of CN108252517A publication Critical patent/CN108252517A/en
Application granted granted Critical
Publication of CN108252517B publication Critical patent/CN108252517B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The present invention relates to a kind of prefabricated concrete structure laminated floor slab girder muscle to cover construction method, makes cladding system, by steel plate bending into a kind of open-type catching groove;Catching groove is in V-shape;The bottom of V-shape catching groove is plane;V-shape catching groove after tying up muscle, is placed into the upper end of girder rib, then floor is poured by construction of precast floorslab, prefabricated superimposed sheet formwork;After pouring and finishing standing a period of time, operating personnel station carries out floor on V-shape catching groove the operation of plucking process, and before steam-cured, V-shape catching groove is removed for next piece of construction of precast floorslab.Prefabricated concrete structure laminated floor slab girder muscle of the present invention covers construction method, simple in structure easy to operate, improves construction quality, improves construction efficiency, reduces construction cost.

Description

Prefabricated concrete structure laminated floor slab girder muscle covers construction method
Technical field
The present invention relates to a kind of construction techniques, are to be related to a kind of prefabricated concrete structure overlapping building specifically Plate girder muscle covers construction method.
Background technology
When prefabricated concrete structure laminated floor slab produces, to ensure precast concrete board member and cast-in-place overlapping layers It combines closely, so as to prevent floor preformed layer and in-situ layer from misplacing, we select truss-like laminated floor slab, in factory's production, We only pour preformed layer, and girder rib is exposed, and concrete residue is attached on exposed girder rib, and very big difficulty is brought to production Degree.
At present, superimposed sheet girder rib covering method there is no special equipment, and traditional way is:Pvc pipe is cut in two, is detained On girder rib, but pvc pipe turnover utilization rate is too low, area coverage is smaller, and since arc-shaped pipe surface is smooth, easily It comes off, the operation that the processes such as plucking are carried out on girder rib that operating personnel can not stablize.
Invention content
Deficiency in for the above-mentioned prior art, the present invention provide a kind of simple in structure easy to operate, raising construction quality, Improve the prefabricated concrete structure laminated floor slab girder muscle covering construction method of construction efficiency.
The technical solution used in the present invention is:
A kind of prefabricated concrete structure laminated floor slab girder muscle covers construction method, includes the following steps:
Cladding system is made, by steel plate bending into a kind of open-type catching groove;Catching groove is in V-shape;The bottom of V-shape catching groove is flat Face;
V-shape catching groove after tying up muscle, is placed into the upper end of girder rib, then by construction of precast floorslab, prefabricated superimposed sheet formwork Floor is poured;
After pouring and finishing standing a period of time, operating personnel station carries out floor on V-shape catching groove the operation of plucking process, Before steam-cured, V-shape catching groove is removed for next piece of construction of precast floorslab.
The V-shape catching groove opening size is 17 millimeters --- 22 millimeters;V-shape catching groove bottom width is 40 millimeters --- 50 millimeters.
The advantageous effect of the present invention compared with the prior art:
Prefabricated concrete structure laminated floor slab girder muscle of the present invention covers construction method, and simple in structure easy to operate, raising is applied Working medium amount improves construction efficiency, reduces construction cost.
Description of the drawings
Fig. 1 is that the V-shape catching groove of prefabricated concrete structure laminated floor slab girder muscle covering construction method of the present invention is three-dimensional Structure diagram;
Fig. 2 is that the truss-like laminated floor slab of prefabricated concrete structure laminated floor slab girder muscle covering construction method of the present invention pours The exposed dimensional structure diagram of girder rib before preformed layer;
Fig. 3 is that the truss-like laminated floor slab of prefabricated concrete structure laminated floor slab girder muscle covering construction method of the present invention pours The dimensional structure diagram of V-shape catching groove is provided with before preformed layer on exposed girder rib.
Critical piece symbol description in attached drawing:
In figure:
1st, V-shape catching groove 2, girder rib.
Specific embodiment
Referring to the drawings and embodiment the present invention will be described in detail:
Attached drawing 1-3 includes the following steps it is found that a kind of prefabricated concrete structure laminated floor slab girder muscle covering construction method:
Cladding system is made, by steel plate bending into a kind of open-type catching groove;Catching groove is in V-shape;The bottom of V-shape catching groove 1 is flat Face;
V-shape catching groove 1 after tying up muscle, is placed into the upper end of girder rib 2, so by construction of precast floorslab, prefabricated superimposed sheet formwork Floor is poured afterwards;
After pouring and finishing standing a period of time, operating personnel station carries out floor on V-shape catching groove 1 behaviour of plucking process Make, before steam-cured, V-shape catching groove is removed for next piece of construction of precast floorslab.
The V-shape catching groove opening size is 17 millimeters --- 22 millimeters;V-shape catching groove bottom width is 40 millimeters --- 50 millimeters.
Prefabricated concrete structure laminated floor slab girder muscle of the present invention covers construction method, simple in structure easy to operate, carries High construction quality improves construction efficiency, reduces construction cost.
The above described is only a preferred embodiment of the present invention, not the structure of the present invention is made in any form Limitation.Any simple modification, equivalent change and modification that every technical spirit according to the present invention makees above example, Belong in the range of technical scheme of the present invention.

Claims (2)

1. a kind of prefabricated concrete structure laminated floor slab girder muscle covers construction method, which is characterized in that includes the following steps:
Cladding system is made, by steel plate bending into a kind of open-type catching groove;Catching groove is in V-shape;The bottom of V-shape catching groove is flat Face;
V-shape catching groove after tying up muscle, is placed into the upper end of girder rib, then by construction of precast floorslab, prefabricated superimposed sheet formwork Floor is poured;
After pouring and finishing standing a period of time, operating personnel station carries out floor on V-shape catching groove the operation of plucking process, Before steam-cured, V-shape catching groove is removed for next piece of construction of precast floorslab.
2. prefabricated concrete structure laminated floor slab girder muscle covering construction method according to claim 1, it is characterised in that: The V-shape catching groove opening size is 17 millimeters --- 22 millimeters;V-shape catching groove bottom width is 40 millimeters --- 50 millimeters.
CN201711038952.2A 2017-10-31 2017-10-31 Construction method for covering truss ribs of composite floor slab with prefabricated concrete structure Active CN108252517B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711038952.2A CN108252517B (en) 2017-10-31 2017-10-31 Construction method for covering truss ribs of composite floor slab with prefabricated concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711038952.2A CN108252517B (en) 2017-10-31 2017-10-31 Construction method for covering truss ribs of composite floor slab with prefabricated concrete structure

Publications (2)

Publication Number Publication Date
CN108252517A true CN108252517A (en) 2018-07-06
CN108252517B CN108252517B (en) 2021-03-30

Family

ID=62721455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711038952.2A Active CN108252517B (en) 2017-10-31 2017-10-31 Construction method for covering truss ribs of composite floor slab with prefabricated concrete structure

Country Status (1)

Country Link
CN (1) CN108252517B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29818094U1 (en) * 1998-10-09 1999-01-14 Geiger Christian contraption   to the   Backfill   from   Flat filling bricks
CN2698878Y (en) * 2004-04-16 2005-05-11 浙江杭萧钢构股份有限公司 Truss type superimposed sheet
CN201217872Y (en) * 2008-06-18 2009-04-08 黑龙江宇辉新型建筑材料有限公司 Prefabricated stacking floor
CN204983312U (en) * 2015-06-24 2016-01-20 沈阳建筑大学 Novel precast concrete coincide floor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE29818094U1 (en) * 1998-10-09 1999-01-14 Geiger Christian contraption   to the   Backfill   from   Flat filling bricks
CN2698878Y (en) * 2004-04-16 2005-05-11 浙江杭萧钢构股份有限公司 Truss type superimposed sheet
CN201217872Y (en) * 2008-06-18 2009-04-08 黑龙江宇辉新型建筑材料有限公司 Prefabricated stacking floor
CN204983312U (en) * 2015-06-24 2016-01-20 沈阳建筑大学 Novel precast concrete coincide floor

Also Published As

Publication number Publication date
CN108252517B (en) 2021-03-30

Similar Documents

Publication Publication Date Title
CN105649197B (en) Rear pouring tape construction method of Afforestation Landscape under the conditions of in advance
CN104032869B (en) A kind of Prefabricated stacking floor and precast construction method thereof
CN106368365B (en) Logical muscle formula reinforced concrete slab structure and its making and assembly method
CN107859059B (en) Connecting node structure of prefabricated sandwich side wall and prefabricated superposed bottom plate and construction method thereof
CN106284653B (en) A kind of construction method that balcony construct capital interspaces in advance
CN205421919U (en) Sealing device and stagnant water structure of post -cast strip or construction joint
CN106948502A (en) A kind of water-proof top cover and its construction method
CN101798853B (en) Construction method of thin-wall box body hollow floor slab
CN108252517A (en) Prefabricated concrete structure laminated floor slab girder muscle covers construction method
CN103015597A (en) Construction method of energy-saving ribbed cavity floor
CN208451857U (en) Mold is arranged in a kind of assembled architecture precast concrete wall side keyway
CN1702252B (en) Method for processing concrete mesh-beam floor system
RU2598951C2 (en) Installation for producing concrete slab fitted with cladding elements
CN104110131B (en) A kind of wall structure post hollow concrete formwork
CN207727733U (en) The spliced gutter that can be had enough to meet the need
CN103015598A (en) Construction method of energy-saving ribbed cavity floor
CN207582763U (en) Two-way close spelling laminated floor slab connecting joint structure with groove type embedded part
CN104631675B (en) A kind of two-sided prefabricated superimposed sheet
CN109356126A (en) Double of Precast Gallery structure and gallery construction method
CN213952977U (en) Anti-leakage structure and pouring mold
CN204983312U (en) Novel precast concrete coincide floor
CN212405654U (en) Ribbed prestressed laminated slab
RU2017134367A (en) METHOD FOR PRODUCING BALCONY AND BALCONY
CN106968366A (en) A kind of construction method for pouring constructional column free removal template
CN204491948U (en) A kind of two-sided prefabricated superimposed sheet

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant