CN108239896A - Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method - Google Patents

Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method Download PDF

Info

Publication number
CN108239896A
CN108239896A CN201810235567.5A CN201810235567A CN108239896A CN 108239896 A CN108239896 A CN 108239896A CN 201810235567 A CN201810235567 A CN 201810235567A CN 108239896 A CN108239896 A CN 108239896A
Authority
CN
China
Prior art keywords
disease treatment
foundation base
existing railway
longeron
usage plan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810235567.5A
Other languages
Chinese (zh)
Inventor
张李林
杨俊东
张守振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fourth Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Original Assignee
Fourth Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fourth Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd filed Critical Fourth Engineering Co Ltd of China Railway 23rd Bureau Group Co Ltd
Priority to CN201810235567.5A priority Critical patent/CN108239896A/en
Publication of CN108239896A publication Critical patent/CN108239896A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2/00General structure of permanent way

Abstract

The invention discloses a kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structures, and the main beam including being used to support rail, the both ends of the main beam are fixed.The construction method based on above-mentioned constructing structure is further included, is included the following steps:First, rail is removed;The 2nd, main beam and secondary crossbeam are installed;3rd, longeron is set up;The 4th, rail is installed;5th, refoot construction.It is an object of the invention to:For the problem that existing existing railway Disease Treatment of Foundation Base construction technology, exist can not realize do not cut off traffic in the case of construct, a kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method are provided.The constructing structure and construction method make somebody a mere figurehead rail track, can guarantee that Business Line normally under the premise of driving, carries out thorough Disease Treatment of Foundation Base.

Description

Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method
Technical field
The invention belongs to construction of railways technical fields, and in particular, to a kind of existing railway Disease Treatment of Foundation Base line frame Empty constructing structure and the construction method based on the constructing structure.
Background technology
The existing railway design standard that China is now in operation state is relatively low, in recent years, due to railway speed increase, rate of traffic flow Greatly, start many reasons such as heavy haul train, prolonged fatigue rupture, winter freeze-thaw damage, ground water pressure be excessive, to runing In substrate destruction it is more serious.Caused by bottom slab crack, frost boiling, arch deformation etc. in various degree the defects of and disease it is more next It is more, circuit stabilization is influenced, jeopardizes traffic safety.Existing construction technology can only first stop the operation of rail track, then carry out iron Road Disease Treatment of Foundation Base construction, which results in huge economic losses.
Invention content
It is an object of the invention to:For existing existing railway Disease Treatment of Foundation Base construction technology, existing can not realize The problem of being constructed in the case of not cutting off traffic provides a kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure And construction method.The constructing structure and construction method make somebody a mere figurehead rail track, under the premise of can guarantee that Business Line is normally driven a vehicle, into The thorough Disease Treatment of Foundation Base of row.
To achieve these goals, the technical solution adopted by the present invention is:
A kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure, the main beam including being used to support rail, institute The both ends for stating main beam are fixed.Using main beam structure, first the both ends of main beam structure are fixed, then are laid in the top of crossbeam Rail, so as to construct to the substrate below rail.This programme can meet under the premise of Business Line is normally driven a vehicle, Carry out thorough Disease Treatment of Foundation Base.
Preferably, the buttress of fixed setting is further included, the both ends of the crossbeam are arranged on the top of the buttress, Using branch pier structure, the fixation for making main beam both ends is more stable.
Preferably, formwork erection is poured and is made the buttress at the scene, ensures the stability of support construction, so as to improve The safety of circuit.
Preferably, sleeper head is further included, the sleeper head is arranged between the main beam and the buttress.Pillow Wood has good antivibration characteristic, and this programme makes the vibration resistance of structure stronger.
Preferably, longeron and secondary crossbeam are further included;The longeron is arranged on the top of the main beam;The pair Crossbeam is arranged on the lower section of the longeron.In the extending direction of rail, i.e., on longitudinal direction, by setting up longeron, and main beam it Between set up the mode of secondary crossbeam, the support for making rail is more dense, so as to improve travel safety.
Preferably, the main beam and secondary crossbeam are connect respectively by U-shaped connector with the longeron, connecting portion Part is simply firm, convenient for in-site installation and dismounting.
Preferably, the longeron is set side by side with two, and the longeron is connected by connecting plate to be extended, and two The connector of longeron is interlaced.It is set up in parallel two longerons, it is ensured that the stability of structure;And be staggered, it further improves vertical The stress intensity of beam.
Based on the construction method of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure, include the following steps:
First, rail is removed;
The 2nd, main beam and secondary crossbeam are installed;
3rd, longeron is set up;
The 4th, rail is installed;
5th, refoot construction.
Based on above-mentioned constructing structure, since its is simple in structure so that difficulty of construction substantially reduces.And the construction party of this programme In method, step 1 to the four fundamental rules workshop off period that is able to be expert at can carry out.Finally, the construction that refoots is carried out, carries out thorough substrate Disease Treatment.
Preferably, in the step 1, further include rail cut-off, the operation of erection joint clamping plate.Due to substrate Disease may be in local appearance, and rail longitudinal length is longer.At this point, in order to avoid constructing on a large scale, to the stabilization of rail Property impacts.This programme then under the premise of rail stability is influenced as small as possible, carries out local Disease Treatment of Foundation Base.
Preferably, in the step 2, the operation that accurate adjustment is carried out to the position of main beam and secondary crossbeam is further included. Ensure the position precision of main beam and secondary crossbeam, so as to ensure the accuracy of rail, improve travel safety.
In conclusion by adopting the above-described technical solution, compared with the prior art, the beneficial effects of the invention are as follows:
1st, the present invention can guarantee that Business Line normally under the premise of driving, carries out thorough Disease Treatment of Foundation Base, economy and society Meeting remarkable benefit, has and widely promotes the use prospect.
2nd, section of the present invention is small, does not invade limit, is especially suitable for constructing in the narrow space of single-track tunnel, meets single-track tunnel hole Interior aerial hardened link safety clearance requirement solves the headroom limitation problem of single-track railway tunnel.
3rd, overhead transmission line needs skylight to reduce, more light and flexible during construction, especially during constructing tunnel, to existing Structure is destroyed smaller, it is only necessary to gutter be repaired after the completion of construction.
4th, difficulty of construction reduces, and particularly convenient for having bad luck, installing and reinforcing in tunnel, greatly shortens fixed track usage plan Construction period.
5th, meet large span overhead transmission line requirement, meet intensity, stability requirement.
Description of the drawings
Fig. 1 is the main structure diagram of the present invention.
Fig. 2 is the A portions enlarged structure schematic diagram of the present invention.
Fig. 3 is the side structure schematic view of the present invention.
Fig. 4 is the work progress schematic diagram of the present invention.
Specific embodiment
In order to make the purpose , technical scheme and advantage of the present invention be clearer, with reference to the accompanying drawings and embodiments, it is right The present invention is further elaborated.It should be appreciated that specific embodiment described herein is only to explain the present invention, not For limiting the present invention.
The present embodiment discloses a kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure, as shown in Figs. 1-3, to answer For constructing tunnel, the main beam 1 including being used to support rail, the both ends of the main beam 1 are fixed.Main beam uses H Shaped steel, size are 290mm × 200mm × 8mm × 12mm.
Specifically, as shown in Figs. 1-3, the present embodiment further includes the buttress 2 of fixed setting, the both ends setting of the crossbeam 1 In the top of the buttress 2.Formwork erection is poured and is made the buttress 2 at the scene.Sleeper head 3 is further included, the sleeper head 3 is arranged on Between the main beam 1 and the buttress 2.Branch pier foundation, implantation reinforcing bar, dog, steel plate, asbestos are poured using high-strength mortar The buttress of paper composition meets required precision, faces combination forever and greatly improves construction efficiency.
Specifically, as shown in Figs. 1-3, the present embodiment further includes longeron 4 and secondary crossbeam 5;The longeron 4 is arranged on the master The top of crossbeam 1;The pair crossbeam 5 is arranged on the lower section of the longeron 4.The main beam 1 and secondary crossbeam 5 are respectively by U-shaped Connector 6 is connect with the longeron 3.The longeron 4 is set side by side with two, and the longeron 4 is connected by connecting plate 7 to be extended, And the connector of two longerons 4 is interlaced.Rail distance rod is provided between the longeron 4 and rail.Longeron uses biplate 45B works Word girder steel, longeron size are 450mm × 152mm × 13.5mm × 10mm, are 87.4kg/m per linear meter(lin.m.) weight, joint length is 12m, longeron is longitudinally connected to be bolted using the installation of connecting plate 7, and connecting plate 7 is steel plate.Secondary crossbeam uses H profile steel, and size is 290mm×200mm×8mm×12mm.Major and minor crossbeam is uniformly distributed arrangement by 1m spacing, and buttress is symmetrically and evenly divided by 3m spacing Cloth is arranged.
Specifically, as shown in Figs. 1-3, rail is fixed on the top of the main beam 1 and secondary crossbeam 4 by fastener 8.It is described Insulation spacer is both provided between main beam 1 and rail and between the secondary crossbeam 4 and rail.Use spring strip II type fastener Install the needs that L-type nylon spacer solves insulation of track circuit additional between rail and gauge apron, it is good to ensure to insulate It is good, the normal use for the Block signaling equipment that automatically closes up.
Fixed track usage plan makes somebody a mere figurehead scheme using sunk type, and using the more light self-control steel construction of weight, use is had bad luck in hole Hand fit's flat car cart can be completed.Main force structure is longitudinal main stress structure-longeron and lateral main stress The major and minor crossbeam of structure.Buttress, major and minor crossbeam, longeron and U-shaped connector composition stress frame is selected to make somebody a mere figurehead track circuit And it reinforces.Its whole force path is:Rail → major and minor crossbeam (H profile steel) → longeron (I-steel) → sleeper head → buttress.It protects Demonstrate,prove fixed track usage plan after Rail inspection, circuit rigidity and stability, it is ensured that Heavy Haul Freight Train by when be perfectly safe.This Outside, using the loads change of strain transducer monitoring of structures, dynamic monitoring is to reduce construction risk.
This embodiment reduces a large amount of mechanical work and labour, construction site electricity consumption uses tunnel intraoral illumination power Electricity, the internal combustion apparatus used in tunnel are small machine, and energy-saving and emission-reduction in work progress reach preferable environment protecting.No It needs to hang from wheel running device and material is had bad luck in fortune flat car tunnel, does not need to track lifter progress steel beam lifting operation. The large-scale circuit transport lifting special equipment such as track crane, flat car is not needed to, through calculating, 6000 yuan of track strengthening cost reduction/ M, fixed track usage plan construction only needs 12 skylight points (each 3~4h of skylight) from preparation of construction to aerial completion, than other engineering methods At least reduce 5 skylight blocking times, economic and social benefit is notable.
The construction method of the present invention described in detail below, as shown in figure 4, including the following steps:
1st, light, cable change shifting and reinforce
Light, cable carry out site inspection before changing shifting to existing optical cable, determine light, cable length and change shifting scheme, according to Scene needs to prepare optical cable connecting box, optical cable, cable, punch device, expansion bolt, iron wire, mackintosh etc. in advance.Use electricity Hammer is drilled in tunnel side wall and installs expansion bolt.Optical cable lengthens optical cable using optical cable connecting box and carries out continued access, and cable makes Continued access is carried out with jumper.It is unified to be bundled using iron wire after the completion of light, the continued access of cable scene, at binding using gum cover pipe into Row protection.Light, cable after reinforcing is hung on the expansion bolt that tunnel side wall is installed, it is firm using iron wire reinforce.
2nd, rail cut-off, erection joint clamping plate
It is investigated for the rail in the range of fixed track usage plan and defect detecting test, it is ensured that rail state of the art is good.By 25m The rail end that rail is cut-off for 12.5m rail and after cut-offfing punch and erection joint clamping plate.
3rd, change and move draining, pour branch pier foundation
Change and check water flow, water (flow) direction, and make ditch stopend in advance before moving draining.Preparation, which changes, moves draining use φ 100mm wired hoses, pour φ 150mm steel pipes, bamboo blanket template and TK grouting materials that buttress uses.Manual demolition ditch And cable trough cover boards, it is transported to refuge chamber and carries out pile, pile is neat, firm, unsuitable excessively high, and meeting railway security gauge will It asks.Steel pipe is transferred, and hose is penetrated in steel pipe in buttress position.In ditch, upstream position installs stopend, template packet card Firmly hose, temporary clay is blocked after blocking using TK grouting materials at gap.Ditch checks drainage situation after changing, it is ensured that flows in ditch Water is smoothly discharged by hose.Installation form carries out pouring buttress using TK grouting materials at the steel pipe of buttress position decentralization.
4th, sleeper head is set up
The preferable conservator of quality is selected, conservator is cut-off into 600mm bolster wood using internal combustion handsaw, sleeper makes after cut-offfing Binding reinforcing is carried out with φ 8mm iron wires and iron wire is inlaid into sleeper using hand hammer, it is ensured that surfacing.Select quality preferable Plank, specification is the same as sleeper head size, thickness 50mm, 30mm, 20mm.It is set up in length and breadth for every layer when sleeper pier is set up, using taking off Nail layering nail connects, and in the steel plate of top layer setting 600mm × 600mm × 20mm, is carried out between steel plate, longeron and sleeper head using railway spike It is fixed.Implantation reinforcing bar is carried out at high-strength mortar buttress, reinforcing bar is welded with top layer steel plate.Buttress elevation is according to circuit longitudinal slope It is controlled, is controlled using spirit level, total powerstation.
5th, longeron and major and minor crossbeam are unloaded on the way
Longeron and major and minor the crossbeam building up station near job location carry out entrucking without barrier, and entrucking is hung using 1 25t Vehicle lifts ,+2 N17 flat cars cooperation shipments of 2 JY290 railcars.It is live manually using crowbar, argue, the rope made of hemp, mounting board etc. Tool unloads, transports and pile.It unloads and is completed in point, pile is neatly firm, carries out support pad reinforcing when necessary, and intrusion is forbidden to pacify Full gauge.
6th, rail is removed, major and minor crossbeam is installed
It is recycled during manual demolition fastener according to the classification of fastener specification, convenient for being installed and used when restoring.When rail is removed, Rail is transported to other than major and minor construction of beam range temporarily storage using hanger rail device and pulley, original position is transported back after installing It is installed.Major and minor crossbeam is forbidden to overlap with rail foot, avoids causing track circuit red band, using rubber mat plate as Support pad is isolated.In order to adjust track level, height, used using 2mm, 5mm, 10mm nylon back plate as track accurate adjustment.In order to Ensure that crossbeam position is accurate, rail is marked using paint in both sides, and crossbeam, which penetrated on rear center's alignment rail, to be marked Heart point.Railway roadbed ballast is using bag weaved pack pile other than boundary of works area.
7th, longeron, accurate adjustment are set up
Unilateral longeron sets up 2 450mm I-steel, and 2 I-steel are forbidden to occur using alternate joint when longeron is matched Opposite joint.Longeron connector is attached and is fastened using connecting plate and bolt.Longeron is connect with crossbeam using U-shaped card and steel Board slot use is bolted and fastens, and installs spring washer during connection additional to prevent bolt looseness.Longeron height, horizontal adjustment are adopted It is carried out with choker block asbestos paper, it is uneven to be controlled using spirit level.
8th, detaching sleeper, fastener for installing
Rail is removed at tunnel bottom before excavating, the sleeper of unit is excavated in extraction, installs crossbeam fastener system.In order to avoid there is rail Road circuit red band, fastener system install insulation spacer additional, and the card of L-type nylon material is installed between gauge apron and the rail flange of rail Slot.Fastener use spring strip II type fastener, install and be combined according to 1435mm gauges, gauge rail to when transfiniting use 0-6,2-4 Nylon baffle seat adjustment.Line frame dead band installs rail distance rod additional.
9th, rail, installation sleeper are removed
Rail is removed in tunnel bottom after the completion of refooting, and is inserted into sleeper, fastener for installing.
10th, it is upper to be cut, make firm by ramming
Ballast backfill is carried out using the ballast of pack.Line tamping is carried out using flexible shaft tamping machine, in the range of reinforcing rail It makes firm by ramming at pillow bottom, it is ensured that the closely knit stabilization of railway roadbed.
11st, longeron and major and minor crossbeam are removed
Longeron and major and minor crossbeam first removed when removing longeron using electric track flatcar by longeron transport tunnel and under Road.Major and minor crossbeam is first segmented when removing removes circuit rail, treats that major and minor crossbeam restores circuit rail and fastener after removing. Major and minor crossbeam carries out benefit quarrel to major and minor crossbeam position immediately after having removed, makes firm by ramming, it is ensured that railway roadbed is closely knit, stablizes.Major and minor crossbeam Longeron is transported into tunnel and lower road using electric track flatcar after dismounting.
12nd, circuit geometric dimension is rebuild
Using locomotive traction K13 pneumatic ballast vehicles to tunnel refoot regulation location carry out unloading quarrel.Using tamping car to tunnel It refoots and renovates the mechanical levelling of location progress, makes firm by ramming.After the completion of making firm by ramming, circuit is opened after reaching train clearance condition, it is artificial on duty Patrol foster, circuit ladder raises speed to constant speed.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all essences in the present invention All any modification, equivalent and improvement made within refreshing and principle etc., should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure, it is characterised in that:Including being used to support rail Main beam (1), the both ends of the main beam (1) are fixed.
2. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 1, it is characterised in that:Also wrap The buttress (2) of fixed setting is included, the both ends of the crossbeam (1) are arranged on the top of the buttress (2).
3. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 2, it is characterised in that:It is described Formwork erection is poured and is made buttress (2) at the scene.
4. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 2, it is characterised in that:Also wrap Sleeper head (3) is included, the sleeper head (3) is arranged between the main beam (1) and the buttress (2).
5. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 1, it is characterised in that:Also wrap Include longeron (4) and secondary crossbeam (5);The longeron (4) is arranged on the top of the main beam (1);The pair crossbeam (5) is arranged on The lower section of the longeron (4).
6. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 5, it is characterised in that:It is described Main beam (1) and secondary crossbeam (5) are connect respectively by U-shaped connector (6) with the longeron (3).
7. existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 5, it is characterised in that:It is described Longeron (4) is set side by side with two, and the longeron (4) is connected by connecting plate (7) to extend, and the connector phase of two longerons (4) Mutually staggeredly.
It is 8. special based on the construction method of the existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure described in claim 5 Sign is, includes the following steps:
First, rail is removed;
The 2nd, main beam and secondary crossbeam are installed;
3rd, longeron is set up;
The 4th, rail is installed;
5th, refoot construction.
9. the construction method of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 8, special Sign is:In the step 1, further include rail cut-off, the operation of erection joint clamping plate.
10. the construction method of existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure according to claim 8, special Sign is:In the step 2, the operation that accurate adjustment is carried out to the position of main beam and secondary crossbeam is further included.
CN201810235567.5A 2018-03-21 2018-03-21 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method Pending CN108239896A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810235567.5A CN108239896A (en) 2018-03-21 2018-03-21 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810235567.5A CN108239896A (en) 2018-03-21 2018-03-21 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method

Publications (1)

Publication Number Publication Date
CN108239896A true CN108239896A (en) 2018-07-03

Family

ID=62700073

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810235567.5A Pending CN108239896A (en) 2018-03-21 2018-03-21 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method

Country Status (1)

Country Link
CN (1) CN108239896A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371765A (en) * 2018-11-19 2019-02-22 中铁第四勘察设计院集团有限公司 Pass through the track deformation control structure in the Railway Tunnel of large-scale activity tomography
CN115839045A (en) * 2022-12-15 2023-03-24 中铁西北科学研究院有限公司 Roadbed uneven settlement deformation area renovation process and frozen soil renovation roadbed structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003082603A (en) * 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track
EP1621671A2 (en) * 2004-07-29 2006-02-01 Atros Espana, S.A. A high safety, modular system for provisionally supporting working railway tracks during under-track works.
CN205259051U (en) * 2015-12-22 2016-05-25 中铁三局集团有限公司 Railway existing line large -span crossbeam system of making somebody a mere figurehead
CN106192620A (en) * 2016-07-28 2016-12-07 中铁第四勘察设计院集团有限公司 A kind of railway ballastless track supporting layer and substructure change method
CN106758590A (en) * 2016-12-20 2017-05-31 中国神华能源股份有限公司 The construction beam and construction method of railroad track are changed under the conditions of for not stopping transport
CN107268352A (en) * 2017-08-03 2017-10-20 中国铁道科学研究院铁道建筑研究所 Refoot the fixed track usage plan device of operation for tunnel
CN208038934U (en) * 2018-03-21 2018-11-02 中铁二十三局集团第四工程有限公司 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003082603A (en) * 2001-09-12 2003-03-19 East Japan Railway Co Construction method for structure under rail track
EP1621671A2 (en) * 2004-07-29 2006-02-01 Atros Espana, S.A. A high safety, modular system for provisionally supporting working railway tracks during under-track works.
CN205259051U (en) * 2015-12-22 2016-05-25 中铁三局集团有限公司 Railway existing line large -span crossbeam system of making somebody a mere figurehead
CN106192620A (en) * 2016-07-28 2016-12-07 中铁第四勘察设计院集团有限公司 A kind of railway ballastless track supporting layer and substructure change method
CN106758590A (en) * 2016-12-20 2017-05-31 中国神华能源股份有限公司 The construction beam and construction method of railroad track are changed under the conditions of for not stopping transport
CN107268352A (en) * 2017-08-03 2017-10-20 中国铁道科学研究院铁道建筑研究所 Refoot the fixed track usage plan device of operation for tunnel
CN208038934U (en) * 2018-03-21 2018-11-02 中铁二十三局集团第四工程有限公司 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
常凯等: "重载铁路隧底隆起病害换底整治技术", 铁道建筑, no. 04, pages 23 - 26 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371765A (en) * 2018-11-19 2019-02-22 中铁第四勘察设计院集团有限公司 Pass through the track deformation control structure in the Railway Tunnel of large-scale activity tomography
CN109371765B (en) * 2018-11-19 2024-04-02 中铁第四勘察设计院集团有限公司 Rail deformation control structure in high-speed railway tunnel crossing large movable fault
CN115839045A (en) * 2022-12-15 2023-03-24 中铁西北科学研究院有限公司 Roadbed uneven settlement deformation area renovation process and frozen soil renovation roadbed structure
CN115839045B (en) * 2022-12-15 2023-10-20 中铁西北科学研究院有限公司 Roadbed differential settlement deformation region remediation process and frozen soil remediation roadbed structure

Similar Documents

Publication Publication Date Title
CN111676819A (en) Jacking construction method for combined type temporary beam continuous reinforced line large-span frame structure bridge
CN102926299A (en) Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN110230261B (en) Mounting construction method for upper frame beam of double-layer synchronous beam
CN109235292B (en) Railway bridge beam replacing process
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
CN102817325A (en) Construction method of simply supported-continuous switching system of negative moment beam prestressed precast box beam
WO2016138776A1 (en) Lowly disposed line structure used in medium-low speed magnetic levitation traffic engineering fill section
CN112227416A (en) Construction method of assembled steel pipe support and distribution beam combined support
CN208038934U (en) Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure
CN108979664A (en) Existing subway tunnel based on mobile casting platform protects steel structure pouring construction method
CN109137633A (en) Level crossing mouth railway roadbed and preparation method
CN108239896A (en) Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method
CN114150593B (en) Simple arch bridge dismantling and reconstructing structure and arch bridge dismantling and reconstructing method
CN108708290B (en) Box bridge frame hollow structure of small-radius railway curve unit and cast-in-place construction method
CN108374297B (en) Business Line tunnel, bridge section concrete sleeper swap method
CN103669132B (en) The big number of P60-1/42 has tiny fragments of stone, coal, etc. high-speed switch both wired slotting paving construction methods
CN208995842U (en) Level crossing mouth railway roadbed
CN104480915B (en) A kind of anti-rail hydraulic climbing formwork for high gradient slope concreting
CN105926381A (en) Method for changing ballast track bed of tunnel to ballastless track under condition of uninterrupted train working
CN204311418U (en) A kind of anti-rail hydraulic climbing formwork for high gradient slope concreting
CN107143336A (en) A kind of road constructing structure against the wind with shield synchronous construction rail
CN111926649A (en) Reinforced integrally-built crossing plate for railway special line and line rail fixing device
CN217419727U (en) Prefabricated foundation structure for railway detection equipment
CN110258217A (en) The horizontal lift beam overhead transmission line construction method of prestressing force
CN114717883B (en) Rapid installation method of prefabricated foundation structure for railway detection equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination