CN106192620A - A kind of railway ballastless track supporting layer and substructure change method - Google Patents

A kind of railway ballastless track supporting layer and substructure change method Download PDF

Info

Publication number
CN106192620A
CN106192620A CN201610605595.2A CN201610605595A CN106192620A CN 106192620 A CN106192620 A CN 106192620A CN 201610605595 A CN201610605595 A CN 201610605595A CN 106192620 A CN106192620 A CN 106192620A
Authority
CN
China
Prior art keywords
supporting layer
track
rail
railway
substructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610605595.2A
Other languages
Chinese (zh)
Other versions
CN106192620B (en
Inventor
徐勇
蔡德强
文望青
张勇
康小英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201610605595.2A priority Critical patent/CN106192620B/en
Publication of CN106192620A publication Critical patent/CN106192620A/en
Application granted granted Critical
Publication of CN106192620B publication Critical patent/CN106192620B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/16Transporting, laying, removing, or replacing rails; Moving rails placed on sleepers in the track
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/40Means or arrangements for temporarily supporting laid tracks, or rails or sleepers in the track
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/09Ballastless systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The present invention relates to railway ballastless track disease technology for eliminating field, change method in particular to a kind of railway ballastless track supporting layer and substructure.During the point of skylight, the track plates of cut-out is removed, region to be onstructed sets up temporary steel rail and connects operational railway;During the point of skylight, remove interim rail, region to be onstructed sets up steel bearing beam, steel bearing beam is laid current rail and connects operational railway, remove the supporting layer below current rail;During the point of skylight, the lower section casting concrete at current rail forms new supporting layer;Cycle alternation is carried out successively, until all of supporting layer has been changed.By the present invention in that and construction area bulit on stilts passed through rail with steel bearing beam, Along Railway can be properly functioning, need not stop transport, ensure that the properly functioning of track, additionally the present invention can eliminate the disease problem occurred in track underlying support layer and substructure thoroughly, thoroughly eliminate track hidden danger, there is great promotional value.

Description

A kind of railway ballastless track supporting layer and substructure change method
Technical field
The present invention relates to railway ballastless track disease technology for eliminating field, in particular to a kind of railway ballastless track supporting layer And substructure changes method.
Background technology
Non-fragment orbit is little with good stability, maintenance workload, by bus comfort level height, track length in service life, The advantages such as structure height is low are widely used in China Railway High-speed, and meanwhile high-speed railway requires that track must possess high smooth-going Property, need sub rail foundation structure to have the highest stability.Although it is built or adopt in the Design of High-speed Railway founded a capital, construction etc. Build measure by unprecedented high standard, but owing to China is vast in territory, railway construction condition is sufficiently complex, still has very The multifactor stability that may affect non-fragment orbit, such as construction quality, foundation settlement etc..
The supporting layer of ballastless track of high-speed railway and substructure are the passes affecting non-fragment orbit ride comfort and traffic safety Key factor, owing to there may be the situations such as concrete leakiness, locally geological condition change in construction, causes non-fragment orbit to support Layer and substructure do not meet design requirement, and fragment-free track slab and supporting layer cracking, deformation may be caused to cause track irregularity, Although ballastless track structure can be improved by adjustment fastener, lifting track plates, the again measure such as perfusion mortar, dead-end fracture Unfavoured state, but this method simply cured the symptoms, not the disease, under the High-speed Train Loads of long term frequent, do not obtain the bottom of radical cure Fault of construction grows with each passing day, and disease can produce again in the course of time, even affects traffic safety, therefore for non-fragment orbit disease Really produced by supporting layer and substructure defect if verified, then can not only non-fragment orbit be renovated, and need support Layer and substructure remove reconstruction simultaneously.For high ferro visitor specially, once maintenance shut-downs, the common people will be directly affected and normally go on a journey, make Become bad social influence, under ensureing secured premise, carry out construction merely with Window time be necessary.At present to nothing Regulation in the case of tiny fragments of stone, coal, etc. track does not cuts off traffic remains at many technical barriers, be pointed to below non-fragment orbit supporting layer and under Portion's structure carries out changeing the most difficult under traffic-operating period, thus seek one do not cut off traffic, conjunction safe and reliable, economic Reason, easy construction, adaptable ballastless track of high-speed railway supporting layer and substructure to change method imperative.
Summary of the invention
Present invention aim to solve the prior art mentioned in the above-mentioned background technology supporting layer at non-fragment orbit And the problem that it can not be repaired when going wrong in the case of not affecting railway operation by substructure, it is provided that Yi Zhongtie Road non-fragment orbit supporting layer and substructure change method.
The technical scheme is that a kind of railway ballastless track supporting layer and substructure change method, its feature exists In: comprise the following steps:
1), the stratum of track both lateral sides is reinforced, vertical by the track plates in region to be onstructed during the point of skylight Cut off to two ends;
2), during the point of skylight, the track plates of cut-out is removed, second supporting layer in region to be onstructed sets up interim Rail connects operational railway;
3), during the point of skylight, remove interim rail, second supporting layer in region to be onstructed sets up steel bearing beam, at steel Lay current rail on bearing beam and connect operational railway, remove the second supporting layer below current rail and substructure thereof;
4), the lower section casting concrete at current rail forms new supporting layer and substructure;
5), after concrete strength reaches requirement, translation steel bearing beam is to next construction point circulation construction, handling track plates To new supporting layer, and on track plates, reinstall the operational railway at rail connection two ends.
In further step 2, the method setting up interim rail is: in the second supporting layer upper end face frame in region to be onstructed If the some sleepers along track horizontal direction, sleeper is laid temporary steel rail, use fastener that interim rail is fixed on pillow On wood, adjust interim rail and longitudinal two ends of rail are connected with the rail on operational railway.
In further step 3, the method setting up steel bearing beam is: under the operational railway at longitudinal two ends in region to be onstructed Excavate mounting groove, erection support in mounting groove on first supporting layer of side, steel bearing beam is longitudinally set up in two phases along track To bearing on be suspended in above second supporting layer in region to be onstructed.
Further the installation method of bearing is: the first support below the operational railway at longitudinal direction two ends, region to be onstructed Cut mounting groove on Ceng, in mounting groove, place a block plate, then lay the rubber of one piece of support stringer in the upper end of steel plate Plate forms the seat structure of support steel bearing beam.
In further step 3, the laying method of current rail is: by two two longerons being made by I-steel Longitudinally it is respectively rested on two relative bearings, by the many crossbeams along track lateral arrangement between two longerons along track It is interconnected to form steel bearing beam structure, current rail is placed in the upper end of longeron, adjust the position of current rail by it with existing Track connects, and is connected to one with longeron by current rail by fastener.
In further step 5, circulation construction method be: by need remove track below the second supporting layer and under It is longitudinally split for several isometric circulation construction areas that portion's structure presses track, and each circulation construction area is along track the most successively It is divided into isometric the first circulation construction cell, the second circulation construction cell and the 3rd circulation construction cell, follows each simultaneously The first circulation construction cell in ring construction area carries out Demolition Construction, and after having constructed, translation steel bearing beam is executed to the second circulation The construction of the second circulation construction cell is carried out, the most alternately, until all of circulation construction area is constructed above work order unit Complete.
In further step 1, the method for stratum consolidation is: if inserted to play on the soil layer of the both lateral sides in region to be onstructed Dry root bolt anchorage soil layer.
In further step 1, the method for stratum consolidation is: if inserted to play on the soil layer of the both lateral sides in region to be onstructed Dry root bolt anchorage soil layer.
Advantages of the present invention has: 1, enter non-fragment orbit supporting layer and substructure in the case of not disrupted circuit operation Row changes, less on driving impact.
2, the disease management occurred for supporting layer and substructure of non-fragment orbit all can use, applied widely, adopts With steel bearing beam section construction, can quickly renovate the disease region of longer-range, utilize supporting layer that steel bearing beam makes somebody a mere figurehead in construction and Substructure, by changeing substructure, can administer the mass defect problem of substructure thoroughly, it is to avoid occur two Secondary disease.
3, during construction, every circuit independently uses a set of steel bearing beam system to reinforce, and therefore constructs and is not affected by distance between centers of tracks, Due to every line can independent construction, therefore can carry out construction organization according to circuit practical operation situation, easy construction is flexible, construction stream Aquation operation, without special construction requirement, difficulty of construction is low.
4, arrange a set of steel bearing beam under every circuit supporting layer and substructure are changed, multiple region can be carried out simultaneously Construction, steel bearing beam can be used, accelerate construction speed, and construction area is divided into the circulation construction cell of multiple little sections, Not only the segmentation with track structure matches, simultaneously less to structural perturbation, safe and reliable.
5, utilizing little span steel bearing beam to carry out changeing supporting layer and substructure piecemeal, defective substructure can get Renovating thoroughly, under rail, structure and track structure can recover to design point.
By the present invention in that and passed through by construction area bulit on stilts rail with steel bearing beam, Along Railway can be properly functioning, no With stoppage in transit, it is ensured that track properly functioning, additionally the present invention can eliminate track underlying support layer and substructure thoroughly The middle disease problem occurred, thoroughly eliminates track hidden danger, has great promotional value.
Accompanying drawing explanation
The steel bearing beam mounting structure schematic top plan view of Fig. 1: the present invention;
The steel bearing beam mounting structure schematic longitudinal section of Fig. 2: the present invention;
The longeron of Fig. 3: the present invention and the mounting structure schematic diagram of bearing;
The steel bearing beam mounting structure schematic cross-sectional view of Fig. 4: the present invention;
The mounting structure schematic diagram of the interim rail of Fig. 5: the present invention;
Wherein: 1 longeron;2 crossbeams;3 stiffeners;4 pass through rail;5 interim rail;6 first supporting layers; 7 sleepers;8 rubber slabs;9 steel plates;10 risers;11 transverse slats;12 second supporting layers.
Detailed description of the invention
The present invention is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Such as Fig. 1~5, the present embodiment changes the method for supporting layer and substructure to be needed to remove for using steel bearing beam to be set up in The top of the second supporting layer 12 (as shown in the dotted line frame in Fig. 1) of construction is as the supporting construction of current rail 4, it is ensured that rail Road circuit properly functioning.The structure of steel bearing beam is as it is shown in figure 1, include two longerons 1 being longitudinally arranged along track, and longeron 1 is I-beam structure, the web of longeron 1 is vertically arranged.Formation is connected by the crossbeam 2 along track lateral arrangement between two longerons 1 Overall structure, crossbeam 2 generally uses two pieces of channel-section steel assembly to be made, and the U mouth of two blocks of channel-section steels is supported or opposed and is bolted to connection For overall structure, the two ends of crossbeam 2 are respectively protruding between two blocks of flange plates of two longerons 1 and form stable frame structure, Ensure the spacing between longeron.
Support the ability of current rail 4 to further enhance longeron 1, the present embodiment is also at two blocks of flange plates of longeron 1 Between be welded with the stiffener 3 of vertically layout, enhanced the vertical enabling capabilities of whole longeron 1 by stiffener 3, it is to avoid During train passage, longeron 1 is damaged by pressure.Crossbeam 2 is channel-section steel structure, and stiffener 3 lays respectively at the transverse ends of crossbeam 2, puts more energy into Plate 3 is deep into the two ends being bolted on crossbeam 2 between two panels channel-section steel, and crossbeam 2 is fixed on longeron 1 by bolt arrangement On, as shown in Figure 4.Actually stiffener 3 can also be arranged on other positions of longeron 1, however it is necessary that and evades fastener, it is impossible to Fastener produces interferes.
Below the operational railway at longitudinal two ends that the two ends of longeron 1 are separately fixed at the second supporting layer 12 to be removed On one supporting layer 6, first supporting layer 6 at two ends being provided with bearing, as shown in figures 2-3, the present embodiment is vertical in region to be onstructed Cut 15~20mm deep mounting grooves on the first supporting layer 6 below the operational railway at two ends, in mounting groove, place one Block thickness is the steel plate 9 of 10~20mm, then in rubber slab 8 formation that the upper end of steel plate 9 one piece of thickness of laying is 30~40mm Hold the seat structure of steel bearing beam.
The two ends of longeron 1 are provided with stopping means, and the stopping means of the present embodiment includes being positioned at longeron 1 end cross both sides Two blocks of angle steel, angle steel includes the riser 10 being positioned at longeron 1 sidepiece and by below operational railway first of bolt anchoring Transverse slat 11 on support layer 6, transverse slat 11 is fixed on the steel angle structure of the lower end formation L-type of riser 10, and longeron 1 is positioned at two pieces of risers 10 Between avoid horizontal rocking by the position-limiting action of riser 10.
The two ends of longeron 1 are respectively rested on the rubber slab 8 on first supporting layer 6 at longitudinal two ends in region to be onstructed, Rubber slab 8 is set and can farthest form cushioning effect, decrease the rigid collision between each parts, it is to avoid parts Damage.Angle steel and first supporting layer 6 at the spacing longitudinal two ends being fixed on region to be onstructed of bolt are passed through in longitudinal two ends of longeron 1 On.
Owing to the track of high-speed railway is all long-play, the construction period of the present embodiment can only be in the sky of every track Window point is constructed, and some construction procedure can not be fully finished at a skylight point, it is necessary in several skylights, point is carried out.Track Plate is in cutting with during removing, the longest, needs the time of one or more skylight point to carry out, and therefore cuts removing After the track plates cut, need interim rail 5 is installed.As it is shown in figure 5, the installation method of interim rail 5 is: directly execute waiting Laying railway sleepers 7 on second supporting layer 12 in territory, work area, sleeper 7 is laterally laid according to track, then lays temporary steel rail on sleeper 7 5, the two ends of interim rail 5 are connected with operational railway respectively, to ensure the normal pass of track.
Concrete construction method is: 1, reinforce the stratum of track both lateral sides, and the reinforcement means of the present embodiment is, Directly inserted to play anchor pole on the soil layer of track both lateral sides, reinforces the soil layer of region to be onstructed both lateral sides, it is to avoid prop up removing During support layer, there is the phenomenon collapsed in the soil layer of both sides, after soil layer has been reinforced, and indulging the track plates in region to be onstructed Cutting off to two ends, soil layer is reinforced and the cutting of track plates all can affect the properly functioning of train, it is therefore desirable in skylight, point is carried out;
2), during the point of skylight, use hanging device to be removed by the track plates of cut-out, region to be onstructed sets up interim Rail 5 connects operational railway, is directly removing the sleeper 7 setting up some direction across bridge above the second supporting layer 12 of track plates, On sleeper 7, lay temporary steel rail 5 again, the two ends of rail are connected with the rail on operational railway respectively, so can not shadow Ringing the normal pass of train, the circuit speed of service of interim rail 5 is no more than 45KM/h;
3), during the point of skylight, remove interim rail 5 and sleeper 7, the first supporting layer 6 below operational railway is opened Digging 15~20mm deep mounting grooves, in mounting groove, one piece of thickness of placement is the steel plate 9 of 10~20mm, then the upper end at steel plate 9 Lay the rubber slab 8 that one piece of thickness is 30~40mm and form the seat structure of support steel bearing beam, by longitudinal two ends of longeron 1 respectively Being anchored on the first supporting layer 6, between longeron 1, welding beam 2 forms steel bearing beam, is spaced between two blocks of flange plates of longeron 1 Welding polylith stiffener 3, then lays current rail 4 in longeron upper surface, and current rail 4 is fixed on longeron 1 by fastener The two ends of current rail 4 are connected with the rail of operational railway and do not affect the normal pass of train, on steel bearing beam by upper surface respectively There is a lot of spaces to be easy to excavate, utilize the space of the space on steel bearing beam and both sides to excavate and remove the second supporting layer 12 and the The structure of two supporting layer 12 bottoms, the degree of depth of dismounting judges according to practical situation, removes job demand during the point of skylight Carry out;
4), in the lower section of current rail 4 use early strength concrete to pour and form the second new supporting layer 12,
5), after concrete strength reaches requirement, translation steel bearing beam is to next construction point circulation construction, handling track plates To the second new supporting layer 12, and on track plates, reinstall rail connection two ends track.
It practice, the present embodiment can be circulated construction according to the length of construction area, so can effectively accelerate Construction speed, improves efficiency of construction, it is possible to use manpower and material resources sparingly, and reduces construction cost.
The method of circulation construction specifically is: if track the second supporting layer 12 removed is longitudinally split by track is by needing Dry isometric circulation construction area, each circulation construction area is longitudinally in turn divided into the first isometric circulation construction along track Unit, the second circulation construction cell and the 3rd circulation construction cell, execute the first circulation in each circulation construction area simultaneously Work order unit carries out Demolition Construction, after having constructed, carries out the second circulation and execute above translation steel bearing beam to the second circulation construction cell The construction of work order unit, the most alternately, until all of circulation construction area has been constructed.
The ultimate principle of the present invention, principal character and advantages of the present invention have more than been shown and described.The technology of the industry Personnel, it should be appreciated that the present invention is not restricted to the described embodiments, simply illustrating this described in above-described embodiment and description The principle of invention, the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these become Change and improvement both falls within scope of the claimed invention.Claimed scope by appending claims and Equivalent defines.

Claims (6)

1. a railway ballastless track supporting layer and substructure change method, it is characterised in that: comprise the following steps:
1), the stratum of track both lateral sides is reinforced, by longitudinal the two of the track plates in region to be onstructed during the point of skylight End-grain cutting is broken;
2), being removed by the track plates of cut-out during the point of skylight, the second supporting layer (12) in region to be onstructed is upper to be set up temporarily Rail (5) connects operational railway;
3), removing interim rail (5) during the point of skylight, the second supporting layer (12) in region to be onstructed is upper sets up steel bearing beam, Steel bearing beam is laid current rail (4) and connects operational railway, remove current rail (4) lower section the second supporting layer (12) and Substructure;
4), the lower section casting concrete at current rail forms new supporting layer and substructure;
5), after concrete strength reaches requirement, translation steel bearing beam is to next construction point circulation construction, and handling track plates is to newly Supporting layer on, and reinstall on track plates rail connect two ends operational railway.
2. a kind of railway ballastless track supporting layer as claimed in claim 1 and substructure change method, it is characterised in that: step In rapid 2, the method setting up interim rail is: set up some along track in the second supporting layer (12) upper surface in region to be onstructed The sleeper (7) that horizontal direction is arranged, at the upper temporary steel rail (5) of laying of sleeper (7), interim rail (5) is fixed on by use fastener On sleeper (7), adjust interim rail (5) and longitudinal two ends of rail are connected with the rail on operational railway.
3. a kind of railway ballastless track supporting layer as claimed in claim 1 and substructure change method, it is characterised in that: step In rapid 3, the method setting up steel bearing beam is: the first supporting layer (6) below the operational railway at longitudinal two ends in region to be onstructed Upper excavation mounting groove, erection support in mounting groove, steel bearing beam is longitudinally set up on two relative bearings suspension along track The second supporting layer (12) top in region to be onstructed.
4. a kind of railway ballastless track supporting layer as claimed in claim 3 and substructure change method, it is characterised in that: The installation method of seat is: cut installation on the first supporting layer (6) below the operational railway at longitudinal direction two ends, region to be onstructed Groove, places a block plate (9) in mounting groove, then lays the rubber slab (9) of one piece of support stringer (1) in the upper end of steel plate (9) Form the seat structure of support steel bearing beam.
5. a kind of railway ballastless track supporting layer as claimed in claim 1 and substructure change method, it is characterised in that: step In rapid 3, the laying method of current rail (4) is: two two longerons (1) being made by I-steel longitudinally divided along track It is not shelved on two relative bearings, is interconnected mutually by the many crossbeams along track lateral arrangement (2) between two longerons (1) Connect formation steel bearing beam structure, current rail (4) be placed in the upper end of longeron (1), adjust the position of current rail (4) by its with both There is track to connect, by fastener, current rail (4) is connected to one with longeron (1).
6. a kind of railway ballastless track supporting layer as claimed in claim 1 and substructure change method, it is characterised in that: step In rapid 5, the method for circulation construction is: the second supporting layer (12) below track remove needs and substructure are indulged by track To being divided into several isometric circulation construction areas, each circulation construction area is longitudinally in turn divided into isometric the along track One circulation construction cell, the second circulation construction cell and the 3rd circulation construction cell, simultaneously in each circulation construction area First circulation construction cell carries out Demolition Construction, and after having constructed, translation steel bearing beam is carried out above the second circulation construction cell The construction of the second circulation construction cell, the most alternately, until all of circulation construction area has been constructed.
CN201610605595.2A 2016-07-28 2016-07-28 A kind of railway ballastless track supporting layer and substructure change method Active CN106192620B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610605595.2A CN106192620B (en) 2016-07-28 2016-07-28 A kind of railway ballastless track supporting layer and substructure change method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610605595.2A CN106192620B (en) 2016-07-28 2016-07-28 A kind of railway ballastless track supporting layer and substructure change method

Publications (2)

Publication Number Publication Date
CN106192620A true CN106192620A (en) 2016-12-07
CN106192620B CN106192620B (en) 2017-12-12

Family

ID=57495714

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610605595.2A Active CN106192620B (en) 2016-07-28 2016-07-28 A kind of railway ballastless track supporting layer and substructure change method

Country Status (1)

Country Link
CN (1) CN106192620B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108239896A (en) * 2018-03-21 2018-07-03 中铁二十三局集团第四工程有限公司 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method
CN108425293A (en) * 2018-05-15 2018-08-21 中铁第四勘察设计院集团有限公司 Insert the interim transition structure of causeway trouble in a kind of both wired non-fragment orbit location
CN108611929A (en) * 2018-05-15 2018-10-02 中铁第四勘察设计院集团有限公司 A method of both causeway trouble was inserted in wired non-fragment orbit location
CN109183530A (en) * 2018-09-29 2019-01-11 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of interim overhead device of route for non-fragment orbit Disease Treatment and method
CN110029531A (en) * 2019-04-23 2019-07-19 中国铁道科学研究院集团有限公司铁道建筑研究所 The interim overhead device of high-speed rail non-fragment orbit route and method suitable for high speed traveling
CN113153357A (en) * 2021-04-29 2021-07-23 重庆大学 Tunnel inverted arch half-width dismantling device and construction method
CN115162075A (en) * 2022-08-09 2022-10-11 中国铁道科学研究院集团有限公司 Construction method for replacing telescopic regulator
CN115262304A (en) * 2022-09-13 2022-11-01 中铁上海工程局集团有限公司 Auxiliary tool for replacing anchor rod of small-space track beam and anchor rod replacing method
CN118835496A (en) * 2024-08-21 2024-10-25 四川铁拓科技有限公司 Temporary transition supporting structure of railway ballastless track and ballastless track replacing method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3840795A1 (en) * 1988-12-03 1990-06-07 Zueblin Ag Method for producing a ballastless railway superstructure, and precast parts and device for carrying out the method
WO2005098136A1 (en) * 2004-04-08 2005-10-20 Porr Technobau Und Umwelt Ag Ballastless superstructure for railborne traffic
CN201505976U (en) * 2009-10-23 2010-06-16 河北众鑫源桥隧设备制造有限公司 Translational ballastless track plate mold
CN202298390U (en) * 2011-10-09 2012-07-04 石家庄铁道大学 Ballastless track rush repair device
CN202830761U (en) * 2012-08-29 2013-03-27 中铁二院工程集团有限责任公司 Railway steel truss girder bridge ballastless track laying structure
CN202945511U (en) * 2012-12-11 2013-05-22 中铁二十局集团有限公司 Hoisting device for replacing plate-type ballastless track reinforced concrete base plate
CN202945512U (en) * 2012-12-11 2013-05-22 中铁二十局集团有限公司 Device for replacing plate-type ballastless track reinforced concrete base plate
CN103147370A (en) * 2013-03-29 2013-06-12 中铁一局集团有限公司 Device and method for replacing track slab of slab ballastless track
CN103952954A (en) * 2014-05-16 2014-07-30 株洲长远铁路建机有限公司 Method for replacing subway track plate, subway plate replacing vehicle and plate replacing unit
CN204382488U (en) * 2015-01-09 2015-06-10 秦皇岛老虎重工有限公司 High ferro ballastless track slab mold combined rubber bearing

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3840795A1 (en) * 1988-12-03 1990-06-07 Zueblin Ag Method for producing a ballastless railway superstructure, and precast parts and device for carrying out the method
WO2005098136A1 (en) * 2004-04-08 2005-10-20 Porr Technobau Und Umwelt Ag Ballastless superstructure for railborne traffic
CN201505976U (en) * 2009-10-23 2010-06-16 河北众鑫源桥隧设备制造有限公司 Translational ballastless track plate mold
CN202298390U (en) * 2011-10-09 2012-07-04 石家庄铁道大学 Ballastless track rush repair device
CN202830761U (en) * 2012-08-29 2013-03-27 中铁二院工程集团有限责任公司 Railway steel truss girder bridge ballastless track laying structure
CN202945511U (en) * 2012-12-11 2013-05-22 中铁二十局集团有限公司 Hoisting device for replacing plate-type ballastless track reinforced concrete base plate
CN202945512U (en) * 2012-12-11 2013-05-22 中铁二十局集团有限公司 Device for replacing plate-type ballastless track reinforced concrete base plate
CN103147370A (en) * 2013-03-29 2013-06-12 中铁一局集团有限公司 Device and method for replacing track slab of slab ballastless track
CN103952954A (en) * 2014-05-16 2014-07-30 株洲长远铁路建机有限公司 Method for replacing subway track plate, subway plate replacing vehicle and plate replacing unit
CN204382488U (en) * 2015-01-09 2015-06-10 秦皇岛老虎重工有限公司 High ferro ballastless track slab mold combined rubber bearing

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
董明: "高速铁路无砟轨道底座板整体抬升方案设计及试验研究", 《铁道标准设计》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108239896A (en) * 2018-03-21 2018-07-03 中铁二十三局集团第四工程有限公司 Existing railway Disease Treatment of Foundation Base fixed track usage plan constructing structure and construction method
CN108425293A (en) * 2018-05-15 2018-08-21 中铁第四勘察设计院集团有限公司 Insert the interim transition structure of causeway trouble in a kind of both wired non-fragment orbit location
CN108611929A (en) * 2018-05-15 2018-10-02 中铁第四勘察设计院集团有限公司 A method of both causeway trouble was inserted in wired non-fragment orbit location
CN109183530A (en) * 2018-09-29 2019-01-11 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of interim overhead device of route for non-fragment orbit Disease Treatment and method
CN109183530B (en) * 2018-09-29 2024-03-12 中国铁道科学研究院集团有限公司铁道建筑研究所 Line temporary overhead device and method for ballastless track disease remediation
CN110029531A (en) * 2019-04-23 2019-07-19 中国铁道科学研究院集团有限公司铁道建筑研究所 The interim overhead device of high-speed rail non-fragment orbit route and method suitable for high speed traveling
CN110029531B (en) * 2019-04-23 2020-10-27 中国铁道科学研究院集团有限公司铁道建筑研究所 Temporary overhead device and method for high-speed rail ballastless track line suitable for high-speed driving
CN113153357A (en) * 2021-04-29 2021-07-23 重庆大学 Tunnel inverted arch half-width dismantling device and construction method
CN115162075A (en) * 2022-08-09 2022-10-11 中国铁道科学研究院集团有限公司 Construction method for replacing telescopic regulator
CN115262304A (en) * 2022-09-13 2022-11-01 中铁上海工程局集团有限公司 Auxiliary tool for replacing anchor rod of small-space track beam and anchor rod replacing method
CN118835496A (en) * 2024-08-21 2024-10-25 四川铁拓科技有限公司 Temporary transition supporting structure of railway ballastless track and ballastless track replacing method

Also Published As

Publication number Publication date
CN106192620B (en) 2017-12-12

Similar Documents

Publication Publication Date Title
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
CN106049209B (en) A kind of interim rail support meanss changed for railway ballastless track supporting layer
CN102979041B (en) Soft overhead reinforcing jacking method for construction of span box bridge of jacking block of underpass turnout group of railway
CN109235292B (en) Railway bridge beam replacing process
CN206538637U (en) A kind of track strengthening device for existing railway
CN105464008B (en) Large longitudinal beam system line reinforcement construction device and method
CN106758590B (en) Construction temporary beam for replacing railway track under non-stop condition and construction method
CN102926299A (en) Railway elevating and fixing device and railway bridge and culvert construction method adopting railway elevating and fixing device
CN107059506A (en) A method for replacing a track plate of a slab ballastless track
CN108385451A (en) Board-like ballastless track boards replacing options under a kind of special operation condition
KR100556219B1 (en) Replacement of superstructures of railway bridges and induced injuries using the same.
CN105908583A (en) System for replacing tunnel ballast track bed with ballastless track under non-interruption traveling condition
CN205893837U (en) A interim rail strutting arrangement that is used for railway ballastless track supporting layer to tear open trading
CN109338831B (en) Ballastless track deviation rectifying method based on rope saw cutting
CN107268352A (en) Refoot the fixed track usage plan device of operation for tunnel
KR100865752B1 (en) Railway bridge replacement method
CN117344588A (en) Ballastless track maintenance method in operation skylight period
CN202298390U (en) Ballastless track rush repair device
CN110725160A (en) Double-block type point-support floating slab track bed structure
CN112523017A (en) Subway turnout area integral ballast bed settlement renovation method
CN117107562A (en) Method for replacing high-speed rail curve super-high section ballastless track plate
CN105926381A (en) Method for changing ballast track bed of tunnel to ballastless track under condition of uninterrupted train working
CN117107563A (en) A method for replacing ballastless track slabs in the curved super-elevation section of the high-speed railway base section
CN214459224U (en) A ballastless track structure suitable for long-span bridges
CN210341507U (en) Temporary overhead device for high-speed rail ballastless track line suitable for high-speed traffic

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant