CN108233277A - A kind of extra long distance shoal sea bed extra large cable laying technique - Google Patents

A kind of extra long distance shoal sea bed extra large cable laying technique Download PDF

Info

Publication number
CN108233277A
CN108233277A CN201810136880.3A CN201810136880A CN108233277A CN 108233277 A CN108233277 A CN 108233277A CN 201810136880 A CN201810136880 A CN 201810136880A CN 108233277 A CN108233277 A CN 108233277A
Authority
CN
China
Prior art keywords
extra large
cable
large cable
laying
extra
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810136880.3A
Other languages
Chinese (zh)
Inventor
高宏飙
王健
陈心楠
季晓强
罗雯雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou Campus of Hohai University
Jiangsu Marine Longyuan Wind Power Generation Co Ltd
Original Assignee
Changzhou Campus of Hohai University
Jiangsu Marine Longyuan Wind Power Generation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Campus of Hohai University, Jiangsu Marine Longyuan Wind Power Generation Co Ltd filed Critical Changzhou Campus of Hohai University
Priority to CN201810136880.3A priority Critical patent/CN108233277A/en
Publication of CN108233277A publication Critical patent/CN108233277A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G1/00Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
    • H02G1/06Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
    • H02G1/10Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle in or under water
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Electric Cable Installation (AREA)

Abstract

The invention discloses a kind of extra long distance shoal sea bed extra large cable laying techniques, in a manner that first laying backlash is buried, are completed by interim rolling wheel support, the miniature construction ship with idler wheel, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough.It is an advantage of the invention that:In a manner that first laying backlash is buried, the laying problem of extra long distance shallow sea beach sea bed extra large cable is realized by interim rolling wheel support, the miniature construction ship with idler wheel, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough, it is simple for process easy to operate and time-consuming shorter;By interim rolling wheel support, miniature construction ship and inflatable inner tube in laid processes, extra large cable is avoided to be towed on sea bed, reduces the abrasion of extra large cable.

Description

A kind of extra long distance shoal sea bed extra large cable laying technique
Technical field
The present invention relates to extra large cables to lay technology field, and in particular to a kind of extra long distance shoal sea bed extra large cable laying technique.
Background technology
The section electricity submitting of marine wind electric field sea is generally realized by submarine cable, but is needed in the routing of Partial Sea Area extra large cable By the shoal of dozens of kilometres, Tideland resources are sandwiched between, shallow draft cable layer oceangoing ship is difficult to enter, and extra large cable laying becomes A great problem.
Invention content
In order to solve the above technical problems, the present invention provides a kind of extra long distance shoal sea bed extra large cable laying technique, use The mode that first laying backlash is buried realizes the laying of extra long distance shallow sea beach sea bed extra large cable.
The technical solution adopted by the present invention is:
A kind of extra long distance shoal sea bed extra large cable laying technique, using first laying backlash bury by the way of, by interim rolling wheel support, Miniature construction ship with idler wheel, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough are completed.
Further, specific embodiment is as follows:
A, preparation before laying:Routing underwater topography, prospecting geology are measured, and extra large cable of the sea-anchor to Chao Xia areas is swept using special Traction repeatedly is carried out in laying routing, removes submarine obstacle, supratidal zone checks extra large cable laying routing in the ebb period;
B, the erection of interim rolling wheel support and miniature construction ship are cast:According to underwater topography and geology, in supratidal zone shoal Marine site sets up interim rolling wheel support, is equipped with idler wheel on the interim rolling wheel support, miniature apply is cast in subtidal zone depth of water marine site Work ship is also equipped with idler wheel on the miniature construction ship;
C, the laying of carrying cable and it is twisted the installation of machine:The machine of being twisted is dug at beginning and end ridge is logged in extra large cable, if Traction anchor is put, installation is twisted machine, and will be twisted machine by GPS navigation positioning and be attached with carrying cable;
D, the in place of cable and cable layer is crossed:By cable layer by Bo Lan factories harbour, accommodation is adjusted, by the extra large cable in cable factory It is delivered in cable layer cable disk along trestle, then will lay cable ship approaching bank as possible using high tide level, and utilize anchoring Alignment system is stabilized by cable layer;
E, the laying of extra large cable:Extra large cable head out of cable disk is pulled out, is sent into water by cable laying machine, and is spaced and fixes below extra large cable Inflatable inner tube estimates extra large cable using length, extra large cable is blocked, end socket, laying is pulled out in the extra large cable head for logging in starting point one end After ship, active rotary head on extra large cable head is set, and active rotary head and extra large cable are logged in the carrying cable being twisted on machine of starting point It links together, treats that extra large cable is drawn to the idler wheel being preset in extra large cable routing, the inflatable inner tube in extra large cable is just released, by extra large cable It is shelved on the idler wheel on miniature construction ship and interim rolling wheel support on the way, then starts the machine that is twisted and draw extra large cable to stepping on Lu Qidian is simultaneously fixed, and then extra large cable cable layer drives towards bank, while the extra large cable on cable disk is at the uniform velocity released, and is applied to extra large cable If the shoal area that ship can not reach, the extra large cable head for logging in terminal is pulled out into laying ship, active rotary head is set, then by logging in Extra large cable head is dragged to and logs in terminal, and fix by be twisted machine and the carrying cable of terminal point, finally moves down extra large cable from idler wheel, Sinking is on sea bed;
F, extra large cable is embedded:Water spray self-propulsion type lays plough and coordinates with water pump, extra large cable is route scour out ditch, then extra large cable is via deposited If plough enters in ditch, finally by laying plough mud by burying submarine cable.
Further, the interim rolling wheel support set up in the step b, the spacing between two neighboring interim rolling wheel support are 1km, The miniature construction ship cast in the step b, the spacing between adjacent two miniature construction ships are also 1km.
Further, the special sea-anchor of sweeping in the step a is three hock anchors or four hock anchor.
The beneficial effects of the invention are as follows:1st, in a manner that first laying backlash is buried, by interim rolling wheel support, with the micro- of idler wheel Type construction ship, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough realize that the laying of extra long distance shallow sea beach sea bed extra large cable is asked Topic, it is simple for process easy to operate and time-consuming shorter;2nd, by interim rolling wheel support, miniature construction ship and inflation in laid processes Tire avoids extra large cable from being towed on sea bed, reduces the abrasion of extra large cable.
Specific embodiment
In order to deepen the understanding of the present invention, below in conjunction with embodiment, the invention will be further described, the embodiment It is only used for explaining the present invention, not restrict the protection scope of the present invention.
A kind of extra long distance shoal sea bed extra large cable laying technique, using first laying backlash bury by the way of, by interim rolling wheel support, Miniature construction ship with idler wheel, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough are completed, and specific embodiment is as follows:
A, preparation before laying:Underwater topography, the prospecting geology of extra large cable routing are measured, and using special sea-anchor of sweeping to Chao Xia areas Extra large cable laying routing on carry out traction repeatedly, remove submarine obstacle, special sea-anchor of sweeping is generally three teeth or four hock anchors, two A to four are one group, are connected to side by side on a steel shoulder pole, and supratidal zone examines extra large cable laying routing in the ebb period It looks into;
B, the erection of interim rolling wheel support and miniature construction ship are cast:According to underwater topography and geology, in supratidal zone shoal Marine site sets up interim rolling wheel support, and the spacing between interim rolling wheel support is 1km, and interim rolling wheel support lower part is small-sized steel-pipe pile, Shoal is squeezed into vibration hammer, idler wheel is installed on interim rolling wheel support, miniature construction ship is cast simultaneously in subtidal zone depth of water marine site Anchor, the spacing between miniature construction ship are 1km, and idler wheel is also equipped on miniature construction ship;
C, the laying of carrying cable and it is twisted the installation of machine:The machine of being twisted is dug at beginning and end ridge is logged in extra large cable, if Traction anchor is put, installation is twisted machine respectively on the being twisted machine ridge at both ends, and determines to be twisted machine and traction by GPS navigation positioning Two carrying cables are then connected respectively to two and are twisted on machine by the link position of wirerope;
D, the in place of cable and cable layer is crossed:By cable layer by Bo Lan factories harbour, accommodation is adjusted, by the cable disk of workboat Center is aligned with the cable bridge center of crossing of manufacturer, and band cable fixes accommodation, and the extra large cable in cable factory is delivered to extra large cable along trestle and is applied If in ship tow disk, crossing cable speed control in average 1200m/h, cable ship approaching bank as possible then will be laid using high tide level, It is and using anchoring system that cable layer is stabilized;
E, the laying of extra large cable:Extra large cable head out of cable disk is pulled out, is sent into water by cable laying machine, and is spaced and fixes below extra large cable Inflatable inner tube is estimated required extra large cable length, is then blocked extra large cable, end socket, will be embedded in extra large cable and log in routing starting point one end After extra large cable head pulls out cable layer, active rotary head is set on extra large cable head, then by active rotary head with logging in starting point The carrying cable being twisted on machine is connected, and startup is twisted machine, and extra large cable head is dragged to and logs in starting point, and is fixed, when extra large cable is drawn When to the idler wheel being preset in extra large cable routing, the inflatable inner tube in extra large cable is just released, miniature is applied what extra large cable was shelved on the way On idler wheel on work ship and interim rolling wheel support, extra large cable rolls on idler wheel, can prevent extra large cable from wearing, then will laying Ship drives towards bank, while at the uniform velocity releases extra large cable in extra large cable routing, and the extra large cable of releasing is also laid in miniature workboat on the way On idler wheel on oceangoing ship and interim rolling wheel support, during the shoal area being unable to reach to cable layer, then it will be embedded in extra large cable and log in The extra large cable head of routing destination terminal stamps active rotary head, and pull out laying ship, then by active rotary head and the strand for logging in terminal point Carrying cable on grinding machine is connected, start log in terminal be twisted machine, extra large cable head is dragged to embedded terminal, and fix, most Extra large cable is moved down from idler wheel afterwards, sinking is on sea bed;
F, extra large cable is embedded:Water spray self-propulsion type laying plough is straddled in extra large cable, starts and is mounted on barge charging pump, water pump will be extra large It is the high pressure sea water with pressure by turn seawater after motor operating in pump, high pressure sea water is ploughed by laying after water sucking On input port, through piping, ejected from multiple rows of nozzle on plough body, by the mud scour out ditch in seabed;Control sprays water The size and telescopic rod of pressure control the upper and lower so as to change the angle of excavation of plough body;Extra large cable is passed through by extra large cable guider Plough body is gone out from plough body end, and into the ditch of injection molding, finally backfill is in extra large cable for the mud ejected, by extra large cable It is embedded;Laying plough is formed water jet principle of propeller, is realized on sea bed face voluntarily by waterpower mode.

Claims (4)

1. a kind of extra long distance shoal sea bed extra large cable laying technique, which is characterized in that in a manner that first laying backlash is buried, by Interim rolling wheel support, the miniature construction ship with idler wheel, driving idler wheel and shallow sea self-propulsion type extra large cable laying plough are completed.
A kind of 2. extra long distance shoal sea bed extra large cable laying technique according to claim 1, which is characterized in that specific implementation Mode is as follows:
A, preparation before laying:Routing underwater topography, prospecting geology are measured, and extra large cable of the sea-anchor to Chao Xia areas is swept using special Traction repeatedly is carried out in laying routing, removes submarine obstacle, supratidal zone checks extra large cable laying routing in the ebb period;
B, the erection of interim rolling wheel support and miniature construction ship are cast:According to underwater topography and geology, in supratidal zone shoal Marine site sets up interim rolling wheel support, is equipped with idler wheel on the interim rolling wheel support, miniature apply is cast in subtidal zone depth of water marine site Work ship is also equipped with idler wheel on the miniature construction ship;
C, the laying of carrying cable and it is twisted the installation of machine:The machine of being twisted is dug at beginning and end ridge is logged in extra large cable, if Traction anchor is put, installation is twisted machine, and will be twisted machine by GPS navigation positioning and be attached with carrying cable;
D, the in place of cable and cable layer is crossed:By cable layer by Bo Lan factories harbour, accommodation is adjusted, by the extra large cable in cable factory It is delivered in cable layer cable disk along trestle, then will lay cable ship approaching bank as possible using high tide level, and utilize anchoring Alignment system is stabilized by cable layer;
E, the laying of extra large cable:Extra large cable head out of cable disk is pulled out, is sent into water by cable laying machine, and is spaced and fixes below extra large cable Inflatable inner tube estimates extra large cable using length, extra large cable is blocked, end socket, laying is pulled out in the extra large cable head for logging in starting point one end After ship, active rotary head on extra large cable head is set, and active rotary head and extra large cable are logged in the carrying cable being twisted on machine of starting point It links together, treats that extra large cable is drawn to the idler wheel being preset in extra large cable routing, the inflatable inner tube in extra large cable is just released, by extra large cable It is shelved on the idler wheel on miniature construction ship and interim rolling wheel support on the way, then starts the machine that is twisted and draw extra large cable to stepping on Lu Qidian is simultaneously fixed, and then extra large cable cable layer drives towards bank, while the extra large cable on cable disk is at the uniform velocity released, and is applied to extra large cable If the shoal area that ship can not reach, the extra large cable head for logging in terminal is pulled out into laying ship, active rotary head is set, then by logging in Extra large cable head is dragged to and logs in terminal, and fix by be twisted machine and the carrying cable of terminal point, finally moves down extra large cable from idler wheel, Sinking is on sea bed;
F, extra large cable is embedded:Water spray self-propulsion type lays plough and coordinates with water pump, extra large cable is route scour out ditch, then extra large cable is via deposited If plough enters in ditch, finally by laying plough mud by burying submarine cable.
A kind of 3. extra long distance shoal sea bed extra large cable laying technique according to claim 2, which is characterized in that the step The interim rolling wheel support set up in b, the spacing between two neighboring interim rolling wheel support are 1km, are cast in the step b miniature Construction ship, the spacing between adjacent two miniature construction ships are also 1km.
A kind of 4. extra long distance shoal sea bed extra large cable laying technique according to claim 2, which is characterized in that the step Special sea-anchor of sweeping in a is three hock anchors or four hock anchor.
CN201810136880.3A 2018-02-09 2018-02-09 A kind of extra long distance shoal sea bed extra large cable laying technique Pending CN108233277A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810136880.3A CN108233277A (en) 2018-02-09 2018-02-09 A kind of extra long distance shoal sea bed extra large cable laying technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810136880.3A CN108233277A (en) 2018-02-09 2018-02-09 A kind of extra long distance shoal sea bed extra large cable laying technique

Publications (1)

Publication Number Publication Date
CN108233277A true CN108233277A (en) 2018-06-29

Family

ID=62661360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810136880.3A Pending CN108233277A (en) 2018-02-09 2018-02-09 A kind of extra long distance shoal sea bed extra large cable laying technique

Country Status (1)

Country Link
CN (1) CN108233277A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109687353A (en) * 2018-11-13 2019-04-26 南通市海洋水建工程有限公司 A kind of the sea cable paving system and its laying method of high-quality and high-efficiency
CN110474259A (en) * 2019-08-30 2019-11-19 北京海瑞兴能源科技有限责任公司 Log in section cable laying system and a laying method
CN110539853A (en) * 2019-09-11 2019-12-06 北京海瑞兴能源科技有限责任公司 Cable laying ship deck arrangement and construction method for laying long-distance sand shores and submarine cables
CN112061323A (en) * 2020-08-20 2020-12-11 北京海瑞兴能源科技有限责任公司 Special ship for laying construction of landing section submarine cable under small tidal range and construction method
CN113067289A (en) * 2020-08-28 2021-07-02 华电重工股份有限公司 Submarine cable laying method
CN113644594A (en) * 2021-07-29 2021-11-12 宝胜长飞海洋工程有限公司 Flush buried submarine cable laying method
CN113964736A (en) * 2021-10-14 2022-01-21 亨通海洋工程有限公司 Submarine cable long-distance intertidal zone landing construction process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101962139A (en) * 2010-09-15 2011-02-02 远东电缆有限公司 Cable delivery disc and lifting mode thereof
CN103247977A (en) * 2013-05-14 2013-08-14 国家电网公司 Multiphase submarine cable transversal arrangement circularly laying construction method
CN103266625A (en) * 2013-05-31 2013-08-28 中海石油(中国)有限公司番禺作业公司 Gravity base structure seabed base disc
CN103545759A (en) * 2012-07-16 2014-01-29 浙江欣海船舶设计研究院有限公司 Back-twist frame device of offshore cable laying ship
CN105552790A (en) * 2016-02-03 2016-05-04 中国水利水电第十三工程局有限公司 Submarine cable deployment guide device of wind power station in intertidal zone

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101962139A (en) * 2010-09-15 2011-02-02 远东电缆有限公司 Cable delivery disc and lifting mode thereof
CN103545759A (en) * 2012-07-16 2014-01-29 浙江欣海船舶设计研究院有限公司 Back-twist frame device of offshore cable laying ship
CN103247977A (en) * 2013-05-14 2013-08-14 国家电网公司 Multiphase submarine cable transversal arrangement circularly laying construction method
CN103266625A (en) * 2013-05-31 2013-08-28 中海石油(中国)有限公司番禺作业公司 Gravity base structure seabed base disc
CN105552790A (en) * 2016-02-03 2016-05-04 中国水利水电第十三工程局有限公司 Submarine cable deployment guide device of wind power station in intertidal zone

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109687353A (en) * 2018-11-13 2019-04-26 南通市海洋水建工程有限公司 A kind of the sea cable paving system and its laying method of high-quality and high-efficiency
CN109687353B (en) * 2018-11-13 2024-02-09 南通市海洋水建工程有限公司 High-quality and high-efficiency submarine cable laying system and laying method thereof
CN110474259A (en) * 2019-08-30 2019-11-19 北京海瑞兴能源科技有限责任公司 Log in section cable laying system and a laying method
CN110539853A (en) * 2019-09-11 2019-12-06 北京海瑞兴能源科技有限责任公司 Cable laying ship deck arrangement and construction method for laying long-distance sand shores and submarine cables
CN112061323A (en) * 2020-08-20 2020-12-11 北京海瑞兴能源科技有限责任公司 Special ship for laying construction of landing section submarine cable under small tidal range and construction method
CN113067289A (en) * 2020-08-28 2021-07-02 华电重工股份有限公司 Submarine cable laying method
CN113644594A (en) * 2021-07-29 2021-11-12 宝胜长飞海洋工程有限公司 Flush buried submarine cable laying method
CN113964736A (en) * 2021-10-14 2022-01-21 亨通海洋工程有限公司 Submarine cable long-distance intertidal zone landing construction process

Similar Documents

Publication Publication Date Title
CN108233277A (en) A kind of extra long distance shoal sea bed extra large cable laying technique
CN103247977B (en) Multiphase submarine cable transverse arrangement of turbo circulation laying and construction method
CN102418358B (en) Power positioning jet-flow spraying type ditcher
CN203584490U (en) Submarine cable or soft pipe burying device and workboat
CN108755644B (en) Transfer platform for cable traction in intertidal zone login and installation method thereof
CN105604079A (en) Tunnel immersed tube coupling construction method applicable to high-flow-rate condition
KR101782456B1 (en) Submarine cable laying apparatus and laying method
CN1039442C (en) Barge-loading type seabeach pipeline excavator
CN111576526A (en) Rock-based seabed cable laying device and laying method thereof
CN208884603U (en) Spouting cable burial machine
CN109594603B (en) Jet-flow type ROV (remote operated vehicle) trencher for quickly cleaning sludge above sea pipe
CN108832551A (en) The laying of batholith sea bed high-pressure undersea cable and guard method
CN216564303U (en) Formula pipe cable is laid and is buried machine is spouted in hank
CN212336126U (en) Rock-based seabed cable laying device
CN105220726A (en) Native device is broken through in the controlled spray of flow
CN203911369U (en) Self-propelled sea cable laying plough used in shallow sea
CN114498456A (en) Formula pipe cable is laid and is buried machine is spouted in hank
KR101578110B1 (en) Salvage lifting device of moon water jet and salvaging method by salvage lifting machine of moon water jet
CN210482418U (en) Deepwater non-contact burying device
CN104565537A (en) Synchronous laying and buried depth construction method for seabed glass reinforced plastic pipelines
RU2175617C1 (en) Cable laying complex
Hill et al. Development of an improved cable trenching plowshare
CN116054031B (en) Construction method for protecting submarine cable of dynamic section of deep-open sea floating type fan
CN218648474U (en) Crawler self-walking type submarine cable laying device
CN208835616U (en) A kind of underwater burying machine of major diameter submarine cable

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180629