CN108194045A CN201810085058.9A CN201810085058A CN108194045A CN 108194045 A CN108194045 A CN 108194045A CN 201810085058 A CN201810085058 A CN 201810085058A CN 108194045 A CN108194045 A CN 108194045A
Authority
CN
China
Prior art keywords
casing
refractory protection
protection set
reaction
central tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810085058.9A
Other languages
Chinese (zh)
Other versions
CN108194045B (en
Inventor
韩雨桐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Shengli Petroleum Engineering Corp
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810085058.9A priority Critical patent/CN108194045B/en
Publication of CN108194045A publication Critical patent/CN108194045A/en
Application granted granted Critical
Publication of CN108194045B publication Critical patent/CN108194045B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B29/00Cutting or destroying pipes, packers, plugs or wire lines, located in boreholes or wells, e.g. cutting of damaged pipes, of windows; Deforming of pipes in boreholes or wells; Reconditioning of well casings while in the ground
    • E21B29/10Reconditioning of well casings, e.g. straightening

Landscapes

  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Geology (AREA)
  • Mining & Mineral Resources (AREA)
  • Physics & Mathematics (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physical Or Chemical Processes And Apparatus (AREA)

Abstract

The present invention relates to a kind of casing repairing devices.Its technical solution is:Packer is installed in the bottom of oil well casing, top is equipped with isolating and protecting sand;Tubing anchor is installed in the inner wall of the oil well casing on the top of isolating and protecting sand; the lower end of central tube is fixed by the inner wall of tubing anchor and oil well casing; the top of tubing anchor is equipped with metal packer; the top of the central tube connect fixation with wellhead assembly; refractory protection set is connected by pressure balance check valve in the lower section of centering short segment; thermit reaction raw material is equipped in the annular housing of the refractory protection set; and refractory protection set is sleeved on the outer wall of central tube; the inner cavity installation reaction of central tube induces tubing string, and advantageous effect is:The thermit reaction raw material that inner cavity is covered to refractory protection by electric heating tube heats; so as to make thermit reaction raw material that controllable thermit reaction occur; the breakage of casing is blocked and is repaired; the casing inner diameter different problems of existing recovery technique are avoided, also avoid existing the problem of being leaked again by cement.

Description

A kind of casing repairing device
Technical field
The present invention relates to a kind of petroleum pipeline tool prosthetic device and method, more particularly to a kind of casing repairing devices.
Background technology
In the recovery process of oil gas field, since geological conditions is more complicated, such as inclined shaft, horizontal well etc., often go out The situation of existing oil well casing breakage.Casing damage can cause to endanger as follows to oil field development:1st, flow string cannot be normal G.I.H;2nd, when casing bad position is in water layer or layer of sand position, oil well largely can be discharged or shake out;3rd, stimulation of well Can not carry out;4th, the outer blowout of casing is easily caused;5th, oil well is caused to be scrapped.
To casing collapse, seamed or hole repairing has following several method:1st, squeeze cementing:When formation pressure is little, break When splitting and missing not serious, it can be placed under repair with the method for squeeze cementing.Its technique method is:First with it is smaller than casing inner diameter by 8~ 10 millimeters of gauguste cutter latus rectums, then in the next hanging plugging device in cut appropriate location(Tool title is bridge plug), cut with Well-sinking seals off temporarily, then a certain amount of cement mortar is injected more than bridge plug, it is made to be frozen into cement plug, after cement plug solidification, The cement plug opened in casing is bored, and pressure testing checks the cut quality of cement sealing, after sealing to be confirmed is up-to-standard, then bores out outstanding Empty plugging device(Bridge plug), and sand washing is to shaft bottom.The casing repaired in this way can generally bear the pressure of 40~80 megapascal, with The well has high-voltage construction that lower packet is answered to protect afterwards, and the section is avoided to bear high pressure.2nd, allowance law:Exactly pasted on the inner wall of bad casing One layer of thin-walled tube, to achieve the purpose that reparation.Its technological principle is:Ripple is covered on a kind of special high pressure resistant rubber tube Pipe(Thin-wall tube)After arriving well inner sleeve damage position down, building the pressure makes rubber tube expansion distending bellows simultaneously, is close to bellows Casing breakage inner wall, and casing and bellows are bonded into one by binding agent, after to be bonded dose of curing, movable drilling tool, High pressure resistant rubber tube takes out.This inflatable technology method is simple, safe operation.3rd, casing replacing:When rupture location is on oil well top, And when can be buckled to taking-up cut more than casing, accident section more than casing can be all brought up with method of reverse deduction, tripping in is new again Casing is tight to buckling well.The benefit of the method is to ensure that the consistency of casing inner diameter, and downhole tool during later operation can be suitable Profit passes through;Shortcoming is that the casing screw thread degree of tightening of underground make-up is not so good as to obtain tightly, and the cost of more casing replacing on well head Compare high, also more difficult operation.
Wherein, subsidize repairing method the problem is that:When needing sand control, tripping in sand control pipe is needed;When need over the ground When layer transformation is acidified, tripping in is needed to be acidified tubing string;When needing to carry out pressure break to stratum, then tripping in fracturing string;Due to The internal diameter of steel pipe is less than the internal diameter of casing, in this way, the diameter of the tool of tripping in and specification are required for becoming smaller, causes the liquid of injection Amount becomes smaller, and influences the effect of sand control, acidification and pressure break, in addition, steel pipe forms a projection shape of internal surface of sleeve pipe, in this way, under Enter tubing string and be susceptible to situation about blocking.
Squeeze method slurry processes the problem is that:When scene needs acidizing treatment, because cement is alkaline, acid solution and water Mud can react, and the loophole repaired can be caused to leak out again in this way.
Invention content
The purpose of the present invention provides a kind of casing repairing device, uses aiming at drawbacks described above of the existing technology The iron of generation and alundum (Al2O3) are overlayed on the breakage of oil well casing, then by grinding so as to real by the method for thermit reaction The problem of having showed the reparation of oil well casing, having also avoided the problem of internal diameter in the prior art becomes smaller and leak out again.
A kind of casing repairing device that the present invention mentions, technical solution are:Including the first blind plugging(2), the first packer (3), isolating and protecting sand(4), the second blind plugging(5), tubing anchor(6), metal packer(7), tin system protection plug(8), electric heating tube (9), thermit reaction raw material(10), refractory protection set(13), pressure balance check valve(14), centering short segment(15), reaction induce Tubing string(17), central tube(18), in oil well casing(1)Bottom install the first packer(3), and the first packer(3)Bottom Portion is equipped with the first blind plugging(2), in the first packer(3)Top be equipped with isolating and protecting sand(4);In the isolating and protecting sand(4) Top oil well casing(1)Inner wall installation tubing anchor(6), central tube(18)Lower end pass through tubing anchor(6)With oil well set Pipe(1)Inner wall fix, and the central tube(18)Bottom install the second blind plugging(5), the tubing anchor(6)Top be equipped with Metal packer(7), the central tube(18)Top and wellhead assembly(16)Connection is fixed, and middle part is equipped with centering short segment (15), in centering short segment(15)Lower section pass through pressure balance check valve(14)Connect refractory protection set(13), the fire resisting guarantor Sheath(13)Annular housing in be equipped with thermit reaction raw material(10), and refractory protection set(13)It is sleeved on central tube(18)It is outer Wall, the refractory protection set(13)Outer wall be equipped with multiple through-holes, and install tin system protection plug(8), the central tube(18)'s Inner cavity installation reaction induces tubing string(17), induce tubing string in reaction(17)Bottom be equipped with electric heating tube(9), pass through electric heating tube (9)To refractory protection set(13)The thermit reaction raw material of inner cavity(10)It is heated, so as to make thermit reaction raw material(10)Occur Chemical reaction, by the breakage of casing(19)It blocks and repairs.
Preferably, above-mentioned reaction induces tubing string(17)Middle part be equipped with locator(11)And temperature sensor(12), lead to Cross locator(11)By the breakage of oil well casing(19)Positioning;Pass through temperature sensor(12)To refractory protection set(13)Interior Thermit reaction raw material(10)Reaction result be monitored.
Preferably, above-mentioned thermit reaction raw material(10)Using aluminium powder and di-iron trioxide according to volume ratio 2:1 ratio It is uniformly mixed.
Preferably, above-mentioned refractory protection set(13)Bottom lock, open top and is installed on pressure balance check valve (14), the refractory protection set(13)Outer wall be equipped with multiple inclined through-holes, make the collar extension and oil well casing of through-hole(1)It is interior Wall is corresponding;The refractory protection set(13)Inside and central tube(18)Contact, the reaction induce tubing string(17)Bottom is set Some electric heating tubes(9)After starting heating, heat is directly passed through into central tube(18)It is transmitted to refractory protection set(13)Interior aluminium Thermal response raw material(10), induce thermit reaction.
Preferably, above-mentioned tin system protection plug(8)It melts at high temperature, so as to which the iron of thermit reaction production and three be aoxidized Two aluminium are discharged into oil well casing(1)Tube wall and breakage(19).
Preferably, above-mentioned tubing anchor(6)Using LMD tubing anchors.
Preferably, the first above-mentioned packer(3)Using 3Y445 packers.
The beneficial effects of the invention are as follows:Pass through the first blind plugging of tripping in, the first packer and isolating and protecting in oil well casing Sand, so as to which the fluid of lower part and the cavity at casing damage be separated;Again by repair tubing string tripping in casing breakage near, Tripping in reaction induces tubing string again, and startup power supply switchs, and the electric heater for heating that tubing string bottom is induced by reaction repairs tubing string Interior refractory protection set, until the thermit reaction raw material generation thermit reaction in refractory protection set, and the iron of thermit reaction generation The breakage of casing can be carried out mending-leakage reparation, and pass through grinding by water and alundum (Al2O3), be finally completed repairing for oil well casing It is multiple, the casing inner diameter different problems after reparation of the existing technology are avoided, also avoid existing to leak again by cement The problem of;For the present invention using thermit reaction, the method that grinding and scraping is recycled to be combined is restored to the part of casing repairing Tunica pipe and reaches the performance of tunica pipe with the requirement of diameter.
Description of the drawings
Attached drawing 1 is the structure diagram of the present invention;
Attached drawing 2 is the structure diagram of thermit reaction raw material and refractory protection set;
Attached drawing 3 is the structure diagram that reaction induces tubing string;
In upper figure:Oil well casing 1, the first blind plugging 2, the first packer 3, isolating and protecting sand 4, the second blind plugging 5, tubing anchor 6, metal Packer 7, tin system protection plug 8, electric heating tube 9, thermit reaction raw material 10, locator 11, temperature sensor 12, refractory protection set 13rd, pressure balance check valve 14, centering short segment 15, wellhead assembly 16, reaction induce tubing string 17, central tube 18, breakage 19, more Side shape shape 9.1, closed base 13.1, groove 13.2, casing repairing section a-a.
Specific embodiment
The preferred embodiment of the present invention is illustrated below in conjunction with attached drawing, it should be understood that preferred reality described herein It applies example to be merely to illustrate and explain the present invention, be not intended to limit the present invention.
Embodiment 1, with reference to attached drawing 1,2 and 3, a kind of casing repairing device that the present invention mentions, including the first blind plugging 2, the One packer 3, isolating and protecting sand 4, the second blind plugging 5, tubing anchor 6, metal packer 7, tin system protection plug 8, electric heating tube 9, aluminium Thermal response raw material 10, refractory protection set 13, pressure balance check valve 14, centering short segment 15, reaction induce tubing string 17, central tube 18, the first packer 3 is installed in the bottom of oil well casing 1, and the bottom of the first packer 3 is equipped with the first blind plugging 2, in the first envelope Isolating and protecting sand 4 is equipped with every the top of device 3;Tubing anchor is installed in the inner wall of the oil well casing 1 on the top of the isolating and protecting sand 4 6, the lower end of central tube 18 is fixed by tubing anchor 6 and the inner wall of oil well casing 1, and the bottom installation second of the central tube 18 Blind plugging 5, the top of the tubing anchor 6 are equipped with metal packer 7, and the top of the central tube 18 is connect admittedly with wellhead assembly 16 Fixed, middle part is equipped with centering short segment 15, and refractory protection set 13 is connected by pressure balance check valve 14 in the lower section of centering short segment 15, Thermit reaction raw material 10 is equipped in the annular housing of the refractory protection set 13, and refractory protection set 13 is sleeved on the outer of central tube 18 Wall is equipped with multiple through-holes, and install tin system protection plug 8 on the downside of the outer wall of refractory protection set 13, the central tube 18 it is interior Chamber installation reaction induces tubing string 17, and the bottom outside that tubing string 17 is induced in reaction is equipped with electric heating tube 9, right by electric heating tube 9 The thermit reaction raw material 10 that refractory protection covers 13 inner cavities is heated, will so as to chemically react thermit reaction raw material 10 The breakage 19 of casing, which blocks, to be repaired.
With reference to attached drawing 3, in addition, the middle part that the reaction of the present invention induces tubing string 17 is equipped with locator 11 and temperature sensor 12, the breakage 19 of oil well casing is positioned by locator 11, which is used to position the position of breakage 19;Pass through temperature Degree sensor 12 is monitored the reaction result of the thermit reaction raw material 10 in refractory protection set 13, moreover, reaction induces pipe Column 17 is made of heat-barrier material, itself heat transfer coefficient is small, and the heat for reducing thermit reaction is transmitted to the interior of reaction induction tubing string Chamber, because inner cavity is equipped with the electric lead being connect with electric heating tube 9, the data line also being connect with temperature sensor, locator, It cannot all be burnt out because of the heat of thermit reaction;Electric heating tube 9 is sleeved on the bottom outside that reaction induces tubing string 17, heat-insulated closing Good, when power switch is after well head starts, electric heating tube 9 is begun to warm up, and heat passes through central tube made of metal 18 first Outer wall, the thermit reaction raw material 10 being transmitted in refractory protection set 13, until temperature promotion starts to aluminium powder and di-iron trioxide Reaction, since its reaction is exothermic reaction, reacted successively upwards from the lower section of refractory protection set 13, generate molten iron and three Al 2 O water, the density of molten iron is big, and the multiple through-holes being equipped with along refractory protection 13 outer walls of set flow out, the plug of tin system protection at this time 8 melt at high temperature, so, the iron and alundum (Al2O3) of liquid can smoothly flow out, due under refractory protection set 13 Side is equipped with metal packer 7, in this way, the iron and alundum (Al2O3) of liquid can only cover the seam between 13 and casing along refractory protection Gap flows up, and entire chamber is smaller, and temperature is higher, and the aluminium powder of refractory protection set 13 and di-iron trioxide continuation are being reacted, So the iron and alundum (Al2O3) of liquid can be flowed up persistently, until encountering the breakage of casing, breakage is filled Get up, and the temperature outside breakage is relatively low, just starts to solidify in this way, until breakage filling finishes, the iron of liquid and three oxygen Change the gap that two aluminium are continued between casing and refractory protection set 13 to flow up, until final thermit reaction finishes, slowly It is cooled into firm repair layer;At this time since reaction induces tubing string still mounted on the center of refractory protection set 13, temperature passes Sensor still by the control room of temperature data uploading to outer wellhead, can begin to decline according to temperature from well head and then judge aluminothermy Reaction terminates, and above proposes reaction and induces tubing string, then carry out grinding and the scraping operations of next step.
Wherein, thermit reaction raw material 10 of the invention uses aluminium powder and di-iron trioxide according to volume ratio 2:1 ratio is mixed Close uniform, and the size of the breakage measured according to the survey meter of well logging determines the number of filling aluminium powder and di-iron trioxide Amount, so as to meet the needs of casing repairing.
With reference to attached drawing 2, the bottom of refractory protection of the invention set 13 is equipped with closed base 13.1, and the closed base 13.1 center is equipped with groove 13.2, and the groove 13.2 is arc groove, and induces the polygon of 17 bottom of tubing string with reacting The electric heating tube 9 of shape shape 9.1 coordinates, and can play the role of positioning and fixed, and reaction is induced tubing string 17 is located in closing The center of pedestal 13.1, convenient for the temperature Synchronous lifting around during heating, keep from heat it is uneven caused by reaction it is different Influence the quality of casing repairing;In addition, refractory protection covers 13 open top and is installed on pressure balance check valve 14, it is described resistance to The outer wall of fiery protective case 13 is equipped with multiple inclined through-holes, and the collar extension for making through-hole is corresponding with the inner wall of oil well casing 1;It is described resistance to The inside of fiery protective case 13 is contacted with central tube 18, and the reaction induces the electric heating tube 9 that 17 bottom of tubing string is equipped with and starts heating Afterwards, the thermit reaction raw material 10 heat being directly transmitted to by central tube 18 in refractory protection set 13, induces thermit reaction.
The refractory protection set 13 is annular tubular structure, and inner wall is equipped with refractory material, can bear 2500 degree of height Temperature, for example using refractory brick made of zirconium oxide, top setting pressure balance check valve 14 avoids the aluminium at the top of in reaction process Powder and brown iron oxide seriously collapse, and make the two-way pressure balance of refractory protection set 13, also avoid aluminium powder and brown iron oxide disposable Fast reaction controls reaction speed, reduces the severe degree of reaction.
Tin system protection plug 8 melts at high temperature, and tin system protection plug 8 melts, in this way, by aluminium due to being tin system under high temperature The iron and alundum (Al2O3) of thermal response generation are discharged into the tube wall of oil well casing 1 and breakage 19, and set is realized after cooled and solidified The reparation of pipe, then make casing inner diameter identical with scraping by being ground.
In addition, since the thermit reaction of the present invention is carried out under confined conditions at one, so in refractory protection set 13 Top setting pressure balance check valve 14 can control the process of thermit reaction, although thermit reaction is violent, pass through air inlet Control, and the thermit reaction of the present invention is made to maintain a relatively mild reaction process, the method for use is:First, according to volume Proportioning 2:1 ratio addition aluminium powder and brown iron oxide, and aluminium powder and brown iron oxide are more fluffy, you can make reaction mild, protect Safety is demonstrate,proved.
The tubing anchor 6 of the present invention uses LMD tubing anchors, and the first packer 3 uses 3Y445 packers.
The application method of a kind of casing repairing device that the present invention mentions, includes the following steps:
1st, first, by the survey meter of well logging, the breakage 19 of oil well casing 1 is found, by 3 tripping in oil well set of the first packer Pipe lower part is insulated, and installs the first blind plugging 2, the crude oil of casing part is isolated, then by 4 the first envelope of tripping in of isolating and protecting sand Protective layer is formed every 3 top of device;
2nd, into oil well casing 1, tubing string is repaired in tripping in:By the second blind plugging 5, tubing anchor 6, metal packer 7, thermit reaction raw material 10th, the reparation tubing string tripping in oil well set that refractory protection set 13, pressure balance check valve 14, centering short segment 15 and central tube 18 form In pipe 1, and entire tubing string of repairing is positioned, carried out after the completion of positioning setting, entire one section of tubing string is repaired by above carrying Height pushes again, so that it may so that tubing anchor 6 is completed setting, make entirely to repair tubing string and is supported;Continue to push, insulate metal Device 7 is realized setting;
3rd, 18 tripping in of the central tube reaction into oil well casing 1 induces tubing string 17, and react the electrical heating for inducing 17 bottom of tubing string Pipe 9 is located at the bottom of refractory protection set 13, and thermit reaction raw material 10 is housed in refractory protection set 13, starts electric heating tube 9, heat Refractory protection is covered by the thermit reaction raw material 10 in 13 by the outer wall of central tube 18 and is heated to reaction temperature;And it is induced in reaction Installation positioner 11 and temperature sensor 12 on tubing string 17, after thermit reaction raw material 10 starts reaction, due to aluminium powder and three oxygen It is exothermic reaction to change the chemical reaction between two iron, so, the temperature data that temperature sensor 12 obtains is in lasting rising, from well Mouth may determine that reaction induces the induction of tubing string 17 and reacts successfully, and stopping continues to heat, and at this moment the data of temperature sensor 12 maintain Process that is steady or slowly rising, illustrates aluminium powder and di-iron trioxide in sustained response, the iron and alundum (Al2O3) of generation then lead to The through-hole crossed on the outside of refractory protection set 13 flows in the gap between refractory protection set 13 and casing and the breakage 19 of casing, directly Terminate to reaction, the data of temperature sensor feedback decline, and complete thermit reaction to the mending-leakage around the breakage of oil well casing;
4th, it takes out reaction and induces tubing string 17, along oil well casing tripping in survey meter, find out the reparation situation of oil well casing, then will Central tube rotates, and can separate upper portion centers pipe and the central tube of 15 lower part of centering short segment, stay in oil well casing inner cavity The iron that generates after being centering short segment 15, pressure balance check valve 14, lower part central tube, refractory protection set 13 and thermit reaction And alundum (Al2O3), then by grinding, the component left in above-mentioned oil well casing is ground, then again by the remaining object of grinding and Isolating and protecting sand 4 is washed out by clean-out service outside oil well casing;
5th, the tripping in latus rectum pipe cleaning in oil well casing, is made identical above and below the internal diameter of oil well casing by scraping, is fully returned to cover The design requirement of pipe, tripping in survey meter, detects oil well casing, finds out the recovery situation of casing again again;Finally by first 3 and first blind plugging 2 of packer is taken out, and completes casing repairing operation.
It should be noted that:The process of above-mentioned thermit reaction is as follows:
Electric heating tube 9 is sleeved on the bottom outside that reaction induces tubing string 17, heat-insulated to close, when power switch is after well head starts, Electric heating tube 9 is begun to warm up, and heat by the outer wall of central tube made of metal 18, is transmitted in refractory protection set 13 first Thermit reaction raw material 10, until temperature promotion starts to react to aluminium powder and di-iron trioxide, since its reaction is exothermic reaction, because This, from the lower section of refractory protection set 13 reacts, generates molten iron and alundum (Al2O3) water successively upwards, and the density of molten iron is big, along Refractory protection covers multiple through-holes outflow that 13 outer walls are equipped with, and the plug of tin system protection at this time 8 melts at high temperature, so, liquid Iron and alundum (Al2O3) can smoothly flow out, due to refractory protection set 13 lower section be equipped with metal packer 7, in this way, liquid Iron and alundum (Al2O3) can only along refractory protection cover 13 and casing between gap flow up, entire chamber is smaller, temperature Degree is higher, and the aluminium powder of refractory protection set 13 and di-iron trioxide continuation are being reacted, so, the iron and alundum (Al2O3) of liquid can Flowed up with lasting, until encountering the breakage of casing, breakage filling got up, and the temperature outside breakage compared with It is low, just start to solidify in this way, until breakage filling finishes, the iron and alundum (Al2O3) of liquid continue on casing and fire resisting guarantor Gap between sheath 13 flows up, until final thermit reaction finishes, is slowly cooled into firm repair layer.
In addition, the refractory protection set 13 of the present invention is annular tubular structure, inner wall uses refractory brick made of zirconium oxide, 2500 degree of high temperature can be born, top setting pressure balance check valve 14 avoids the aluminium powder at top and oxidation in reaction process Iron powder seriously collapses, and makes the two-way pressure balance of refractory protection set 13, also avoids aluminium powder and the disposable fast reaction of brown iron oxide, Reaction speed is controlled, reduces the severe degree of reaction.
In addition, the grinding and scraping of the present invention are the prior art, no longer it is described in detail.
Embodiment 2, the bottom of refractory protection of the invention set 13 are equipped with closed base 13.1, and the closed base 13.1 Center be equipped with groove 13.2, the groove 13.2 is polygonal grooves, and the polygon with react induction tubing string 17 bottom The electric heating tube 9 of shape coordinates, and can play the role of positioning and fixed;In addition, open top and the peace of refractory protection set 13 Equipped with pressure balance check valve 14, it is respectively equipped in the different level height of the outer wall of refractory protection set 13 multiple inclined Through-hole, the collar extension for making the through-hole of differentiated levels is corresponding with the inner wall of oil well casing 1, equipped with the multigroup of differentiated levels Through-hole, there are the advantages of be:In 10 reaction process of thermit reaction raw material in refractory protection set 13, the reaction generation of lower part Liquid iron and alundum (Al2O3) can be flowed out along the through-hole of bottom, middle part reaction generation liquid iron and alundum (Al2O3) It can be flowed out along the through-hole at middle part, the iron and alundum (Al2O3) of the liquid of top reaction generation can be along the through-hole streams on top Go out, mainly ensure that the iron of liquid and alundum (Al2O3) smoothly can all flow out in refractory protection set 13, so as to fill out Fill the gap between refractory protection set 13 and casing and breakage.
The above, is only the part preferred embodiment of the present invention, and any those skilled in the art may profit Equivalent technical solution is changed or is revised as with the technical solution of above-mentioned elaboration.Therefore, technology according to the present invention Any simple modification or substitute equivalents that scheme is carried out, belong to the greatest extent the scope of protection of present invention.

Claims (7)

1. a kind of casing repairing device, it is characterized in that:Including the first blind plugging(2), the first packer(3), isolating and protecting sand(4)、 Second blind plugging(5), tubing anchor(6), metal packer(7), tin system protection plug(8), electric heating tube(9), thermit reaction raw material (10), refractory protection set(13), pressure balance check valve(14), centering short segment(15), reaction induce tubing string(17), central tube (18), in oil well casing(1)Bottom install the first packer(3), and the first packer(3)Bottom be equipped with the first blind plugging (2), in the first packer(3)Top be equipped with isolating and protecting sand(4);In the isolating and protecting sand(4)Top oil well set Pipe(1)Inner wall installation tubing anchor(6), central tube(18)Lower end pass through tubing anchor(6)With oil well casing(1)Inner wall consolidate It is fixed, and the central tube(18)Bottom install the second blind plugging(5), the tubing anchor(6)Top be equipped with metal packer (7), the central tube(18)Top and wellhead assembly(16)Connection is fixed, and middle part is equipped with centering short segment(15), it is short in righting Section(15)Lower section pass through pressure balance check valve(14)Connect refractory protection set(13), the refractory protection set(13)Annular Thermit reaction raw material is equipped in cavity(10), and refractory protection set(13)It is sleeved on central tube(18)Outer wall, the refractory protection Set(13)Outer wall be equipped with multiple through-holes, and install tin system protection plug(8), the central tube(18)Inner cavity installation reaction induce Tubing string(17), induce tubing string in reaction(17)Bottom be equipped with electric heating tube(9), pass through electric heating tube(9)To refractory protection set (13)The thermit reaction raw material of inner cavity(10)It is heated, so as to make thermit reaction raw material(10)It chemically reacts, by casing Breakage(19)It blocks and repairs.
2. casing repairing device according to claim 1, it is characterized in that:The reaction induces tubing string(17)Middle part set There is locator(11)And temperature sensor(12), pass through locator(11)By the breakage of oil well casing(19)Positioning;Pass through temperature Spend sensor(12)To refractory protection set(13)Interior thermit reaction raw material(10)Reaction result be monitored.
3. casing repairing device according to claim 1, it is characterized in that:The thermit reaction raw material(10)Using aluminium powder With di-iron trioxide according to volume ratio 2:1 ratio is uniformly mixed.
4. casing repairing device according to claim 1, it is characterized in that:The refractory protection set(13)Bottom lock, Open top and it is installed on pressure balance check valve(14), the refractory protection set(13)Outer wall be equipped with it is multiple inclined logical Hole makes the collar extension and oil well casing of through-hole(1)Inner wall it is corresponding;The refractory protection set(13)Inside and central tube(18) Contact, the reaction induce tubing string(17)The electric heating tube that bottom is equipped with(9)After starting heating, heat is directly passed through into central tube (18)It is transmitted to refractory protection set(13)Interior thermit reaction raw material(10), induce thermit reaction.
5. casing repairing device according to claim 1, it is characterized in that:The tin system protection plug(8)It melts at high temperature Change, so as to which the iron of thermit reaction production and alundum (Al2O3) are discharged into oil well casing(1)Tube wall and breakage(19).
6. casing repairing device according to claim 1, it is characterized in that:The tubing anchor(6)Using LMD tubing anchors.
7. casing repairing device according to claim 1, it is characterized in that:First packer(3)It is sealed using 3Y445 Every device.
CN201810085058.9A 2018-01-29 2018-01-29 Sleeve pipe prosthetic devices Active CN108194045B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810085058.9A CN108194045B (en) 2018-01-29 2018-01-29 Sleeve pipe prosthetic devices

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810085058.9A CN108194045B (en) 2018-01-29 2018-01-29 Sleeve pipe prosthetic devices

Publications (2)

Publication Number Publication Date
CN108194045A true CN108194045A (en) 2018-06-22
CN108194045B CN108194045B (en) 2020-07-10

Family

ID=62591054

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810085058.9A Active CN108194045B (en) 2018-01-29 2018-01-29 Sleeve pipe prosthetic devices

Country Status (1)

Country Link
CN (1) CN108194045B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110671069A (en) * 2018-07-03 2020-01-10 中国石油化工股份有限公司 Method for suspending and erecting sand bridge in oil-water well casing and leakage repairing method
CN111636839A (en) * 2020-06-03 2020-09-08 胡淑美 Coal mine excavation cement pipe crack repairing device and repairing method thereof
CN113137200A (en) * 2021-04-29 2021-07-20 扬州工业职业技术学院 Chemical method repairing device for petroleum casing pipe
WO2023031617A1 (en) * 2021-09-02 2023-03-09 Philip Head All metal-to-metal casing patch

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1074970A (en) * 1992-01-29 1993-08-04 西安近代化学研究所 Explosives for underground welding and expanding well casing in oil field
CN101457637A (en) * 2009-01-06 2009-06-17 刘文西 Sealing expansion tube apparatus for repairing petroleum thermal production well and implementing method
CN102516963A (en) * 2011-10-17 2012-06-27 中国石油天然气股份有限公司 Chemical composite resin mounting agent for oil-water well casing restoration
WO2015030721A1 (en) * 2013-08-27 2015-03-05 Halliburton Energy Services, Inc. Acid diversion treatments in injection wells using permeability modifiers
WO2015150828A2 (en) * 2014-04-04 2015-10-08 Bisn Tec Ltd Well casing/tubing disposal
US20160053591A1 (en) * 2013-04-12 2016-02-25 Welltec A/S A downhole expandable tubular
CN106930713A (en) * 2015-12-31 2017-07-07 中国石油天然气股份有限公司 A kind of casing damage restorative procedure
CN107474808A (en) * 2017-07-17 2017-12-15 陕西森瑞石油技术开发有限公司 A kind of Oil/gas Well sleeve plugging resin sealing agent and preparation method and application

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1074970A (en) * 1992-01-29 1993-08-04 西安近代化学研究所 Explosives for underground welding and expanding well casing in oil field
CN101457637A (en) * 2009-01-06 2009-06-17 刘文西 Sealing expansion tube apparatus for repairing petroleum thermal production well and implementing method
CN102516963A (en) * 2011-10-17 2012-06-27 中国石油天然气股份有限公司 Chemical composite resin mounting agent for oil-water well casing restoration
US20160053591A1 (en) * 2013-04-12 2016-02-25 Welltec A/S A downhole expandable tubular
WO2015030721A1 (en) * 2013-08-27 2015-03-05 Halliburton Energy Services, Inc. Acid diversion treatments in injection wells using permeability modifiers
WO2015150828A2 (en) * 2014-04-04 2015-10-08 Bisn Tec Ltd Well casing/tubing disposal
CN106930713A (en) * 2015-12-31 2017-07-07 中国石油天然气股份有限公司 A kind of casing damage restorative procedure
CN107474808A (en) * 2017-07-17 2017-12-15 陕西森瑞石油技术开发有限公司 A kind of Oil/gas Well sleeve plugging resin sealing agent and preparation method and application

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
人民教育出版社化学室 编: "《化学及解题指导》", 30 June 2000 *
张明之 等: "《铸造词典》", 30 April 1986 *
成都铁路局成都焊轨厂 编: "《铝热焊接钢轨》", 31 July 1975 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110671069A (en) * 2018-07-03 2020-01-10 中国石油化工股份有限公司 Method for suspending and erecting sand bridge in oil-water well casing and leakage repairing method
CN111636839A (en) * 2020-06-03 2020-09-08 胡淑美 Coal mine excavation cement pipe crack repairing device and repairing method thereof
CN111636839B (en) * 2020-06-03 2022-10-28 胡淑美 Coal mine excavation cement pipe crack repairing device and repairing method thereof
CN113137200A (en) * 2021-04-29 2021-07-20 扬州工业职业技术学院 Chemical method repairing device for petroleum casing pipe
CN113137200B (en) * 2021-04-29 2023-01-24 扬州工业职业技术学院 Chemical method repairing device for petroleum casing pipe
WO2023031617A1 (en) * 2021-09-02 2023-03-09 Philip Head All metal-to-metal casing patch
GB2625029A (en) * 2021-09-02 2024-06-05 Head Philip All metal-to-metal casing patch

Also Published As

Publication number Publication date
CN108194045B (en) 2020-07-10

Similar Documents

Publication Publication Date Title
CN108194045A (en) A kind of casing repairing device
CN108204216A (en) A kind of application method of casing repairing device
EP1395732B1 (en) In-situ casting of well equipment
US10760374B2 (en) Tool for metal plugging or sealing of casing
US20060144591A1 (en) Method and apparatus for repair of wells utilizing meltable repair materials and exothermic reactants as heating agents
WO2018063829A1 (en) Tool for metal plugging or sealing of casing
US3379252A (en) Well completion for extreme temperatures
CN108457612A (en) A kind of petroleum casing pipe chemical method restorative procedure
CN107605454A (en) Go out gas drilling hole and go out the method for gas drilling hole conveying coal gas
CN104929558B (en) Fixed point takes set process
CN108252673B (en) A kind of petroleum casing pipe chemical method prosthetic device
US11299949B2 (en) Thermal apparatus and associated methods
CN204691750U (en) Supercritical CO 2 laminated distributor under well gas injection tube column
CN114763732A (en) Pressure control casing drilling method for underground injection pressure containing stratum
RU2237796C1 (en) Method for reinforcing well shaft and device for realization of said method
CA3142209A1 (en) Downhole preheating start-up method for super heavy oil reservoir developed for dual-horizontal-well sagd
SU1618870A1 (en) Method of cementing wells
US3583485A (en) Thermal prestressing of casing
RU2330933C1 (en) Method of producing formation insulation during cementation of casing pipe
WO2024083173A1 (en) Casing nipple and tubular structure
CA2541318A1 (en) Well cementing apparatus and method
US20230349264A1 (en) Methods to repair well liner hangers
CN117108239A (en) Packer device for underground and plugging method for underground
RU2153571C2 (en) Method of tightness recovery of well tubing-casing annular space
RU1788195C (en) Method of sealing of connections of pipes in borehole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Liu Dongzhang

Inventor after: Han Yutong

Inventor before: Han Yutong

CB03 Change of inventor or designer information
TA01 Transfer of patent application right

Effective date of registration: 20200615

Address after: 257091 No.55 Fuqian street, Dongying Economic and Technological Development Zone, Dongying City, Shandong Province

Applicant after: Liu Dongzhang

Applicant after: Liu Bowen

Applicant after: Zou Xiaonan

Address before: 257091 No. 18 East Fourth Road, Dongying District Economic Development Zone, Dongying, Shandong

Applicant before: Han Yutong

TA01 Transfer of patent application right
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20230506

Address after: 257000 No. 258, Ji'nan Road, Dongying District, Shandong, Dongying

Patentee after: SINOPEC SHENGLI PETROLEUM ENGINEERING Co.,Ltd.

Address before: 257091 No.55, Fuqian street, Dongying Economic and Technological Development Zone, Dongying City, Shandong Province

Patentee before: Liu Dongzhang

Patentee before: Liu Bowen

Patentee before: Zou Xiaonan

TR01 Transfer of patent right