CN108193771A - A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node - Google Patents
A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node Download PDFInfo
- Publication number
- CN108193771A CN108193771A CN201810227830.6A CN201810227830A CN108193771A CN 108193771 A CN108193771 A CN 108193771A CN 201810227830 A CN201810227830 A CN 201810227830A CN 108193771 A CN108193771 A CN 108193771A
- Authority
- CN
- China
- Prior art keywords
- partition
- steel
- steel beam
- column
- rectangular
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims 43
- 239000010959 steel Substances 0.000 title claims 43
- 238000005192 partition Methods 0.000 title claims 25
- 238000003466 welding Methods 0.000 claims 3
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/185—Connections not covered by E04B1/21 and E04B1/2403, e.g. connections between structural parts of different material
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
一种装配化矩形钢管混凝土柱‑钢梁隔板贯通节点,属于建筑结构工程技术领域。所述节点包括矩形钢管混凝土柱、多个牛腿钢梁、多个连接板、两个贯通隔板和多个端板;牛腿钢梁包括上翼缘、下翼缘和腹板;两个贯通隔板分别为第一隔板和第二隔板,第一隔板和第二隔板分别与矩形钢管混凝土柱的两端连接,每个贯通隔板均设有多个在不同方向的伸出臂,第一隔板与第二隔板在同一方向的伸出臂与其对应的牛腿钢梁的上、下翼缘连接;矩形钢管混凝土柱柱壁与其对应的连接板的一端连接,连接板的另一端与其对应的牛腿钢梁一端的腹板连接,牛腿钢梁的另一端与端板连接。所述节点在工厂预制完成,运到现场进行安装,减少了现场焊接量并保证了加工精度。
An assembled rectangular steel pipe concrete column-steel girder partition through joint belongs to the technical field of building structure engineering. The joints include rectangular steel pipe concrete columns, multiple corbel steel beams, multiple connecting plates, two through partitions and multiple end plates; the corbel steel beams include upper flanges, lower flanges and webs; two The through partitions are the first partition and the second partition respectively, the first partition and the second partition are respectively connected with the two ends of the rectangular steel tube concrete column, and each through partition is provided with a plurality of extensions in different directions. For the arms, the arms of the first partition and the second partition in the same direction are connected with the upper and lower flanges of the corresponding corbel steel beams; the rectangular steel pipe concrete column wall is connected with one end of the corresponding connecting plate, and the The other end of the plate is connected to the web at one end of the corresponding corbel beam, and the other end of the corbel beam is connected to the end plate. The nodes are prefabricated in the factory and shipped to the site for installation, which reduces the amount of on-site welding and ensures processing accuracy.
Description
技术领域technical field
本发明涉及建筑结构工程技术领域,特别涉及一种装配化矩形钢管混凝土柱-钢梁隔板贯通节点。The invention relates to the technical field of building structure engineering, in particular to an assembled rectangular steel pipe concrete column-steel beam partition through joint.
背景技术Background technique
矩形钢管混凝土柱与钢梁连接方便,连接节点受力明确,承载力高,可靠度高。与钢梁连接形成的框架体系具有平面布置灵活,结构简单,易于实现构件的标准化等优点。因此,矩形方钢管混凝土柱与钢梁连接节点已在高层及超高层建筑中表现出了很好的应用前景。The rectangular concrete-filled steel tube column is conveniently connected to the steel beam, the force of the connection node is clear, the bearing capacity is high, and the reliability is high. The frame system formed by connecting with steel beams has the advantages of flexible layout, simple structure, and easy realization of standardization of components. Therefore, the joints between rectangular square concrete-filled steel tube columns and steel beams have shown good application prospects in high-rise and super high-rise buildings.
我国《矩形钢管混凝土结构技术规程》(CECS159:2004)推荐的矩形钢管混凝土柱-钢梁连接节点包括四种:内隔板式连接,带短梁的内隔板式连接,外环板式连接,隔板贯通式连接。隔板贯通式连接包括全螺栓隔板贯通节点。内隔板式节点的节点内部不易施焊,影响了管内混凝土的浇注,使其在应用中受到钢管混凝土柱边长的影响。外环板式节点需要足够大的水平环板来保证节点的强度,导致用钢量明显增大。隔板贯通节点整体节点区段可以工厂预制,受理机制明确,可以减小柱壁的屈曲变形,承载力高,可以实现结构的“强节点,弱构件”。my country's "Technical Regulations for Rectangular Concrete-filled Steel Tube Structures" (CECS159:2004) recommends four types of rectangular concrete-filled steel tube column-steel beam connection nodes: inner diaphragm connection, inner diaphragm connection with short beams, outer ring plate connection, Partition through connection. Diaphragm through connections include fully bolted diaphragm through connections. The inside of the joint of the inner diaphragm joint is not easy to be welded, which affects the pouring of the concrete in the tube, and makes it affected by the side length of the CFST column in application. The outer ring plate joint needs a sufficiently large horizontal ring plate to ensure the strength of the joint, resulting in a significant increase in steel consumption. The overall joint section of the partition through joint can be prefabricated in the factory, the acceptance mechanism is clear, the buckling deformation of the column wall can be reduced, the bearing capacity is high, and the "strong joint, weak member" of the structure can be realized.
目前的隔板贯通节点存在现场焊接量大,隔板与钢柱连接位置存在二次焊接,焊接质量不易保证。全螺栓隔板贯通节点虽然减少了现场焊接量,但是钢梁与矩形钢管混凝土柱仍需要现场安装。由于我国目前构件制作的精度的不够,很多时候存在螺栓孔位置有误差而导致钢梁安装不上的现象。At present, there is a large amount of on-site welding at the penetration joint of the partition, and there is secondary welding at the connection position between the partition and the steel column, and the welding quality is not easy to guarantee. Although the full-bolt diaphragm penetration joints reduce the amount of on-site welding, the steel beams and rectangular steel tube concrete columns still need to be installed on site. Due to the insufficient precision of the current component manufacturing in our country, there are often errors in the position of the bolt holes, which lead to the phenomenon that the steel beam cannot be installed.
发明内容Contents of the invention
为了解决现有技术中节点现场焊接量大以及对加工精度要求高的技术问题,本发明提供了一种装配化矩形钢管混凝土柱-钢梁隔板贯通节点,包括矩形钢管混凝土柱、多个牛腿钢梁、多个连接板、两个贯通隔板和多个端板。In order to solve the technical problems of large amount of on-site welding of nodes and high requirements on machining accuracy in the prior art, the present invention provides an assembled rectangular steel tube concrete column-steel beam partition through node, which includes a rectangular steel tube concrete column, a plurality of Leg steel beams, multiple connection plates, two through bulkheads, and multiple end plates.
所述牛腿钢梁包括上翼缘、下翼缘和腹板,两个贯通隔板分别为第一隔板和第二隔板,第一隔板和第二隔板分别与矩形钢管混凝土柱的两端连接,每个贯通隔板均设有多个在不同方向的伸出臂,且每个方向的伸出臂对应矩形钢管混凝土柱的一个侧壁,每个伸出臂对应一个牛腿钢梁,且每个牛腿钢梁对应一个连接板,第一隔板与第二隔板在同一方向的伸出臂与其对应的牛腿钢梁的上、下翼缘连接,每个贯通隔板上设置通孔,矩形钢管混凝土柱柱壁与其对应的连接板的一端连接,连接板的另一端与其对应的牛腿钢梁一端的腹板连接,牛腿钢梁的另一端与端板连接。The corbel steel beam includes an upper flange, a lower flange and a web, and the two through partitions are the first partition and the second partition respectively, and the first partition and the second partition are respectively connected with the rectangular concrete filled steel pipe column The two ends are connected, and each through partition is provided with a plurality of extension arms in different directions, and the extension arms in each direction correspond to a side wall of the rectangular steel tube concrete column, and each extension arm corresponds to a corbel steel beams, and each corbel steel beam corresponds to a connecting plate, the extension arms of the first partition and the second partition in the same direction are connected with the upper and lower flanges of the corresponding corbel steel beams, and each through partition A through hole is set on the plate, the column wall of the rectangular steel pipe concrete column is connected with one end of the corresponding connecting plate, the other end of the connecting plate is connected with the web plate of one end of the corresponding corbel steel beam, and the other end of the corbel steel beam is connected with the end plate .
所述第一隔板与所述矩形钢管混凝土柱一端的端口通过焊接固定连接,所述第二隔板与所述矩形钢管混凝土柱的另一端的端口通过焊接固定连接。The first partition is fixedly connected to the port at one end of the rectangular steel tube concrete column by welding, and the second partition is fixedly connected to the port at the other end of the rectangular steel tube concrete column by welding.
所述伸出臂与所述与其对应的牛腿钢梁的上、下翼缘焊接连接或者螺栓连接。The extension arm is welded or bolted to the upper and lower flanges of the corresponding corbel steel beam.
所述连接板与所述与其对应矩形钢管混凝土柱柱壁焊接连接。The connecting plate is welded to the wall of the corresponding rectangular steel pipe concrete column.
所述连接板与所述与其对应的牛腿钢梁的腹板焊接连接或者螺栓连接。The connecting plate is welded or bolted to the web of the corresponding corbel steel beam.
所述牛腿钢梁的数量是2个、3个或者4个,所述牛腿钢梁、所述连接板、所述伸出臂和所述端板数量相同。The number of the corbel steel beams is 2, 3 or 4, and the number of the corbel steel beams, the connecting plates, the extension arms and the end plates is the same.
所述牛腿钢梁与所述与其对应的端板焊接连接。The corbel steel beam is welded to the corresponding end plate.
所述第一隔板和第二隔板分别与带有法兰的矩形钢管混凝土柱螺栓连接。The first partition and the second partition are respectively connected with flanged rectangular steel tube concrete column bolts.
所述端板通过端板连接板与带有长圆孔的钢梁连接。The end plate is connected with the steel beam with the long round hole through the end plate connecting plate.
所述端板连接板与端板焊接连接,与所述带有长圆孔的钢梁螺栓连接。The connecting plate of the end plate is welded to the end plate, and is connected to the steel beam with the oblong hole by bolts.
本发明所述的装配化矩形钢管混凝土柱-钢梁隔板贯通节点,其有益效果如下:The beneficial effects of the assembled rectangular steel pipe concrete column-steel beam partition through the joint described in the present invention are as follows:
1、由矩形钢管混凝土柱、牛腿钢梁、连接板、贯通隔板和端板组成的节点在工厂预制完成,运到现场进行安装,减少了现场焊接量并保证了加工精度。1. The joints composed of rectangular steel tube concrete columns, corbel steel beams, connection plates, through partitions and end plates are prefabricated in the factory and transported to the site for installation, which reduces the amount of on-site welding and ensures the processing accuracy.
2、带有法兰的矩形钢管混凝土柱与隔板进行螺栓连接,避免了现场焊接量大且焊接质量不能保证的缺陷,由于隔板是厚钢板,这样设置避免了贯通隔板的二次焊接导致隔板的层状撕裂。2. The flanged rectangular concrete-filled steel tube column is bolted to the partition, which avoids the defects of large amount of welding on site and the welding quality cannot be guaranteed. Since the partition is a thick steel plate, this setting avoids secondary welding through the partition resulting in lamellar tearing of the separator.
3、端板通过端板连接板与带有长圆孔的钢梁螺栓连接,通过长圆孔吸收安装及加工的误差,保证安装精度。3. The end plate is connected with the steel beam bolts with long round holes through the end plate connecting plate, and the errors of installation and processing are absorbed through the long round holes to ensure the installation accuracy.
4、该节点在工厂整体预制完成,完全实现了结构的装配化施工,施工速度快且连接质量容易保证。4. The node is prefabricated in the factory as a whole, which fully realizes the assembly construction of the structure. The construction speed is fast and the connection quality is easy to guarantee.
附图说明Description of drawings
图1是本发明提供的节点与钢梁连接的分解示意图。Fig. 1 is an exploded schematic view of the connection between a node and a steel beam provided by the present invention.
图2是本发明提供的节点的分解示意图。Fig. 2 is an exploded schematic diagram of a node provided by the present invention.
图3是本发明提供的实施例1的立体结构示意图。Fig. 3 is a schematic three-dimensional structure diagram of Embodiment 1 provided by the present invention.
图4是本发明提供的实施例1的俯视图。Fig. 4 is a top view of Embodiment 1 provided by the present invention.
图5是本发明提供的实施例1的前视图。Fig. 5 is a front view of Embodiment 1 provided by the present invention.
图6是本发明提供的实施例2的立体结构示意图。Fig. 6 is a schematic three-dimensional structure diagram of Embodiment 2 provided by the present invention.
图7是本发明提供的实施例2的俯视图。Fig. 7 is a top view of Embodiment 2 provided by the present invention.
图8是本发明提供的实施例2的前视图。Fig. 8 is a front view of Embodiment 2 provided by the present invention.
图9是本发明提供的实施例3的立体结构示意图。Fig. 9 is a schematic three-dimensional structure diagram of Embodiment 3 provided by the present invention.
图10是本发明提供的实施例3的俯视图。Fig. 10 is a top view of Embodiment 3 provided by the present invention.
图11是本发明提供的实施例3的前视图。Fig. 11 is a front view of Embodiment 3 provided by the present invention.
图12是本发明提供的实施例4的立体结构示意图。Fig. 12 is a schematic three-dimensional structure diagram of Embodiment 4 provided by the present invention.
图13是本发明提供的实施例4的俯视图。Fig. 13 is a top view of Embodiment 4 provided by the present invention.
图14是本发明提供的实施例4的前视图。Fig. 14 is a front view of Embodiment 4 provided by the present invention.
其中,in,
1矩形钢管混凝土柱,2牛腿钢梁,3连接板,4贯通隔板,5端板,6伸出臂,7通孔,8带法兰的矩形钢管混凝土柱,9法兰,10钢梁,11长圆孔,12端板连接板,13上翼缘,14下翼缘,15腹板,16第一隔板,17第二隔板,18螺栓。1 Rectangular concrete-filled steel pipe column, 2 Corbel steel beam, 3 Connection plate, 4 Through partition, 5 End plate, 6 Extending arm, 7 Through hole, 8 Rectangular steel pipe concrete column with flange, 9 Flange, 10 Steel Beam, 11 oblong holes, 12 end plate connecting plates, 13 upper flange, 14 lower flange, 15 web, 16 first partition, 17 second partition, 18 bolts.
具体实施方式Detailed ways
为了解决现有技术存在的问题,如图1至图14所示,本发明提供了一种装配化矩形钢管混凝土柱-钢梁隔板贯通节点,包括矩形钢管混凝土柱1、多个牛腿钢梁2、多个连接板3、两个贯通隔板4和多个端板5;In order to solve the problems existing in the prior art, as shown in Fig. 1 to Fig. 14, the present invention provides an assembled rectangular steel tube concrete column-steel beam partition through joint, including a rectangular steel tube concrete column 1, a plurality of corbel steel Beam 2, multiple connecting plates 3, two through partitions 4 and multiple end plates 5;
牛腿钢梁2包括上翼缘13、下翼缘14和腹板15,两个贯通隔板4分别为第一隔板16和第二隔板17,第一隔板16与矩形钢管混凝土柱1一端的端口通过焊接固定连接,第二隔板17与矩形钢管混凝土柱1的另一端的端口通过焊接固定连接,每个贯通隔板4均设有多个在不同方向的伸出臂6,且每个方向的伸出臂6对应矩形钢管混凝土柱1一侧的柱壁,每个伸出臂6对应一个牛腿钢梁2,且每个牛腿钢梁2对应一个连接板3,第一隔板16与第二隔板17在同一方向的伸出臂6与其对应的牛腿钢梁2的上翼缘13和下翼缘14连接,每个贯通隔板上设置通孔7,矩形钢管混凝土柱1的柱壁与其对应的连接板3的一端焊接连接,连接板3的另一端与其对应的牛腿钢梁2一端的腹板15连接,牛腿钢梁2的另一端与对应的端板5焊接连接;The corbel steel beam 2 includes an upper flange 13, a lower flange 14, and a web 15. The two through partitions 4 are the first partition 16 and the second partition 17 respectively. The first partition 16 and the rectangular steel pipe concrete column 1. The port at one end is fixedly connected by welding, and the second partition 17 is fixedly connected with the port at the other end of the rectangular steel pipe concrete column 1 by welding. Each penetrating partition 4 is provided with a plurality of extending arms 6 in different directions. And the extending arm 6 in each direction corresponds to the column wall on one side of the rectangular steel pipe concrete column 1, each extending arm 6 corresponds to a corbel steel beam 2, and each corbel steel beam 2 corresponds to a connecting plate 3, the first A partition 16 and the extension arm 6 of the second partition 17 in the same direction are connected with the upper flange 13 and the lower flange 14 of the corresponding corbel steel beam 2, and a through hole 7 is set on each through partition, rectangular The column wall of the steel pipe concrete column 1 is welded to one end of the corresponding connecting plate 3, the other end of the connecting plate 3 is connected to the web 15 at one end of the corresponding corbel steel beam 2, and the other end of the corbel steel beam 2 is connected to the corresponding The end plate 5 is welded and connected;
第一隔板16和第二隔板17分别与带有法兰的矩形钢管混凝土柱8的法兰9通过螺栓18连接;The first dividing plate 16 and the second dividing plate 17 are respectively connected with the flange 9 of the rectangular steel pipe concrete column 8 with the flange by bolts 18;
端板5与端板连接板12的一端焊接连接,端板连接板12的另一端与带有长圆孔11的钢梁10通过螺栓18连接;The end plate 5 is welded to one end of the end plate connecting plate 12, and the other end of the end plate connecting plate 12 is connected to the steel beam 10 with the oblong hole 11 through a bolt 18;
所述矩形钢管混凝土柱1的外部钢管为焊接钢板、对接槽钢或冷弯钢管;The outer steel pipe of the rectangular concrete-filled steel tube column 1 is a welded steel plate, butt channel steel or cold-formed steel pipe;
所述钢梁10为H型钢梁或工字钢梁;The steel beam 10 is an H-shaped steel beam or an I-shaped steel beam;
所述连接板3与矩形钢管混凝土柱1的柱壁采用坡口焊缝或者角焊缝;The connecting plate 3 and the column wall of the rectangular steel pipe concrete column 1 adopt groove welds or fillet welds;
所述螺栓18优选为高强螺栓;The bolt 18 is preferably a high-strength bolt;
所述矩形钢管混凝土柱1内部的混凝土为普通混凝土、高强混凝土或者自密实混凝土。The concrete inside the rectangular concrete-filled steel tube column 1 is ordinary concrete, high-strength concrete or self-compacting concrete.
本发明中,牛腿钢梁2的数量可以是2个、3个或者4个,所述牛腿钢梁2、所述连接板3、所述伸出臂6和所述端板5数量相同,以下以牛腿钢梁2、连接板3、伸出臂6和端板5的数量为4个为例进行详细介绍。In the present invention, the number of corbel steel beams 2 can be 2, 3 or 4, and the number of the corbel steel beams 2, the connecting plates 3, the extension arms 6 and the end plates 5 is the same , the following takes the number of corbel steel beams 2, connecting plates 3, outriggers 6 and end plates 5 as four as an example for detailed introduction.
实施例1Example 1
如图3至图5所示,第一隔板16与第二隔板17在同一方向的伸出臂6与其对应的牛腿钢梁2的上翼缘13和下翼缘14通过螺栓18连接,矩形钢管混凝土柱1的柱壁与其对应的连接板3的一端焊接连接,连接板3的另一端与其对应的牛腿钢梁2一端的腹板15通过螺栓18连接.。As shown in Figures 3 to 5, the extension arms 6 of the first partition 16 and the second partition 17 in the same direction are connected to the upper flange 13 and the lower flange 14 of the corbel steel beam 2 by bolts 18 , the column wall of the rectangular steel pipe concrete column 1 is welded to one end of the corresponding connecting plate 3, and the other end of the connecting plate 3 is connected to the web 15 at one end of the corresponding corbel steel beam 2 through bolts 18.
本实施例1中装配化矩形钢管混凝土柱-钢梁隔板贯通节点的具体实施过程包括:The specific implementation process of the assembled rectangular concrete-filled steel tube column-steel beam partition joint in Example 1 includes:
步骤1、根据设计要求确定的节点尺寸,加工贯通隔板4,贯通隔板四周伸出矩形钢管混凝土柱1柱壁足够长尺寸的外伸翼缘,确保螺栓连接可以实现,贯通隔板4的伸出臂6逐步过渡到与牛腿钢梁2同宽;Step 1. According to the node size determined according to the design requirements, process the penetrating partition 4, extend the outrigger flange of the column wall of the rectangular steel tube concrete column 1 that is sufficiently long to ensure that the bolt connection can be realized, and pass through the partition 4. The outstretched arm 6 gradually transitions to the same width as the corbel steel beam 2;
步骤2、贯通隔板4的外伸翼缘上预留螺栓孔,贯通隔板4的伸出臂6预留螺栓孔,螺栓孔的数量及直径根据设计承载力的要求确定;Step 2. Bolt holes are reserved on the outstretched flange of the penetrating partition 4, and bolt holes are reserved on the extending arm 6 of the penetrating partition 4. The number and diameter of the bolt holes are determined according to the requirements of the design bearing capacity;
步骤3、连接板3上预留螺栓孔,根据抗剪承载力需要确定;Step 3. Bolt holes are reserved on the connecting plate 3, which is determined according to the shear bearing capacity;
步骤4、在工厂将第一隔板16和第二隔板17与两者之间的矩形钢管混凝土柱1焊接连接,同时将连接板3与矩形钢管混凝土柱1的柱壁焊接连接,形成一个节点域构件;Step 4. Weld and connect the first partition 16 and the second partition 17 to the rectangular steel tube concrete column 1 between them in the factory, and at the same time weld the connecting plate 3 to the column wall of the rectangular steel tube concrete column 1 to form a node domain component;
步骤5、加工带有法兰的矩形钢管混凝土柱8,在法兰9上加工与贯通隔板4上位置和数量相同的预留螺栓孔,在工厂进行拼装;Step 5, process the rectangular concrete-filled steel tube column 8 with the flange, process the reserved bolt holes on the flange 9 with the same position and quantity as those on the through partition plate 4, and assemble them in the factory;
步骤6、加工带有螺栓孔的牛腿钢梁2,上翼缘13与下翼缘14上螺栓孔的位置和数量与伸出臂6相同,腹板15上螺栓孔的位置和数量与连接板3相同;Step 6, process the corbel steel beam 2 with bolt holes, the position and quantity of the bolt holes on the upper flange 13 and the lower flange 14 are the same as those of the outrigger 6, and the position and quantity of the bolt holes on the web 15 are the same as those connected Same for plate 3;
步骤7、将牛腿钢梁2与节点域构件进行拼装,上翼缘13和下翼缘14分别与第一隔板16和第二隔板17的伸出臂6通过螺栓18连接,腹板15与连接板3通过螺栓18连接,并将牛腿钢梁2与节点域构件作为整体运往现场,整体安装;Step 7: Assemble the corbel steel beam 2 with the node domain members, the upper flange 13 and the lower flange 14 are respectively connected with the extension arms 6 of the first partition 16 and the second partition 17 by bolts 18, and the web 15 and the connection plate 3 are connected by bolts 18, and the corbel steel beam 2 and the node domain components are transported to the site as a whole and installed as a whole;
步骤8,在钢梁10上加工长圆孔11,在端板连接板12加工螺栓孔,螺栓孔的数量和位置与长圆孔11相对应;Step 8, machining oblong holes 11 on the steel beam 10, machining bolt holes in the end plate connecting plate 12, the quantity and position of the bolt holes correspond to the oblong holes 11;
步骤9、在现场,待下部的带法兰的矩形钢管混凝土柱8安装完成,将法兰9与节点域构件上的第二隔板17通过螺栓18连接,再将第一隔板16与上部带法兰的矩形钢管混凝土柱8的法兰9通过螺栓18连接;Step 9. At the site, after the installation of the lower rectangular concrete-filled steel tube column 8 with flanges is completed, connect the flange 9 with the second partition 17 on the node domain member through bolts 18, and then connect the first partition 16 with the upper The flange 9 of the rectangular steel tube concrete column 8 with flange is connected by bolt 18;
步骤10、在现场将端板5与端板连接板12焊接连接,端板连接板12与钢梁10通过螺栓18连接。Step 10, welding and connecting the end plate 5 and the end plate connecting plate 12 on site, and connecting the end plate connecting plate 12 and the steel beam 10 through bolts 18 .
实施例2Example 2
如图6至图8所示,第一隔板16与第二隔板17在同一方向的伸出臂6与其对应的牛腿钢梁2的上翼缘13和下翼缘14焊接连接,矩形钢管混凝土柱1的柱壁与其对应的连接板3的一端焊接连接,连接板3的另一端与其对应的牛腿钢梁2一端的腹板15通过螺栓18连接。As shown in Figures 6 to 8, the extension arms 6 of the first partition 16 and the second partition 17 in the same direction are welded to the upper flange 13 and the lower flange 14 of the corresponding corbel steel beam 2, rectangular The column wall of the steel pipe concrete column 1 is welded to one end of the corresponding connecting plate 3 , and the other end of the connecting plate 3 is connected to the web 15 at one end of the corresponding corbel steel beam 2 by bolts 18 .
本实施例2中装配化矩形钢管混凝土柱-钢梁隔板贯通节点的具体实施过程包括:The specific implementation process of the assembled rectangular steel pipe concrete column-steel beam partition through joint in Example 2 includes:
步骤1、根据设计要求确定的节点尺寸,加工贯通隔板4,贯通隔板四周伸出矩形钢管混凝土柱1柱壁足够长尺寸的外伸翼缘,确保螺栓连接可以实现,贯通隔板4的伸出臂6逐步过渡到与牛腿钢梁2同宽;Step 1. According to the node size determined according to the design requirements, process the penetrating partition 4, extend the outrigger flange of the column wall of the rectangular steel tube concrete column 1 that is sufficiently long to ensure that the bolt connection can be realized, and pass through the partition 4. The outstretched arm 6 gradually transitions to the same width as the corbel steel beam 2;
步骤2、贯通隔板4的外伸翼缘上预留螺栓孔,螺栓孔的数量及直径根据设计承载力的要求确定;Step 2. Bolt holes are reserved on the overhanging flange of the penetrating partition 4, and the number and diameter of the bolt holes are determined according to the requirements of the design bearing capacity;
步骤3、连接板3上预留螺栓孔,根据抗剪承载力需要确定;Step 3. Bolt holes are reserved on the connecting plate 3, which is determined according to the shear bearing capacity;
步骤4、在工厂将第一隔板16和第二隔板17与两者之间的矩形钢管混凝土柱1焊接连接,同时将连接板3与矩形钢管混凝土柱1的柱壁焊接连接,形成一个节点域构件;Step 4. Weld and connect the first partition 16 and the second partition 17 to the rectangular steel tube concrete column 1 between them in the factory, and at the same time weld the connecting plate 3 to the column wall of the rectangular steel tube concrete column 1 to form a node domain component;
步骤5、加工带有法兰的矩形钢管混凝土柱8,在法兰9上加工与贯通隔板4上位置和数量相同的预留螺栓孔,在工厂进行拼装;Step 5, process the rectangular concrete-filled steel tube column 8 with the flange, process the reserved bolt holes on the flange 9 with the same position and quantity as those on the through partition plate 4, and assemble them in the factory;
步骤6、加工端部带有坡口的牛腿钢梁2,在腹板15上加工螺栓孔,螺栓孔的位置和数量与连接板3相同;Step 6, processing the corbel steel beam 2 with grooves at the end, processing bolt holes on the web 15, the position and quantity of the bolt holes are the same as those of the connecting plate 3;
步骤7、将牛腿钢梁2与节点域构件进行拼装,上翼缘13和下翼缘14分别与第一隔板16和第二隔板17的伸出臂6通过焊接连接,腹板15与连接板3通过螺栓18连接,并将牛腿钢梁2与节点域构件作为整体运往现场,整体安装;Step 7: Assemble the corbel steel beam 2 with the node domain members, the upper flange 13 and the lower flange 14 are respectively connected to the extension arms 6 of the first partition 16 and the second partition 17 by welding, and the web 15 Connect with the connection plate 3 through bolts 18, and transport the corbel steel beam 2 and the node domain components as a whole to the site for overall installation;
步骤8,在钢梁10上加工长圆孔11,在端板连接板12加工螺栓孔,螺栓孔的数量和位置与长圆孔11相对应;Step 8, machining oblong holes 11 on the steel beam 10, machining bolt holes in the end plate connecting plate 12, the quantity and position of the bolt holes correspond to the oblong holes 11;
步骤9、在现场,待下部的带法兰的矩形钢管混凝土柱8安装完成,将法兰9与节点域构件上的第二隔板17通过螺栓18连接,再将第一隔板16与上部带法兰的矩形钢管混凝土柱8的法兰9通过螺栓18连接;Step 9. At the site, after the installation of the lower rectangular concrete-filled steel tube column 8 with flanges is completed, connect the flange 9 with the second partition 17 on the node domain member through bolts 18, and then connect the first partition 16 with the upper The flange 9 of the rectangular steel tube concrete column 8 with flange is connected by bolt 18;
步骤10、在现场将端板5与端板连接板12焊接连接,端板连接板12与钢梁10通过螺栓18连接。Step 10, welding and connecting the end plate 5 and the end plate connecting plate 12 on site, and connecting the end plate connecting plate 12 and the steel beam 10 through bolts 18 .
实施例3Example 3
如图9至图11所示,第一隔板16与第二隔板17在同一方向的伸出臂6与其对应的牛腿钢梁2的上翼缘13和下翼缘14焊接连接,矩形钢管混凝土柱1的柱壁与其对应的连接板3的一端焊接连接,连接板3的另一端与其对应的牛腿钢梁2一端的腹板15焊接连接。As shown in Figures 9 to 11, the extension arms 6 of the first partition 16 and the second partition 17 in the same direction are welded to the upper flange 13 and the lower flange 14 of the corresponding corbel steel beam 2, rectangular The column wall of the steel pipe concrete column 1 is welded to one end of the corresponding connecting plate 3 , and the other end of the connecting plate 3 is welded to the web 15 at one end of the corresponding corbel steel beam 2 .
本实施例3中装配化矩形钢管混凝土柱-钢梁隔板贯通节点的具体实施过程包括:The specific implementation process of the assembled rectangular steel pipe concrete column-steel beam partition through joint in Example 3 includes:
步骤1、根据设计要求确定的节点尺寸,加工贯通隔板4,贯通隔板四周伸出矩形钢管混凝土柱1柱壁足够长尺寸的外伸翼缘,确保螺栓连接可以实现,贯通隔板4的伸出臂6逐步过渡到与牛腿钢梁2同宽;Step 1. According to the node size determined according to the design requirements, process the penetrating partition 4, extend the outrigger flange of the column wall of the rectangular steel tube concrete column 1 that is sufficiently long to ensure that the bolt connection can be realized, and pass through the partition 4. The outstretched arm 6 gradually transitions to the same width as the corbel steel beam 2;
步骤2、贯通隔板4的外伸翼缘上预留螺栓孔,螺栓孔的数量及直径根据设计承载力的要求确定;Step 2. Bolt holes are reserved on the overhanging flange of the penetrating partition 4, and the number and diameter of the bolt holes are determined according to the requirements of the design bearing capacity;
步骤3、加工带有坡口的连接板3;Step 3, processing the connecting plate 3 with grooves;
步骤4、在工厂将第一隔板16和第二隔板17与两者之间的矩形钢管混凝土柱1焊接连接,同时将连接板3与矩形钢管混凝土柱1的柱壁焊接连接,形成一个节点域构件;Step 4. Weld and connect the first partition 16 and the second partition 17 to the rectangular steel tube concrete column 1 between them in the factory, and at the same time weld the connecting plate 3 to the column wall of the rectangular steel tube concrete column 1 to form a node domain component;
步骤5、加工带有法兰的矩形钢管混凝土柱8,在法兰9上加工与贯通隔板4上位置和数量相同的预留螺栓孔,在工厂进行拼装;Step 5, process the rectangular concrete-filled steel tube column 8 with the flange, process the reserved bolt holes on the flange 9 with the same position and quantity as those on the through partition plate 4, and assemble them in the factory;
步骤6、加工端部带有坡口的牛腿钢梁2;Step 6, processing the corbel steel beam 2 with grooves at the end;
步骤7、将牛腿钢梁2与节点域构件进行拼装,上翼缘13和下翼缘14分别与第一隔板16和第二隔板17的伸出臂6通过焊接连接,腹板15与连接板3通过焊接连接,并将牛腿钢梁2与节点域构件作为整体运往现场,整体安装;Step 7: Assemble the corbel steel beam 2 with the node domain members, the upper flange 13 and the lower flange 14 are respectively connected to the extension arms 6 of the first partition 16 and the second partition 17 by welding, and the web 15 It is connected with the connection plate 3 by welding, and the corbel steel beam 2 and the node domain components are transported to the site as a whole and installed as a whole;
步骤8,在钢梁10上加工长圆孔11,在端板连接板12加工螺栓孔,螺栓孔的数量和位置与长圆孔11相对应;Step 8, machining oblong holes 11 on the steel beam 10, machining bolt holes in the end plate connecting plate 12, the quantity and position of the bolt holes correspond to the oblong holes 11;
步骤9、在现场,待下部的带法兰的矩形钢管混凝土柱8安装完成,将法兰9与节点域构件上的第二隔板17通过螺栓18连接,再将第一隔板16与上部带法兰的矩形钢管混凝土柱8的法兰9通过螺栓18连接;Step 9. At the site, after the installation of the lower rectangular concrete-filled steel tube column 8 with flanges is completed, connect the flange 9 with the second partition 17 on the node domain member through bolts 18, and then connect the first partition 16 with the upper The flange 9 of the rectangular steel tube concrete column 8 with flange is connected by bolt 18;
步骤10、在现场将端板5与端板连接板12焊接连接,端板连接板12与钢梁10通过螺栓18连接。Step 10, welding and connecting the end plate 5 and the end plate connecting plate 12 on site, and connecting the end plate connecting plate 12 and the steel beam 10 through bolts 18 .
实施例4Example 4
如图12至图14所示,第一隔板16与第二隔板17在同一方向的伸出臂6与其对应的牛腿钢梁2的上翼缘13和下翼缘14通过螺栓18连接,矩形钢管混凝土柱1的柱壁与其对应的连接板3的一端焊接连接,连接板3的另一端与其对应的牛腿钢梁2一端的腹板15焊接连接。As shown in Figures 12 to 14, the extension arms 6 of the first partition 16 and the second partition 17 in the same direction are connected to the upper flange 13 and the lower flange 14 of the corbel steel beam 2 by bolts 18 , the column wall of the rectangular steel pipe concrete column 1 is welded to one end of the corresponding connecting plate 3 , and the other end of the connecting plate 3 is welded to the web 15 at one end of the corresponding corbel steel beam 2 .
本实施例4中装配化矩形钢管混凝土柱-钢梁隔板贯通节点的具体实施过程包括:The specific implementation process of the assembled rectangular concrete filled steel pipe column-steel beam partition through joint in Example 4 includes:
步骤1、根据设计要求确定的节点尺寸,加工贯通隔板4,贯通隔板四周伸出矩形钢管混凝土柱1柱壁足够长尺寸的外伸翼缘,确保螺栓连接可以实现,贯通隔板4的伸出臂6逐步过渡到与牛腿钢梁2同宽;Step 1. According to the node size determined according to the design requirements, process the penetrating partition 4, extend the outrigger flange of the column wall of the rectangular steel tube concrete column 1 that is sufficiently long to ensure that the bolt connection can be realized, and pass through the partition 4. The outstretched arm 6 gradually transitions to the same width as the corbel steel beam 2;
步骤2、贯通隔板4的外伸翼缘上预留螺栓孔,贯通隔板4的伸出臂6预留螺栓孔,螺栓孔的数量及直径根据设计承载力的要求确定;Step 2. Bolt holes are reserved on the outstretched flange of the penetrating partition 4, and bolt holes are reserved on the extending arm 6 of the penetrating partition 4. The number and diameter of the bolt holes are determined according to the requirements of the design bearing capacity;
步骤3、加工带有坡口的连接板3;Step 3, processing the connecting plate 3 with grooves;
步骤4、在工厂将第一隔板16和第二隔板17与两者之间的矩形钢管混凝土柱1焊接连接,同时将连接板3与矩形钢管混凝土柱1的柱壁焊接连接,形成一个节点域构件;Step 4. Weld and connect the first partition 16 and the second partition 17 to the rectangular steel tube concrete column 1 between them in the factory, and at the same time weld the connecting plate 3 to the column wall of the rectangular steel tube concrete column 1 to form a node domain component;
步骤5、加工带有法兰的矩形钢管混凝土柱8,在法兰9上加工与贯通隔板4上位置和数量相同的预留螺栓孔,在工厂进行拼装;Step 5, process the rectangular concrete-filled steel tube column 8 with the flange, process the reserved bolt holes on the flange 9 with the same position and quantity as those on the through partition plate 4, and assemble them in the factory;
步骤6、加工带有螺栓孔的牛腿钢梁2,上翼缘13与下翼缘14的螺栓孔的位置和数量与伸出臂6相同;Step 6, processing the corbel steel beam 2 with bolt holes, the position and quantity of the bolt holes of the upper flange 13 and the lower flange 14 are the same as those of the extension arm 6;
步骤7、将牛腿钢梁2与节点域构件进行拼装,上翼缘13和下翼缘14分别与第一隔板16和第二隔板17的伸出臂6通过螺栓18连接,腹板15与连接板3通过焊接连接,并将牛腿钢梁2与节点域构件作为整体运往现场,整体安装;Step 7: Assemble the corbel steel beam 2 with the node domain members, the upper flange 13 and the lower flange 14 are respectively connected with the extension arms 6 of the first partition 16 and the second partition 17 by bolts 18, and the web 15 and the connection plate 3 are connected by welding, and the corbel steel beam 2 and the node domain components are transported to the site as a whole and installed as a whole;
步骤8,在钢梁10上加工长圆孔11,在端板连接板12加工螺栓孔,螺栓孔的数量和位置与长圆孔11相对应;Step 8, machining oblong holes 11 on the steel beam 10, machining bolt holes in the end plate connecting plate 12, the quantity and position of the bolt holes correspond to the oblong holes 11;
步骤9、在现场,待下部的带法兰的矩形钢管混凝土柱8安装完成,将法兰9与节点域构件上的第二隔板17通过螺栓18连接,再将第一隔板16与上部带法兰的矩形钢管混凝土柱8的法兰9通过螺栓18连接;Step 9. At the site, after the installation of the lower rectangular concrete-filled steel tube column 8 with flanges is completed, connect the flange 9 with the second partition 17 on the node domain member through bolts 18, and then connect the first partition 16 with the upper The flange 9 of the rectangular steel tube concrete column 8 with flange is connected by bolt 18;
步骤10、在现场将端板5与端板连接板12焊接连接,端板连接板12与钢梁10通过螺栓18连接。Step 10, welding and connecting the end plate 5 and the end plate connecting plate 12 on site, and connecting the end plate connecting plate 12 and the steel beam 10 through bolts 18 .
以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection of the present invention. within range.
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810227830.6A CN108193771A (en) | 2018-03-20 | 2018-03-20 | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810227830.6A CN108193771A (en) | 2018-03-20 | 2018-03-20 | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108193771A true CN108193771A (en) | 2018-06-22 |
Family
ID=62595984
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810227830.6A Pending CN108193771A (en) | 2018-03-20 | 2018-03-20 | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108193771A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109138179A (en) * | 2018-10-17 | 2019-01-04 | 辽宁工程技术大学 | A kind of assembled friction energy-dissipating Self-resetting partition perforation node |
CN111005450A (en) * | 2019-12-18 | 2020-04-14 | 中建科工集团有限公司 | Assembled implicit beam-column joint and construction method thereof |
CN112031180A (en) * | 2020-08-19 | 2020-12-04 | 江南大学 | Beam column node connecting device and application thereof |
CN112609898A (en) * | 2020-11-30 | 2021-04-06 | 中国建筑第八工程局有限公司 | Assembled steel structure column and construction method thereof |
CN114150765A (en) * | 2021-11-12 | 2022-03-08 | 广州地铁设计研究院股份有限公司 | Frame beam column connecting node structure and construction method thereof |
CN114622655A (en) * | 2020-12-11 | 2022-06-14 | 上海同济绿建土建结构预制装配化工程技术有限公司 | Connecting structure of special-shaped steel pipe concrete column and H-shaped steel beam |
CN114961391A (en) * | 2022-06-27 | 2022-08-30 | 重庆大学 | Assembled node of steel pipe concrete special-shaped column and H-shaped steel beam |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08135018A (en) * | 1994-11-10 | 1996-05-28 | Kajima Corp | Mixed structure of reinforced concrete columns and steel beams |
CN102425237A (en) * | 2011-10-19 | 2012-04-25 | 沈阳建筑大学 | On-site assembling type extending arm combined node |
CN102733489A (en) * | 2012-06-29 | 2012-10-17 | 中国建筑股份有限公司 | H-shaped steel beam and H-shaped steel column strong-axis variable-beam height fabricated node and construction method thereof |
CN103437425A (en) * | 2013-08-27 | 2013-12-11 | 陕西建科兴业钢结构有限公司 | Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method |
KR20140021278A (en) * | 2012-08-09 | 2014-02-20 | 서울대학교산학협력단 | Rigid joint of cft column and steel beam by horizontal welding diaphragm of flange plates and connecting bars |
CN104652615A (en) * | 2015-02-04 | 2015-05-27 | 北京工业大学 | Beam-column joint connection device of assembly type steel structure system |
CN105464221A (en) * | 2015-12-28 | 2016-04-06 | 天津大学 | Partition plate penetrating node for connecting rectangular steel tube concrete column with box-shaped steel beam |
CN105863081A (en) * | 2016-05-20 | 2016-08-17 | 西安建筑科技大学 | Multi-cavity concrete filled steel tube combination column and steel beam bolt joint and assembly method |
CN106638958A (en) * | 2016-11-18 | 2017-05-10 | 天津大学 | Assembling type embedded beam-column joint structure |
CN208056293U (en) * | 2018-03-20 | 2018-11-06 | 辽宁工程技术大学 | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node |
-
2018
- 2018-03-20 CN CN201810227830.6A patent/CN108193771A/en active Pending
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08135018A (en) * | 1994-11-10 | 1996-05-28 | Kajima Corp | Mixed structure of reinforced concrete columns and steel beams |
CN102425237A (en) * | 2011-10-19 | 2012-04-25 | 沈阳建筑大学 | On-site assembling type extending arm combined node |
CN102733489A (en) * | 2012-06-29 | 2012-10-17 | 中国建筑股份有限公司 | H-shaped steel beam and H-shaped steel column strong-axis variable-beam height fabricated node and construction method thereof |
KR20140021278A (en) * | 2012-08-09 | 2014-02-20 | 서울대학교산학협력단 | Rigid joint of cft column and steel beam by horizontal welding diaphragm of flange plates and connecting bars |
CN103437425A (en) * | 2013-08-27 | 2013-12-11 | 陕西建科兴业钢结构有限公司 | Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method |
CN104652615A (en) * | 2015-02-04 | 2015-05-27 | 北京工业大学 | Beam-column joint connection device of assembly type steel structure system |
CN105464221A (en) * | 2015-12-28 | 2016-04-06 | 天津大学 | Partition plate penetrating node for connecting rectangular steel tube concrete column with box-shaped steel beam |
CN105863081A (en) * | 2016-05-20 | 2016-08-17 | 西安建筑科技大学 | Multi-cavity concrete filled steel tube combination column and steel beam bolt joint and assembly method |
CN106638958A (en) * | 2016-11-18 | 2017-05-10 | 天津大学 | Assembling type embedded beam-column joint structure |
CN208056293U (en) * | 2018-03-20 | 2018-11-06 | 辽宁工程技术大学 | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109138179A (en) * | 2018-10-17 | 2019-01-04 | 辽宁工程技术大学 | A kind of assembled friction energy-dissipating Self-resetting partition perforation node |
CN111005450A (en) * | 2019-12-18 | 2020-04-14 | 中建科工集团有限公司 | Assembled implicit beam-column joint and construction method thereof |
CN112031180A (en) * | 2020-08-19 | 2020-12-04 | 江南大学 | Beam column node connecting device and application thereof |
CN112031180B (en) * | 2020-08-19 | 2021-06-11 | 江南大学 | Beam column node connecting device and application thereof |
CN112609898A (en) * | 2020-11-30 | 2021-04-06 | 中国建筑第八工程局有限公司 | Assembled steel structure column and construction method thereof |
CN114622655A (en) * | 2020-12-11 | 2022-06-14 | 上海同济绿建土建结构预制装配化工程技术有限公司 | Connecting structure of special-shaped steel pipe concrete column and H-shaped steel beam |
CN114150765A (en) * | 2021-11-12 | 2022-03-08 | 广州地铁设计研究院股份有限公司 | Frame beam column connecting node structure and construction method thereof |
CN114150765B (en) * | 2021-11-12 | 2023-01-20 | 广州地铁设计研究院股份有限公司 | Frame beam column connecting node structure and construction method thereof |
CN114961391A (en) * | 2022-06-27 | 2022-08-30 | 重庆大学 | Assembled node of steel pipe concrete special-shaped column and H-shaped steel beam |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108193771A (en) | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node | |
CN108532759B (en) | Ring plate splicing hollow sandwich steel pipe concrete composite joint and its installation method | |
CN103967133B (en) | Rectangular steel-tube concrete column and H profile steel beam bolted and welded connection node | |
CN107476446B (en) | Banded enhancement mode node that H shaped steel roof beam and wide steel core concrete column minor face are connected | |
CN107761957A (en) | New Sleeve quadrate steel pipe column and H profile steel beam assembling type node and its construction method | |
CN110670735A (en) | A prefabricated through-cross clapboard rectangular concrete-filled steel tubular column-steel beam joint structure | |
CN109339250B (en) | Node reinforced spliced steel pipe concrete connection structure and construction method thereof | |
CN107268805A (en) | A kind of prefabricated assembled beam column box node | |
CN208056293U (en) | A kind of assembling rectangular steel-tube concrete column-girder steel partition board perforation node | |
CN207988140U (en) | New Sleeve quadrate steel pipe column and H profile steel beam assembling type node | |
CN110878587A (en) | Module assembly type building beam column node connection structure | |
CN110359556A (en) | The bean column node of assembling type steel structure built-in inserted plate quadrate steel pipe column end plate connection | |
CN213038987U (en) | A kind of square steel tube concrete column-steel beam upper welded and lower bolted clapboard through node | |
CN107327029B (en) | A steel tube concrete column-steel beam assembled space node | |
CN207176940U (en) | A kind of concrete filled steel tube pole steel beam assembled space nodes | |
CN216108977U (en) | Assembled square steel pipe column-H shaped steel roof beam-baffle link up node | |
CN103306376A (en) | Assembled concrete-filled steel tube composite-column-steel reinforced concrete beam node | |
CN113605541A (en) | Outer ring type beam column rigid connection node | |
CN207878666U (en) | Connecting assembly for special-shaped steel pipe concrete column and H-shaped steel beam | |
CN206800653U (en) | A kind of concrete filled steel tube pole steel beam end plate type bolt connection node | |
CN105604194A (en) | Through angle steel type square steel tube concrete column and H-shaped steel beam connection node | |
CN207194175U (en) | A kind of prefabricated assembled bean column node box | |
CN205296391U (en) | A baffle link up node that is used for rectangle steel core concrete column and H girder steel to connect | |
CN106948496A (en) | A kind of concrete filled steel tube pole steel beam end plate type bolt connection node | |
CN108589931A (en) | The precast construction connecting node that concrete is combined with steel construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180622 |
|
RJ01 | Rejection of invention patent application after publication |