CN108152659A - A kind of method for judging electromagnetic potential transformer turn-to-turn insulation short circuit - Google Patents

A kind of method for judging electromagnetic potential transformer turn-to-turn insulation short circuit Download PDF

Info

Publication number
CN108152659A
CN108152659A CN201711437197.5A CN201711437197A CN108152659A CN 108152659 A CN108152659 A CN 108152659A CN 201711437197 A CN201711437197 A CN 201711437197A CN 108152659 A CN108152659 A CN 108152659A
Authority
CN
China
Prior art keywords
groups
turn
electromagnetic potential
voltage
alternating current
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201711437197.5A
Other languages
Chinese (zh)
Other versions
CN108152659B (en
Inventor
裴继东
蒋延磊
靳耀珂
赵志南
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Original Assignee
Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd filed Critical Pingdingshan Power Supply Co of State Grid Henan Electric Power Co Ltd
Priority to CN201711437197.5A priority Critical patent/CN108152659B/en
Publication of CN108152659A publication Critical patent/CN108152659A/en
Application granted granted Critical
Publication of CN108152659B publication Critical patent/CN108152659B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R31/00Arrangements for testing electric properties; Arrangements for locating electric faults; Arrangements for electrical testing characterised by what is being tested not provided for elsewhere
    • G01R31/50Testing of electric apparatus, lines, cables or components for short-circuits, continuity, leakage current or incorrect line connections
    • G01R31/72Testing of electric windings
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R35/00Testing or calibrating of apparatus covered by the other groups of this subclass
    • G01R35/02Testing or calibrating of apparatus covered by the other groups of this subclass of auxiliary devices, e.g. of instrument transformers according to prescribed transformation ratio, phase angle, or wattage rating

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

The present invention provides a kind of methods for judging electromagnetic potential transformer turn-to-turn insulation short circuit, make single-phase use suitable for electromagnetic potential transformer or more single-phase electricity electromagnetic type voltage transformer combinations make three-phase use in V V-arrangements, first pressurize and measure in adjacent two electromagnetic potential transformers, when voltmeter instruction is larger, illustrate bad with the presence of an electromagnetic potential transformer turn-to-turn insulation, pressure regulator is down to zero in time.The electromagnetic potential transformer of overvoltage is added to repeat to test, and according to different situations judged the uninflated electromagnetic potential transformer of another and any one again.The present invention only needs to coordinate simple operations by simple components, you can realizes the judgement to problem, using simplicity, helps to improve working efficiency.

Description

A kind of method for judging electromagnetic potential transformer turn-to-turn insulation short circuit
Technical field
The invention belongs to power system security guard method technical field more particularly to a kind of judgement electromagnetic potential mutual inductances The method of device turn-to-turn insulation short circuit.
Technical background
At present, when electric voltage exception occur in 10kV, 35kV, 110kV, 220kV electromagnetic potential, in order to ensure electric system is pacified Entirely, fault spread is prevented, it is usually that electromagnetic potential transformer is out of service, treat professional testing crew inspection.
When electromagnetic potential transformer longtime running, temperature can increase naturally, and when turn-to-turn insulation is bad, insulation also can be with Decline, form turn-to-turn short circuit, cause monitoring voltage abnormal.When testing crew reaches working site experiment, electromagnetic potential Mutual inductor temperature has declined, and turn-to-turn insulation is restored.Since the test voltage of no-load voltage ratio bridge test instrument offer is than relatively low, The electromagnetic potential transformer that turn-to-turn insulation is restored is measured, is susceptible to erroneous judgement.Often occur at that time that power transmission is normal, mistake Once there is monitoring voltage exception again in the time.
A kind of electromagnetic potential transformer turn-to-turn short circuit detection dress of the disclosure of the invention of Patent No. 201710267297.1 It puts and method, the detection device includes that module, high speed acquisition module occur for high frequency low voltage steep-sided pulse and to be built-in with analysis soft The host computer of part;Module occurs for the high frequency low voltage steep-sided pulse for generating nanosecond steep-sided pulse, and steep-sided pulse signal is injected Into tested electromagnetic potential transformer winding;The high speed acquisition module passes through tested electromagnetic potential transformer for acquiring Signature waveform after winding, containing winding short circuit failure, and pre-processed and be transmitted to host computer after being stored;The host computer The signature waveform received is analyzed and processed using repetition pulse method, so as to obtain tested electromagnetic potential transformer winding Short trouble feature.The invention can not only be positioned but also can be determined for being detected to voltage transformer winding early stage turn-to-turn fault Amount compares turn-to-turn insulation situation, avoids the further expansion of failure, the safe and stable operation for electric system provides reliable guarantor Barrier.
A kind of generator terminal voltage mutual inductor turn-to-turn short circuit of the disclosure of the invention of Patent No. 201410039668.7 exists Line method of discrimination measures main transformer high-pressure side residual voltage, factory's low pressure side residual voltage, generator neutral point residual voltage and divides The fundamental wave virtual value of each residual voltage is not calculated;It is exhausted over the ground that stator winding is calculated using injected type stator ground protection principle Edge resistance value;Definite value, and institute are acted when the fundamental wave virtual value of the generator neutral point residual voltage is more than stator ground fault protection The fundamental wave virtual value of fundamental wave virtual value and factory's low pressure side residual voltage for stating main transformer high-pressure side residual voltage is below institute Definite value is stated, and the stator winding insulation against ground resistance value does not reduce, be then judged as generator terminal voltage mutual inductor turn-to-turn Short circuit is alarmed after delay, and is latched sensitive section of zero-sequence fundamental voltage stator ground fault protection.The inventive method can be accurate Judge generator generator terminal PT shorted-turn faults, effectively prevent the malfunction of stator ground fault protection in the case, while significantly Shorten the malfunction elimination time.
However, the above method is required to that a large amount of detection electronic component and intelligent processing module, cost Gao Yi is configured Damage, use and maintenance cost are higher, are unfavorable under the conditions of bad working environments or simple operating mode, fast and simple to be judged, institute To need a kind of simple and convenient method for judging the short circuit of voltage transformer turn-to-turn insulation being easily achieved.
Invention content
The present invention provides a kind of methods for judging electromagnetic potential transformer turn-to-turn insulation short circuit, it is only necessary to pass through simple member Part coordinates simple operations, you can realizes the judgement to problem, using simplicity, helps to improve working efficiency.
In order to solve the above technical problems, the present invention provides a kind of judgement electromagnetic potential transformer turn-to-turn insulation short circuits Method includes the following steps:
1)The detection device for judging the short circuit of electromagnetic potential transformer turn-to-turn insulation is chosen, including AC voltage regulator one, exchange Voltmeter one;
2)By fault-free equal in adjacent three electromagnetic potential transformers to be checked or have and for only one is broken down, it will Three voltage transformers are respectively defined as A groups, B groups, C groups, and the secondary side of A groups with B groups is corresponded to winding parallel connection respectively;
3)It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and passes through AC voltage regulator to A groups, B group secondary sides Parallel connected end is slowly pressurizeed, and observes the voltage value of alternating current ammeter;
4)When the indicating value of alternating current ammeter increase by a relatively large margin, and one does not occur with the slow pressurization of AC voltage regulator When directly keeping smaller indicating value, it was demonstrated that A groups, B groups are all trouble-free electromagnetic potential transformers;
5)It by alternating current ammeter and is connected between B groups, the high-voltage winding of C groups, and passes through AC voltage regulator to B groups, C group secondary sides Parallel connected end is slowly pressurizeed, and observes the voltage value of alternating current ammeter;
6)When the indicating value of alternating current ammeter increase by a relatively large margin, and one does not occur with the slow pressurization of AC voltage regulator When directly keeping smaller indicating value, it was demonstrated that A groups, B groups, C groups are all trouble-free electromagnetic potential transformers, test ending;
7)When progress step 3)Afterwards, the indicating value of alternating current ammeter is with the slow increasing of appearance by a relatively large margin of pressurizeing of AC voltage regulator Greatly, when and finally keeping larger indicating value, it was demonstrated that it is bad with the presence of an electromagnetic potential transformer turn-to-turn insulation between A groups, B groups, Pressure regulator is down to zero in time at this time, repeats step 5);
8)When the indicating value of alternating current ammeter is with the slow increase of appearance by a relatively large margin of pressurizeing of AC voltage regulator, and finally keeps During larger indicating value, it was demonstrated that B group electromagnetic potential transformers are bad there are turn-to-turn insulation, pressure regulator are down to zero in time at this time, inspection Test end;
9)When progress step 7)Afterwards, the indicating value of alternating current ammeter does not occur by a relatively large margin with the slow pressurization of AC voltage regulator Increase, and when being always maintained at smaller indicating value, it was demonstrated that A group electromagnetic potential transformers are bad there are turn-to-turn insulation, at this time and When pressure regulator is down to zero, test ending;
10)When progress step 5)Afterwards, the indicating value of alternating current ammeter occurs by a relatively large margin with the slow pressurization of AC voltage regulator When increasing, and finally keeping larger indicating value, it was demonstrated that C group electromagnetic potential transformers are bad there are turn-to-turn insulation, in time will at this time Pressure regulator is down to zero, test ending;
11)When progress step 6)Afterwards, three electromagnetic potential transformers that can be adjacent to next group are according to step 2)To step 10) Method carry out coding check, until checking the electromagnetic potential transformer there are failure.
Further, the AC voltage regulator is preferably 220V AC voltage regulators.
Further, the inspection voltage of the AC voltage regulator is no more than 60V.
Further, the A.C. voltmeter is preferably 750V A.C. voltmeters.
Induction voltage transformer in the present invention, operation principle is identical with transformer, and basic structure is also iron The heart and primary side, secondary side winding.Feature is capacity very little and more constant, close to light condition during normal operation.Voltage The impedance very little of mutual inductor in itself, once short circuit occurs for secondary side, coil is burnt in sharp increase by electric current.For this purpose, voltage Side of mutual inductor is connected to fuse, while secondary side reliable ground, in order to avoid primary side, the insulation damage of secondary side When, there is high potential over the ground and causes the person and equipment breakdown in secondary side.
The method of the present invention is particularly well suited to electromagnetic potential transformer and makees single-phase use or more single-phase electricity magnetic-type voltages Mutual inductor combination makees three-phase use in V-V shapes, due to the sensitivity of current transformer substation Power System Shortcuts trip system, Dang Yitai Electromagnetic potential transformer breaks down that turn-to-turn short circuit occurs, and when leading to monitoring voltage exception, system will alarm rapidly And electricity is jumped, so, while the probability that two or more single-phase electricity electromagnetic type voltage transformer failures occur is smaller, thus it is of the invention The premise of application is equal fault-free or to have and only one is broken down in electromagnetic potential transformer, can meet most feelings Breakdown judge under condition, and be to be considered as three mutual induction of voltage using three adjacent electromagnetic potential transformers as one group Device is in application, mostly three single-phase potential transformer connections use.
It can be using as common detection device, by simply detecting step the beneficial effects of the present invention are the present invention Suddenly, quick, accurate judgement electromagnetic potential transformer is with the presence or absence of turn-to-turn short circuit, i.e., two electromagnetic potential transformers two in office Secondary pressurization, then the method by shunt voltage table judge that electromagnetic potential transformer is bad with the presence or absence of turn-to-turn insulation.This letter The disclosure of list and practical approach is conducive to improve working efficiency, achievees the purpose that accurate judgement failure electromagnetic potential transformer, It is especially suitable for complicated severe work condition environment, is particularly easy to realize and practical.
Description of the drawings
Below in conjunction with attached drawing, the technical solution in the embodiment of the present invention is described:
Fig. 1 is the detection wiring diagram of detection device of the present invention.
Fig. 2 is the judgement schematic diagram in the embodiment of the present invention one.
Specific embodiment
Embodiment one
As shown in Figure 1 and Figure 2, judge by actual condition common sense, with equal nothing in adjacent three electromagnetic potential transformers to be checked Failure or have and only one break down for, three voltage transformers are respectively defined as A groups, B groups, C groups, choose 220V AC voltage regulator and 750V A.C. voltmeters judge the detection of electromagnetic potential transformer turn-to-turn insulation short circuit according to Fig. 1 assemblings Device, it is specific to judge that once several situations judge for operation point:
Judge 1:The secondary side of A groups with B groups is corresponded into winding parallel connection respectively, by alternating current ammeter and is connected to A groups, the high pressure of B groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of A groups, B group secondary sides, observe the voltage of alternating current ammeter Value;When the indicating value of alternating current ammeter increase by a relatively large margin does not occur, and always with the slow pressurization of AC voltage regulator When keeping smaller indicating value, it was demonstrated that A groups, B groups are all trouble-free electromagnetic potential transformers;By alternating current ammeter and be connected to B groups, Between the high-voltage winding of C groups, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of B groups, C group secondary sides, observe alternating current The voltage value of table;When there is not increase by a relatively large margin with the slow pressurization of AC voltage regulator in the indicating value of alternating current ammeter, And when being always maintained at smaller indicating value, it was demonstrated that A groups, B groups, C groups are all trouble-free electromagnetic potential transformers, test ending;
Judge 2:It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and it is secondary to A groups, B groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter;The indicating value of alternating current ammeter is slow with AC voltage regulator There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that has the electromagnetic potential mutual between A groups, B groups Sensor is bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time,;By alternating current ammeter and it is connected to B groups, the high pressure of C groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of B groups, C group secondary sides, observe the voltage of alternating current ammeter Value;When there is increase by a relatively large margin with the slow pressurization of AC voltage regulator in the indicating value of alternating current ammeter, and finally keep compared with During big indicating value, it was demonstrated that B group electromagnetic potential transformers are bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time, examine Terminate, judge that simple diagram is as shown in Figure 2;
Judge 3:It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and it is secondary to A groups, B groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter;The indicating value of alternating current ammeter is slow with AC voltage regulator There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that has the electromagnetic potential mutual between A groups, B groups Sensor is bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time,;By alternating current ammeter and it is connected to B groups, the high pressure of C groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of B groups, C group secondary sides, observe the voltage of alternating current ammeter Value;The indicating value of alternating current ammeter does not occur increase by a relatively large margin with the slow pressurization of AC voltage regulator, and protects always When holding smaller indicating value, it was demonstrated that A group electromagnetic potential transformers are bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time, Test ending;
Judge 4:The secondary side of A groups with B groups is corresponded into winding parallel connection respectively, by alternating current ammeter and is connected to A groups, the high pressure of B groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of A groups, B group secondary sides, observe the voltage of alternating current ammeter Value;When the indicating value of alternating current ammeter increase by a relatively large margin does not occur, and always with the slow pressurization of AC voltage regulator When keeping smaller indicating value, it was demonstrated that A groups, B groups are all trouble-free electromagnetic potential transformers, C group failures;It at this time can be in order to test This judgement is demonstrate,proved, by alternating current ammeter and is connected between B groups, the high-voltage winding of C groups, and it is secondary to B groups, C groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter, indicating value the delaying with AC voltage regulator of alternating current ammeter There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that there are turn-to-turns for C groups electromagnetic potential transformer Pressure regulator is down to zero, test ending by defective insulation in time at this time;
After all judgements, if there is the situation for judging 1, three electromagnetic potential transformers that can be adjacent to next group According to the step 2 in specification)To step 10)Method carry out coding check, until check there are failure electromagnetic type electricity Press mutual inductor.
Embodiment two
Judge by actual condition common sense, with fault-free equal in adjacent three electromagnetic potential transformers to be checked or have and only For one is broken down, three voltage transformers are respectively defined as A groups, B groups, C groups, choose 220V AC voltage regulators and 750V A.C. voltmeters what is different from the first embodiment is that in the Wiring detection method of embodiment one, judge 2,3,4 situation It is as follows:
Judge 2:It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and it is secondary to A groups, B groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter;The indicating value of alternating current ammeter is slow with AC voltage regulator There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that has the electromagnetic potential mutual between A groups, B groups Sensor is bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time,;By alternating current ammeter and it is connected to A groups, the high pressure of C groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of A groups, C group secondary sides, observe the voltage of alternating current ammeter Value;When there is increase by a relatively large margin with the slow pressurization of AC voltage regulator in the indicating value of alternating current ammeter, and finally keep compared with During big indicating value, it was demonstrated that A group electromagnetic potential transformers are bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time, examine Terminate;
Judge 3:It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and it is secondary to A groups, B groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter;The indicating value of alternating current ammeter is slow with AC voltage regulator There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that has the electromagnetic potential mutual between A groups, B groups Sensor is bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time,;By alternating current ammeter and it is connected to A groups, the high pressure of C groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of A groups, C group secondary sides, observe the voltage of alternating current ammeter Value;The indicating value of alternating current ammeter does not occur increase by a relatively large margin with the slow pressurization of AC voltage regulator, and protects always When holding smaller indicating value, it was demonstrated that B group electromagnetic potential transformers are bad there are turn-to-turn insulation, and pressure regulator is down to zero in time at this time, Test ending;
Judge 4:The secondary side of A groups with B groups is corresponded into winding parallel connection respectively, by alternating current ammeter and is connected to A groups, the high pressure of B groups Between winding, and pass through AC voltage regulator and slowly pressurize to the parallel connected end of A groups, B group secondary sides, observe the voltage of alternating current ammeter Value;When the indicating value of alternating current ammeter increase by a relatively large margin does not occur, and always with the slow pressurization of AC voltage regulator When keeping smaller indicating value, it was demonstrated that A groups, B groups are all trouble-free electromagnetic potential transformers, C group failures;It at this time can be in order to test This judgement is demonstrate,proved, by alternating current ammeter and is connected between A groups, the high-voltage winding of C groups, and it is secondary to A groups, C groups to pass through AC voltage regulator The parallel connected end of side is slowly pressurizeed, and observes the voltage value of alternating current ammeter, indicating value the delaying with AC voltage regulator of alternating current ammeter There is increase by a relatively large margin in slow pressurization, and when finally keeping larger indicating value, it was demonstrated that there are turn-to-turns for C groups electromagnetic potential transformer Pressure regulator is down to zero, test ending by defective insulation in time at this time.
Embodiment three
Above-described embodiment mainly consider with fault-free equal in adjacent three electromagnetic potential transformers or have and only one generation For failure, this can meet most of fault condition and judge, when the two or more electromagnetic potential transformers events of appearance During barrier, it can be judged according to following principle, i.e., according to one method of embodiment, first in adjacent two electromagnetic potential transformers Pressurize and measure, when voltmeter instruction it is larger when, illustrate it is bad with the presence of an electromagnetic potential transformer turn-to-turn insulation, and When pressure regulator is down to zero.The electromagnetic type that the uninflated electromagnetic potential transformer of another has been added into overvoltage with any one again Voltage transformer repeats above-mentioned experiment.There is all big person of numerical value twice when measuring voltage, illustrate the voltage all to pressurize twice Mutual inductor is problematic.Only there is primary big person when measuring voltage, the electromagnetic potential transformer for illustrating all to pressurize twice is Alright, it only pressurizes primary and occurs measuring the electromagnetic potential transformer that the big person of voltage is damage.
The foregoing is merely presently preferred embodiments of the present invention, is not intended to limit the invention, the general technology people of this field Member using the solution of the present invention it will be recognized that can also realize many optional embodiments.It is all in the spirit and principles in the present invention Within all any modification, equivalent and improvement made etc., should all be included in the protection scope of the present invention.

Claims (4)

  1. A kind of 1. method for judging electromagnetic potential transformer turn-to-turn insulation short circuit, which is characterized in that include the following steps:
    1)The detection device for judging the short circuit of electromagnetic potential transformer turn-to-turn insulation is chosen, including AC voltage regulator one, exchange Voltmeter one;
    2)By fault-free equal in adjacent three electromagnetic potential transformers to be checked or have and for only one is broken down, it will Three voltage transformers are respectively defined as A groups, B groups, C groups, and the secondary side of A groups with B groups is corresponded to winding parallel connection respectively;
    3)It by alternating current ammeter and is connected between A groups, the high-voltage winding of B groups, and passes through AC voltage regulator to A groups, B group secondary sides Parallel connected end is slowly pressurizeed, and observes the voltage value of alternating current ammeter;
    4)When the indicating value of alternating current ammeter increase by a relatively large margin, and one does not occur with the slow pressurization of AC voltage regulator When directly keeping smaller indicating value, it was demonstrated that A groups, B groups are all trouble-free electromagnetic potential transformers;
    5)It by alternating current ammeter and is connected between B groups, the high-voltage winding of C groups, and passes through AC voltage regulator to B groups, C group secondary sides Parallel connected end is slowly pressurizeed, and observes the voltage value of alternating current ammeter;
    6)When the indicating value of alternating current ammeter increase by a relatively large margin, and one does not occur with the slow pressurization of AC voltage regulator When directly keeping smaller indicating value, it was demonstrated that A groups, B groups, C groups are all trouble-free electromagnetic potential transformers, test ending;
    7)When progress step 3)Afterwards, the indicating value of alternating current ammeter is with the slow increasing of appearance by a relatively large margin of pressurizeing of AC voltage regulator Greatly, when and finally keeping larger indicating value, it was demonstrated that it is bad with the presence of an electromagnetic potential transformer turn-to-turn insulation between A groups, B groups, Pressure regulator is down to zero in time at this time, repeats step 5);
    8)When the indicating value of alternating current ammeter is with the slow increase of appearance by a relatively large margin of pressurizeing of AC voltage regulator, and finally keeps During larger indicating value, it was demonstrated that B group electromagnetic potential transformers are bad there are turn-to-turn insulation, pressure regulator are down to zero in time at this time, inspection Test end;
    9)When progress step 7)Afterwards, the indicating value of alternating current ammeter does not occur by a relatively large margin with the slow pressurization of AC voltage regulator Increase, and when being always maintained at smaller indicating value, it was demonstrated that A group electromagnetic potential transformers are bad there are turn-to-turn insulation, at this time and When pressure regulator is down to zero, test ending;
    10)When progress step 5)Afterwards, the indicating value of alternating current ammeter occurs by a relatively large margin with the slow pressurization of AC voltage regulator When increasing, and finally keeping larger indicating value, it was demonstrated that C group electromagnetic potential transformers are bad there are turn-to-turn insulation, in time will at this time Pressure regulator is down to zero, test ending;
    11)When progress step 6)Afterwards, three electromagnetic potential transformers that can be adjacent to next group are according to step 2)To step 10) Method carry out coding check, until checking the electromagnetic potential transformer there are failure.
  2. 2. the method as described in claim 1 for judging the short circuit of electromagnetic potential transformer turn-to-turn insulation, it is characterised in that:It is described AC voltage regulator is preferably 220V AC voltage regulators.
  3. 3. the method as described in claim 1 for judging the short circuit of electromagnetic potential transformer turn-to-turn insulation, it is characterised in that:It is described The inspection voltage of AC voltage regulator is no more than 60V.
  4. 4. the method as described in claim 1 for judging the short circuit of electromagnetic potential transformer turn-to-turn insulation, it is characterised in that:It is described A.C. voltmeter is preferably 750V A.C. voltmeters.
CN201711437197.5A 2017-12-26 2017-12-26 Method for judging turn-to-turn insulation short circuit of electromagnetic voltage transformer Active CN108152659B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711437197.5A CN108152659B (en) 2017-12-26 2017-12-26 Method for judging turn-to-turn insulation short circuit of electromagnetic voltage transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711437197.5A CN108152659B (en) 2017-12-26 2017-12-26 Method for judging turn-to-turn insulation short circuit of electromagnetic voltage transformer

Publications (2)

Publication Number Publication Date
CN108152659A true CN108152659A (en) 2018-06-12
CN108152659B CN108152659B (en) 2020-02-04

Family

ID=62463169

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711437197.5A Active CN108152659B (en) 2017-12-26 2017-12-26 Method for judging turn-to-turn insulation short circuit of electromagnetic voltage transformer

Country Status (1)

Country Link
CN (1) CN108152659B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112968423A (en) * 2021-02-06 2021-06-15 山东理工大学 Overcurrent protection method for protecting turn-to-turn short circuit fault of low-voltage winding of grounding transformer

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102778615A (en) * 2011-05-11 2012-11-14 大连互感器有限公司 Error experiment device of zero sequence voltage mutual inductors
CN103257334A (en) * 2013-05-15 2013-08-21 河南省电力公司平顶山供电公司 6-35KV electro-magnetic voltage transformer quick diagnosing instrument and using method
CN106771514A (en) * 2016-11-25 2017-05-31 国网河南省电力公司平顶山供电公司 A kind of device and method of quick lookup voltage transformer failure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102778615A (en) * 2011-05-11 2012-11-14 大连互感器有限公司 Error experiment device of zero sequence voltage mutual inductors
CN103257334A (en) * 2013-05-15 2013-08-21 河南省电力公司平顶山供电公司 6-35KV electro-magnetic voltage transformer quick diagnosing instrument and using method
CN106771514A (en) * 2016-11-25 2017-05-31 国网河南省电力公司平顶山供电公司 A kind of device and method of quick lookup voltage transformer failure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112968423A (en) * 2021-02-06 2021-06-15 山东理工大学 Overcurrent protection method for protecting turn-to-turn short circuit fault of low-voltage winding of grounding transformer
CN112968423B (en) * 2021-02-06 2022-06-17 山东理工大学 Overcurrent protection method for protecting turn-to-turn short circuit fault of low-voltage winding of grounding transformer

Also Published As

Publication number Publication date
CN108152659B (en) 2020-02-04

Similar Documents

Publication Publication Date Title
CN100570384C (en) Method for testing electric secondary AC loop
RU2542494C2 (en) Device and method for detection of ground short-circuit
CN104569724A (en) Transformer short-circuit fault comprehensive diagnosis method
CN103454544B (en) A kind of detection method based on the linear magnetism elimination circuit of electronic jumper
CN102023249A (en) Method for performing preventive test without detaching high-voltage lead of 220-kV zinc oxide arrestor
CN102608485B (en) Detection method for zero-sequence current loops of transformer substations
CN102540001A (en) Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN102565618A (en) Method for detecting zero-sequence voltage circuit of transformer substation
CN108107325A (en) A kind of method of quick lookup threephase potential transformer failure
CN102944762B (en) Debugging method of phase sequences of loops at two sides of synchronization point before commissioning of generator set
CN102901894A (en) Test method and device for testing 500kV zinc oxide arrester
Leal et al. Comparison of online techniques for the detection of inter-turn short-circuits in transformers
CN104535886A (en) Transformer iron core multipoint grounding diagnosis and processing method
Behjat et al. An experimental approach for investigating low-level interturn winding faults in power transformers
CN104065034A (en) Low-voltage failure detector
CN108152659A (en) A kind of method for judging electromagnetic potential transformer turn-to-turn insulation short circuit
CN206096309U (en) Ferroresonance detects and prevention and cure combined test platform
CN102221652A (en) Method and device for testing 500kV metal oxide arrester
CN103235234A (en) Grounding detecting method adopting arc suppression system
CN110146829A (en) A kind of direct-current switch power supply fault diagnosis easily-testing instrument and test method
CN203630312U (en) Direct current motor armature fault detection device
CN106771514B (en) A kind of device and method of quick lookup voltage transformer failure
CN2722265Y (en) DC grounding on-line tester
CN104183379A (en) Connecting device for maintenance of secondary side of electric power current transformer
CN102226773B (en) Test bench for X-ray detection apparatuses

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant