CN108118727A - 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺 - Google Patents

地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺 Download PDF

Info

Publication number
CN108118727A
CN108118727A CN201711403064.6A CN201711403064A CN108118727A CN 108118727 A CN108118727 A CN 108118727A CN 201711403064 A CN201711403064 A CN 201711403064A CN 108118727 A CN108118727 A CN 108118727A
Authority
CN
China
Prior art keywords
wall
leads
hole
pressure
led
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711403064.6A
Other languages
English (en)
Inventor
谭纯
荀为卓
宋玮卿
蔡炜
赵永强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN201711403064.6A priority Critical patent/CN108118727A/zh
Publication of CN108118727A publication Critical patent/CN108118727A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/46Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil

Abstract

本发明涉及到一种地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺,其步骤是:在导墙翼板上引孔,在孔内打设一定深度的高压旋喷桩,高压旋喷注浆,利用高压旋喷桩改善槽壁的土体以达到槽壁加固的目的。本发明可以有效的解决在导墙完成后需要改善地墙上层土体的强度问题;其次,高压旋喷工艺、设备简单、操作简便,可快速高效的大规模展开施工,能有效的节省时间;再者,只在导墙上隔一定距离引孔可以降低导墙被破坏的可能,使得槽壁后加固成为可能。

Description

地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺
技术领域
本发明涉及一种在地下连续墙导墙完成以后的导墙侧壁肋板外的槽壁后加固施工工艺。
背景技术
随着沿海城市的发展,中心城区建设时间越来越紧张,在地下连续墙导墙实施后实际施工时如发现表层土体容易塌方将会影响地下连续墙的施工质量,此时再要进行槽壁加固就需要破除导墙,这样工期将大大延长,此时进行导墙侧壁肋板外的槽壁后加固施工工艺,可以以较小的代价解决了导墙实施后槽壁加固的无法实施的难题,是一个更高效的解决方案。
发明内容
本发明是要解决在导墙实施后重新进行槽壁加固的问题,提供一种在地下连续墙导墙完成以后的导墙侧壁肋板外的槽壁后加固施工工艺。
为实现上述目的,本发明是通过以下技术方案实现的:
一种地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺,其步骤是:
1)导墙翼板上引孔
按照表层土体性能,设计旋喷桩和布孔位置,旋喷桩桩径为800mm-1200mm,旋喷桩深度为地表下1.5m-20m范围内,布孔的间距为600mm-1000mm;根据旋喷桩桩径和布孔的间距在导墙翼板上引孔,引孔位置在导墙侧壁外避开导墙肋板的位置,引孔距离导墙肋板外10cm-20cm;
2)高压旋喷注浆
在引孔内打设高压旋喷管,采用常规的二重管高压旋喷桩工艺进行二重管高压旋喷,在导墙下方地墙的槽壁两侧形成一道由高压旋喷桩喷射的桩体固结区域,达到槽壁加固的目的;
3)养护
二重管高压旋喷实施完毕后,养护10-14天即可开始后续的地墙成槽工艺。
步骤2)中,如需要在较短周期内实施后续地墙的成槽,则在旋喷桩浆液内掺掺5%-10%水玻璃,以增快水泥凝结速度,达到较短周期内实施地下连续墙的施工。
本发明的有益效果是:本发明可以有效的解决在导墙完成后需要改善地墙上层土体的强度问题;其次,高压旋喷工艺、设备简单、操作简便,可快速高效的大规模展开施工,能有效的节省时间;再者,只在导墙上隔一定距离引孔可以降低导墙被破坏的可能,使得槽壁后加固成为可能。
附图说明
图1是导墙侧壁肋板外的槽壁后加固施工平面示意图;
图2是导墙侧壁肋板外的槽壁后加固施工剖面示意图。
具体实施方式
下面结合附图与实施例对本发明作进一步说明。
如图1至图2所示,本发明的地下连续墙导墙施工后导墙侧壁外的槽壁后加固施工工艺,其施工步骤是:
1)导墙翼板上引孔
按照表层土体性能,设计好旋喷桩2的桩径D并按搭接10-20cm布孔,由此定位后在导墙翼板上引孔1。引孔1距离导墙肋3外10cm-20cm,一般旋喷桩2的桩径D设计为800mm-1200mm,考虑搭接20cm布孔即间距S为600mm-1000mm布孔,旋喷桩2深一般为需要进行土体补强的土体,一般是地表下1.5m-20m范围,视需要加固的土层深度而定。
2)高压旋喷注浆
在引孔内打设高压旋喷管4,高压旋喷桩采用二重管(引孔1和高压旋喷管4)高压旋喷,按照常规二重管高压旋喷桩工艺实施。在导墙下方地墙的槽壁两侧形成一道由高压旋喷桩喷射的桩体固结区域,由于固结区域的土体强度较原状土性能更优而达到槽壁加固的目的。
如实际需要在较短周期内实施后续地墙的成槽,则在旋喷桩浆液内掺少量水玻璃(一般掺5%-10%),以增快水泥凝结速度,达到较短周期内实施地下连续墙的施工。
3)养护
二重管高压旋喷实施完毕后,养护10-14天即可开始后续的地墙成槽工艺。
本发明的地下连续墙导墙完成以后的导墙侧壁肋板外的槽壁后加固施工工艺,包括由引孔及高压旋喷桩体形成的加固体帷幕,改善原状土的力学性能,使得在地墙成槽阶段土体不容易塌方,只在导墙肋板外侧引孔,不会大规模破坏已经施工完成的导墙,避免因重新进行槽壁加固而破除已完成的导墙;使用二重管施工工艺形成加固体帷幕,达到在短时间内快速形成加固土体强度,而且加固土体比较均匀;在高压旋喷桩体内掺入少量水玻璃5%-10%以在段时间内快速凝结,以便快速进行后续的成槽施工。

Claims (2)

1.一种地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺,其特征在于,其步骤是:
1)导墙翼板上引孔
按照表层土体性能,设计旋喷桩和布孔位置,旋喷桩桩径为800mm-1200mm,旋喷桩深度为地表下1.5m-20m范围内,布孔的间距为600mm-1000mm;根据旋喷桩桩径和布孔的间距在导墙翼板上引孔,引孔位置在导墙侧壁外避开导墙肋板的位置,引孔距离导墙肋板外10cm-20cm;
2)高压旋喷注浆
在引孔内打设高压旋喷管,采用常规的二重管高压旋喷桩工艺进行二重管高压旋喷,在导墙下方地墙的槽壁两侧形成一道由高压旋喷桩喷射的桩体固结区域,达到槽壁加固的目的;
3)养护
二重管高压旋喷实施完毕后,养护10-14天即可开始后续的地墙成槽工艺。
2.根据权利要求1所述的地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺,其特征在于:步骤2)中,如需要在较短周期内实施后续地墙的成槽,则在旋喷桩浆液内掺掺5%-10%水玻璃,以增快水泥凝结速度,达到较短周期内实施地下连续墙的施工。
CN201711403064.6A 2017-12-22 2017-12-22 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺 Pending CN108118727A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711403064.6A CN108118727A (zh) 2017-12-22 2017-12-22 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711403064.6A CN108118727A (zh) 2017-12-22 2017-12-22 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺

Publications (1)

Publication Number Publication Date
CN108118727A true CN108118727A (zh) 2018-06-05

Family

ID=62231012

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711403064.6A Pending CN108118727A (zh) 2017-12-22 2017-12-22 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺

Country Status (1)

Country Link
CN (1) CN108118727A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067254A (zh) * 2019-06-06 2019-07-30 上海智平基础工程有限公司 一种超薄带肋止水帷幕的旋喷钻头
CN110820722A (zh) * 2019-11-19 2020-02-21 建基建设集团有限公司 一种用于含缠绕物地层或垃圾场地层防渗墙的施工方法
CN113026768A (zh) * 2021-03-26 2021-06-25 中国建筑一局(集团)有限公司 一种临海推填区超深地下连续墙成槽加固结构及其工法
CN113668504A (zh) * 2021-08-20 2021-11-19 中建八局第三建设有限公司 一种中隔地下连续墙成槽应急加固施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429766A (zh) * 2008-11-27 2009-05-13 吴哲慧 一种地基加固的高压旋喷桩施工工艺
CN102561361A (zh) * 2012-03-05 2012-07-11 中交第四航务工程局有限公司 用于上软下硬土层的超深t形槽壁桩及其成槽施工方法
CN202945519U (zh) * 2012-12-05 2013-05-22 浙江华光市政建设有限公司 一种控制运营期路堤沉降的加固结构
CN106121271A (zh) * 2016-07-02 2016-11-16 杭州固特建筑加固技术工程有限公司 一种基于旋喷桩基础上的接桩结构
CN106869198A (zh) * 2017-01-20 2017-06-20 榆林华源电力有限责任公司 一种松散土质下陷空区利用井字梁加固杆塔基础的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101429766A (zh) * 2008-11-27 2009-05-13 吴哲慧 一种地基加固的高压旋喷桩施工工艺
CN102561361A (zh) * 2012-03-05 2012-07-11 中交第四航务工程局有限公司 用于上软下硬土层的超深t形槽壁桩及其成槽施工方法
CN202945519U (zh) * 2012-12-05 2013-05-22 浙江华光市政建设有限公司 一种控制运营期路堤沉降的加固结构
CN106121271A (zh) * 2016-07-02 2016-11-16 杭州固特建筑加固技术工程有限公司 一种基于旋喷桩基础上的接桩结构
CN106869198A (zh) * 2017-01-20 2017-06-20 榆林华源电力有限责任公司 一种松散土质下陷空区利用井字梁加固杆塔基础的方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067254A (zh) * 2019-06-06 2019-07-30 上海智平基础工程有限公司 一种超薄带肋止水帷幕的旋喷钻头
CN110820722A (zh) * 2019-11-19 2020-02-21 建基建设集团有限公司 一种用于含缠绕物地层或垃圾场地层防渗墙的施工方法
CN110820722B (zh) * 2019-11-19 2021-04-09 建基建设集团有限公司 一种用于含缠绕物地层或垃圾场地层防渗墙的施工方法
CN113026768A (zh) * 2021-03-26 2021-06-25 中国建筑一局(集团)有限公司 一种临海推填区超深地下连续墙成槽加固结构及其工法
CN113668504A (zh) * 2021-08-20 2021-11-19 中建八局第三建设有限公司 一种中隔地下连续墙成槽应急加固施工方法

Similar Documents

Publication Publication Date Title
CN108118727A (zh) 地墙导墙实施后导墙侧壁外的槽壁后加固施工工艺
CN204112308U (zh) 一种基于大卵石、高渗透系数地层的简易袖阀注浆装置
CN104278667A (zh) 一种地下溶洞的充填处理方法
CN103912003B (zh) 一种简便快捷封堵地层动水及孔隙的方法
CN104674827A (zh) 一种富水地层基坑新型全封闭止水体系及施工方法
CN103696416B (zh) 一种地基处理方法
CN101832143A (zh) 一种处治隧道渗漏水的方法
CN112609673A (zh) 深层共振密实加固杂填土地基的装置及方法
CN204530730U (zh) 一种富水地层基坑新型全封闭止水体系
CN104594370B (zh) 喀斯特地区高压联合冲洗灌浆方法及其结构
CN103742162B (zh) 盾尾顶部设置有同步注浆装置的盾构机及同步注浆装置
CN107338790A (zh) 旋喷搅拌复合桩施工方法
CN103161151A (zh) 一种高压旋喷中空加固管桩的施工方法及高压旋喷中空加固管桩
CN102409666A (zh) 防空洞走向上桩基础施工工艺
JP6703517B2 (ja) ジオポリマーと土の原位置混合によって地盤内に要素を形成する方法
CN107938652B (zh) 一种嵌岩型钢水泥搅拌墙及其施工方法
CN207862925U (zh) 一种注浆护筒装置
CN108222025A (zh) 地下导墙完成以后的导墙槽口内的槽壁后加固施工方法
CN107700508A (zh) 一种型钢搅喷水泥土帷幕支护桩的施工方法
CN107653889A (zh) 一种型钢压灌水泥土帷幕支护桩的施工方法
CN104005416A (zh) 一种用于高陡边坡素填土反压条件下大直径孔桩塌孔的处理方法
CN112281828A (zh) 一种新型复合桩结构及施工方法
CN102444137B (zh) 一种真空预压泥浆封闭墙的施工方法
CN203769790U (zh) 盾尾顶部设置有同步注浆装置的盾构机及同步注浆装置
CN105672329A (zh) 深基坑大尺寸预制围护结构及施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180605