CN108118715A - Large equipment base pedestal does paste-making method - Google Patents
Large equipment base pedestal does paste-making method Download PDFInfo
- Publication number
- CN108118715A CN108118715A CN201611076554.5A CN201611076554A CN108118715A CN 108118715 A CN108118715 A CN 108118715A CN 201611076554 A CN201611076554 A CN 201611076554A CN 108118715 A CN108118715 A CN 108118715A
- Authority
- CN
- China
- Prior art keywords
- pedestal
- screw rod
- surrounding
- top surface
- iron plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
Abstract
The present invention relates to a kind of large equipment base pedestals to do paste-making method, it includes the following steps:Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar, is rinsed well with clear water;Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if screw rod weld no-reinforcing-bar, in addition connects welding steel muscle and comes;Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than substructure height;Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid error;Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and less than base top surface, it is ensured that pedestal is filled.Simple and convenient of the present invention reduces workload;Substantially increase the precision of equipment installation.
Description
Technical field
The present invention relates to one kind to do paste-making method, and specifically large equipment base pedestal does paste-making method.
Background technology
Before the installation of mini-plant basis, by small mould starch, adjustment every time will take out gasket, then increase
Or reduce and do height and flatness that slurry carrys out adjust pad, again and again, labor intensity is big, inefficient, and precision
It is poor.
The content of the invention
It is contemplated that the defects of overcoming the prior art, provides a kind of large equipment base pedestal and does paste-making method, construction letter
It is single, it is easy to make, it is easy for construction.
In order to solve the above-mentioned technical problem, the present invention is realized in:
A kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar,
It is rinsed well with clear water;
Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if
In addition screw rod weld no-reinforcing-bar connects welding steel muscle and comes;
Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than
Substructure height;
Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid
Error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than
Seat top surface, it is ensured that pedestal is filled.
The beneficial effects of the invention are as follows:The pedestal that equipment is carried out using grouting way is starched, simple and convenient, reduces work
Amount;The absolute altitude of control device pedestal and flatness are adjusted using plant bottom case additional bolts simultaneously, substantially increases equipment peace
The precision of dress.
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structure diagram of dabbing.
Fig. 2 is the structure diagram of welding pedestal.
Fig. 3 is the structure diagram of installation form.
Specific embodiment
A kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
As shown in Figure 1:Step 1:Pre-embedded bolt 2 in Equipment Foundations 1, carries out dabbing in the Equipment Foundations among pre-embedded bolt
3, after exposing reinforcing bar 4, rinsed well with clear water;
As shown in Figure 2:Step 2:The pedestal 7 that screw rod 6 is installed in one surrounding welding iron plate 5 and iron plate is welded on reinforcing bar 4,
Screw rod keeps vertical, if screw rod weld no-reinforcing-bar, in addition connects welding steel muscle and comes;
As shown in Figure 3:Step 3:In pedestal surrounding installation form 8, template surrounds pedestal surrounding and reserves position and is in the milk,
Form height is higher than substructure height;
Step 4:By instrument regulation nut the flatness of pedestal and absolute altitude is made to reach installation requirement, the pedestal after adjustment cannot
Touching, in order to avoid error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than
Seat top surface, it is ensured that pedestal is filled.
Claims (1)
1. a kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar,
It is rinsed well with clear water;
Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if
In addition screw rod weld no-reinforcing-bar connects welding steel muscle and comes;
Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than
Substructure height;
Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid
Error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than
Seat top surface, it is ensured that pedestal is filled.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611076554.5A CN108118715A (en) | 2016-11-30 | 2016-11-30 | Large equipment base pedestal does paste-making method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611076554.5A CN108118715A (en) | 2016-11-30 | 2016-11-30 | Large equipment base pedestal does paste-making method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108118715A true CN108118715A (en) | 2018-06-05 |
Family
ID=62225998
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611076554.5A Pending CN108118715A (en) | 2016-11-30 | 2016-11-30 | Large equipment base pedestal does paste-making method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108118715A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109371824A (en) * | 2018-12-19 | 2019-02-22 | 苏州规划设计研究院股份有限公司 | Bridge pier and its construction method with high-intensitive bearing pad stone |
CN109914465A (en) * | 2019-03-25 | 2019-06-21 | 五冶集团上海有限公司 | A kind of raw material mill bolt embedment box installation method |
CN111395386A (en) * | 2020-04-22 | 2020-07-10 | 五冶集团上海有限公司 | Installation and construction method of grinding roller base of raw material mill |
CN111716519A (en) * | 2019-03-18 | 2020-09-29 | 新疆八一钢铁股份有限公司 | Method for mounting and manufacturing embedded steam turbine supporting bottom plate |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03272393A (en) * | 1990-03-19 | 1991-12-04 | Onoda:Kk | Installation method for base plate for installing machine |
CN101644373A (en) * | 2008-08-06 | 2010-02-10 | 鞍钢电气有限责任公司 | Method for mounting bedding liner plate of motor foundation plate |
CN101871265A (en) * | 2010-07-02 | 2010-10-27 | 中国十七冶集团有限公司 | Flat shim plate-adjustable grouting installation method |
CN102286988A (en) * | 2011-06-29 | 2011-12-21 | 天津二十冶建设有限公司 | Grouting shim plate construction method |
CN103590416A (en) * | 2013-11-01 | 2014-02-19 | 浙江水利水电学院 | Pre-buried construction method for high-precision foundation bolts |
-
2016
- 2016-11-30 CN CN201611076554.5A patent/CN108118715A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03272393A (en) * | 1990-03-19 | 1991-12-04 | Onoda:Kk | Installation method for base plate for installing machine |
CN101644373A (en) * | 2008-08-06 | 2010-02-10 | 鞍钢电气有限责任公司 | Method for mounting bedding liner plate of motor foundation plate |
CN101871265A (en) * | 2010-07-02 | 2010-10-27 | 中国十七冶集团有限公司 | Flat shim plate-adjustable grouting installation method |
CN102286988A (en) * | 2011-06-29 | 2011-12-21 | 天津二十冶建设有限公司 | Grouting shim plate construction method |
CN103590416A (en) * | 2013-11-01 | 2014-02-19 | 浙江水利水电学院 | Pre-buried construction method for high-precision foundation bolts |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109371824A (en) * | 2018-12-19 | 2019-02-22 | 苏州规划设计研究院股份有限公司 | Bridge pier and its construction method with high-intensitive bearing pad stone |
CN111716519A (en) * | 2019-03-18 | 2020-09-29 | 新疆八一钢铁股份有限公司 | Method for mounting and manufacturing embedded steam turbine supporting bottom plate |
CN109914465A (en) * | 2019-03-25 | 2019-06-21 | 五冶集团上海有限公司 | A kind of raw material mill bolt embedment box installation method |
CN111395386A (en) * | 2020-04-22 | 2020-07-10 | 五冶集团上海有限公司 | Installation and construction method of grinding roller base of raw material mill |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108118715A (en) | Large equipment base pedestal does paste-making method | |
CN101871265B (en) | Flat shim plate-adjustable grouting installation method | |
CN204040056U (en) | A kind of location and installation support of pre-embedded anchoring bolts | |
CN201896365U (en) | Installing and fixing device for flat plate pre-embedded piece on surface of concrete | |
CN203320700U (en) | Steel structure column foot connecting structure | |
CN104234385A (en) | Mounting and construction method for terrace large-size steel plate embedded part | |
CN104032969A (en) | Precise positioning and process regulation and control device for vibration isolation support embedded plate | |
CN205776306U (en) | A kind of steel column foot bolt positioning device and steel column foot structure | |
CN204252284U (en) | Built-in fitting bracing means | |
CN103352476A (en) | Large-scale bolt high-precision pre-burying construction method | |
CN103572774A (en) | Leveling ruler flat underboarding mortar bedding method | |
CN203347249U (en) | Perpendicularity adjusting device applied to steel column mounting | |
CN203334192U (en) | Steel truss girder jointing rod piece height difference adjusting device | |
CN206408969U (en) | A kind of support meanss for being used to adjust bent cap vertical and horizontal gradient | |
CN211114901U (en) | Bracket device convenient to precast beam is under construction fast | |
CN202390753U (en) | Fixing structure of bridge table and post cap embedded part | |
CN103669566B (en) | The construction method of the steel reinforced concrete pedestal on large span grid roof | |
CN203639934U (en) | Pre-buried positioning device for equipment foundation bolt | |
CN201605595U (en) | Equipment anchor bolt installation device | |
CN213951992U (en) | Auxiliary temporary supporting device for old bridge replacement support construction | |
CN205476528U (en) | Precast pile device of taking one's place fast | |
CN203307838U (en) | Large-sized melting furnace equipment foundation with embedded parts capable of being adjusted at high precision | |
CN107059913A (en) | A kind of reactor built-in fitting supporting construction and method for embedding | |
CN206873639U (en) | Bay window wall adjusts absolute altitude structure | |
CN203160707U (en) | Adjustable t-shaped controller |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20180605 |