CN108118715A - Large equipment base pedestal does paste-making method - Google Patents

Large equipment base pedestal does paste-making method Download PDF

Info

Publication number
CN108118715A
CN108118715A CN201611076554.5A CN201611076554A CN108118715A CN 108118715 A CN108118715 A CN 108118715A CN 201611076554 A CN201611076554 A CN 201611076554A CN 108118715 A CN108118715 A CN 108118715A
Authority
CN
China
Prior art keywords
pedestal
screw rod
surrounding
top surface
iron plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611076554.5A
Other languages
Chinese (zh)
Inventor
林耀忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201611076554.5A priority Critical patent/CN108118715A/en
Publication of CN108118715A publication Critical patent/CN108118715A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes

Abstract

The present invention relates to a kind of large equipment base pedestals to do paste-making method, it includes the following steps:Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar, is rinsed well with clear water;Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if screw rod weld no-reinforcing-bar, in addition connects welding steel muscle and comes;Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than substructure height;Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid error;Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and less than base top surface, it is ensured that pedestal is filled.Simple and convenient of the present invention reduces workload;Substantially increase the precision of equipment installation.

Description

Large equipment base pedestal does paste-making method
Technical field
The present invention relates to one kind to do paste-making method, and specifically large equipment base pedestal does paste-making method.
Background technology
Before the installation of mini-plant basis, by small mould starch, adjustment every time will take out gasket, then increase Or reduce and do height and flatness that slurry carrys out adjust pad, again and again, labor intensity is big, inefficient, and precision It is poor.
The content of the invention
It is contemplated that the defects of overcoming the prior art, provides a kind of large equipment base pedestal and does paste-making method, construction letter It is single, it is easy to make, it is easy for construction.
In order to solve the above-mentioned technical problem, the present invention is realized in:
A kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar, It is rinsed well with clear water;
Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if In addition screw rod weld no-reinforcing-bar connects welding steel muscle and comes;
Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than Substructure height;
Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid Error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than Seat top surface, it is ensured that pedestal is filled.
The beneficial effects of the invention are as follows:The pedestal that equipment is carried out using grouting way is starched, simple and convenient, reduces work Amount;The absolute altitude of control device pedestal and flatness are adjusted using plant bottom case additional bolts simultaneously, substantially increases equipment peace The precision of dress.
Description of the drawings
The present invention is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the structure diagram of dabbing.
Fig. 2 is the structure diagram of welding pedestal.
Fig. 3 is the structure diagram of installation form.
Specific embodiment
A kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
As shown in Figure 1:Step 1:Pre-embedded bolt 2 in Equipment Foundations 1, carries out dabbing in the Equipment Foundations among pre-embedded bolt 3, after exposing reinforcing bar 4, rinsed well with clear water;
As shown in Figure 2:Step 2:The pedestal 7 that screw rod 6 is installed in one surrounding welding iron plate 5 and iron plate is welded on reinforcing bar 4, Screw rod keeps vertical, if screw rod weld no-reinforcing-bar, in addition connects welding steel muscle and comes;
As shown in Figure 3:Step 3:In pedestal surrounding installation form 8, template surrounds pedestal surrounding and reserves position and is in the milk, Form height is higher than substructure height;
Step 4:By instrument regulation nut the flatness of pedestal and absolute altitude is made to reach installation requirement, the pedestal after adjustment cannot Touching, in order to avoid error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than Seat top surface, it is ensured that pedestal is filled.

Claims (1)

1. a kind of large equipment base pedestal does paste-making method, it is characterised in that it includes the following steps:
Step 1:Pre-embedded bolt in Equipment Foundations carries out dabbing in the Equipment Foundations among pre-embedded bolt, after exposing reinforcing bar, It is rinsed well with clear water;
Step 2:The pedestal that screw rod is installed in one surrounding welding iron plate and iron plate is welded on reinforcing bar, screw rod keeps vertical, if In addition screw rod weld no-reinforcing-bar connects welding steel muscle and comes;
Step 3:In pedestal surrounding installation form, template surrounds pedestal surrounding and reserves position and is in the milk, and form height is higher than Substructure height;
Step 4:Adjusting nut makes the flatness of pedestal and absolute altitude reaches installation requirement, and the pedestal after adjustment cannot be touched, in order to avoid Error;
Step 5:Grouting material is poured, operating room is forbidden to touch pedestal, and the top surface absolute altitude of grouting material is higher than base end face and the bottom of less than Seat top surface, it is ensured that pedestal is filled.
CN201611076554.5A 2016-11-30 2016-11-30 Large equipment base pedestal does paste-making method Pending CN108118715A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611076554.5A CN108118715A (en) 2016-11-30 2016-11-30 Large equipment base pedestal does paste-making method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611076554.5A CN108118715A (en) 2016-11-30 2016-11-30 Large equipment base pedestal does paste-making method

Publications (1)

Publication Number Publication Date
CN108118715A true CN108118715A (en) 2018-06-05

Family

ID=62225998

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611076554.5A Pending CN108118715A (en) 2016-11-30 2016-11-30 Large equipment base pedestal does paste-making method

Country Status (1)

Country Link
CN (1) CN108118715A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371824A (en) * 2018-12-19 2019-02-22 苏州规划设计研究院股份有限公司 Bridge pier and its construction method with high-intensitive bearing pad stone
CN109914465A (en) * 2019-03-25 2019-06-21 五冶集团上海有限公司 A kind of raw material mill bolt embedment box installation method
CN111395386A (en) * 2020-04-22 2020-07-10 五冶集团上海有限公司 Installation and construction method of grinding roller base of raw material mill
CN111716519A (en) * 2019-03-18 2020-09-29 新疆八一钢铁股份有限公司 Method for mounting and manufacturing embedded steam turbine supporting bottom plate

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03272393A (en) * 1990-03-19 1991-12-04 Onoda:Kk Installation method for base plate for installing machine
CN101644373A (en) * 2008-08-06 2010-02-10 鞍钢电气有限责任公司 Method for mounting bedding liner plate of motor foundation plate
CN101871265A (en) * 2010-07-02 2010-10-27 中国十七冶集团有限公司 Flat shim plate-adjustable grouting installation method
CN102286988A (en) * 2011-06-29 2011-12-21 天津二十冶建设有限公司 Grouting shim plate construction method
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03272393A (en) * 1990-03-19 1991-12-04 Onoda:Kk Installation method for base plate for installing machine
CN101644373A (en) * 2008-08-06 2010-02-10 鞍钢电气有限责任公司 Method for mounting bedding liner plate of motor foundation plate
CN101871265A (en) * 2010-07-02 2010-10-27 中国十七冶集团有限公司 Flat shim plate-adjustable grouting installation method
CN102286988A (en) * 2011-06-29 2011-12-21 天津二十冶建设有限公司 Grouting shim plate construction method
CN103590416A (en) * 2013-11-01 2014-02-19 浙江水利水电学院 Pre-buried construction method for high-precision foundation bolts

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109371824A (en) * 2018-12-19 2019-02-22 苏州规划设计研究院股份有限公司 Bridge pier and its construction method with high-intensitive bearing pad stone
CN111716519A (en) * 2019-03-18 2020-09-29 新疆八一钢铁股份有限公司 Method for mounting and manufacturing embedded steam turbine supporting bottom plate
CN109914465A (en) * 2019-03-25 2019-06-21 五冶集团上海有限公司 A kind of raw material mill bolt embedment box installation method
CN111395386A (en) * 2020-04-22 2020-07-10 五冶集团上海有限公司 Installation and construction method of grinding roller base of raw material mill

Similar Documents

Publication Publication Date Title
CN108118715A (en) Large equipment base pedestal does paste-making method
CN101871265B (en) Flat shim plate-adjustable grouting installation method
CN204040056U (en) A kind of location and installation support of pre-embedded anchoring bolts
CN201896365U (en) Installing and fixing device for flat plate pre-embedded piece on surface of concrete
CN203320700U (en) Steel structure column foot connecting structure
CN104234385A (en) Mounting and construction method for terrace large-size steel plate embedded part
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN205776306U (en) A kind of steel column foot bolt positioning device and steel column foot structure
CN204252284U (en) Built-in fitting bracing means
CN103352476A (en) Large-scale bolt high-precision pre-burying construction method
CN103572774A (en) Leveling ruler flat underboarding mortar bedding method
CN203347249U (en) Perpendicularity adjusting device applied to steel column mounting
CN203334192U (en) Steel truss girder jointing rod piece height difference adjusting device
CN206408969U (en) A kind of support meanss for being used to adjust bent cap vertical and horizontal gradient
CN211114901U (en) Bracket device convenient to precast beam is under construction fast
CN202390753U (en) Fixing structure of bridge table and post cap embedded part
CN103669566B (en) The construction method of the steel reinforced concrete pedestal on large span grid roof
CN203639934U (en) Pre-buried positioning device for equipment foundation bolt
CN201605595U (en) Equipment anchor bolt installation device
CN213951992U (en) Auxiliary temporary supporting device for old bridge replacement support construction
CN205476528U (en) Precast pile device of taking one's place fast
CN203307838U (en) Large-sized melting furnace equipment foundation with embedded parts capable of being adjusted at high precision
CN107059913A (en) A kind of reactor built-in fitting supporting construction and method for embedding
CN206873639U (en) Bay window wall adjusts absolute altitude structure
CN203160707U (en) Adjustable t-shaped controller

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180605