CN108104839A - The quick repairing construction system of baseboard of coal mine roadway and its construction method - Google Patents
The quick repairing construction system of baseboard of coal mine roadway and its construction method Download PDFInfo
- Publication number
- CN108104839A CN108104839A CN201711335366.4A CN201711335366A CN108104839A CN 108104839 A CN108104839 A CN 108104839A CN 201711335366 A CN201711335366 A CN 201711335366A CN 108104839 A CN108104839 A CN 108104839A
- Authority
- CN
- China
- Prior art keywords
- construction
- equipment
- baseboard
- coal mine
- construction system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 125
- 239000003245 coal Substances 0.000 title claims abstract description 37
- 238000004873 anchoring Methods 0.000 claims abstract description 52
- 238000005553 drilling Methods 0.000 claims abstract description 51
- 230000008439 repair process Effects 0.000 claims abstract description 47
- 239000011440 grout Substances 0.000 claims abstract description 22
- 238000000034 method Methods 0.000 claims abstract description 21
- 238000002156 mixing Methods 0.000 claims abstract description 14
- 238000005457 optimization Methods 0.000 claims abstract description 9
- 238000007569 slipcasting Methods 0.000 claims description 17
- 230000003028 elevating effect Effects 0.000 claims description 15
- 229910000831 Steel Inorganic materials 0.000 claims description 10
- 239000010959 steel Substances 0.000 claims description 10
- 239000002002 slurry Substances 0.000 claims description 9
- 238000013519 translation Methods 0.000 claims description 9
- 238000000605 extraction Methods 0.000 claims description 7
- 239000011435 rock Substances 0.000 claims description 7
- 239000004033 plastic Substances 0.000 claims description 6
- 238000007789 sealing Methods 0.000 claims description 6
- 239000002828 fuel tank Substances 0.000 claims description 4
- 229920000742 Cotton Polymers 0.000 claims description 3
- 239000003795 chemical substances by application Substances 0.000 claims description 3
- 239000010985 leather Substances 0.000 claims description 3
- 230000002787 reinforcement Effects 0.000 claims description 3
- 238000003756 stirring Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 2
- 229940074869 marquis Drugs 0.000 claims description 2
- VBUNOIXRZNJNAD-UHFFFAOYSA-N ponazuril Chemical compound CC1=CC(N2C(N(C)C(=O)NC2=O)=O)=CC=C1OC1=CC=C(S(=O)(=O)C(F)(F)F)C=C1 VBUNOIXRZNJNAD-UHFFFAOYSA-N 0.000 claims description 2
- 239000011347 resin Substances 0.000 claims description 2
- 229920005989 resin Polymers 0.000 claims description 2
- 210000002435 tendon Anatomy 0.000 claims description 2
- 239000000203 mixture Substances 0.000 claims 1
- 238000010977 unit operation Methods 0.000 claims 1
- 239000003921 oil Substances 0.000 description 23
- 230000032258 transport Effects 0.000 description 23
- 238000010586 diagram Methods 0.000 description 9
- 238000005516 engineering process Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 230000008520 organization Effects 0.000 description 3
- 239000004744 fabric Substances 0.000 description 2
- 239000010720 hydraulic oil Substances 0.000 description 2
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000000739 chaotic effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 230000017525 heat dissipation Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000011068 loading method Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000004451 qualitative analysis Methods 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
- 238000005067 remediation Methods 0.000 description 1
- 238000009418 renovation Methods 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 230000003068 static effect Effects 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
- 238000003786 synthesis reaction Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
- E21D20/025—Grouting with organic components, e.g. resin
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0006—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by the bolt material
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F13/00—Transport specially adapted to underground conditions
- E21F13/06—Transport of mined material at or adjacent to the working face
- E21F13/066—Scraper chain conveyors
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Mechanical Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Road Repair (AREA)
Abstract
A kind of quick repairing construction system of baseboard of coal mine roadway and its construction method, construction system includes prosthetic appliance, two operatings carry equipment, anchor bolt grouting equipment and tensioning equipment, the prosthetic appliance is laneway repair machine, anchor bolt grouting equipment includes anchoring drilling machine, flat car, mixing plant and grouting pump, tensioning equipment includes tensioner and tensioning pump station, and construction method includes step 1:Optimization distribution of equipment;Step 2:Each equipment conveying in construction system in place and is debugged;Step 3:Pre-pouring grout is constructed;Step 4:Anchoring construction;Step 5:Anchorage cable stretching;For the present invention using procedure operation, automatically walk can be achieved in each equipment in construction system, and mechanization degree is high, and hand labor intensity is small, can greatly improve baseboard of coal mine roadway repairing construction speed, improves operating environment, reduces construction cost as a result,.
Description
Technical field
The present invention relates to the technical fields of baseboard of coal mine roadway reparation more particularly to a kind of baseboard of coal mine roadway quickly to repair
Construction system and its construction method.
Background technology
In recent years, as the increase of coal mining depth and intensity, roadway surrounding rock control and safety issue become increasingly conspicuous,
Especially under the conditions of high-ground stress, reinforcing soft broken coal rock, deformation of the surrounding rock in tunnel is serious, and wherein Floor Heave in Roadway is particularly problematic.
For having occurred and that the tunnel of serious pucking, no matter using which kind of administration way, top priority has been exactly bottom application work, is then adopted
Take further technical measures.
Current roadway floor repairing construction is generally using a variety of constructions such as pneumatic pick, jumbolter, loading machine, rubber tire transport trolleys
Equipment corresponding construction technology and specification need to successively construct with each equipment, each equipment, almost without rank between each work post
Connect cooperation, the construction working between each construction team lacks coordinative operation, organizes so complicated construction system, it is necessary to be familiar with
The performance characteristics of each equipment reasonably select the model and quantity of construction machinery, also need to understand thoroughly various construction methods, construction technology rule
Model, but at present in roadway floor repairing construction, mainly with working experience or qualitative analysis, can not accomplish construction organization
Rationalization and management it is scientific, cause that roadway repair construction efficiency is low, and complicated organization, equipment replacement is frequent, people
Work labor intensity is big, long construction period, and construction cost is high.
As the roadway floors such as the promotion of roadway repair machineryization level, laneway repair machine, anchoring drilling machine repair special set
It is standby more and more to be applied, largely improve roadway floor remediation efficiency, but at this stage each equipment still with only
Based on vertical work, lacking and cooperate, no and roadway floor renovation technique organically combines, and causes equipment component vacancy rate high,
Process is numerous and diverse, and construction organization is chaotic.
For this purpose, the designer of the present invention, in view of drawbacks described above, by concentrating on studies and designing, synthesis is engaged in for many years for a long time
The experience and achievement of related industry, research and design go out a kind of quick repairing construction system of baseboard of coal mine roadway and its construction method,
To overcome drawbacks described above.
The content of the invention
It is an object of the invention to provide a kind of quick repairing construction system of baseboard of coal mine roadway and its construction methods, use
Procedure operation, automatically walk can be achieved in each equipment in construction system, and mechanization degree is high, and hand labor intensity is small, can be big
Width improves baseboard of coal mine roadway repairing construction speed, improves operating environment, reduces construction cost.
To solve the above problems, the invention discloses a kind of quick repairing construction systems of baseboard of coal mine roadway, it includes repair
Multiple equipment, two operatings carry equipment, anchor bolt grouting equipment and tensioning equipment, it is characterised in that:
The prosthetic appliance is laneway repair machine, and anchor bolt grouting equipment includes anchoring drilling machine, flat car, mixing plant and slip casting
Pump, tensioning equipment include tensioner and tensioning pump station;
The laneway repair machine is by quartering hammer, dipper, bucket, swing arm, a fortune scratch board conveyor structure, motor pump group and walking
Crawler belt forms, and the traveling crawler is equipped with car body, and a fortune scratch board conveyor structure and motor pump group, institute are carried on the car body
The front end for stating car body is equipped with swing arm, and the swing arm is moved by hydraulic cylinder driving, and the front end of the swing arm is hinged with
Dipper, the dipper are driven movement by another hydraulic cylinder, and the quartering hammer is fixed on dipper, and the bucket is arranged on
The free end of dipper;
The anchoring drilling machine is at least 2, and wherein First anchoring drilling machine is arranged in laneway repair machine rear certain distance
It is interior to carry out the construction of pre-pouring grout hole, wherein second anchoring drilling machine be arranged in the First anchoring drilling machine rear certain distance with
Carry out the construction of anchor hole;
The flat car quantity corresponds to anchoring drilling machine, therefore at least 2 flat cars are separately positioned at least 2 anchoring drilling machines
Rear and steel wire rope hook is installed, the flat car is connected respectively by steel wire rope with the pump truck of corresponding anchoring drilling machine, by
The pump truck of anchoring drilling machine is driven walking, and the grouting pump and mixing plant are fixed on the flat car in front, the tensioning pump
Station is fixed on the flat car at rear, and is passed through hydralic hose and be connected with tensioner.
Wherein:It is trackless truck that two operating, which carries equipment, and the trackless truck is in laneway repair machine and abandons between cash field
Reciprocation cycle transports spoil.
Wherein:Two operating carries equipment and includes belt transport unit and elevating conveyor, and the elevating conveyor is spread along roadway direction
Roadway floor one side is located at, the elevating conveyor is scraper blade elevating conveyor or leather belt reshipment machine.
Wherein:2 rear support legs of the belt transport unit are attached by bolt and laneway repair machine, to ensure skin
Stability with transporter operation.
Wherein:The belt transport unit further includes belt, 2 deflection oil cylinders and 2 flexion-extension oil cylinders, 2 flexion-extensions
Oil cylinder be individually fixed in 2 deflection oil cylinder telescopic rod end connecting seat, the belt be hingedly connected to 2 deflection oil cylinders and
The telescopic rod ends of 2 flexion-extension oil cylinders, are thus supported belt and angular adjustment.
Wherein:The anchoring drilling machine includes pump truck and drill carriage, and the pump truck includes the fuel tank being located on movable pump car body
With motor pump group, the drill carriage mainly includes the dust-extraction unit, securing device and the radiator that are located on portable drill carriage body, described
Radiator is located at the front of dust-extraction unit, and the front end of the radiator is fixed with feeding body and work by double leval jib translation system
Make arm.
Wherein:The double leval jib translation system includes quadric chain and driven in translation oil cylinder to realize firm shifting
Dynamic, the feeding body is mounted on the working arm that amplitude-variable is adjusted.
Wherein:The securing device includes at least two firm support legs, and the bottom of the firm support leg, which is equipped with, to be consolidated
Seat.
A kind of quick method for repairing and constructing of baseboard of coal mine roadway is also disclosed, it is fast by baseboard of coal mine roadway as described above
Fast repairing construction system is realized, it is characterised in that is comprised the following steps:
Step 1:Optimization distribution of equipment;
Step 2:Each equipment conveying in construction system in place and is debugged, to be repaired section of tunnel is cleared up, by striking
Jowling is helped to check back and two stability helped, anchor cable reinforcement is used to unstable surrounding rock;
Step 3:Pre-pouring grout is constructed, and is carried out pre-pouring grout hole construction, installation pre-pouring grout pipe and sealing of hole using anchoring drilling machine, is adopted
Grouting slurries are prepared with mixing plant, slip casting operation is completed using grouting pump, and carries out Hou Ning;
Step 4:Anchoring construction, operating personnel are carried out the construction of anchor hole using anchoring drilling machine, tree are used cooperatively after pore-forming
Fat Anchor Agent installs high strength steel strand anchor cable, configures special-shaped high intensity arch tray, installs aligning ball pad additional, and in drilling interpolation
Enter slip casting aluminium-plastic pipe, using cotton yarn and double slurries sealing of holes, by slip casting aluminium-plastic pipe to anchor cable hole slip casting, after the completion of slip casting, go forward side by side
Row Hou Ning;
Step 5:Anchorage cable stretching pre-tightens anchor cable using tensioner tensioning, after the completion of tensioning, manually separates anchor cable head reinforcing bar
Beam is bent around, to prevent lockset from loosening, and smooth location.
By said structure, the quick repairing construction system of baseboard of coal mine roadway of the invention and its construction method have
Following effect:
1st, according to roadway floor repairing construction technological requirement, reasonably select its relative special-purpose equipment and arrange the construction of each equipment
Position by Optimal Configuration Method and scheduling decision method, determines the quantity of each equipment and real-time matching relationship, forms coal respectively
The construction system that ore deposit roadway floor is quickly repaired;
2nd, using procedure operation, automatically walk can be achieved in each equipment in construction system, and mechanization degree is high, artificial labor
Fatigue resistance is small, can greatly improve baseboard of coal mine roadway repairing construction speed, improves operating environment, reduces construction cost.
The detailed content of the present invention can be obtained by aftermentioned explanation and institute's attached drawing.
Description of the drawings
Fig. 1 shows a kind of side view cloth of the first embodiment of the quick repairing construction system of baseboard of coal mine roadway of the present invention
Put figure;
Fig. 2 shows a kind of vertical view cloth of the first embodiment of the quick repairing construction system of baseboard of coal mine roadway of the present invention
Put figure;
Fig. 3 shows the side view arrangement schematic diagram of another embodiment of the present invention;
Fig. 4 shows the vertical view arrangement schematic diagram of another embodiment of the present invention;
Fig. 5 shows the laneway repair machine of the present invention and belt transport unit connection diagram;
Fig. 6 shows the anchoring drilling machine structure diagram of the present invention;
Fig. 7 a and Fig. 7 b show the pre-pouring grout of the present invention and the side view arrangement schematic diagram of anchor cable (bar) construction;
Fig. 8 shows pre-pouring grout and the vertical view arrangement schematic diagram of anchor cable (bar) construction.
Reference numeral:
1 it is laneway repair machine, 2 be trackless truck, 3 be anchoring drilling machine, 4 be grouting pump, 5 be mixing plant, 6 is flat car, 7
It is tensioning pump station for tensioner, 8,9 be belt transport unit, 10 be scraper blade elevating conveyor, 11 be quartering hammer, 12 be dipper, 13 is
Bucket, 14 be swing arm, 15 be a fortune scratch board conveyor structure, 16 be motor pump group, 17 be traveling crawler, 18 be rear support leg, 19 be
Deflection oil cylinder, 20 be pitching oil cylinder, 21 be belt, 22 be feeding body, 23 be working arm, 24 be securing device, 25 be heat dissipation
Device, 26 be dust-extraction unit, 27 be fuel tank, 28 be motor pump group, 29 be anchor hole, 30 be pre-pouring grout hole.
Specific embodiment
It is described in further detail to technical solution of the present invention in the following with reference to the drawings and specific embodiments, so that this field
Technical staff can be better understood from the present invention and be practiced, but illustrated embodiment is not as a limitation of the invention.
The quick repairing construction system of baseboard of coal mine roadway of the present invention can include prosthetic appliance, two operatings carry equipment, anchoring
Grouting equipment and tensioning equipment, and according to the difference of baseboard of coal mine roadway repairing construction environment and execution conditions, two operatings carry
Two kinds of forms can be used in equipment, and one of which includes trackless truck 2, and another kind includes belt transport unit 9.
Referring to Fig. 1 and Fig. 2, it is shown that the first of the quick repairing construction system of a kind of baseboard of coal mine roadway of the invention is implemented
The layout drawing of example, prosthetic appliance are laneway repair machine 1, and it is trackless truck 2 that two operatings, which carry equipment, and anchor bolt grouting equipment includes anchor
Gu drilling machine 3, flat car 6, mixing plant 5 and grouting pump 4, tensioning equipment can include tensioner 7 and tensioning pump station 8, with reference to attached
Figure describes in detail.
Referring to Fig. 5, the laneway repair machine 1 mainly transports scraper plate fortune by quartering hammer 11, dipper 12, bucket 13, swing arm 14, one
Transfer mechanism 15, motor pump group 16 and traveling crawler 17 form, and the traveling crawler 17 is equipped with car body, is carried on the car body
One fortune scratch board conveyor structure 15 and motor pump group 16, the front end of the car body are equipped with swing arm 14, and the swing arm 14 can pass through a liquid
Compressing cylinder driving is moved, and the front end of the swing arm 14 is hinged with dipper 12, the dipper 12 by another hydraulic cylinder into
Row drive motion (as shown in Figure 5), and the quartering hammer 11 is fixed on dipper 12, the bucket 13 is arranged on the freedom of dipper 12
End, the concrete structure of specially designed laneway repair machine 1 of the invention, can realize the broken of tunnel, moreover it is possible to quick in time as a result,
Carry out the transfer of material.
The laneway repair machine 1 can drive corresponding component to be broken to realize to Floor Heave in Roadway by operating cylinder as a result,
Function that is broken, skimming, and using a fortune scratch board conveyor structure 15 by gangue reprint to trackless truck 2, the trackless truck 2 exists
Laneway repair machine 1 and abandon reciprocation cycle transport spoil between cash field.
The anchoring drilling machine 3 can be at least 2, wherein First anchoring drilling machine 3 and be arranged in 1 rear one of laneway repair machine
In set a distance, to carry out the construction of pre-pouring grout hole, wherein second anchoring drilling machine 3 is arranged in 3 rear one of First anchoring drilling machine
In set a distance, to carry out the construction of anchor hole, pre-pouring grout hole and anchor hole are mutually staggered, arranged in blossom type, the tunnel
The bottom application work that rises of repair machine 1 has certain independence compared with pre-pouring grout hole and anchor hole construction, but not completely independent, applies
Construction equipment distance is too near, easily interferes, can not normal operation, apart from too far, easily there is the problems such as secondary pucking in tunnel, increases
Workload, so two 3 speed of applications of anchoring drilling machine should match with the bottom speed of application that rises of laneway repair machine 1, distance of constructing
Holding is basically unchanged.
Referring to Fig. 6, it is shown that the structure diagram of anchoring drilling machine, the anchoring drilling machine 3 include pump truck and drill carriage, the pump
Car owner will include the fuel tank 27 being located on movable pump car body and motor pump group 28, and the drill carriage mainly includes being located at portable bore
Dust-extraction unit 26, securing device 24 and radiator 25 on car body, the radiator is located at the front of dust-extraction unit 26, described to dissipate
The front end of hot device 25 is fixed with feeding body 22 and working arm 23, the double leval jib translation system bag by double leval jib translation system
Containing quadric chain and driven in translation oil cylinder to realize firm movement, the feeding body 22 is mounted on what amplitude-variable was adjusted
On working arm 23, the deflection of feeding body 22 is realized by the adjusting of working arm 23, so as to without moving body, it becomes possible to
Once two bottom plate anchor hole constructions are completed in parking, wherein, the securing device 24 can include at least two firm support legs, institute
Firm seat can be equipped with by stating the bottom of firm support leg, it is preferred that the firm seat is cross, to provide preferably firm effect
Fruit.
6 quantity of flat car corresponds to anchoring drilling machine 3, therefore at least 2 flat cars 6 are separately positioned at least 2 anchorings
The rear of drilling machine 3 is simultaneously equipped with steel wire rope hook, and the flat car 6 passes through steel wire rope and the pump truck of corresponding anchoring drilling machine 3 respectively
It is connected, walking is driven by the pump truck of anchoring drilling machine 3, the grouting pump 4 and mixing plant 5 are fixed on the flat car 6 in front,
The tensioning pump station 8 is fixed on the flat car 6 at rear, and is passed through hydralic hose and be connected with tensioner 7, and the flat car 6 is equal
It is provided with holding brake device.
Wherein, the easily-consumed products such as the slip casting raw material needed for the construction system, anchor cable (bar), tool box are also disposed in flat car
On 6.It when flat car 6 needs to move forwards, is dragged by 3 pump truck of anchoring drilling machine by steel wire rope, when the needs of flat car 6 stop
When machine works, it is fixed using holding brake device.
The mixing plant 5 can prepare grouting slurries, and auxiliary staircase is fixed with beside it, convenient for completing slurries stirring
Operation, the grouting pump 4 can utilize slurries to complete slip casting operation, and the tensioning pump station 8 can be that tensioner 7 provides hydraulic oil completion
Anchor cable (bar) tensioning.
Referring to Fig. 3 and Fig. 4, it is shown that another embodiment of the quick repairing construction system of baseboard of coal mine roadway of the present invention,
Prosthetic appliance is laneway repair machine 1, and two operatings carry equipment and include belt transport unit 9 and elevating conveyor, and anchor bolt grouting equipment includes
Anchoring drilling machine 3, flat car 6, mixing plant 5 and grouting pump 4, tensioning equipment include tensioner 7 and tensioning pump station 8, the elevating conveyor
Roadway floor one side is laid on along roadway direction, the elevating conveyor can be scraper blade elevating conveyor 10, it is possible to use leather belt reshipment machine is treated
After the completion of tunnel opposite side pre-pouring grout and anchor cable (bar) construction, the scraper blade elevating conveyor 10, which is just replaced, arrives tunnel opposite side, so
It can ensure that entire construction system is continuously constructed, and each equipment remains that relative position is constant.
Referring to Fig. 5, laneway repair machine 1 and 9 connection diagram of belt transport unit, the belt transport unit are also shown
92 rear support legs 18 are attached by bolt and laneway repair machine 1, to ensure the stability of the operation of belt transport unit 9,
The belt transport unit 9 may also include 21,2 deflection oil cylinders 19 of belt and 2 flexion-extension oil cylinders 20, the 2 deflection oil cylinder
19 are fixed on the both sides of transporter body, and described 2 pitch the telescopic rod end that oil cylinder 20 is individually fixed in 2 deflection oil cylinders 19
The connecting seat at end, the belt 21 are hingedly connected to the telescopic rod end of 2 deflection oil cylinders 19 and 2 flexion-extension oil cylinders 20, as a result,
Oil cylinders 19 can be deflected by 2 and belt 21 is supported 2 flexion-extension oil cylinders 20 and angular adjustment, the belt transport unit
9 are mounted at 1 tail pedestal of laneway repair machine, and using fluid motor-driven, hydraulic oil is provided by laneway repair machine 1,
One end of 2 deflection oil cylinders 19 and 2 pitching oil cylinders 20 by transporter body and 1 tail pedestal of laneway repair machine into
Marketing axis is connected, and the other end is connected with belt 21, it can be achieved that 9 multi-faceted adjusting of belt transport unit, and can ensure scraper plate turn
Carrier aircraft 10 is arranged in 9 range of deflection of belt transport unit.
The belt transport unit 9 can be adjusted by deflecting oil cylinder 19 and pitching oil cylinder 20, certain up and down
In the range of adjust, and the 21 end rotation axis of belt of belt transport unit 9 is in the underface of 1 tail discharge port of laneway repair machine,
The speed of service of belt transport unit 9 is more than the speed of service that laneway repair machine one transports scratch board conveyor structure 15, scraper blade elevating conveyor
10 speed of service is more than the speed of service of belt transport unit 9, i.e., the reprinting ability of follow-up corollary equipment is set slightly larger than front end
Standby reprinting ability, to give full play to the construction ability of laneway repair machine 1, gangue reprint efficiency highest at this time, laneway repair machine 1
Bottom application work is played continuously without stagnation.
Referring to Fig. 7 a, 7b and Fig. 8, it is shown that for the arrangement schematic diagram that pre-pouring grout and anchor cable (bar) are constructed, 29 He of anchor hole
Pre-pouring grout hole 30 mutually staggers, and is arranged in blossom type, the spacing of wells according to heading sizes, grouting pressure, anchor cable (bar) length,
The parameters such as prestressing force size, which calculate, to be determined, ensures that each adjacent anchor hole 29 and 30 coverage of pre-pouring grout hole are overlapped mutually.
The present invention discloses a kind of quick method for repairing and constructing of baseboard of coal mine roadway, the construction method passes through above-mentioned
The quick repairing construction system of baseboard of coal mine roadway realize, mainly comprise the following steps:
Step 1:Optimization distribution of equipment;
Due between various kinds of equipment in construction system there is cooperate, the relation that mutually restricts, in order to ensure tunnel
Pucking administers the continuity of construction, and each equipment in Proper Match construction system is one of key, tunnel Forming Quality after reparation
It is again closely related with the reasonable disposition of its equipment, and it is largely fixed the construction efficiency and construction speed of construction system.It closes
Reason configures the quantity of each equipment and the construction effect for using preferable decision-making dispatching method that can improve construction system in construction system
Rate, economic benefit provide theoretical foundation to formulate arrangement and method for construction.
Each equipment optimizing configuration method is multi objective function optimization method, using multi objective function optimization method to applying
Laneway repair machine, two operatings carry equipment, anchoring drilling machine, flat car, mixing plant, grouting pump, tensioner and tensioning pump in work system
The quantity stood optimizes configuration, should be according to construction technology, execution conditions and each construction equipment during practice of construction
The variation of working condition, is adjusted in due course using this method.It should be selected first according to construction condition and quantities leading
Equipment, i.e. laneway repair machine and anchoring drilling machine, once laneway repair machine and anchoring drilling machine are selected, quantity will not adjust, then root
The ancillary equipments such as equipment, flat car, mixing plant, grouting pump, tensioner and tensioning pump station, which are carried, according to two operatings should ensure that key machine
The principle of peak performance is played, carries out matching their quantity, ensures that leading equipment is efficient.
According to the analysis to the operation principle of each equipment in construction system, the unit construction cost with construction system can be established
Multiple-objection optimization allocation models with One-Shift Costs comprehensive utilization ratio is object function, then have following object functions:
In formula:F1--- the unit construction cost of construction system;
F2--- the One-Shift Costs comprehensive utilization ratio of construction system;
I --- 0,1,2,3,4,5,6,7 represents laneway repair machine, anchoring drilling machine, trackless truck, flat car, stirring respectively
It stands, grouting pump, tensioner, tensioning pump station;
Xi--- the quantity of each equipment in construction system;
Ci--- the machine-team of each equipment takes in construction system;
Ki--- the utilization rate of each equipment in construction system;
N --- the laneway repair machine machine-team working time;
Q0--- laneway repair machine productivity;
P01--- the probability of laneway repair machine free time.
For the Optimization Solution problem of multiple objective function, should be calculated using the method for static configuration, due to above-mentioned more
Object function Relationship Comparison is complicated, and F1And F2It is not XiContinuous function, calculate optimal solution X with conventional Method of Seeking DerivativeiIt is
Unworkable, it can calculate by the following method, should initial X be set according to total construction work amount firstiValue, according to more
Objective optimization configuration function calculates corresponding F1And F2;Then least square is pressed to these initial numerical value using MATLAB softwares
Principle carries out fitting of a polynomial, draws F1And F2On XiHigher order functionality graph;Finally according to F1And F2Higher order functionality it is bent
Line chart carries out coordinating to correct drawing corresponding Z using set of weights is legal to two object functions1And Z2, to obtain one to each point
Opposite optimal solution of all preferable scheme of target as multiple objective function.
Step 2:Each equipment conveying in construction system in place and is debugged, to be repaired section of tunnel is cleared up, by striking
Jowling is helped to check back and two stability helped, anchor cable (bar) reinforcement is used to unstable surrounding rock.
Operating personnel carry equipment according to suitable two operating of site operation environment and condition selection, by operating roadway repair
The quartering hammer 11 of machine crushes pucking tunnel, and spoil is transported scratch board conveyor by the one of laneway repair machine using bucket 13
Structure 15 is transferred to two operatings and carries in equipment, and two operatings carry equipment and are transported through spoil, and pass through laneway repair machine 1 to tunnel bottom
Plate is compacted.
Step 3:Pre-pouring grout is constructed, and due to roadway floor soft broken, for reinforced roadway floor crack and blocks tunnel bottom
Plate surface layer country rock prevents roadway floor anchor rope grouting hole collapse hole.Operating personnel carry out pre-pouring grout hole construction using anchoring drilling machine 3,
Pre-pouring grout pipe and sealing of hole are installed, grouting slurries are prepared using mixing plant 5, slip casting operation is completed using grouting pump 4, and carries out marquis
It is solidifying.
Step 4:Anchoring construction, operating personnel are carried out the construction of anchor hole using anchoring drilling machine 3, are used cooperatively after pore-forming
Resin anchoring agent installs high strength steel strand anchor cable, configures special-shaped high intensity arch tray, installs aligning ball pad additional, and in drilling
Slip casting aluminium-plastic pipe is inserted into, using cotton yarn and double slurries sealing of holes, by slip casting aluminium-plastic pipe to anchor cable hole slip casting, after the completion of slip casting, and
Carry out Hou Ning.
Step 5:Anchorage cable stretching and smooth location, operating personnel pre-tighten anchor cable using 7 tensioning of tensioner, after the completion of tensioning,
Manually separation anchor cable head tendon, bends, around to prevent lockset from loosening.
Entire construction system can carry out continuous high-efficient repairing construction operation, after the completion of construction, it is necessary to entirely constructing
Place clear up perfect, and each equipment is transported and IMM algorithm.
The construction system and its construction method that baseboard of coal mine roadway of the invention is quickly repaired as a result, can be according to tunnel bottom
Plate repairing construction technological requirement reasonably selects its relative special-purpose equipment and simultaneously arranges the position of each equipment, by Optimal Configuration Method and
Scheduling decision method determines the quantity of each equipment and real-time matching relationship respectively.The construction system uses procedure operation, construction
Each equipment can realize automatically walk in system, and mechanization degree is high, and hand labor intensity is small, can greatly improve baseboard of coal mine roadway
Repairing construction speed improves operating environment, reduces construction cost.
It is readily apparent that above description and record is only illustrated in the disclosure being not intended to be limiting of the invention
Appearance, application or use.Although describing in embodiment and embodiment being described in the drawings, the present invention does not limit
By attached drawing example and be described as in embodiment it is now recognized that optimal mode to implement the particular case of the teachings of the present invention
Son, the scope of the present invention is by any embodiment of the description and appended claims including falling into front.
Claims (9)
1. a kind of quick repairing construction system of baseboard of coal mine roadway, it includes prosthetic appliance, two operatings carry equipment, anchor bolt grouting is set
Standby and tensioning equipment, it is characterised in that:
The prosthetic appliance is laneway repair machine, and anchor bolt grouting equipment includes anchoring drilling machine, flat car, mixing plant and grouting pump,
Tensioning equipment includes tensioner and tensioning pump station;
The laneway repair machine is by quartering hammer, dipper, bucket, swing arm, a fortune scratch board conveyor structure, motor pump group and traveling crawler
Composition, the traveling crawler are equipped with car body, a fortune scratch board conveyor structure and motor pump group, the vehicle are carried on the car body
The front end of body is equipped with swing arm, and the swing arm is moved by hydraulic cylinder driving, and the front end of the swing arm is hinged with dipper,
The dipper is driven movement by another hydraulic cylinder, and the quartering hammer is fixed on dipper, and the bucket is arranged on dipper
Free end;
The anchoring drilling machine is at least 2, wherein First anchoring drilling machine be arranged in the certain distance of laneway repair machine rear with
Pre-pouring grout hole construction is carried out, wherein second anchoring drilling machine is arranged in the First anchoring drilling machine rear certain distance to carry out
The construction of anchor hole;
The flat car quantity corresponds to anchoring drilling machine, therefore after at least 2 flat cars are separately positioned at least 2 anchoring drilling machines
Side is simultaneously equipped with steel wire rope hook, and the flat car is connected respectively by steel wire rope with the pump truck of corresponding anchoring drilling machine, by anchoring
The pump truck of drilling machine is driven walking, and the grouting pump and mixing plant are fixed on the flat car in front, and the tensioning pump station is consolidated
It is scheduled on the flat car at rear, and passes through hydralic hose and be connected with tensioner.
2. the quick repairing construction system of baseboard of coal mine roadway as described in claim 1, it is characterised in that:Two operating, which carries, to be set
It is standby for trackless truck, the trackless truck is in laneway repair machine and abandons reciprocation cycle transport spoil between cash field.
3. the quick repairing construction system of baseboard of coal mine roadway as described in claim 1, it is characterised in that:Two operating, which carries, to be set
For comprising belt transport unit and elevating conveyor, the elevating conveyor is laid on roadway floor one side, the elevating conveyor along roadway direction
For scraper blade elevating conveyor or leather belt reshipment machine.
4. the quick repairing construction system of baseboard of coal mine roadway as claimed in claim 3, it is characterised in that:The belt-conveying dress
2 rear support legs put are attached by bolt and laneway repair machine, to ensure the stability of belt transport unit operation.
5. the quick repairing construction system of baseboard of coal mine roadway as claimed in claim 3, it is characterised in that:The belt-conveying dress
It puts and further includes belt, 2 deflection oil cylinders and 2 flexion-extension oil cylinders, 2 flexion-extensions oil cylinder is individually fixed in 2 and deflects oil cylinder
The connecting seat of telescopic rod end, the belt are hingedly connected to the telescopic rod end of 2 deflection oil cylinders and 2 flexion-extension oil cylinders, by
Belt is supported for this and angular adjustment.
6. the quick repairing construction system of baseboard of coal mine roadway as described in any in claim 1-5, it is characterised in that:The anchor
Gu drilling machine includes pump truck and drill carriage, the pump truck includes the fuel tank being located on movable pump car body and motor pump group, the drill carriage
Main dust-extraction unit, securing device and the radiator for including being located on portable drill carriage body, the radiator are located at dust-extraction unit
Front, the front end of the radiator is fixed with feeding body and working arm by double leval jib translation system.
7. the quick repairing construction system of baseboard of coal mine roadway as claimed in claim 6, it is characterised in that:The double leval jib translation
System includes quadric chain and driven in translation oil cylinder to realize firm movement, and the feeding body is mounted on amplitude-variable tune
On the working arm of section.
8. the quick repairing construction system of baseboard of coal mine roadway as claimed in claim 6, it is characterised in that:The securing device bag
Containing at least two firm support legs, the bottom of the firm support leg is equipped with firm seat.
9. a kind of quick method for repairing and constructing of baseboard of coal mine roadway, passes through the coal mine roadway as described in any in claim 1-8
The quick repairing construction system of bottom plate is realized, it is characterised in that is comprised the following steps:
Step 1:Optimization distribution of equipment;
Step 2:Each equipment conveying in construction system in place and is debugged, to be repaired section of tunnel is cleared up, is asked by striking side
Top checks back and two stability helped, and anchor cable reinforcement is used to unstable surrounding rock;
Step 3:Pre-pouring grout is constructed, and pre-pouring grout hole construction is carried out using anchoring drilling machine, installation pre-pouring grout pipe and sealing of hole, using stirring
It mixes station and prepares grouting slurries, complete slip casting operation using grouting pump, and carry out Hou Ning;
Step 4:Anchoring construction, operating personnel are carried out the construction of anchor hole using anchoring drilling machine, resin anchor are used cooperatively after pore-forming
Gu high strength steel strand anchor cable is installed in agent, special-shaped high intensity arch tray is configured, aligning ball pad is installed additional, and note is inserted into drilling
Aluminium-plastic pipe is starched, using cotton yarn and double slurries sealing of holes, by slip casting aluminium-plastic pipe to anchor cable hole slip casting, after the completion of slip casting, and carries out marquis
It is solidifying;
Step 5:Anchorage cable stretching pre-tightens anchor cable using tensioner tensioning, after the completion of tensioning, manually separates anchor cable head tendon, to
Surrounding is bent, to prevent lockset from loosening, and smooth location.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711335366.4A CN108104839B (en) | 2017-12-14 | 2017-12-14 | The quick repairing construction system of baseboard of coal mine roadway and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711335366.4A CN108104839B (en) | 2017-12-14 | 2017-12-14 | The quick repairing construction system of baseboard of coal mine roadway and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108104839A true CN108104839A (en) | 2018-06-01 |
CN108104839B CN108104839B (en) | 2019-06-25 |
Family
ID=62216841
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201711335366.4A Active CN108104839B (en) | 2017-12-14 | 2017-12-14 | The quick repairing construction system of baseboard of coal mine roadway and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108104839B (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952808A (en) * | 2018-07-04 | 2018-12-07 | 中铁六局集团有限公司 | Large volume internal axial pressure compensator installation engineering method |
CN109667618A (en) * | 2019-02-25 | 2019-04-23 | 闫红世 | A kind of grouting vehicle backfilling coal cutting roadway |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242476A (en) * | 1996-03-08 | 1997-09-16 | Maeda Corp | Cutter head for drilling machine |
CN103643707A (en) * | 2013-12-19 | 2014-03-19 | 中煤科工集团西安研究院有限公司 | Roadway repair machine integrating drilling, digging, transporting and loading |
CN103899249A (en) * | 2014-04-28 | 2014-07-02 | 中煤科工集团西安研究院有限公司 | Coal mine roadway bottom board anchoring drill carriage |
CN104564090A (en) * | 2014-12-13 | 2015-04-29 | 中国煤炭科工集团太原研究院有限公司 | Multifunctional tunnel repairing integrated machine |
CN104632233A (en) * | 2014-12-13 | 2015-05-20 | 中国煤炭科工集团太原研究院有限公司 | Mechanical repair technology of distortional roadway and roadway repair machine |
CN105201525A (en) * | 2015-10-19 | 2015-12-30 | 河南理工大学 | Repairable bottom heave control method |
-
2017
- 2017-12-14 CN CN201711335366.4A patent/CN108104839B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242476A (en) * | 1996-03-08 | 1997-09-16 | Maeda Corp | Cutter head for drilling machine |
CN103643707A (en) * | 2013-12-19 | 2014-03-19 | 中煤科工集团西安研究院有限公司 | Roadway repair machine integrating drilling, digging, transporting and loading |
CN103899249A (en) * | 2014-04-28 | 2014-07-02 | 中煤科工集团西安研究院有限公司 | Coal mine roadway bottom board anchoring drill carriage |
CN104564090A (en) * | 2014-12-13 | 2015-04-29 | 中国煤炭科工集团太原研究院有限公司 | Multifunctional tunnel repairing integrated machine |
CN104632233A (en) * | 2014-12-13 | 2015-05-20 | 中国煤炭科工集团太原研究院有限公司 | Mechanical repair technology of distortional roadway and roadway repair machine |
CN105201525A (en) * | 2015-10-19 | 2015-12-30 | 河南理工大学 | Repairable bottom heave control method |
Non-Patent Citations (3)
Title |
---|
张幼振: "《煤矿巷道底鼓机械化治理技术应用研究》", 《煤炭科学技术》 * |
李旺年等: "《ZDY750L底锚钻机在新元矿底板锚固施工中的应用》", 《中国煤炭学会钻探工程专业委员会2017年钻探工程学术研讨会论文集》 * |
李旺年等: "《全液压履带钻机在煤矿巷道底板锚固施工中的应用》", 《煤矿现代化》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108952808A (en) * | 2018-07-04 | 2018-12-07 | 中铁六局集团有限公司 | Large volume internal axial pressure compensator installation engineering method |
CN109667618A (en) * | 2019-02-25 | 2019-04-23 | 闫红世 | A kind of grouting vehicle backfilling coal cutting roadway |
Also Published As
Publication number | Publication date |
---|---|
CN108104839B (en) | 2019-06-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102022122B (en) | Support-type comprehensive tunneler | |
CN205766713U (en) | Building 3D printing equipment | |
CN204783054U (en) | Tunnel invert concrete lining's sliding template | |
CN108952763A (en) | A kind of equipment and its engineering method for vcehicular tunnel, railway tunnel supporting construction | |
CN203174447U (en) | Side-cutting type turnout screen scarifier | |
CN108104839B (en) | The quick repairing construction system of baseboard of coal mine roadway and its construction method | |
CN202039857U (en) | Lifting type tunnel excavation support operation rack | |
CN105604581A (en) | Hoisting and rotating type installation equipment of tunnel ditch cable groove combination template and construction method of hoisting and rotating type installation equipment | |
CN102042021A (en) | Automatically walking stepped mobile trestle | |
CN104153553B (en) | A kind of fully-automatic intelligent mud wall machine | |
CN112761691B (en) | Distributed anchoring grouting supporting device for fault broken zone of deep mine | |
CN102337795B (en) | Drilling device and drilling method | |
CN109723445A (en) | Parallel three steps full section of tunnel entirety driving method | |
CN104632233A (en) | Mechanical repair technology of distortional roadway and roadway repair machine | |
CN112360340A (en) | Automatic anchor rod drill carriage | |
CN109611026A (en) | Coal working face mobile hydraulic anchoring drill carriage | |
CN102121390B (en) | Telescopic tunneling immediate support device | |
KR101359929B1 (en) | Constructing method for tunnel using mobile mixer having hopper for supplying steel fiber, and tunnel structure | |
CN204753510U (en) | Digital multi -functional canal lining machine | |
CN109322298A (en) | Vibrating and impacting construction of ballast pile unit and construction method with bottom discharge | |
CN208416569U (en) | A kind of workbench manipulator for tunnel support construction equipment | |
CN101187309B (en) | Door frame type seepage-proof earthwork cloth spreading machine for tunnel | |
CN108518179A (en) | A kind of baseboard of coal mine roadway minor diameter anchor cable clean-out machine and construction method | |
CN206797384U (en) | Supporting trailer after shield machine marshaling travelling platform and shield machine | |
CN104500131A (en) | Transportation system and transportation method for deslagging in inclined shaft construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |