CN108091008A - A kind of underground pipe gallery electrical equipment power control system - Google Patents

A kind of underground pipe gallery electrical equipment power control system Download PDF

Info

Publication number
CN108091008A
CN108091008A CN201611033878.0A CN201611033878A CN108091008A CN 108091008 A CN108091008 A CN 108091008A CN 201611033878 A CN201611033878 A CN 201611033878A CN 108091008 A CN108091008 A CN 108091008A
Authority
CN
China
Prior art keywords
pipe gallery
underground pipe
nfc
information
cabin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611033878.0A
Other languages
Chinese (zh)
Other versions
CN108091008B (en
Inventor
刘雁飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Smelting Vast Of Heaven Energy-Conserving And Environment-Protective Technology Co Ltd In Hunan
Zhongye Changtian International Engineering Co Ltd
Original Assignee
Smelting Vast Of Heaven Energy-Conserving And Environment-Protective Technology Co Ltd In Hunan
Zhongye Changtian International Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Smelting Vast Of Heaven Energy-Conserving And Environment-Protective Technology Co Ltd In Hunan, Zhongye Changtian International Engineering Co Ltd filed Critical Smelting Vast Of Heaven Energy-Conserving And Environment-Protective Technology Co Ltd In Hunan
Priority to CN201611033878.0A priority Critical patent/CN108091008B/en
Publication of CN108091008A publication Critical patent/CN108091008A/en
Application granted granted Critical
Publication of CN108091008B publication Critical patent/CN108091008B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/00174Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys
    • G07C9/00571Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys operated by interacting with a central unit
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/00174Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys
    • G07C9/00182Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys operated with unidirectional data transmission between data carrier and locks
    • GPHYSICS
    • G07CHECKING-DEVICES
    • G07CTIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
    • G07C9/00Individual registration on entry or exit
    • G07C9/00174Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys
    • G07C9/00896Electronically operated locks; Circuits therefor; Nonmechanical keys therefor, e.g. passive or active electrical keys or other data carriers without mechanical keys specially adapted for particular uses

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

A kind of underground pipe gallery electrical equipment power control system provided by the invention, including:NFC mobile terminal, underground pipe gallery Tomcat-AdminPortal and NFC smart locks;NFC smart locks read the identity information of NFC mobile terminal, when identity information is legal identity information, perform unlocking action, after unlocking the effective unlocking signal of NFC smart locks is sent to underground pipe gallery Tomcat-AdminPortal, smart lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal by NFC mobile terminal, the underground pipe gallery cabin information that underground pipe gallery Tomcat-AdminPortal will enter according to described in, work power load power supply transmission into the cabin that will enter goes code, and connects the work power load power supply in the cabin that will enter immediately;According to the underground pipe gallery cabin information that will be left, the work power load power supply into the cabin that will be left sends open command, the work power load power supply in the cabin that will be left described in disconnection immediately.So as to save power consumption.

Description

A kind of underground pipe gallery electrical equipment power control system
Technical field
The present invention relates to wireless communication technique field, more particularly to a kind of underground pipe gallery electrical equipment power control system.
Background technology
Underground pipe gallery be built in Urban Underground for accommodate at least two class municipal engineering pipelines structures and affiliated facility, Underground pipe gallery for it is various adhere to separately different majors, by the municipal engineering pipeline of different division managements provide laying space.Fig. 1 (a) And the sectional schematic diagram and floor map of certain Urban Underground piping lane in the prior art are shown in Fig. 1 (b), such as Fig. 1 (a) Shown, underground pipe gallery is divided into multiple mutually isolated cabins, and different types of pipeline is laid in each cabin, such as natural gas tube, feedwater A variety of heterogeneitys such as pipe, sewage pipe, telecommunications pipe, power pipe and power pipe, source and the different municipal engineering pipeline of whereabouts. As shown in Fig. 1 (b), to ensure that pipeline can safely and smoothly enter underground pipe gallery, in each pipeline cabin in underground pipe gallery often One hoisting port (either referred to as personnel escape mouthful) can be set for the transport of pipeline or the discrepancy of personnel every a distance.
To ensure that underground pipe gallery space environment disclosure satisfy that the demand of laying and the Maintenance and Repair work of pipeline, buried pipe The facilities such as illumination, ventilation, maintenance, draining, fire-fighting and monitoring would generally be provided in corridor.Such as with reference to certain city shown in Fig. 2 City's underground pipe gallery daily management schematic diagram, it is known that A pipelines, the B pipelines in certain city need periodic inspection, and A pipelines are located at ground The A segment pipes cabin of lower piping lane, B pipelines are located at the B section electric compartments of Urban Underground piping lane, the ownership A departments of A pipelines, B pipeline ownerships B departments.In A departments to underground pipe gallery manager's reporting, examination and repair plan, after obtaining underground pipe gallery manager approval, A departments send A pipeline maintenance personnel be allowed for access underground pipe gallery A segment pipes cabin carry out pipeline maintenance, enter ground in A pipeline maintenance personnel Before lower piping lane, underground pipe gallery manager needs to open the electricity consumptions such as illumination, ventilation, monitoring or maintenance in A segment pipes cabin in advance The power supply of equipment, after A pipeline maintenances personnel maintenance finishes and goes out underground pipe gallery, underground pipe gallery manager will mutually apply again The power-off of electric equipment.
It follows that in the prior art, A pipeline maintenances personnel finish from entrance underground pipe gallery to final maintenance and leave underground During the entire process of piping lane, the power supply of electrical equipment is constantly in opening, wastes substantial amounts of power consumption.
The content of the invention
The present invention provides a kind of underground pipe gallery electrical equipment power control system, to solve waste in the prior art The problem of a large amount of power consumptions.
In order to achieve the object, the technical solution that the application provides is as follows:
A kind of underground pipe gallery electrical equipment power control system, the underground pipe gallery electrical equipment control system include:NFC Mobile terminal, underground pipe gallery Tomcat-AdminPortal and the NFC smart locks being arranged on underground pipe gallery fire resistant doorsets;
The NFC smart locks are used to read the identity information of the NFC mobile terminal, and are legal in the identity information In the case of identity information, unlocking action is performed, and sends NFC intelligence to the underground pipe gallery Tomcat-AdminPortal after being unlocked Effective unlocking signal can be locked, the legal identity information is used for the legitimacy of one NFC mobile terminal of unique mark;
The NFC mobile terminal is used to reading the smart lock NFC tag informations of the NFC smart locks, and by the intelligence Lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal, and the smart lock NFC tag information is used for unique mark one A NFC smart locks;
The underground pipe gallery Tomcat-AdminPortal is used for according to the effective unlocking signal of the NFC smart locks and the intelligence NFC tag information can be locked, determines the underground pipe gallery cabin information that the NFC mobile terminal will enter and the ground that will be left Lower piping lane cabin information;And according to the underground pipe gallery cabin information that will enter, the work into the cabin that will enter The transmission of power load power supply goes code, for connecting the work power load power supply in the cabin that will enter;Foundation The underground pipe gallery cabin information that will be left, the work power load power supply into the cabin that will be left, which sends to disconnect, to be referred to Order, for disconnecting the work power load power supply in the cabin that will be left.
Preferably, further include:NFC information input terminals;
The NFC information input terminals be used for the NFC smart locks read the NFC mobile terminal identity information it Before, obtain the identity information of NFC mobile terminal;The identity information is sent to the underground pipe gallery Tomcat-AdminPortal.
Preferably, the underground pipe gallery Tomcat-AdminPortal is additionally operable to:
Judge whether the identity information is legal identity information;If it is, the identity information is stored in it is legal In identity information list.
Preferably, the NFC smart locks read the identity information of the NFC mobile terminal, and are in the identity information In the case of legal identity information, the process for performing unlocking action specifically includes:
Read the identity information of the NFC mobile terminal;The identity information is sent to underground pipe gallery management system clothes Business device;Judge the feelings that the identity information is stored in legal identity information list in the underground pipe gallery Tomcat-AdminPortal Under condition, the unlocking instruction that the underground pipe gallery Tomcat-AdminPortal is sent is received;It performs to unlock according to the unlocking instruction and move Make.
Preferably, the underground pipe gallery Tomcat-AdminPortal is additionally operable to:
Before the smart lock NFC tag information for reading the NFC smart locks in the NFC mobile terminal, moved to the NFC Dynamic terminal sends piping lane management system application program;By the piping lane management system application program to the NFC mobile terminal It sends and the relevant smart lock NFC tag information database of the NFC mobile terminal identity information.
Preferably, the NFC mobile terminal reads the smart lock NFC tag information of the NFC smart locks, and by the intelligence It NFC tag information can be locked is sent to the process of underground pipe gallery Tomcat-AdminPortal and specifically include:
The NFC mobile terminal reads the smart lock NFC tag information of the NFC smart locks;According to the smart lock NFC Piping lane management system application program is opened in label information, triggering;By the piping lane management system application program, by the intelligence Lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal.
Preferably, the NFC mobile terminal is additionally operable to:The smart lock NFC tag information is being sent to underground pipe gallery After Tomcat-AdminPortal, the NFC smart locks of the underground pipe gallery Tomcat-AdminPortal transmission are received in underground pipe gallery Location information, location information of the NFC smart locks in underground pipe gallery be the underground pipe gallery Tomcat-AdminPortal according to It is determined according to the smart lock NFC tag information.
Preferably, the NFC mobile terminal is additionally operable to:
The underground pipe gallery cabin that the NFC mobile terminal will enter is received from the underground pipe gallery Tomcat-AdminPortal Room information and the underground pipe gallery cabin information that will be left.
Preferably, the underground pipe gallery electrical equipment power control system further includes:
It is arranged in underground pipe gallery difference cabin, is used for obtaining the work of the energy information of work power load power supply Electric load electric energy meter, the work power load electric energy meter in different cabins have different identity.
Preferably, the underground pipe gallery electrical equipment power control system further includes:
Be arranged in each cabin of underground pipe gallery, for in each cabin in a dormant state in electrical equipment into The dormancy power load power supply of row power supply.
Preferably, the underground pipe gallery electrical equipment power control system further includes:
It is arranged in underground pipe gallery, for obtaining the electric energy of dormancy power load power supply in each cabin of underground pipe gallery letter The dormancy power load electric energy meter of breath.
Preferably, the underground pipe gallery Tomcat-AdminPortal is additionally operable to, and is used in the work into the cabin that will be left After electric load power supply sends open command, from the corresponding work power load electric energy meter in the cabin, the cabin is obtained Room this task power load power supply is from being switched to the energy value that is consumed in disconnection process.
A kind of underground pipe gallery electrical equipment power control system provided by the invention, the underground pipe gallery electrical equipment control System includes:NFC mobile terminal, underground pipe gallery Tomcat-AdminPortal and the NFC intelligence being arranged on underground pipe gallery fire resistant doorsets It can lock;The NFC smart locks are used to read the identity information of the NFC mobile terminal, and are legal body in the identity information In the case of part information, unlocking action is performed, and sends NFC intelligence to the underground pipe gallery Tomcat-AdminPortal after being unlocked Effective unlocking signal is locked, the legal identity information is used for the legitimacy of one NFC mobile terminal of unique mark;The NFC is moved Dynamic terminal is used to read the smart lock NFC tag information of the NFC smart locks, and the smart lock NFC tag information is sent To underground pipe gallery Tomcat-AdminPortal, the smart lock NFC tag information is used for one NFC smart lock of unique mark;It is described Underground pipe gallery Tomcat-AdminPortal is used for according to the effective unlocking signal of the NFC smart locks and the smart lock NFC label Information determines the underground pipe gallery cabin information that the NFC mobile terminal will enter and the underground pipe gallery cabin that will be left Information;And according to the underground pipe gallery cabin information that will enter, the work power load electricity into the cabin that will enter Source sends and goes code, for connecting the work power load power supply in the cabin that will enter;It will be from according to described in The underground pipe gallery cabin information opened, the work power load power supply into the cabin that will be left sends open command, for breaking Open the work power load power supply in the cabin that will be left.Pass through NFC mobile terminal in the embodiment of the present invention and NFC intelligence Mutual identification between locking, generates the effective unlocking signal of NFC smart locks and the smart lock NFC tag information, buried pipe Corridor Tomcat-AdminPortal is determined according to the effective unlocking signal of the NFC smart locks and the smart lock NFC tag information The underground pipe gallery cabin information that NFC mobile terminal will enter, and the work in the cabin that will enter described in connection immediately is used Electric load power supply and the definite underground pipe gallery cabin information that will be left, disconnect the work in the cabin that will be left immediately Power load power supply, so as to save power consumption.
Description of the drawings
It in order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention, for those of ordinary skill in the art, without creative efforts, can be with Other attached drawings are obtained according to these attached drawings.
Fig. 1 (a) is the sectional schematic diagram for certain Urban Underground piping lane that the prior art provides;
Fig. 1 (b) is the floor map for certain Urban Underground piping lane that the prior art provides;
Fig. 2 is certain Urban Underground piping lane daily management schematic diagram that the prior art provides;
Fig. 3 is the structure diagram of underground pipe gallery access control system provided in an embodiment of the present invention;
Fig. 4 is between underground pipe gallery bay section disclosed by the embodiments of the present invention and underground pipe gallery Tomcat-AdminPortal 110 Relation schematic diagram;
Fig. 5 be the embodiment of the present invention disclosed in underground pipe gallery electrical equipment power control system with it is each in underground pipe gallery Electrical equipment carries out information exchange schematic diagram.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, below in conjunction with the accompanying drawings to the present invention Specific embodiment be described in detail.
The present invention provides a kind of underground pipe gallery electrical equipment power control system, to solve waste in the prior art The problem of a large amount of power consumptions.Referring to Fig. 3, which can include:NFC (Near Field Communication, closely Wireless communication technique) mobile terminal 100, it underground pipe gallery Tomcat-AdminPortal 110 and is arranged on underground pipe gallery fire resistant doorsets NFC smart locks 120;It should be noted that the underground pipe gallery Tomcat-AdminPortal 110 in the embodiment of the present invention can be set In piping lane control centre, it is connected by wired or wireless network with NFC mobile terminal 100 and NFC smart locks 120.NFC is moved Dynamic terminal 100 is carried at piping lane scene by pipeline maintenance personnel, can be configured in NFC mobile terminal 100 and NFC smart locks 120 NFC reader or the related software with NFC read functions, NFC mobile terminal 100 can be mobile phone, PC (Personal Computer, personal computer) machine, tablet computer etc., the embodiment of the present invention is not specifically limited.
The NFC smart locks 120 are used to read the identity information of the NFC mobile terminal 100, and in the identity information In the case of legal identity information, unlocking action is performed, and after being unlocked to the underground pipe gallery Tomcat-AdminPortal 110 The effective unlocking signal of NFC smart locks is sent, the legal identity information is legal for one NFC mobile terminal of unique mark Property;
It should be noted that the identity information of the NFC mobile terminal 100 includes:The NFC label of NFC mobile terminal 100 Information, owner's name of NFC mobile terminal 100, the owner affiliated function of NFC mobile terminal 100, NFC mobile terminal 100 come At least one of electric number and the MAC Address of NFC mobile terminal 100, as having recorded NFC mobile terminal 100 in the following table 1 Identity information:
Mobile phone NFC label ID Owner affiliated function Owner's name Phone number Mobile phone MAC Address
NF.1 D.1 H.1 A.1 MAC.1
NF.2 D.2 H.2 A.2 MAC.2
NF.3 D.3 H.3 A.3 MAC.3
Table 1
It should be noted that the Wireless Communication Equipment of piping lane can judge piping lane service personnel by the MAC Address in table 1 Identity information, the IP address of router on the ground accessed by piping lane service personnel mobile phone judge piping lane service personnel position.
The NFC mobile terminal 100 is used to reading the smart lock NFC tag informations of the NFC smart locks 120, and by institute It states smart lock NFC tag information and is sent to underground pipe gallery Tomcat-AdminPortal 110, the smart lock NFC tag information is used for One NFC smart lock of unique mark;
Optionally, the two sides of NFC smart locks 120 is respectively equipped with A faces smart lock NFC tag information, B faces smart lock NFC marks Information is signed, there are quarantine measures between two labels, to ensure that NFC mobile terminal 100, can only in A faces brush NFC smart locks 120 Read the smart lock NFC tag information in A faces;When NFC mobile terminal 100 brushes NFC smart locks 120 in B faces, B can only be read The smart lock NFC tag information in face.There is unlocking executing agency in smart lock, equipped with enabling identification device, each fire resistant doorsets are being opened After can be automatically closed or be delayed and be automatically closed after a certain period of time, be not specifically limited in the embodiment of the present invention.
It should be noted that the NFC smart locks 120 disclosed in the embodiment of the present invention read the NFC mobile terminal 100 The process and NFC mobile terminal 100 of identity information read the process of the smart lock NFC tag information of NFC smart locks 120 regardless of Sequencing, can be when NFC mobile terminal 100 brushes NFC smart lock 120, and two processes perform simultaneously, i.e., user uses While NFC mobile terminal 100 brushes 120 unlocking of NFC smart locks, NFC mobile terminal 100 can also read NFC smart locks 120 NFC tag information.
The underground pipe gallery Tomcat-AdminPortal 110 be used for according to 120 effective unlocking signal of NFC smart locks and The smart lock NFC tag information determines underground pipe gallery cabin information that the NFC mobile terminal 100 will enter and i.e. The underground pipe gallery cabin information that will be left;And according to the underground pipe gallery cabin information that will enter, to the cabin that will enter Work power load power supply transmission in room goes code, for connecting the work power load in the cabin that will enter Power supply;The underground pipe gallery cabin information that will be left according to described in, the work power load power supply into the cabin that will be left Open command is sent, for disconnecting the work power load power supply in the cabin that will be left.
It should be noted that power load is divided into dormancy power load and work electricity consumption in piping lane in the embodiment of the present invention Load is powered respectively by the different power supply of two-way, and the work in the cabin that will enter described in connection in the embodiment of the present invention is used After electric load power supply, the state for there are pipeline maintenance personnel to work normally requirement in piping lane is met using the live load of electric equipment; After work power load power supply in the cabin that will be left described in disconnection, meet satisfaction using the work of electric equipment and maintain piping lane The state of safe minimum requirements.
Such as:Piping lane 1# bay sections have 3 ventilation blowers, and 40 lamps, by code requirement, maintaining the power consumption of piping lane safety only needs 1 Platform ventilation blower timing working, 10 lamp illuminations;And have maintenance personal into fashionable, then 40 lamps is needed to illuminate entirely, 3 ventilation blowers are complete It opens.
It should be noted that in the embodiment of the present invention, the work power load electricity in the cabin that will enter described in connection Source is sent to the partial illumination equipment of phase emergency chamber, ventilation equipment, the network equipment, monitoring device and maintenance power-supply device etc. Electricity;So that the electrical energy measurement subsystem in phase emergency chamber disappears each subsystem electric energy after pipeline maintenance personnel enter is measured Consumption, and power consumption and pipeline maintenance personnel are corresponded into department information and are sent to underground pipe gallery Tomcat-AdminPortal 110, ground Accumulation corresponds to department to pipeline maintenance personnel after the power consumption is converted to the electricity charge by lower piping lane Tomcat-AdminPortal 110 In electricity bill, it is achieved thereby that the accurate calculating of energy consumption, and overhaul the metering that the related electricity charge are accurate to department.
A kind of underground pipe gallery electrical equipment power control system provided by the invention, the underground pipe gallery electrical equipment control System includes:NFC mobile terminal, underground pipe gallery Tomcat-AdminPortal and the NFC intelligence being arranged on underground pipe gallery fire resistant doorsets It can lock;The NFC smart locks are used to read the identity information of the NFC mobile terminal, and are legal body in the identity information In the case of part information, unlocking action is performed, and sends NFC intelligence to the underground pipe gallery Tomcat-AdminPortal after being unlocked Effective unlocking signal is locked, the legal identity information is used for the legitimacy of one NFC mobile terminal of unique mark;The NFC is moved Dynamic terminal is used to read the smart lock NFC tag information of the NFC smart locks, and the smart lock NFC tag information is sent To underground pipe gallery Tomcat-AdminPortal, the smart lock NFC tag information is used for one NFC smart lock of unique mark;It is described Underground pipe gallery Tomcat-AdminPortal is used for according to the effective unlocking signal of the NFC smart locks and the smart lock NFC label Information determines the underground pipe gallery cabin information that the NFC mobile terminal will enter and the underground pipe gallery cabin that will be left Information;And according to the underground pipe gallery cabin information that will enter, the work power load electricity into the cabin that will enter Source sends and goes code, for connecting the work power load power supply in the cabin that will enter;It will be from according to described in The underground pipe gallery cabin information opened, the work power load power supply into the cabin that will be left sends open command, for breaking Open the work power load power supply in the cabin that will be left.Pass through NFC mobile terminal in the embodiment of the present invention and NFC intelligence Mutual identification between locking, generates the effective unlocking signal of NFC smart locks and the smart lock NFC tag information, buried pipe Corridor Tomcat-AdminPortal is determined according to the effective unlocking signal of the NFC smart locks and the smart lock NFC tag information The underground pipe gallery cabin information that NFC mobile terminal will enter, and the work in the cabin that will enter described in connection immediately is used Electric load power supply and the definite underground pipe gallery cabin information that will be left, disconnect the work in the cabin that will be left immediately Power load power supply so as to save power consumption, realizes the low cost operation of underground pipe gallery.
Fig. 4 is between underground pipe gallery bay section disclosed by the embodiments of the present invention and underground pipe gallery Tomcat-AdminPortal 110 Relation schematic diagram, to underground pipe gallery electricity consumption in the above-mentioned underground pipe gallery electrical equipment control system disclosed in the embodiment of the present invention The method that equipment is controlled is applied in the following electrical equipment disclosed in underground pipe gallery:
Underground pipe gallery pipeline cabin is divided into multiple bay sections, it is necessary to explanation, city integrated pipe by fire separation and fire resistant doorsets Corridor engineering legislation GB50838-2015 provides that the cabin of natural gas line cabin and receiving power cable should be used every 200m Noninflammability wall of the fire endurance not less than 3.0h carries out fire separation.Door at fire separation should use first class fire resistant doorsets etc.. The situation of remaining bay section of underground pipe gallery pipeline cabin as shown in Figure 4 is the same as pipeline cabin 1# bay sections;Remaining cabin (such as natural gas cabin, Electric compartment) situation with pipeline cabin.
Equipment includes at least illumination, ventilation, monitoring camera-shooting, gate inhibition, the maintenance shown in Fig. 4 in the 1# bay sections of piping lane pipeline cabin The equipment such as power supply, wireless network, electrical energy measurement.
As shown in figure 4, J11, J12 represent maintenance power box, D11~D1n represents illuminator, and F11 represents ventilation blower, L11, L12 represent wireless router, and S11, S12 represent camera, and M1, M2 represent NFC smart locks, and KJ11, KJ12 represent maintenance Power contactor, KF represent ventilation blower contactor, and KD represents light switch, and CJ represents bay section electrical energy measurement, and A represents NFC intelligence Mobile phone.
Pipeline cabin as shown in Figure 4 1# bay sections, which belong to repair apparatus, to be included:NFC maintenance power box J11, J12, maintenance power box Corresponding power circuit, each NFC maintenance power boxes correspond to maintenance power contactor KJ11, a KJ12, corresponding signal line with And corresponding underground pipe gallery management system hardware and software.
Pipeline cabin as shown in Figure 4 1# bay sections, which belong to lighting apparatus, to be included:Illuminator D11~D1n, each bay section headlamp The corresponding light switch KD of tool, corresponding signal line and corresponding underground pipe gallery management system hardware and software.
Pipeline cabin as shown in Figure 4 1# bay sections, which belong to ventilation equipment, includes ventilation blower F11, and ventilation blower corresponds to ventilation blower contactor KF, ventilation equipment further include:Corresponding signal line and corresponding underground pipe gallery management system hardware and software.
Pipeline cabin 1# bay sections as shown in Figure 4, which belong to access control equipment, to be included:NFC smart lock M1, M2, corresponding signal line, And corresponding piping lane management system hardware and software.
Pipeline cabin 1# bay sections as shown in Figure 4 belong to monitoring, the network equipment includes:Camera S11, S12, wireless router L11, L12, monitoring, the corresponding contactor KL of the network equipment and corresponding underground pipe gallery management system hardware and software.
Belonging to electric energy measuring equipment in the 1# bay sections of pipeline cabin as shown in Figure 4 includes:Bay section electric energy meter CJ and correspondence Underground pipe gallery manages system hardware and software.
Optionally, each section underground pipe gallery control subsystem is further included in the embodiment of the present invention, for city Zhong Ge roads The corresponding underground pipe gallery of section is controlled, and each section underground pipe gallery control subsystem can be distributed in city different geographical Different sections of highway carries out information exchange, buried pipe with underground pipe gallery Tomcat-AdminPortal 110 by cable network or wireless network The wake-up instruction and dormancy instruction that electrical equipment of the corridor Tomcat-AdminPortal 110 into cabin is sent can pass through each road Section underground pipe gallery control subsystem carries out signal transfer.NFC smart locks are sent to the underground pipe gallery Tomcat-AdminPortal The NFC tag information that the effective unlocking signal of FC smart locks and the downward piping lane Tomcat-AdminPortal of NFC mobile terminal are sent To carry out signal transfer by each section underground pipe gallery control subsystem.Each section underground pipe gallery control in the embodiment of the present invention Subsystem can also be integrated in underground pipe gallery Tomcat-AdminPortal 110, be in underground pipe gallery Tomcat-AdminPortal 110 One subsystem.
Optionally, the underground pipe gallery electrical equipment control system in the embodiment of the present invention further includes:NFC data inputs are whole End, the NFC information input terminals can be arranged on different location, for example, can be arranged on pipeline affiliated function, piping lane scene, Piping lane control centre etc., the embodiment of the present invention is not specifically limited.NFC information input terminals can be configured with NFC reader Or possess the tablet computer, mobile phone or PC machine of the related software of NFC read functions;The NFC information input terminals pass through wired Network or wireless network communicate with underground pipe gallery Tomcat-AdminPortal 110.
The NFC information input terminals be used for the NFC smart locks read the NFC mobile terminal identity information it Before, obtain the identity information of NFC mobile terminal;The identity information is sent to the underground pipe gallery Tomcat-AdminPortal 110, all legal cellphone informations are sent to each section underground pipe gallery and control subsystem by underground pipe gallery Tomcat-AdminPortal 110 System.Wherein, NFC can be moved eventually at NFC information input terminals site scene by technical staff in the embodiment of the present invention The identity information typing NFC information input terminals at end can also be recorded by NFC mobile terminal 100 by network transmission to NFC information Enter terminal, the embodiment of the present invention is not specifically limited.
It should be noted that the underground pipe gallery Tomcat-AdminPortal 110 is additionally operable to:
Judge whether the identity information is legal identity information;If it is, the identity information is stored in it is legal In identity information list.
The NFC smart locks 120 read the identity information of the NFC mobile terminal 100, and are conjunction in the identity information In the case of method identity information, the process for performing unlocking action specifically includes:
Read the identity information of the NFC mobile terminal 100;The identity information is sent to underground pipe gallery management system Server 110;Judge that the identity information is stored in legal identity information row in the underground pipe gallery Tomcat-AdminPortal 110 In the case of in table, the unlocking instruction that the underground pipe gallery Tomcat-AdminPortal 110 is sent is received;According to the unlocking instruction Perform unlocking action.
The underground pipe gallery Tomcat-AdminPortal 110 is additionally operable to:
Before the smart lock NFC tag information for reading the NFC smart locks 120 in the NFC mobile terminal 100, to institute It states NFC mobile terminal 100 and sends piping lane management system application program;By the piping lane management system application program to described NFC mobile terminal 100 is sent and the relevant smart lock NFC tag information database of 100 identity information of NFC mobile terminal, Underground pipe gallery Tomcat-AdminPortal 110 is periodically updated smart lock NFC tag information database.
Optionally, underground pipe gallery Tomcat-AdminPortal 110 is moved eventually by cable network or wireless network to the NFC End 100 sends piping lane management system application program.
The NFC mobile terminal 100 reads the smart lock NFC tag information of the NFC smart locks 120, and by the intelligence It NFC tag information can be locked is sent to the process of underground pipe gallery Tomcat-AdminPortal 110 and specifically include:
The NFC mobile terminal 100 reads the smart lock NFC tag information of the NFC smart locks 120;According to the intelligence NFC tag information can be locked, piping lane management system application program is opened in triggering;It, will by the piping lane management system application program The smart lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal 110.
The NFC mobile terminal 100 is additionally operable to:The smart lock NFC tag information is being sent to underground pipe gallery management After system server 110, the NFC smart locks 120 of the transmission of underground pipe gallery Tomcat-AdminPortal 110 are received in buried pipe Location information in corridor, location information of the NFC smart locks 120 in underground pipe gallery are the underground pipe gallery management system clothes Business device 110 determines that optionally, the NFC smart locks 120 are in underground pipe gallery according to the smart lock NFC tag information Location information position, embodiment of the present invention such as can be piping lane section, cabin, bay section be not specifically limited.
The NFC mobile terminal 100 is additionally operable to:The NFC is received from the underground pipe gallery Tomcat-AdminPortal to move The dynamic underground pipe gallery cabin information that will enter of terminal 100 and the underground pipe gallery cabin information that will be left.
The underground pipe gallery electrical equipment power control system further includes:
It is arranged in underground pipe gallery difference cabin, is used for obtaining the work of the energy information of work power load power supply Electric load electric energy meter, the work power load electric energy meter in different cabins have different identity.
The underground pipe gallery electrical equipment power control system further includes:
Be arranged in each cabin of underground pipe gallery, for in each cabin in a dormant state in electrical equipment into The dormancy power load power supply of row power supply.
The underground pipe gallery electrical equipment power control system further includes:
It is arranged in underground pipe gallery, for obtaining the electric energy of dormancy power load power supply in each cabin of underground pipe gallery letter The dormancy power load electric energy meter of breath.
The underground pipe gallery Tomcat-AdminPortal is additionally operable to, in the work power load electricity into the cabin that will be left After source sends open command, from the corresponding work power load electric energy meter in the cabin, this work of the cabin is obtained Make power load power supply from the energy value that is consumed in disconnection process is switched to, so as to according to cabin this task power load power supply From being switched to the energy value that is consumed in disconnection process, generation for the electricity bill having into piping lane all departments, so as to fulfill Accurate management to the power consumption of underground pipe gallery operation cost.
It should be noted that the electric energy in dormancy power load electric energy meter and work power load electric energy meter Consumption is both needed to be sent to underground pipe gallery Tomcat-AdminPortal 110, can first be sent to respective stretch underground pipe gallery control system, Underground pipe gallery Tomcat-AdminPortal 110 is sent to by respective stretch underground pipe gallery control system again.
It should be noted that in the embodiment of the present invention, piping lane maintenance personnel can be obtained by NFC smart locks 120 in phase Piping lane maintenance personnel is first sent to respective stretch buried pipe the residence time in phase emergency chamber by the residence time in emergency chamber Corridor control system, then underground pipe gallery Tomcat-AdminPortal 110 is sent to by respective stretch underground pipe gallery control system.
Urban Underground piping lane Tomcat-AdminPortal according to each section underground pipe gallery control subsystem transmission come into pipe Identity information, location information, residence time information and each electrical energy measurement meter reading, each electric energy meter body of corridor maintenance personnel Part generation all departments electricity bill, and electricity bill is sent to corresponding department.It is achieved thereby that the accurate calculating of energy consumption, and The related electricity charge of maintenance are accurate to the metering of department, realize the accurate management to the power consumption of underground pipe gallery operation cost.
With a specific application scenarios, the present invention will be described in detail that above-mentioned underground pipe gallery electricity consumption disclosed in embodiment is set below Standby application of the control system in underground pipe gallery:
As shown in figure 5, it is underground pipe gallery electrical equipment power control system and buried pipe disclosed in the embodiment of the present invention Each electrical equipment carries out information exchange schematic diagram in corridor, and Urban Underground piping lane Tomcat-AdminPortal corresponds to the ground of different sections of highway Lower piping lane control system, as shown piping lane power consumption classification situation in the following table 2,
Table 2
Such as piping lane 1# bay sections have 3 ventilation blowers, 40 lamps, by code requirement, maintaining the power consumption of piping lane safety only needs 1 Ventilation blower timing working, 10 lamp illuminations;And have maintenance personnel into fashionable, then 40 lamps is needed to illuminate entirely, 3 ventilation blower standard-sized sheets. According to system shown in Figure 5, then 1 Fans, 10 lamps are powered by dormancy power circuit in 1# bay sections, remaining 2 Fans, 30 lamps It is powered by work power load power circuit.Each bay section load sharing of X roads underground pipe gallery is dormancy power load and work Power load is powered by two different switches.X roads each bay section of underground pipe gallery dormancy power load can be measured with shared with electric energy Table, X roads underground pipe gallery work each bay section of power load are respectively provided with electric energy meter, and each electrical energy measurement has unique identity to believe Breath.The power consumption of each electric energy meter metering is sent to X roads underground pipe gallery control system.X roads underground pipe gallery access control system X roads underground pipe gallery control system will be sent into piping lane personnel location information, identity information, residence time information.X roads underground Piping lane control system connects the related switch (K1a, K2a ... wait switch in Fig. 4) of each bay section dormancy load, X roads buried pipe pipe for a long time Corridor control system transmits information according to access control system, connect the bay section that someone enters the related switch of live load (K1b in Fig. 4, K2b ... waits switch).X roads underground pipe gallery control system by each metering ammeter power consumption, into piping lane personnel location information, body Part information, residence time information are sent to Urban Underground piping lane Tomcat-AdminPortal.The situation in Y sections is the same as X sections.
Urban Underground piping lane Tomcat-AdminPortal according to each section control system transmit come the body into piping lane personnel Part information, location information, residence time information and each electrical energy measurement meter reading, each electric energy meter identity generation all departments electricity Take bill, and electricity bill is sent to corresponding department.Dormancy circuit electrical energy measurement adds up runs power consumption, power consumption data into piping lane It is sent to underground pipe gallery Tomcat-AdminPortal, underground pipe gallery Tomcat-AdminPortal generation piping lane operation electricity bill, X bay sections Power consumption is included in piping lane work power consumption, adds up into personnel affiliated function piping lane work power consumption, power consumption data are sent to buried pipe Corridor Tomcat-AdminPortal, underground pipe gallery Tomcat-AdminPortal are generated into personnel department piping lane work electricity bill.The electricity charge It is as shown in table 3 to measure each side's relation:
Table 3
In summary:
A kind of underground pipe gallery electrical equipment power control system provided by the invention, the underground pipe gallery electrical equipment control System includes:NFC mobile terminal, underground pipe gallery Tomcat-AdminPortal and the NFC intelligence being arranged on underground pipe gallery fire resistant doorsets It can lock;The NFC smart locks are used to read the identity information of the NFC mobile terminal, and are legal body in the identity information In the case of part information, unlocking action is performed, and sends NFC intelligence to the underground pipe gallery Tomcat-AdminPortal after being unlocked Effective unlocking signal is locked, the legal identity information is used for the legitimacy of one NFC mobile terminal of unique mark;The NFC is moved Dynamic terminal is used to read the smart lock NFC tag information of the NFC smart locks, and the smart lock NFC tag information is sent To underground pipe gallery Tomcat-AdminPortal, the smart lock NFC tag information is used for one NFC smart lock of unique mark;It is described Underground pipe gallery Tomcat-AdminPortal is used for according to the effective unlocking signal of the NFC smart locks and the smart lock NFC label Information determines the underground pipe gallery cabin information that the NFC mobile terminal will enter and the underground pipe gallery cabin that will be left Information;And according to the underground pipe gallery cabin information that will enter, the work power load electricity into the cabin that will enter Source sends and goes code, for connecting the work power load power supply in the cabin that will enter;It will be from according to described in The underground pipe gallery cabin information opened, the work power load power supply into the cabin that will be left sends open command, for breaking Open the work power load power supply in the cabin that will be left.Pass through NFC mobile terminal in the embodiment of the present invention and NFC intelligence Mutual identification between locking, generates the effective unlocking signal of NFC smart locks and the smart lock NFC tag information, buried pipe Corridor Tomcat-AdminPortal is determined according to the effective unlocking signal of the NFC smart locks and the smart lock NFC tag information The underground pipe gallery cabin information that NFC mobile terminal will enter, and the work in the cabin that will enter described in connection immediately is used Electric load power supply and the definite underground pipe gallery cabin information that will be left, disconnect the work in the cabin that will be left immediately Power load power supply, so as to save power consumption.
The above described is only a preferred embodiment of the present invention, not make limitation in any form to the present invention.Though So the present invention is disclosed above with preferred embodiment, however is not limited to the present invention.It is any to be familiar with those skilled in the art Member, without departing from the scope of the technical proposal of the invention, all using the methods and technical content of the disclosure above to the present invention Technical solution makes many possible changes and modifications or is revised as the equivalent embodiment of equivalent variations.Therefore, it is every without departing from The content of technical solution of the present invention, technical spirit according to the invention is to any simple modification made for any of the above embodiments, equivalent Variation and modification, still fall within technical solution of the present invention protection in the range of.

Claims (13)

  1. A kind of 1. underground pipe gallery electrical equipment power control system, which is characterized in that the underground pipe gallery electrical equipment control system System includes:NFC mobile terminal, underground pipe gallery Tomcat-AdminPortal and the NFC intelligence being arranged on underground pipe gallery fire resistant doorsets Lock;
    The NFC smart locks are used to read the identity information of the NFC mobile terminal, and are legal identity in the identity information In the case of information, unlocking action is performed, and sends NFC smart locks to the underground pipe gallery Tomcat-AdminPortal after being unlocked Effective unlocking signal, the legal identity information are used for the legitimacy of one NFC mobile terminal of unique mark;
    The NFC mobile terminal is used to reading the smart lock NFC tag informations of the NFC smart locks, and by the smart lock NFC Label information is sent to underground pipe gallery Tomcat-AdminPortal, and the smart lock NFC tag information is used for one NFC of unique mark Smart lock;
    The underground pipe gallery Tomcat-AdminPortal is used for according to the effective unlocking signal of the NFC smart locks and the smart lock NFC tag information determines the underground pipe gallery cabin information that the NFC mobile terminal will enter and the buried pipe that will be left Corridor cabin information;And according to the underground pipe gallery cabin information that will enter, the work electricity consumption into the cabin that will enter Load power transmission goes code, for connecting the work power load power supply in the cabin that will enter;According to described in The underground pipe gallery cabin information that will be left, the work power load power supply into the cabin that will be left send open command, For disconnecting the work power load power supply in the cabin that will be left.
  2. 2. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that further include:NFC believes Cease typing terminal;
    The NFC information input terminals are used for before the identity information for reading the NFC mobile terminal in the NFC smart locks, Obtain the identity information of NFC mobile terminal;The identity information is sent to the underground pipe gallery Tomcat-AdminPortal.
  3. 3. underground pipe gallery electrical equipment power control system according to claim 2, which is characterized in that the underground pipe gallery Tomcat-AdminPortal is additionally operable to:
    Judge whether the identity information is legal identity information;If it is, the identity information is stored in legal identity In information list.
  4. 4. underground pipe gallery electrical equipment power control system according to claim 3, which is characterized in that the NFC intelligence Lock reads the identity information of the NFC mobile terminal, and in the case where the identity information is legal identity information, execution is opened The process of lock action specifically includes:
    Read the identity information of the NFC mobile terminal;The identity information is sent to underground pipe gallery Tomcat-AdminPortal; In the case where the underground pipe gallery Tomcat-AdminPortal judges that the identity information is stored in legal identity information list, Receive the unlocking instruction that the underground pipe gallery Tomcat-AdminPortal is sent;Unlocking action is performed according to the unlocking instruction.
  5. 5. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that the underground pipe gallery Tomcat-AdminPortal is additionally operable to:
    Before the smart lock NFC tag information for reading the NFC smart locks in the NFC mobile terminal, moved eventually to the NFC End sends piping lane management system application program;It is sent by the piping lane management system application program to the NFC mobile terminal With the relevant smart lock NFC tag information database of the NFC mobile terminal identity information.
  6. 6. underground pipe gallery electrical equipment power control system according to claim 5, which is characterized in that
    The NFC mobile terminal reads the smart lock NFC tag information of the NFC smart locks, and by the smart lock NFC label The process that information is sent to underground pipe gallery Tomcat-AdminPortal specifically includes:
    The NFC mobile terminal reads the smart lock NFC tag information of the NFC smart locks;According to the smart lock NFC label Piping lane management system application program is opened in information, triggering;By the piping lane management system application program, by the smart lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal.
  7. 7. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that the NFC movements Terminal is additionally operable to:After the smart lock NFC tag information is sent to underground pipe gallery Tomcat-AdminPortal, described in reception Location information of the NFC smart locks that underground pipe gallery Tomcat-AdminPortal is sent in underground pipe gallery, the NFC smart locks are on ground Location information in lower piping lane is that the underground pipe gallery Tomcat-AdminPortal is determined according to the smart lock NFC tag information 's.
  8. 8. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that the NFC movements Terminal is additionally operable to:
    The underground pipe gallery cabin letter that the NFC mobile terminal will enter is received from the underground pipe gallery Tomcat-AdminPortal Breath and the underground pipe gallery cabin information that will be left.
  9. 9. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that the underground pipe gallery Electrical equipment power control system further includes:
    It is arranged in underground pipe gallery difference cabin, the work electricity consumption for obtaining the energy information of work power load power supply is born Lotus electric energy meter, the work power load electric energy meter in different cabins have different identity.
  10. 10. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that the buried pipe Corridor electrical equipment power control system further includes:
    Be arranged in each cabin of underground pipe gallery, for in each cabin in a dormant state in electrical equipment supply The dormancy power load power supply of electricity.
  11. 11. underground pipe gallery electrical equipment power control system according to claim 10, which is characterized in that the buried pipe Corridor electrical equipment power control system further includes:
    It is arranged in underground pipe gallery, for obtaining the energy information of dormancy power load power supply in each cabin of underground pipe gallery Dormancy power load electric energy meter.
  12. 12. underground pipe gallery electrical equipment power control system according to claim 9, which is characterized in that
    The underground pipe gallery Tomcat-AdminPortal is additionally operable to, in the work power load power supply hair into the cabin that will be left After sending open command, from the corresponding work power load electric energy meter in the cabin, obtain described this task of cabin and use Electric load power supply is from being switched to the energy value that is consumed in disconnection process.
  13. 13. underground pipe gallery electrical equipment power control system according to claim 1, which is characterized in that further include:Each road Section underground pipe gallery control subsystem, for NFC smart lock of the transfer in corresponding road section underground pipe gallery and underground pipe gallery management system The signal transferred between system server;And NFC mobile terminal of the transfer in corresponding road section underground pipe gallery and underground pipe gallery pipe The signal transferred between reason system server;And transfer is in underground pipe gallery Tomcat-AdminPortal and corresponding road section underground pipe gallery The signal transferred between work power load power supply in cabin.
CN201611033878.0A 2016-11-22 2016-11-22 Power supply control system for electrical equipment of underground pipe gallery Active CN108091008B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611033878.0A CN108091008B (en) 2016-11-22 2016-11-22 Power supply control system for electrical equipment of underground pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611033878.0A CN108091008B (en) 2016-11-22 2016-11-22 Power supply control system for electrical equipment of underground pipe gallery

Publications (2)

Publication Number Publication Date
CN108091008A true CN108091008A (en) 2018-05-29
CN108091008B CN108091008B (en) 2021-04-20

Family

ID=62168542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611033878.0A Active CN108091008B (en) 2016-11-22 2016-11-22 Power supply control system for electrical equipment of underground pipe gallery

Country Status (1)

Country Link
CN (1) CN108091008B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793966A (en) * 2012-11-02 2014-05-14 南京物联传感技术有限公司 NFC based door lock control system and method thereof
CN103940056A (en) * 2014-03-27 2014-07-23 广东美的制冷设备有限公司 Door control equipment, mobile terminal, server, air conditioning system and control method
CN104700230A (en) * 2015-03-26 2015-06-10 中山睿点智能科技有限公司 Self-service check-in smart hotel control system and switching on and off control method thereof
CN105184912A (en) * 2015-07-15 2015-12-23 深圳市物联锁科技有限公司 Intelligent lock monitoring system based on Internet of Things and intelligent lock
CN105844753A (en) * 2016-04-11 2016-08-10 福建三鑫隆信息技术开发股份有限公司 An intelligent well lid electronic lock with lid-opening alarming

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103793966A (en) * 2012-11-02 2014-05-14 南京物联传感技术有限公司 NFC based door lock control system and method thereof
CN103940056A (en) * 2014-03-27 2014-07-23 广东美的制冷设备有限公司 Door control equipment, mobile terminal, server, air conditioning system and control method
CN104700230A (en) * 2015-03-26 2015-06-10 中山睿点智能科技有限公司 Self-service check-in smart hotel control system and switching on and off control method thereof
CN105184912A (en) * 2015-07-15 2015-12-23 深圳市物联锁科技有限公司 Intelligent lock monitoring system based on Internet of Things and intelligent lock
CN105844753A (en) * 2016-04-11 2016-08-10 福建三鑫隆信息技术开发股份有限公司 An intelligent well lid electronic lock with lid-opening alarming

Also Published As

Publication number Publication date
CN108091008B (en) 2021-04-20

Similar Documents

Publication Publication Date Title
EP0619537B1 (en) A method of operating a plurality of ultilities, a utilities network system for carrying out the method and a control device for such a network
CN103793857A (en) Electric power field operating system combined with smartphone
CN106211518A (en) A kind of intelligent city's means of illumination and system
CN102169611A (en) Large self-service intelligent network group charging equipment and guide system for building parking lot
CN110084946B (en) System and method for five-prevention locking based on wearable equipment
CN203480566U (en) Integrated intelligent locking and controlling management system for power transformation and distribution equipment
CN205232362U (en) Property equipment intelligent monitoring system
CN108320076A (en) Bridge structure safe information platform
CN109919451A (en) Based on true power network topology analysis and security knowledge base digital electric network system and method
JP2009024404A (en) Environment management system
CN110137940A (en) A kind of intelligent electric power managing and control system based on mobile visualization
CN108091006A (en) A kind of underground pipe gallery electrical equipment control system
CN107545373A (en) A kind of municipal information analysis and security evaluation management system
CN106126694A (en) The support of a kind of impurely Rehabilitation decision and the construction method of online evaluation platform
CN113949723A (en) Heterogeneous compatible system of thing networking sign for management of wisdom community
CN108091008A (en) A kind of underground pipe gallery electrical equipment power control system
Bhasin et al. Smart city implementation model based on IoT
CN205158452U (en) Railway upper track operation safety control system
Clos The transformation of Poblenou: the new 22@ district
CN206517643U (en) A kind of Lighting Control Assembly based on POE technologies
CN108985541A (en) A kind of comprehensive wisdom operation management system of underground pipe gallery
KR20220165671A (en) System for providing electric vehicle charing service for co-operative housing
Alba Intelligent systems for smart cities
CN105259857B (en) A kind of railway acquisition station computer room supervisory systems
CN108736571A (en) Protective relaying device intelligent management system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant