CN108086608A - A kind of steel structure stairway is marked time the construction method of prefabricated facing - Google Patents

A kind of steel structure stairway is marked time the construction method of prefabricated facing Download PDF

Info

Publication number
CN108086608A
CN108086608A CN201711359103.7A CN201711359103A CN108086608A CN 108086608 A CN108086608 A CN 108086608A CN 201711359103 A CN201711359103 A CN 201711359103A CN 108086608 A CN108086608 A CN 108086608A
Authority
CN
China
Prior art keywords
grc
layer
construction
base
thickness
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711359103.7A
Other languages
Chinese (zh)
Inventor
冯刚
刘雪明
常建新
邓旭
张进财
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Shougang Construction Group Co Ltd
Original Assignee
Beijing Shougang Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Shougang Construction Group Co Ltd filed Critical Beijing Shougang Construction Group Co Ltd
Priority to CN201711359103.7A priority Critical patent/CN108086608A/en
Publication of CN108086608A publication Critical patent/CN108086608A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/104Treads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/104Treads
    • E04F11/16Surfaces thereof; Protecting means for edges or corners thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • E04F11/104Treads
    • E04F11/16Surfaces thereof; Protecting means for edges or corners thereof
    • E04F11/17Surfaces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

A kind of steel structure stairway is marked time the construction method of prefabricated facing, belongs to steel structure stairway technical field of construction.Step includes component entry test, prepares construction material and construction equipment;The dirt of base is removed, the acrylic type gluing oxidant layer of one layer of 1~2mm thickness is uniformly smeared in substrate surface;Rubber slab protective layer is covered, and pops up horizontal line, vertical line and GRC product location lines;GRC cover boards are carried out to fix, weld;GRC products are hung, seam crossing adds acrylic type adhesive using cement mortar;One layer of 3~6mm thickness rubber slab is padded in GRC products and base junction.The advantage is that with total quality is light, combination flexibly, convenient and quick construction, without secondary decoration, be easy to be consistent with periphery decoration style.

Description

A kind of steel structure stairway is marked time the construction method of prefabricated facing
Technical field
The invention belongs to steel structure stairway technical field of construction, more particularly to a kind of steel structure stairway is marked time prefabricated facing Construction method.Be suitable for it is various under the conditions of, the old steel structure stairway of the utilization of all kinds of decorated styles mark time cover glass fiber increasing The installation of reinforced concrete (GRC) plate of material, fixed construction method.
Background technology
Architecture indoor is fitted up at present, especially the fitting-out work of higher gears, and GRC is to be equipped with GRC addition materials with cement mortar The inorganic composite materials that material makees base material, glass fibre is reinforcing material.GRC possesses concrete and cement mortar can not have Good characteristic, such as tensile strength, crack resistance are good, product is thin, good from heavy and light, impact resistance, it is same with concrete and cement mortar Sample have many advantages, such as fire-retardant, durability is good, free from extraneous odour, to human body and environmentally friendly, pollution-free, therefore in contemporary public building More and more applications are obtained.The present invention by provide it is a kind of be suitable for it is various under the conditions of, the steel that reuses of all kinds of decorated styles The installation of structure stair step covering (GRC) plate of material, fixed construction method, by the use of the construction method, can meet The architectural image requirement of design and convenient, mitigation of constructing influence surrounding enviroment.
The content of the invention
It marks time it is an object of the invention to provide a kind of steel structure stairway the construction method of prefabricated facing, solves cover board table Enhancing abrasion resistance in face prolongs the service life, reduces the problems such as noise.
A kind of steel structure stairway is marked time the construction method of prefabricated facing, and main flow is:Preparation of construction → component of marching into the arena inspection It tests → all kinds of ironwares, stent make → and finds exterior wall civil engineering datum line → in place by GRC components specification line setting → GRC components accurately Installation → caulking joint, repairing → maintenance → perception processing → subitem are checked and accepted.Specific steps and parameter are as follows:
1st, according to component processing enterprise standard, field test is carried out by appearance and dimensional discrepancy for component entry test.And into Field component must have the appearance certificate of competency.
2nd, prepare construction material, including GRC products outside, cement mortar, acrylic type adhesive, fluid sealant, antirust paint and The supplementary materials such as welding rod;Prepare construction equipment:It is cutting machine, electric welding machine, spirit level, horizon rule, tape measure, ink line case, angle square, straight Ruler, clearance gauge and linen thread etc..
3rd, the attachments such as dirt, mortar block and the rubbish of stair step base are removed, chipping processing is made in local prominent place. Check whether the quality of base meets the requirements.
4th, in the acrylic type gluing oxidant layer of substrate surface, uniformly one layer of 1~2mm thickness of smearing;Cover the rubber slab of 5mm thickness Protective layer, and it is levelling with horizon rule;
5th, in base's face pop-up horizontal line, vertical line and GRC product location lines, it is necessary to accomplish smooth vertical and horizontal, part and part Between gap uniformity, gap control in≤5mm.
6th, GRC cover boards are carried out to fix, weld;Again GRC cover boards installation effect is carried out with horizon rule;
7th, hanging GRC products, spiral stairs form of marking time carries out from lower to upper in order, suitable for reading to be subject to horizontal line, bottom Hang up properly after, corrected with guiding ruler inspection, must not there is the phenomenon that uneven up and down, gap control is in 3~5mm between product.
8th, after seam crossing adds acrylic type adhesive to mix thoroughly using cement mortar, divide 2~4 times according to the thickness of covering cover board When embedding full seam, each filleting interval 2~4 are small, ensure that caulking agent fully cures.
9th, one layer of 3~6mm thickness rubber slab is padded in GRC products and base junction, to separate GRC plates and base's steel construction Contact directly, and with sealing compound filleting.
Fastener used in fixation described in step 6 use zinc-plated processing, embedded part exposed parts, fumigation free, reinforcing bar and Weld seam etc. makees preservative treatment, generally red lead anti-corrosive paint.
Welding needs control sequence and weld bead height described in step 6, meets design requirement, does pullout tests if necessary.
Above-mentioned construction method carries out acceptance of concealed work work.
The quality inspection and evaluation of above-mentioned construction method:
1st, quantity is checked, ladder is marked time at each inspection layer selective examination three for an inspection layer per floor, and often place marks time selective examination 3~5 Point contacts gap and pedal tread on an empty stomach including pedal surrounding.
2nd, the model of GRC components, accessory and connector, specification and technical conditions meet design and related code requirement.GRC Component strength meets design requirement, surface free from flaw.The method of inspection:Check component dispatch from the factory documentary evidence, qualified product card, Check cement mortar block Measurement Report.Observation checks component surface.
3rd, GRC components installation method and installation quality should meet design requirement, firmly install non-loosening.The method of inspection:It sees Inspection is examined, with hand jog.Check concealment acceptance list.
4th, seam meets design and related code requirement, component are firmly bonded, free from flaw.Visual examination.
The advantage of the invention is that:With total quality is light, combination flexibly, convenient and quick construction, without secondary decoration, easily In the series of advantages such as being consistent with periphery decoration style.Using this construction technology, it is existing to environmental protection to meet country It is required that the application of this construction technology, method, whether old industry cleaning or promoted in the range of the whole city will generate huge Economic benefit and social benefit.
Description of the drawings
Fig. 1 is working sketch of the present invention.Wherein, steel structure stairway mark time 1, acrylic type gluing oxidant layer 2, rubber slab protection Layer 3, mark time filling-foam glue 5, GRC material stair between GRC cover boards of pre-buried fixedly connected part 4, steel structure stairway are stepped on GRC plates Walk cover board 6.
Fig. 2 is present invention construction filleting schematic diagram.Wherein, GRC materials stair step cover board 6, caulking agent 7, steel structure stairway Breast board 8.
Specific embodiment
A kind of steel structure stairway is marked time the construction method of prefabricated facing (GRC) material
1st, as shown in Figure 1:
1.1 base cleaning:The attachments such as dirt, mortar block, the rubbish of stair step base are removed, if local have highlightedly Side, should make chipping processing.Check whether the quality of base meets the requirements;
1.2 base faces pop-up horizontal lines, vertical line and GRC product location lines, it is necessary to accomplish it is smooth vertical and horizontal, part and part it Between gap uniformity, and in≤5mm or so;
1.3 in substrate surface, the uniform acrylic type gluing oxidant layer for smearing one layer of 2mm thickness;
The rubber slab protective layer of 1.4 covering 5mm thickness, and it is levelling with horizon rule;
1.5, according to base's face pop-up horizontal line, vertical line and GRC product location lines, carry out GRC cover board installations, simultaneously Adjust GRC cover boards gap;
1.6 progress GRC cover boards are fixed, welded;Again GRC cover boards installation effect is carried out with horizon rule;
The spiral stairs form of marking time should carry out 1.7 extension GRC products from lower to upper in order, suitable for reading to be subject to horizontal line, It after the hanging up properly of bottom, is corrected with guiding ruler inspection, must not there is the phenomenon that uneven up and down, gap control is left in 5mm between product It is right.
Fastener used in 1.8 preferably uses zinc-plated processing, embedded part exposed parts, fumigation free, reinforcing bar and weld seam etc. should all Make preservative treatment, generally red lead anti-corrosive paint.
1.9 control welding sequences and weld bead height, meet design requirement.Pullout tests are done if necessary.
1.10 construction stages carried out acceptance of concealed work work.
2nd, as shown in Fig. 2 stair steps cover board construction filleting schematic diagram:
2.1GRC cover boards installation check complete it is qualified after, carry out at GRC plate seams, gap between GRC plates and stair breast board Processing.When embedding full seam in three times after being mixed thoroughly using cement mortar plus acrylic type adhesive, each filleting interval 4 are small, ensure Caulking agent fully cures.
During filleting processing, stair should properly protect, and must not have pedestrian by preventing caulking agent bonding from loosely occurring Crack;
2.2GRC component installation surface quality examinations, should meet following provisions:
A. clean surface, seam are tightly coincide;
B. crack does not allow;
C. losing fangle:L 20mm, at 2;
D. voids and pits:The gross area is less than 1%, often locates area and is less than 0.5%;
E. burr thickness:No more than 3mm.

Claims (5)

  1. The construction method of prefabricated facing 1. a kind of steel structure stairway is marked time, which is characterized in that specific steps and parameter are as follows:
    1) according to component processing enterprise standard, field test is carried out by appearance and dimensional discrepancy for component entry test;
    2) prepare construction material, match somebody with somebody including GRC products, cement mortar, acrylic type adhesive, fluid sealant, antirust paint and welding rod Cover material;Prepare construction equipment:Cutting machine, electric welding machine, spirit level, horizon rule, tape measure, ink line case, angle square, ruler, clearance gauge and Linen thread;
    3) dirt, mortar block and the rubbish attachment of stair step base are removed, local prominent place makees chipping processing, checks base Whether the quality of layer meets the requirements;
    4) in the acrylic type gluing oxidant layer of substrate surface, uniformly one layer of 1~2mm thickness of smearing;Cover the rubber slab protection of 5mm thickness Layer, and it is levelling with horizon rule;
    5) in base's face pop-up horizontal line, vertical line and GRC product location lines, smooth vertical and horizontal, the sky between part and part is accomplished Gap uniformity, gap are controlled in≤5mm;
    6) GRC cover boards are carried out to fix, weld;Again GRC cover boards installation effect is carried out with horizon rule;
    7) hanging GRC products, spiral stairs form of marking time carries out from lower to upper in order, suitable for reading to be subject to horizontal line, the extension of bottom It after good, is corrected with guiding ruler inspection, gap control is in 3~5mm between product;
    8) it is embedding full according to the thickness points 2~4 times of covering cover board after seam crossing adds acrylic type adhesive to mix thoroughly using cement mortar When seam, each filleting interval 2~4 are small, ensure that caulking agent fully cures;
    9) one layer of 3~6mm thickness rubber slab is padded in GRC products and base junction, to separate the straight of GRC plates and base steel construction Contact, and with sealing compound filleting.
  2. 2. according to the method described in claim 1, it is characterized in that, fastener is using zinc-plated used in fixation described in step 6) Processing, embedded part exposed parts, fumigation free, reinforcing bar and weld seam make preservative treatment.
  3. 3. according to the method described in claim 1, it is characterized in that, welding described in step 6) needs control sequence and weld seam high Degree, meets design requirement, does pullout tests if necessary.
  4. 4. according to the method described in claim 1, it is characterized in that, carry out acceptance of concealed work work.
  5. 5. according to the method described in claim 1, it is characterized in that, the quality inspection and evaluation of the method:
    1) quantity is checked, per floor, ladder is marked time at each inspection layer selective examination three for an inspection layer, and often place marks time selective examination 3~5 point, Gap and pedal tread are contacted including pedal surrounding on an empty stomach;
    2) model of GRC components, accessory and connector, specification and technical conditions meet design and related code requirement;GRC components Intensity meets design requirement, surface free from flaw;
    3) GRC components installation method and installation quality should meet design requirement, firmly install non-loosening;
    4) seam meets design and related code requirement, component are firmly bonded, free from flaw.
CN201711359103.7A 2017-12-17 2017-12-17 A kind of steel structure stairway is marked time the construction method of prefabricated facing Pending CN108086608A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711359103.7A CN108086608A (en) 2017-12-17 2017-12-17 A kind of steel structure stairway is marked time the construction method of prefabricated facing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711359103.7A CN108086608A (en) 2017-12-17 2017-12-17 A kind of steel structure stairway is marked time the construction method of prefabricated facing

Publications (1)

Publication Number Publication Date
CN108086608A true CN108086608A (en) 2018-05-29

Family

ID=62176599

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711359103.7A Pending CN108086608A (en) 2017-12-17 2017-12-17 A kind of steel structure stairway is marked time the construction method of prefabricated facing

Country Status (1)

Country Link
CN (1) CN108086608A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230020659A1 (en) * 2020-06-03 2023-01-19 Finished Edge Technology LLC Luxury Vinyl Plank Stair Noses and Other Moldings

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2563222Y (en) * 2002-07-19 2003-07-30 李鹏飞 Reinforced composite stair plate
JP2006118227A (en) * 2004-10-22 2006-05-11 Hayakawa Rubber Co Ltd Soundproof mat for metal stairs
CN101906858A (en) * 2009-06-02 2010-12-08 上海市建筑装饰工程有限公司 Seamless installation process for polyline artistic GRC (Glass-fiber Reinforced Composite) board
CN203213004U (en) * 2013-05-09 2013-09-25 华仁建设集团有限公司南京分公司 Anti-skidding rubber mat for steel overpass and steel overpass step
CN204492042U (en) * 2015-02-16 2015-07-22 徐州力泰钢结构有限公司 A kind of low noise steel structure stairway
CN205502424U (en) * 2016-01-27 2016-08-24 中国建筑第八工程局有限公司 Steel stair

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2563222Y (en) * 2002-07-19 2003-07-30 李鹏飞 Reinforced composite stair plate
JP2006118227A (en) * 2004-10-22 2006-05-11 Hayakawa Rubber Co Ltd Soundproof mat for metal stairs
CN101906858A (en) * 2009-06-02 2010-12-08 上海市建筑装饰工程有限公司 Seamless installation process for polyline artistic GRC (Glass-fiber Reinforced Composite) board
CN203213004U (en) * 2013-05-09 2013-09-25 华仁建设集团有限公司南京分公司 Anti-skidding rubber mat for steel overpass and steel overpass step
CN204492042U (en) * 2015-02-16 2015-07-22 徐州力泰钢结构有限公司 A kind of low noise steel structure stairway
CN205502424U (en) * 2016-01-27 2016-08-24 中国建筑第八工程局有限公司 Steel stair

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
向才旺: "《新型建筑装饰材料实用手册(第二版)》", 31 December 2001, 中国建材工业出版社 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230020659A1 (en) * 2020-06-03 2023-01-19 Finished Edge Technology LLC Luxury Vinyl Plank Stair Noses and Other Moldings

Similar Documents

Publication Publication Date Title
de Brito et al. Expert knowledge-based inspection systems
Chew Maintainability of Facilities: Green FM for Building Professionals Second Edition
Lin Maintainability of facilities: for building professionals
CN106149935A (en) Open cladding hollow ceramic plate curtain wall construction method
CN108086608A (en) A kind of steel structure stairway is marked time the construction method of prefabricated facing
CN109083420A (en) Building body and indoor and outdoor decoration integral construction method
WOMEN technical specifications
CN115822305A (en) Construction method for artistic veneer of outer wall of antique building
CAAP et al. Procurement of
ACS DSA
Rangaraj et al. Review Paper on Safety Induction, Quality Control, Productivity Calculation for Residential Building.
Neto et al. Pathological manifestations in a building at the end of its lifespan: a Case Study
JAIL et al. MACOMB COUNTY JAIL INDIGENT INMATE VIDEO COURT ROOM
Manufacturers 2.06 TRIM ACCESSORIES
Hurley 17 Coatings for Concrete
Roseburg ROSEBURG URBAN SANITRY AUTHORITY
Click Master Terrazzo Technologies
CN103498520A (en) Hidden frame super white enamelled glass dry hanging construction method
CN110388016A (en) A kind of big specification walltile enhancing barbola work
Lee An elementary school
BOARD ABC STORE NO. 4 & WAREHOUSE
Plant CONTRACT PROVISIONS AND PLANS
Keesler et al. REPAIR STUDENT DORM DAVIS MANOR
Municipality Rehabilitation and Expansion of the Existing Wastewater Treatment Plant in Jenin City
Manufacturers PART 2 PRODUCTS 2.1 FLUSH WOOD DOORS

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180529